EKONOMI REKAYASA. PERTEMUAN 1 PENDAHULUAN & NPV. Oleh : Arwan Apriyono P. Setyo Nugroho. PROGRAM STUDI TEKNIK SIPIL JURUSAN TEKNIK FAKULTAS SAINS DAN TEKNIK UNSOED TAHUN 2011. Lay Out Presentasi Pengertian ekonomi teknik Formula/Rumus Tingkat bunga NPW. I NTRODUCTION. ?. - PowerPoint PPT Presentation
Citation preview
EKONOMI REKAYASAPERTEMUAN 1
PENDAHULUAN & NPV
Oleh :Arwan ApriyonoP. Setyo Nugroho
PROGRAM STUDI TEKNIK SIPIL JURUSAN TEKNIK FAKULTAS SAINS DAN TEKNIK UNSOED
TAHUN 2011
Lay Out Presentasi1. Pengertian ekonomi teknik2. Formula/Rumus3. Tingkat bunga4. NPW
?
INTRODUCTION
?
INTRODUCTION
Menyewa/Membeli?
INTRODUCTION
INTRODUCTION
Metode Pengambilan Keputusan- NPV/NPW- ROR/IRR
- B/C
Pengetahuan Dasar
-Nilai uang (PV, FV, AV)-Suku bunga (Rerata , Majemuk)-Cost and Benefit-Cast flow diagram
Infuence Factor-Inflasi & Deflasi-Pajak-Depreciation
FinansialDecision Making
Materi :1.Pendahuluan dan NPW2.Analisis investasi ROR/IRR3.Analisis investasi B/C4.Inflasi & Deflasi5.Pajak6.Depreciation/Penurunan nilai7.Replacement Analysis
Referensi :
8. Donald G Newnan et al, 2004, Engineering Economic Analysis, Oxford University Press, Newyork
9. Abol Ardalan, 2000, Economic & Financial Anaysis for Engineering & Project Management, Technomic Publishing Company Book, Pennsylvania
10.Perry Beaumon, 2004, Financial Engineering Principle, Wiley, New Jersey
11.Chan S Park, Fundamental of Engineering Economics, Pearson Education Inc, New Jersey
12.Peter Cassimatis, 1992, Introduction to Engineering Economic, Taylor & Francir Routledge, London
RENCANA KULIAH
MESTI BANYAK EXERCISE.
MARR = Minimum Attractive Rate of Return
MANFAAT-----------
EUAW : Equivalent Uniform Annual Worth
P/F : mencari nilai P dari nilai F; jadi nilai F sudah diketahuiA/F : mencari nilai A dari nilai F; jadi nilai F sudah diketahui
Langkah perhitungan
1. Tuliskan yang diketahui2. Gambarkan dalam bentuk diagram3. Hitung yang ditanyakan
Latihan (15’)1. Berapa uang harus diinvestasikan untuk
mendapatkan 750.000 selama waktu 3 tahun dengan bunga majemuk 10% per tahun ?
2. Berapa yang harus disimpan di bank untuk mendapatkan 15.500.000 selama 2 tahun pada bunga majemuk 1,5 % per bulan ?
No. 1F = 750.00000n = 3 tahunI = 10 %P = F(F/P, i, n) = 750.000(F/P, 0.1, 3) = 563.486
No. 2
F = 15.500.000n = 2 tahun = 24 bulani = 1.5 %P = F(F/P, i, n) = 15.500.000(F/P, 0.015 , 24) =
10.842.930,75
Contoh :Suatu lembaga pembiayaan dalam iklannya menyatakan bahwa bunga pinjaman bunga nominal 12% setahun (sebesar 1% sebulan, dihitung per bulan karena pembayaran biasanya tiap bulan) Berapa sebetulnya bunga efektif dalam setahun?I efektif = (1+0,12/12)12 - 1 =
Bunga efektif selalu lebih besar daripada bunga nominal
Dalam perhitungan ekonomi teknik, jika tanpa penjelasan maka bunga yang dimaksud adalah bunga nominal, bukan bunga efektif.Jika dinyatakan bahwa bunga setahun 36%, maka 36% adalah bunga nominal dalam setahun, sehingga bunga dalam sebulan adalah3%
INTRODUCTION
Prinsip dasarMetode
Pengambilan Keputusan
Menghitung total biaya dan manfaat yang dihasilkan dari
suatu kasus/proyek.
NPV/NPW
NET PRESENT VALUE / NET PRESENT WORTH
The net difference of the present benefits and costs
NPV = PV of Benefit – PV of cost
Alternatif yang paling baik adalah yang memiliki NPV terbesar
NPV/NPW
Example
A car leasing company buys a car from a wholesaler for $24,000 and leases it to a customer for four years at $5,000 per year. Since the maintenance is not included in the lease, the leasing company has to spend $400 per year in servicing the car. At the end of the four years, the leasing company takes back the car and sells it to a secondhand car dealer for$15,000. Calculate the NPV for the case if we will not consider tax, inflation, and depreciation (interest of rate 10%)?
NPV/NPW
ANALYSIS
Step 1 : Making cost flow diagram
NPV/NPW
ANALYSIS
Step 2 : Calculate PV of Cost and Benefit
PV of cost = $24000
PV of Benf = A(P/A, i, n) + F(P/F, i, n)
= 4600 * ((1+0.1)3 – 1)/(0.1(1+0.1)3)
+ 19600*(1+0.1)-4
= 11439,52 + 13387,1
= $24826,62
NPV/NPW
ANALYSIS
Step 3 : Calculate NPV
Total Cost = 24,000
Total Benefit = 11439.52 + 13387.1 = 24826.62
Net Worth of the Project = 826.62
NPV/NPW
ANALYSIS
Step 3 : Calculate NPV
Total Cost = 24,000
Total Benefit = 11439.52 + 13387.1 = 24826.62
Net Worth of the Project = 826.62
NPV/NPW
CONTOH SOAL
Suppose the leasing company of Example 2.1 has to
choose between the following two projects:
1. Lease the car exactly as the case in Example 2.1 which
had a net present worth of $826.62
2. Buy a car at $40,000, lease it for two years at $12,000
per year with no maintenance cost, and sell it
for $24,000 at the end of two years.
NPV/NPW
ANALYSIS
Step 1 : Making cost flow diagram
36000
16000
NPV/NPW
ANALYSIS
= -40000 + 12000 (P/A, 10,3) - 16000 (P/F,10,2) + 36000
(P/F,10,4)
= -40000 + 12000 (2.487) -16000 (0.8264) + 36000 (0.6830)
= 1,209.6
Since project 2 has a higher NPW, it would be the
project to choose
NPW makin besar, makin baik untuk investasi.
Task 1. (due date 24 Oct 2011)diketik diprint pada kertas A4, diberi cover tugas 1 ekonomi rekayasa
1-In a housing project the following sequence of events occurs.At the start of the project (time zero), land is bought at $1,000,000Two months later, $100,000 is paid to the architect for preparing the
designIn month 4, construction is started and the cost of construction (labor and material) is $ 150,000 per month. Every month, one house is built (a total of 12 houses); the first one is ready for sale in month 6. During every month starting from month 8, one house is sold for a price of $ 250,000 each. After all of the houses are built and before all are sold, the cost of maintaining the site is $10,000 per month.Draw the cash flow diagram.
2-Mr. Shop purchases a pizza shop for $120,000. Its operation will result in a net income of $15,000/Yr for the first year, increasing by $2,000 each year after year 1. At the end of the fifth year, the shop is sold for $155,000. Draw the cash flow diagram for this project.
3-A credit card company announces that its interest rate is 1.5% per month.
What is the corresponding effective annual interest rate?