Cibulka_presentation.pdf

Embed Size (px)

Citation preview

  • 8/12/2019 Cibulka_presentation.pdf

    1/45

    Mitigating the Impacts of ElectricTransmission Linespresented to:

    The UC Center SacramentoSacramento, CA

    November 1, 2012

    by:Lloyd Cibulka

    Electric Grid ResearchThis presentation is based in part on work sponsored by the California Public InterestEnergy Research (PIER) program administered by the California Energy Commission; it

    does not necessarily represent the views of, nor has it been approved or disapproved by,the Energy Commission.

  • 8/12/2019 Cibulka_presentation.pdf

    2/45

    Background

    Transmission lines in California (and elsewhere) arebecoming increasingly constrained, while load continuesto grow.

    Californias RPS goals will put added demands on the

    existing transmission system, and will almost certainlyrequire new lines and corridors. Transmission lines are difficult to site and permit, and the

    process can take 810 years, far longer than it takes for

    renewable generation to be ready. Public opposition to lines tends to focus on their visualand environmental impacts.

    2 2012 UC/CIEE uc-ciee.org

  • 8/12/2019 Cibulka_presentation.pdf

    3/45

    Impacts of Transmission Lines

    Physical Right of way (ROW)requirements, construction, etc.

    Pollution Ozone, heat, RFI, corona Electric and magnetic fields Hazards to humans and wildlife

    Visual

    2012 UC/CIEE uc-ciee.org3

  • 8/12/2019 Cibulka_presentation.pdf

    4/45

    4 2012 UC/CIEE uc-ciee.org

    4

  • 8/12/2019 Cibulka_presentation.pdf

    5/45

    Objectives and Benefits of Using NewTransmission Technologies Increase power-carrying capacity within

    existing (constrained) ROWs. Reduce/minimize impacts of transmission

    lines: environmental, visual, footprint, etc. Maximize the use of valuable corridors and

    transmission assets. Facilitate the siting and permitting processes

    for both new lines and upgrades.

    while maintaining system reliability and keeping additional costs to a minimum.

    2012 UC/CIEE uc-ciee.org5

  • 8/12/2019 Cibulka_presentation.pdf

    6/45

    Candidate Transmission Technologies

    Re-rating (static) Real-time (dynamic) rating Sagging Line Mitigator (SLiM) Reconductoring Bundled conductors

    Single-circuit to double-circuit conversion High-temperature, low-sag conductors Compact lines Voltage uprating Advanced and creative towers & conductors

    High phase order design Underground cables (AC) HVDC (conventional) HVDC (new VSC-based) Superconducting cables

    C o s t & C

    o m p l e x i t y

    2012 UC/CIEE uc-ciee.org6

  • 8/12/2019 Cibulka_presentation.pdf

    7/45

    Re-rating of Transmission Lines

    Re-evaluate line rating assumptions to determine newstatic rating: ambient temperature, wind speed, solarinsolation, emissivity of conductor, line clearance, etc.,according to acceptable level of overloading risk.

    The static rating of a transmission line is defined as themaximum sustained current the line can carry and notexceed its limiting temperature or violate its minimumclearance, under the assumed limiting environmentalconditions.

    IEEE Standard 738 provides recommendedprocedures and default parameters for performing linerating calculations.

    2012 UC/CIEE uc-ciee.org7

  • 8/12/2019 Cibulka_presentation.pdf

    8/45

    Static Rating of Transmission Lines

    2012 UC/CIEE uc-ciee.org8

  • 8/12/2019 Cibulka_presentation.pdf

    9/45

    Re-rating of T/Ls: Pros and Cons

    2012 UC/CIEE uc-ciee.org

    Pro: capacity increase ~2530%

    over static rating withminimal increase of risk

    can be used for both

    continuous and emergency(contingency) situations no modifications to ROW

    required least expensive option (no

    hardware upgrades or

    monitoring systems) no additional operatingrequirements

    no additional visual impacts

    Con: need environmental studies or

    other analyses to support newassumptions

    some physical work may be

    needed: splice replacement,re-tensioning, clearanceassessment,relay/transformer/CBupgrades, etc.

    slight increase in line losses

    possible slight increase in lineoverloading risk possible reduction in conductor

    life increase in EMFs, RFI, corona

    9

  • 8/12/2019 Cibulka_presentation.pdf

    10/45

    Re-rating of T/Ls: Other Constraints

    2012 UC/CIEE uc-ciee.org

    Loading limits on adjacent lines Stability constraints: transient

    (disturbances), dynamic (low-leveloscillations, etc.), N1 limitations (RAS &SPS)

    Voltage profile

    Maintenance and age (loss-of-life) issues

    10

  • 8/12/2019 Cibulka_presentation.pdf

    11/45

    Dynamic Rating of Transmission Lines

    2012 UC/CIEE uc-ciee.org

    Graphic courtesy of The Valley Group

    Use of real-time line and ambient environmental data to produce lineratings closer to actual thermal and clearance limits than staticratings. Also called real-time rating.

    11

  • 8/12/2019 Cibulka_presentation.pdf

    12/45

    Dynamic Rating of T/Ls: Pros and Cons

    2012 UC/CIEE uc-ciee.org

    Pro: capacity increase up to

    100%, depending onconditions and time frame

    enables contingency

    (emergency) management:takes advantage of short-term overload capability ofthe conductor

    if on-line monitors are used,some (very minimal) visualimpacts

    Con: may require meteorological

    or on-line monitors: cost &maintenance issues,communications, etc.

    relay upgrade/re-calibration increased transformerloading

    increased line losses increased overloading risk

    reduced conductor life increased EMFs, RFI,corona

    implementation problematicwith MRTU

    12

  • 8/12/2019 Cibulka_presentation.pdf

    13/45

    Dynamic Rating of Transmission Lines

    2012 UC/CIEE uc-ciee.org

    Schematic Showing Two Possib le Attachment Loc ations For ConductorGround Clearance/Sag Monitoring Sensors

    13

  • 8/12/2019 Cibulka_presentation.pdf

    14/45

    SLiM (Sagging Line Mitigator)*

    2012 UC/CIEE uc-ciee.org14

    *Developed with support from the California Energy Commission PIER Program.

    A device that uses a reverse-temperature tensioning material to

    increase transmission line tension, and hence ground clearance andampacity, with increased current (and power).

    Photo: Material Integrity Solutions, Inc.

  • 8/12/2019 Cibulka_presentation.pdf

    15/45

    Reconductoring of T/Ls

    2012 UC/CIEE uc-ciee.org15

    Pro: capacity increase ~2X or more

    in same ROW no tower mods needed least expensive hardware option

    (~$200K/mi for conductors) reduced line losses minimal additional visual

    impacts

    Con: some line hardware costs: new

    clamps, connectors, etc. relaying system upgrades &/or

    re-calibration transformer replacement (?)

    Replace existing conductors with ones of greater sizeand current-carrying capacity.

    Graphic courtesy of 3M Corp.

  • 8/12/2019 Cibulka_presentation.pdf

    16/45

    Bundling Conductors

    2012 UC/CIEE uc-ciee.org16

    Pro: capacity increase ~200% or

    more in same ROW may be able to use existing

    insulators and crossarms; if

    so, costs are similar toreconductoring increase in visual impacts is

    not great

    Con: relay upgrade/re-calibration transformer replacement or

    addition possible insulator, tower &

    crossarm upgrades new hardware: clamps,

    connectors, spacers increase in EMFs, RFI, and

    corona

    Add another conductor to an existing conductor (1 ormore per phase).

    A B C A B C

  • 8/12/2019 Cibulka_presentation.pdf

    17/45

    High-Temperature, Low-Sag Conductors

    2012 UC/CIEE uc-ciee.org17

    Conductors in which the inner core material carries all the

    tension, and the aluminum wires carry almost all the current.Consequently, the conductor can carry more current whilesagging less at higher operating temperatures.

    Developed with support from the California Energy Commission PIER Program.

  • 8/12/2019 Cibulka_presentation.pdf

    18/45

    High-Temperature, Low-Sag Conductors

    2012 UC/CIEE uc-ciee.org18

  • 8/12/2019 Cibulka_presentation.pdf

    19/45

    High-Temperature, Low-SagConductors: Pros and Cons

    2012 UC/CIEE uc-ciee.org19

    Pro: capacity increase of 2X-

    5X on existing structuresand ROWs

    appearance almostidentical to conventionalconductors

    minimal upgrades totowers, crossarms orother hardware

    installation techniquesvery similar toconventional conductors

    Con: conductors about 5X more

    costly per foot than ACSR(but can be used for limitedlengths critical spans)

    protection systems will needupgrade/re-calibration

    splices need specialattention

    increased transformer &adjacent circuit loading increased line losses (%) increased EMFs

  • 8/12/2019 Cibulka_presentation.pdf

    20/45

    Compact Transmission Lines

    2012 UC/CIEE uc-ciee.org20

    Pro: smaller ROWs for reduced

    visual impacts existing towers,

    conductors and insulatorscan sometimes be used as

    is

    Con: may require new insulators

    and line hardware, e.g.,spacers, crossarms, etc.

    maintenance more difficultand expensive, with possiblesafety implications

    somewhat increasedcapacitive effects

    More or less conventional lattice-tower design, but withreduced spacing between conductors. Typicallyaccomplished with tighter tensioning on more and closertowers, and high-dielectric insulators.

  • 8/12/2019 Cibulka_presentation.pdf

    21/45

    Single-Circuit to Double-CircuitLine Conversion

    2012 UC/CIEE uc-ciee.org21

    Rebuild towers to put two circuits in the same space as one line.

    Conventional Single CircuitStructure

    Conventional Double CircuitStructure

  • 8/12/2019 Cibulka_presentation.pdf

    22/45

    Single-Circuit to Double-CircuitLine Conversion: Pros and Cons

    2012 UC/CIEE uc-ciee.org22

    Pro: capacity increase ~200%

    or more in same ROW EMFs can be lower withproper phasingconfiguration

    Con: relay upgrade/re-

    calibration transformer addition significant costs for tower

    upgrades and hardware higher visual impacts,

    RFI, corona increased maintenance

    costs

  • 8/12/2019 Cibulka_presentation.pdf

    23/45

    Voltage Uprating

    2012 UC/CIEE uc-ciee.org23

    Pro:

    increases capacity by theratio Vnew /Vold existing towers,

    conductors andinsulators can sometimes

    be used as is decreased losses voltage levels up to

    1100 kV in use today

    Con:

    may require newinsulators and linehardware

    transformer replacementrequired

    additional visual impacts reactive compensation an

    important factor,increases costs

    Convert the transmission line from the existing voltagelevel to a new, higher voltage level, e.g., from 115 kV to230 kV.

  • 8/12/2019 Cibulka_presentation.pdf

    24/45

    High Phase Order Design

    2012 UC/CIEE uc-ciee.org24

    Pro: capacity increase

    ~2X4X (oversingle-circuit line)

    feasibility proven atNYSEG in 1997

    cost-effective atlonger distances

    Con: little actual experience

    with this design in US expensive tower design conductor spacers or

    limited span lengthsrequired

    maintenance issues dueto tight clearancesbetween phases

    special phase-shiftingtransformers required atsubstations

    Three conventional phases plus three additional phases spaced60 degrees (electrically) between the original phases, in acompact tower arrangement.

    Photo: Siemens Corp. and NYSEG

  • 8/12/2019 Cibulka_presentation.pdf

    25/45

    High Phase Order Design: Spacing

    A

    B

    C

    Original 3 Phases: A-B-C120 apartf = 60 Hz

    A'

    B'

    C'

    New 3 Phases @ 60: A'-B' -C'

    Phase-to-Phase Spacing (Original)

    Phase-to-Phase Spacing (New)

    25 2012 UC/CIEE uc-ciee.org

  • 8/12/2019 Cibulka_presentation.pdf

    26/45

    Underground Cables (AC)

    2012 UC/CIEE uc-ciee.org26

    Pro: visual impacts are zero EMFs lower than O/H

    lines generally more

    acceptable in urban andcongested areas

    less susceptible to damagefrom storms lower risk of sparking fires no hazard to wildlife,

    especially migratory birds

    High-pressure gas or oil filled pipe-type cable system [ ].

  • 8/12/2019 Cibulka_presentation.pdf

    27/45

    Underground Cables (AC)

    2012 UC/CIEE uc-ciee.org27

    Con: costs are typically 5X10X that

    for overhead lines

    construction is difficult, costly andhas environmental impacts maintenance & corrosion issues thermal considerations limit

    operation

    outages generally more difficultand expensive to repair

    potential leakage of SF 6 gas oroil

    expensive to upgrade lengths limited to ~40 miles due

    to capacitance effects splices are a maintenance and

    reliability issue

    Solid dielectric cable system [ ].

  • 8/12/2019 Cibulka_presentation.pdf

    28/45

  • 8/12/2019 Cibulka_presentation.pdf

    29/45

    HVDC Lines: Pros and Cons

    2012 UC/CIEE uc-ciee.org29

    Pro: need only one conductor,

    with earth return, to transmitpower

    can achieve at least 2X-3Xthe power density as AC in

    the same size ROW lower costs than AC fordistances over ~400 miles

    no AC no EMFs lower line losses

    better control of power flow no practical limit on linelength

    can use U/G cables as wellas O/H lines

    Con: high costs of converter

    equipment need lots of substation

    space for converters need lots of reactive

    support in the form offilter capacitors more expensive than

    O/H AC for distancesunder ~400 miles (butthe economics aregetting better)

  • 8/12/2019 Cibulka_presentation.pdf

    30/45

    Conversion of AC Line to DC

    2012 UC/CIEE uc-ciee.org30

    Pro:

    typically ~3X-5X increasein corridor capacity isfeasible, over single-circuit

    AC no EMFs

    no change in visualimpacts increased control of power

    flow no limit on line length

    Con: high costs of converter

    equipment increased footprint of

    substation additional reactive

    support required at theconverters (substations)

    A 3-phase AC line can be converted to two HVDC lines with a

    metallic return, or three HVDC lines with earth return, withoutmodifying the towers, insulators or conductors. Only theterminal equipment changes: AC/DC converters replace thetransformers.

  • 8/12/2019 Cibulka_presentation.pdf

    31/45

    VSC-based HVDC

    2012 UC/CIEE uc-ciee.org31

    Pro: all the benefits of conventional

    HVDC, but with lower costs andreactive requirements

    can use existing AC lines forconversions

    can use solid-dielectric, direct-buried or submarine cables, withlower environmental impacts

    4-quadrant operation forenhanced control of power flow

    cables can easily be direct-buried under existing AC linesor in other ROWs (highwaymedians, railroads, etc.)

    Con: at present, voltage limited to

    300 kV, power to ~500 MWper circuit

    fairly new technology withrelatively positive, albeitlimited, operating experience

    still relatively expensive,compared to conventionaloverhead AC

    An HVDC technology using voltage-source converter (VSC)power electronics instead of line-commutated high-powerthyristors.

  • 8/12/2019 Cibulka_presentation.pdf

    32/45

    HVDC Lines in Highways

    2012 UC/CIEE uc-ciee.org32

  • 8/12/2019 Cibulka_presentation.pdf

    33/45

    HVDC Lines in Electric Rail ROWs

    2012 UC/CIEE uc-ciee.org33

  • 8/12/2019 Cibulka_presentation.pdf

    34/45

    High-Temperature SuperconductingCables

    2012 UC/CIEE uc-ciee.org34

    Pro: ~10X the power capacity of

    much larger conventionalcable systems

    no EMFs, even with ACoperation

    zero losses, except forcryogenics

    niche market applicationsbeing demonstrated today

    Con: very expensive at present still a developing technology

    limited to runs of < 1 mile splices are very tricky forlonger runs

    cryogenics improvementsneeded

    Transmission cables constructed ofsecond-generation (2G)superconducting wire in a liquidnitrogen bath.

  • 8/12/2019 Cibulka_presentation.pdf

    35/45

    Tower Structures

    2012 UC/CIEE uc-ciee.org35

  • 8/12/2019 Cibulka_presentation.pdf

    36/45

    Blending In

    2012 UC/CIEE uc-ciee.org36

    Shiny vs. weathered conductors; lattice vs. pole; bare metal pole vs. painted.

  • 8/12/2019 Cibulka_presentation.pdf

    37/45

    Topographic Background Integration

    2012 UC/CIEE uc-ciee.org37

  • 8/12/2019 Cibulka_presentation.pdf

    38/45

    Foreground Landscape Screening

    2012 UC/CIEE uc-ciee.org38

  • 8/12/2019 Cibulka_presentation.pdf

    39/45

    Landscape Background Integration

    2012 UC/CIEE uc-ciee.org39

  • 8/12/2019 Cibulka_presentation.pdf

    40/45

    Big & Bold Designs

    2012 UC/CIEE uc-ciee.org40

  • 8/12/2019 Cibulka_presentation.pdf

    41/45

    Anti-Camouflage Tower

    2012 UC/CIEE uc-ciee.org41

  • 8/12/2019 Cibulka_presentation.pdf

    42/45

    Other Creative Tower Designs

    2012 UC/CIEE uc-ciee.org42

  • 8/12/2019 Cibulka_presentation.pdf

    43/45

    Towers That Look Like Us

    2012 UC/CIEE uc-ciee.org43

    Choi + Shine Design for Iceland Design Competition

  • 8/12/2019 Cibulka_presentation.pdf

    44/45

    Towers That Look Like Us

    2012 UC/CIEE uc-ciee.org44

    Choi + Shine Design for Iceland Design Competition

  • 8/12/2019 Cibulka_presentation.pdf

    45/45

    Questions?

    Lloyd CibulkaCalifornia Institute for Energy &

    EnvironmentElectric Grid [email protected]

    SAIC