Upload
carlos-lino-rojas-agueero
View
220
Download
0
Embed Size (px)
Citation preview
8/12/2019 Cibulka_presentation.pdf
1/45
Mitigating the Impacts of ElectricTransmission Linespresented to:
The UC Center SacramentoSacramento, CA
November 1, 2012
by:Lloyd Cibulka
Electric Grid ResearchThis presentation is based in part on work sponsored by the California Public InterestEnergy Research (PIER) program administered by the California Energy Commission; it
does not necessarily represent the views of, nor has it been approved or disapproved by,the Energy Commission.
8/12/2019 Cibulka_presentation.pdf
2/45
Background
Transmission lines in California (and elsewhere) arebecoming increasingly constrained, while load continuesto grow.
Californias RPS goals will put added demands on the
existing transmission system, and will almost certainlyrequire new lines and corridors. Transmission lines are difficult to site and permit, and the
process can take 810 years, far longer than it takes for
renewable generation to be ready. Public opposition to lines tends to focus on their visualand environmental impacts.
2 2012 UC/CIEE uc-ciee.org
8/12/2019 Cibulka_presentation.pdf
3/45
Impacts of Transmission Lines
Physical Right of way (ROW)requirements, construction, etc.
Pollution Ozone, heat, RFI, corona Electric and magnetic fields Hazards to humans and wildlife
Visual
2012 UC/CIEE uc-ciee.org3
8/12/2019 Cibulka_presentation.pdf
4/45
4 2012 UC/CIEE uc-ciee.org
4
8/12/2019 Cibulka_presentation.pdf
5/45
Objectives and Benefits of Using NewTransmission Technologies Increase power-carrying capacity within
existing (constrained) ROWs. Reduce/minimize impacts of transmission
lines: environmental, visual, footprint, etc. Maximize the use of valuable corridors and
transmission assets. Facilitate the siting and permitting processes
for both new lines and upgrades.
while maintaining system reliability and keeping additional costs to a minimum.
2012 UC/CIEE uc-ciee.org5
8/12/2019 Cibulka_presentation.pdf
6/45
Candidate Transmission Technologies
Re-rating (static) Real-time (dynamic) rating Sagging Line Mitigator (SLiM) Reconductoring Bundled conductors
Single-circuit to double-circuit conversion High-temperature, low-sag conductors Compact lines Voltage uprating Advanced and creative towers & conductors
High phase order design Underground cables (AC) HVDC (conventional) HVDC (new VSC-based) Superconducting cables
C o s t & C
o m p l e x i t y
2012 UC/CIEE uc-ciee.org6
8/12/2019 Cibulka_presentation.pdf
7/45
Re-rating of Transmission Lines
Re-evaluate line rating assumptions to determine newstatic rating: ambient temperature, wind speed, solarinsolation, emissivity of conductor, line clearance, etc.,according to acceptable level of overloading risk.
The static rating of a transmission line is defined as themaximum sustained current the line can carry and notexceed its limiting temperature or violate its minimumclearance, under the assumed limiting environmentalconditions.
IEEE Standard 738 provides recommendedprocedures and default parameters for performing linerating calculations.
2012 UC/CIEE uc-ciee.org7
8/12/2019 Cibulka_presentation.pdf
8/45
Static Rating of Transmission Lines
2012 UC/CIEE uc-ciee.org8
8/12/2019 Cibulka_presentation.pdf
9/45
Re-rating of T/Ls: Pros and Cons
2012 UC/CIEE uc-ciee.org
Pro: capacity increase ~2530%
over static rating withminimal increase of risk
can be used for both
continuous and emergency(contingency) situations no modifications to ROW
required least expensive option (no
hardware upgrades or
monitoring systems) no additional operatingrequirements
no additional visual impacts
Con: need environmental studies or
other analyses to support newassumptions
some physical work may be
needed: splice replacement,re-tensioning, clearanceassessment,relay/transformer/CBupgrades, etc.
slight increase in line losses
possible slight increase in lineoverloading risk possible reduction in conductor
life increase in EMFs, RFI, corona
9
8/12/2019 Cibulka_presentation.pdf
10/45
Re-rating of T/Ls: Other Constraints
2012 UC/CIEE uc-ciee.org
Loading limits on adjacent lines Stability constraints: transient
(disturbances), dynamic (low-leveloscillations, etc.), N1 limitations (RAS &SPS)
Voltage profile
Maintenance and age (loss-of-life) issues
10
8/12/2019 Cibulka_presentation.pdf
11/45
Dynamic Rating of Transmission Lines
2012 UC/CIEE uc-ciee.org
Graphic courtesy of The Valley Group
Use of real-time line and ambient environmental data to produce lineratings closer to actual thermal and clearance limits than staticratings. Also called real-time rating.
11
8/12/2019 Cibulka_presentation.pdf
12/45
Dynamic Rating of T/Ls: Pros and Cons
2012 UC/CIEE uc-ciee.org
Pro: capacity increase up to
100%, depending onconditions and time frame
enables contingency
(emergency) management:takes advantage of short-term overload capability ofthe conductor
if on-line monitors are used,some (very minimal) visualimpacts
Con: may require meteorological
or on-line monitors: cost &maintenance issues,communications, etc.
relay upgrade/re-calibration increased transformerloading
increased line losses increased overloading risk
reduced conductor life increased EMFs, RFI,corona
implementation problematicwith MRTU
12
8/12/2019 Cibulka_presentation.pdf
13/45
Dynamic Rating of Transmission Lines
2012 UC/CIEE uc-ciee.org
Schematic Showing Two Possib le Attachment Loc ations For ConductorGround Clearance/Sag Monitoring Sensors
13
8/12/2019 Cibulka_presentation.pdf
14/45
SLiM (Sagging Line Mitigator)*
2012 UC/CIEE uc-ciee.org14
*Developed with support from the California Energy Commission PIER Program.
A device that uses a reverse-temperature tensioning material to
increase transmission line tension, and hence ground clearance andampacity, with increased current (and power).
Photo: Material Integrity Solutions, Inc.
8/12/2019 Cibulka_presentation.pdf
15/45
Reconductoring of T/Ls
2012 UC/CIEE uc-ciee.org15
Pro: capacity increase ~2X or more
in same ROW no tower mods needed least expensive hardware option
(~$200K/mi for conductors) reduced line losses minimal additional visual
impacts
Con: some line hardware costs: new
clamps, connectors, etc. relaying system upgrades &/or
re-calibration transformer replacement (?)
Replace existing conductors with ones of greater sizeand current-carrying capacity.
Graphic courtesy of 3M Corp.
8/12/2019 Cibulka_presentation.pdf
16/45
Bundling Conductors
2012 UC/CIEE uc-ciee.org16
Pro: capacity increase ~200% or
more in same ROW may be able to use existing
insulators and crossarms; if
so, costs are similar toreconductoring increase in visual impacts is
not great
Con: relay upgrade/re-calibration transformer replacement or
addition possible insulator, tower &
crossarm upgrades new hardware: clamps,
connectors, spacers increase in EMFs, RFI, and
corona
Add another conductor to an existing conductor (1 ormore per phase).
A B C A B C
8/12/2019 Cibulka_presentation.pdf
17/45
High-Temperature, Low-Sag Conductors
2012 UC/CIEE uc-ciee.org17
Conductors in which the inner core material carries all the
tension, and the aluminum wires carry almost all the current.Consequently, the conductor can carry more current whilesagging less at higher operating temperatures.
Developed with support from the California Energy Commission PIER Program.
8/12/2019 Cibulka_presentation.pdf
18/45
High-Temperature, Low-Sag Conductors
2012 UC/CIEE uc-ciee.org18
8/12/2019 Cibulka_presentation.pdf
19/45
High-Temperature, Low-SagConductors: Pros and Cons
2012 UC/CIEE uc-ciee.org19
Pro: capacity increase of 2X-
5X on existing structuresand ROWs
appearance almostidentical to conventionalconductors
minimal upgrades totowers, crossarms orother hardware
installation techniquesvery similar toconventional conductors
Con: conductors about 5X more
costly per foot than ACSR(but can be used for limitedlengths critical spans)
protection systems will needupgrade/re-calibration
splices need specialattention
increased transformer &adjacent circuit loading increased line losses (%) increased EMFs
8/12/2019 Cibulka_presentation.pdf
20/45
Compact Transmission Lines
2012 UC/CIEE uc-ciee.org20
Pro: smaller ROWs for reduced
visual impacts existing towers,
conductors and insulatorscan sometimes be used as
is
Con: may require new insulators
and line hardware, e.g.,spacers, crossarms, etc.
maintenance more difficultand expensive, with possiblesafety implications
somewhat increasedcapacitive effects
More or less conventional lattice-tower design, but withreduced spacing between conductors. Typicallyaccomplished with tighter tensioning on more and closertowers, and high-dielectric insulators.
8/12/2019 Cibulka_presentation.pdf
21/45
Single-Circuit to Double-CircuitLine Conversion
2012 UC/CIEE uc-ciee.org21
Rebuild towers to put two circuits in the same space as one line.
Conventional Single CircuitStructure
Conventional Double CircuitStructure
8/12/2019 Cibulka_presentation.pdf
22/45
Single-Circuit to Double-CircuitLine Conversion: Pros and Cons
2012 UC/CIEE uc-ciee.org22
Pro: capacity increase ~200%
or more in same ROW EMFs can be lower withproper phasingconfiguration
Con: relay upgrade/re-
calibration transformer addition significant costs for tower
upgrades and hardware higher visual impacts,
RFI, corona increased maintenance
costs
8/12/2019 Cibulka_presentation.pdf
23/45
Voltage Uprating
2012 UC/CIEE uc-ciee.org23
Pro:
increases capacity by theratio Vnew /Vold existing towers,
conductors andinsulators can sometimes
be used as is decreased losses voltage levels up to
1100 kV in use today
Con:
may require newinsulators and linehardware
transformer replacementrequired
additional visual impacts reactive compensation an
important factor,increases costs
Convert the transmission line from the existing voltagelevel to a new, higher voltage level, e.g., from 115 kV to230 kV.
8/12/2019 Cibulka_presentation.pdf
24/45
High Phase Order Design
2012 UC/CIEE uc-ciee.org24
Pro: capacity increase
~2X4X (oversingle-circuit line)
feasibility proven atNYSEG in 1997
cost-effective atlonger distances
Con: little actual experience
with this design in US expensive tower design conductor spacers or
limited span lengthsrequired
maintenance issues dueto tight clearancesbetween phases
special phase-shiftingtransformers required atsubstations
Three conventional phases plus three additional phases spaced60 degrees (electrically) between the original phases, in acompact tower arrangement.
Photo: Siemens Corp. and NYSEG
8/12/2019 Cibulka_presentation.pdf
25/45
High Phase Order Design: Spacing
A
B
C
Original 3 Phases: A-B-C120 apartf = 60 Hz
A'
B'
C'
New 3 Phases @ 60: A'-B' -C'
Phase-to-Phase Spacing (Original)
Phase-to-Phase Spacing (New)
25 2012 UC/CIEE uc-ciee.org
8/12/2019 Cibulka_presentation.pdf
26/45
Underground Cables (AC)
2012 UC/CIEE uc-ciee.org26
Pro: visual impacts are zero EMFs lower than O/H
lines generally more
acceptable in urban andcongested areas
less susceptible to damagefrom storms lower risk of sparking fires no hazard to wildlife,
especially migratory birds
High-pressure gas or oil filled pipe-type cable system [ ].
8/12/2019 Cibulka_presentation.pdf
27/45
Underground Cables (AC)
2012 UC/CIEE uc-ciee.org27
Con: costs are typically 5X10X that
for overhead lines
construction is difficult, costly andhas environmental impacts maintenance & corrosion issues thermal considerations limit
operation
outages generally more difficultand expensive to repair
potential leakage of SF 6 gas oroil
expensive to upgrade lengths limited to ~40 miles due
to capacitance effects splices are a maintenance and
reliability issue
Solid dielectric cable system [ ].
8/12/2019 Cibulka_presentation.pdf
28/45
8/12/2019 Cibulka_presentation.pdf
29/45
HVDC Lines: Pros and Cons
2012 UC/CIEE uc-ciee.org29
Pro: need only one conductor,
with earth return, to transmitpower
can achieve at least 2X-3Xthe power density as AC in
the same size ROW lower costs than AC fordistances over ~400 miles
no AC no EMFs lower line losses
better control of power flow no practical limit on linelength
can use U/G cables as wellas O/H lines
Con: high costs of converter
equipment need lots of substation
space for converters need lots of reactive
support in the form offilter capacitors more expensive than
O/H AC for distancesunder ~400 miles (butthe economics aregetting better)
8/12/2019 Cibulka_presentation.pdf
30/45
Conversion of AC Line to DC
2012 UC/CIEE uc-ciee.org30
Pro:
typically ~3X-5X increasein corridor capacity isfeasible, over single-circuit
AC no EMFs
no change in visualimpacts increased control of power
flow no limit on line length
Con: high costs of converter
equipment increased footprint of
substation additional reactive
support required at theconverters (substations)
A 3-phase AC line can be converted to two HVDC lines with a
metallic return, or three HVDC lines with earth return, withoutmodifying the towers, insulators or conductors. Only theterminal equipment changes: AC/DC converters replace thetransformers.
8/12/2019 Cibulka_presentation.pdf
31/45
VSC-based HVDC
2012 UC/CIEE uc-ciee.org31
Pro: all the benefits of conventional
HVDC, but with lower costs andreactive requirements
can use existing AC lines forconversions
can use solid-dielectric, direct-buried or submarine cables, withlower environmental impacts
4-quadrant operation forenhanced control of power flow
cables can easily be direct-buried under existing AC linesor in other ROWs (highwaymedians, railroads, etc.)
Con: at present, voltage limited to
300 kV, power to ~500 MWper circuit
fairly new technology withrelatively positive, albeitlimited, operating experience
still relatively expensive,compared to conventionaloverhead AC
An HVDC technology using voltage-source converter (VSC)power electronics instead of line-commutated high-powerthyristors.
8/12/2019 Cibulka_presentation.pdf
32/45
HVDC Lines in Highways
2012 UC/CIEE uc-ciee.org32
8/12/2019 Cibulka_presentation.pdf
33/45
HVDC Lines in Electric Rail ROWs
2012 UC/CIEE uc-ciee.org33
8/12/2019 Cibulka_presentation.pdf
34/45
High-Temperature SuperconductingCables
2012 UC/CIEE uc-ciee.org34
Pro: ~10X the power capacity of
much larger conventionalcable systems
no EMFs, even with ACoperation
zero losses, except forcryogenics
niche market applicationsbeing demonstrated today
Con: very expensive at present still a developing technology
limited to runs of < 1 mile splices are very tricky forlonger runs
cryogenics improvementsneeded
Transmission cables constructed ofsecond-generation (2G)superconducting wire in a liquidnitrogen bath.
8/12/2019 Cibulka_presentation.pdf
35/45
Tower Structures
2012 UC/CIEE uc-ciee.org35
8/12/2019 Cibulka_presentation.pdf
36/45
Blending In
2012 UC/CIEE uc-ciee.org36
Shiny vs. weathered conductors; lattice vs. pole; bare metal pole vs. painted.
8/12/2019 Cibulka_presentation.pdf
37/45
Topographic Background Integration
2012 UC/CIEE uc-ciee.org37
8/12/2019 Cibulka_presentation.pdf
38/45
Foreground Landscape Screening
2012 UC/CIEE uc-ciee.org38
8/12/2019 Cibulka_presentation.pdf
39/45
Landscape Background Integration
2012 UC/CIEE uc-ciee.org39
8/12/2019 Cibulka_presentation.pdf
40/45
Big & Bold Designs
2012 UC/CIEE uc-ciee.org40
8/12/2019 Cibulka_presentation.pdf
41/45
Anti-Camouflage Tower
2012 UC/CIEE uc-ciee.org41
8/12/2019 Cibulka_presentation.pdf
42/45
Other Creative Tower Designs
2012 UC/CIEE uc-ciee.org42
8/12/2019 Cibulka_presentation.pdf
43/45
Towers That Look Like Us
2012 UC/CIEE uc-ciee.org43
Choi + Shine Design for Iceland Design Competition
8/12/2019 Cibulka_presentation.pdf
44/45
Towers That Look Like Us
2012 UC/CIEE uc-ciee.org44
Choi + Shine Design for Iceland Design Competition
8/12/2019 Cibulka_presentation.pdf
45/45
Questions?
Lloyd CibulkaCalifornia Institute for Energy &
EnvironmentElectric Grid [email protected]
SAIC