Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
ENVIRONMENTAL IMPACT ASSESSMENT
FOR ROAD SAFETY IMPROVEMENT PROJECT
UKRAINE
2007
E2999 v1 P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
2
TABLE OF CONTENTS
INTRODUCTION
1. PHYSIOGRAPHIC CHARACTERISTICS OF THE REGIONS ALONG THE ROAD
2. GENERAL DESCRIPTION OF THE PROJECT
3. ASSESSMENT OF ENVIRONMENTAL IMPACTS FROM THE PROJECT
5. ASSESSMENT OF IMPACT ON SOCIAL ENVIRONMENT
6. ASSESSMENT OF IMPACT ON TECHNOLOGICAL ENVIRONMENT
7. MEASURES FOR MAINTENANCE OF ENVIRONMENTAL STANDARDS AND ENVIRONMENTAL SAFETY
8. COMPREHENSIVE ASSESSMENT OF INVIRONMENTAL IMPACTS
9. ASSESSMENT OF ENVIRONMENTAL IMPACTS FROM CONSTRUCTION
INTRODUCTION
The Feasibility Study for development of Kyiv-Kharkiv-Debaltsevo-Izvaryne Motorroad (M-
03, M-04) was developed by Ukrdiprodor State Enterprise with involvement of Kharkiv Branch of Kharkivdiproshliakh, Donetsk Branch of Ukrdiprodor, the Regional Research Center of Salvage Archeological Service, and Kyivsoyuzshliakhproject Close Corporation by virtue of Task # 20-1/05 issued on 10 February 2005 by the Motorroad Service in Kharkiv Oblast and approved by Ukravtodor State Motorroad Service of Ukraine. The Environmental Impact Assessment Section was developed by Geotechnologiyi Ltd.
This Book of Environmental Impact Assessment Section is about assessment of environmental impact from the project in Kyiv and Poltava Oblasts.
M-03 with M-04 Motorroad connects the capital of Ukraine with Ukraine’s eastern border with the Russian Federation and crosses the Oblasts of Kyiv, Poltava, Kharkiv, Donetsk, and Lugansk. It provides for local and transit motor transport communication between the Central and the Eastern Regions of Ukraine and for international passenger and freight traffic.
In Kyiv Oblast the road starts at the end of Boryspil detour and crosses the Rayons of Boryspil, Pereyaslav-Khmelnitskiy, Baryshivka, and Yagotyn. In Poltava Oblast the road crosses the Rayons of Pyriatyn, Lubny, Khorol, Velyka Bagachka, Reshetylivka, Poltava, and Chutove.
The need to develop M-03 Motorroad is accounted for by the current inadequate condition of
pavement, lack of convenient interchanges and bypasses around the settlements, and unconformity of engineering and operational characteristics of the motorroad to modern standards.
Development of M-04 Motorroad will enable to:
- improve the riding qualities, the speed of traffic, and the ride comfort; - improve transport links and increase the transit traffic; - increase the levels of environmental safety; and
- increase the levels of road safety.
Research and analysis of environmental conditions and predictive assessments of possible impacts during construction and operation of the motorway are conducted within the permanent right-of-way (40 m), in the safety buffer zone (150 - 300 m from the edge of roadway), and in the affected zone (2 - 3 km).
Brief Description of Designed Activity and the Types of Its Environmental Impacts
The length of Kyiv Oblast section is: along the existing route of M-03 Motorroad: 108.26 km, and together with the existing and designed sections of Boryspil detour: 139.76 km.
The design includes rehabilitation of Boryspil northern bypass, approximate length 25 km, to conform to Category Ib, and rehabilitation of 9.947 km of the road across the city to conform to Category Ib. The sections are also being designed (approximate length: 4.8 km and 4.0 km) which will connect M-03 Motorroad with the section of Boryspil bypass and the section of southern bypass (approximate length 10.5 km). All the said sections will correspond to Category Ib. The bypass sections are shown on the map below:
4
The length of Poltava Oblast section is: along the existing route of M-03 Motorroad (subject
to existing kilometrage): 268.904 km. Besides, the Feasibility Study includes bypass sections where estimation of lengths is based on the design data: - Velyka Krucha Village, Pyriatyn Rayon: 5.205 km;
- Pokrovska Bagachka and Kovtuny Villages, Khorol Rayon: 11.18 km (northern option), 12.03 km (southern option), and 1.37 km across Kovtuny; and
- Vasylivka Town, Chutove Rayon: 8.76 km.
The skeleton maps of bypass sections around the settlements are shown below:
5
The road along all the designed sections will belong to Category Ib and have the following critical parameters: two lanes per each direction, each 3.75 m wide; and 6.0 m wide centre mall and 3.75 m wide verge beyond the bounds of settlements. The pavement will be black bituminous concrete. The design speed will be 140 km/hr and 120 km/hr for irregular terrain. The vertical alignment will correspond to the requirements of State Building Specifications (DBN) В.2.3-4-2000 «Motor Roads» for Category I roads. Design loads: axle static: 11.5 ton-force; on engineering structures: A-15. The roadbed width will be 28.5m. In Kyiv Oblast seven interchanges in two levels are being designed for crossings with other roads and six interchanges for the area of Boryspil detour.
Repair of the pavement and structures on the road will enable to provide for proper traffic capacity of the road, which, in accordance with predictive estimates of Ukrdiprodor, will increase by a factor of 2.8 – 3.0 in Kyiv Oblast and by a factor of 2.8 – 3.0 in Poltava Oblast by the year 2026.
Traffic Volume, conditional vehicle/day
Section of Road
2005 (actual) 2026 (predictive)
in Kyiv Oblast
km 45+000 - km 76+015 16,270 46,850
km 76+015 - km 103+690 14,450 42,660
km 103+690 - km 126+160 12,900 39,220
6
in Poltava Oblast
km 126+160 - km 156+600 12,890 39,300
km 156+600 – km 192+100 12,660 38,980
km 192+100 – km 207+100 10,980 34,200
km 207+100 – km 235+840 11,840 37,180
km 235+840 – km 243+720 11,000 35,480
km 243+720 – km 286+285 11,790 36,940
km 286+285 – km 306+628 12,800 38,780
km 306+628- km 336+873 13,120 38,740
km 336+873 – km 340+961 24,300 64,860
km 340+961 – km 362+500 14,000 33,490
km 362+500 – km 395+064 10,710 27,080
Construction works and further operation of the road after its commissioning will entail a number of negative environmental impacts. The list of expected environmental impacts from the
project during construction and operation:
- geological environment: occurrence or activation of hazardous geodynamic processes is possible (erosion, underflooding, ground flash, etc.);
- landscapes: changes in local landscapes are possible during construction of the roadway, implementation of erosion- and landslide-prevention design approaches, excavation works, fill construction, and quarrying;
- climate and microclimate: no impact expected;
- air: exhaust gas emissions, noise, dust, and carbon black;
- aquatic environment: temporary changes are possible in regimes of runoff in water bodies and in levels of the water table, abrasion, and pollution of aquatic environment with wastewater
containing petrochemicals and other chemical compounds;
- earth: temporary withdrawal of lands for reserves, quarries, rights-of-way, etc.; chemical and garbage pollution;
- plants, animals, and protected areas: cutting down of green plantations in the area of mottorroad expansion; withdrawal of bush and light forest from the right-of-way; changes in migration conditions of wild animals and possible changes in the existing status of biological and
ecological systems in the construction zone; noise; and aerosol fallout;
- social environment (population): withdrawal of lands, demolition of buildings, temporary inconveniences during construction works, temporary man-caused impact on historical and architectural heritage;
positive impacts: creation of new jobs and increase of investment appeal;
- technological environment: impact on buildings and structures is possible from emissions, noise, and vibration;
- positive impacts: upgrade of transport infrastructure, improvement of services, and rehabilitation of transportation links.
Participatory Stakeholder Consultation
7
The communities gained a chance to have a direct influence on decision-making during design by informing the local governments of their requests as to proper improvements of the motorroad. Opinions of the stakeholder communities will be incorporated as required in par. 1.10 of
DBN А.2.2-1-2003.
A sampling poll of the citizens residing in the settlements along the motorroad and in the adjacent territories showed that the communities have a positive attitude to rehabilitation of the motorroad. The main benefits which they expect are improvement of conditions, quality, and speed of traffic, as well as increase in demand for services and private trade opportunities. The communities appreciate inconveniences which may occur during the construction works and may be caused by expected increase in the traffic.
2. PHYSIOGRAPHIC CHARACTERISTICS along the route of designed project
In terms of geological structure, the territory of the project is located within the north-eastern flank of the Ukrainian Precambrian Shield and the south-western rim of the Dnipro-Donetsk Depression, and the surface of its crystalline basement features continuous gradient towards north-
east. The quaternary land sediments form almost continuous cover. Aeolian soils prevail. In river
valleys alluvial and fluviolacustrine sands and clays prevail. The territory of the project features landscapes of the terraced part of Dnipro Lowland. The surface is slightly divided and it features flat watersheds and wide river valleys with
systems of quaternary and neogenic benches, which form benched surface of the lowland. The territory is shaped by erosion and accumulation, glacial and river waters, a glacier, agglomeration of loess-type rocks and fossil grounds, eolian processes, suffosion, etc.
The mean elevations are 50-150 m. The relative elevations vary from 20 to 60 m. The following types of landscapes are observed within the region of the project (west to east):
- mixed coniferous-broad-leaved forest, alluvial outwash, and terraced terrain with sod-podzol and turfy grounds, millet-grass, subors, and lowland bogs;
- forest-steppe, terraced forest and sand with gray forest and taupe podzolized grounds, millet-grass, and subors. The high-water beds include flood-plain and meadow boggy landscapes. The climate of the territory is mild, moderate continental. The winters are long and relatively warm. The summers are sufficiently warm and humid.
The climate is shaped by significant solar radiation and air-mass transport mainly from the west. The total annual solar radiation is 4,000-4,200 MJ/m
2. and the radiation balance is 1,700-1,800 MJ/m
2..
The sunshine duration is 1,850-1,950 hr/year.
The mean temperatures of January are -6,3ºC and the absolute minimum is -36 ºС. Winter lasts from November, when the mean daily air temperature drops below 0ºC, till mid-March. The stable snow cover (mean height 25-30 cm) lasts from mid-December to mid-March.
Summer starts early in May, when the mean daily air temperature rises above +15 ºС, and ends early in September. The mean temperature of July is +19,4 ºС. The absolute maximum of air temperature for the territory is +39 ºС.
The frost-free period lasts 160-165 days. The period when the temperature is above +10ºС lasts 160-165 days and the effective heat sum is 2,600-2,700 º.
The annual precipitation is 520 mm with their most part falling in the warm season.
The adverse climatic conditions include intensive showers with thunderstorms, hail, rainless periods, hot winds (up to 5-10 days), dust storms in summer, ice crust, clear ice, etc.
The territory belongs to a warm agroclimatological zone with insufficient humidity.
8
The vegetation period starts late in March – early in April and ends late in October – early in November. The total duration of such period is 190 - 220 days.
М-03 Motorroad crosses the rivers of Trubizh, Nedra, Supiy, Sula, Psel, Vorskla, Uday,
Khorol, and Kolomak, which belong to the Dnipro basin.
The rivers are of plains type. They feed on snow- (almost 60% of the water yield), rain-, and groundwater. About 50% of the water is yielded for the rivers in spring, 25-30% in summer and autumn, and 25% in winter.
The high flow is in spring. The low water discharge is in summer.
The mean turbidity of the river waters is mainly about 50 g/m³. The virgin flows were changed significantly after having been regulated with many ponds and reservoirs.
The territory of the project is located within the Eastern Forest-Steppe Lowland Agropedological Province, which occupies the eastern part of the Forest-Steppe Agropedological Zone.
The soil cover of the province features diversity of structure and involvement of salinization process (mainly of soda-chloride-sulfate type) in its genesis.
The vegetable cover of the territory features scarce remainder of aspen rickers with oaks and extensive waterlogging of river valleys and depressions. Meadow steppes, steppe meadows, and meadow halophytic aggregations prevailed here formerly. Silva occurs mainly on the sand benches and floodplains. It includes pine and pine-oak (with some alders) aggregations.
In some places there are ravine forests, which, besides prevailing ordinary oak, also include Tatarian maple, Norway maple, ashwood, elm, and teil; buckthorn, hawthorn, wild rose, etc. in the shrub layer; and stellaria graminifolious, ordinary goutweed, ordinary lily of the valley, speckled melic, etc. in the grass layer.
Meadow steppes, almost completely tilled, remain only on the valley slopes and include phytocenoses with prevailing fescue, feather grass, and narrow-leaved June grass. Formations of eastern fescue, Karelin sedge, white bent grass, suaeda prostrata, and herbaceous solonetz cover the lowland saline meadows. The modern vegetation has been affected by considerable man-caused changes: ploughing up of soils, bog reclamation, deforestation. Only 8-10% of the territory is covered with forests.
The fauna is rich and diverse. It is of transient and mixed nature, i.e. it includes representatives of forest, steppe, and water-paludal faunal systems.
All the territory has been developed intensively by agriculture. The lands which will be withdrawn temporarily or permanently belong to agricultural category.
The territory of the project (the zone affected by the road, within 3 km) includes four protected areas in Kyiv Oblast:
Description Category Area, km2 Established
in Type
Distance from the edge of
embankment, m
Distance from the beginning of
road, km*
Borshchivsky Forest 36 1994 Local
sanctuary 220 27.5
Dubyna Botanic 4 1991 Local
sanctuary 1,700 34.1
Vybla Mohyla Complex 2 1991 Object of
local natural heritage
1,250 35.7
Marsh in Solontsi Reserved Area
50 1979 Reserved
area 250 46.0
9
The protected areas are shown on the map below:
10
The following protected areas are located in the zone affected by the mottorroad in Poltava Oblast:
L/I
Distance from the
beginning of road,
km
Description Category Area,
ha
Established
in Type
1 98.2 Polohy Hydrological 100 1994 Local sanctuary
2 111.8 English oak Botanic 0 1982 Object of local natural
heritage
3 111.9 Masalsky Iseland Recreational Forest
Botanic 47 1982 Object of local natural
heritage
4 117.6 Velykokruchansky Hydrological 90 1998 Local sanctuary
5 122.4 Kukvynsky Hydrological 300 1980 National sanctuary
6 152.1 Morozivska Dacha Botanic 855 1969 Object of local natural
heritage
7 160.3 Torgovytsia 135.8 1993 Reserved area
8 162.6 Zhovtneva Dacha Botanic 57 1972 Object of local natural
heritage
9 188 Gryntseve 39 1992 Reserved area
10 188.6 Radky 41 1992 Reserved area
11 191.1 English oak Botanic 0 1992 Object of local natural
heritage
12 191.3 Zayarie 38 1992 Reserved area
13 191.5 Dovzhek 76 1992 Reserved area
14 192.5 English oak Botanic 0 1989 Object of local natural
heritage
15 192.5 Oak-wood Botanic 1 1982 Object of local natural
heritage
16 196.8 Khvoshchivka Hydrological 120 1992 Local sanctuary
17 196.9 Kostiuky Hydrological 237 1993 Local sanctuary
18 250.5 English oaks Botanic 0 1995 Object of local natural
heritage
19 251.3 English oak Botanic 0 1995 Object of local natural
heritage
20 255 English oak Botanic 0 1995 Object of local natural
heritage
21 256.4 Shcherbaky Landscape 289 1995 Local sanctuary
22 259.5 Gariachkivsky Forest
Landscape 366 1993 Local sanctuary
23 271.3 Novodykansky Botanic 51 1995 Local sanctuary
24 291.4 English oaks Botanic 0 1975 Object of local natural
heritage
25 292.1 English oaks Botanic 0 1975 Object of local natural
heritage
26 292.2 English oak Botanic 0 1975 Object of local natural
heritage
27 292.6 Oak-wood Botanic 2 1979 Object of local natural
heritage
11
28 293.3 Kotliarevsky Park 5 1970 Local Landscape Heritage
Park
29 293.5 English oaks Botanic 0 1970 Object of local natural
heritage
30 294.7 English oak Botanic 0 1982 Object of local natural
heritage
31 295.8 Park of Elita Scientific Production Association
Botanic 2 1970 Object of local natural
heritage
32 296.2 Park of Teacher’s
Training Institute Agrobiology Station
5 1964 Local Landscape Heritage
Park
33 297.5 English oak Botanic 0 1982 Object of local natural
heritage
34 298.3 English oak Botanic 0 1982 Object of local natural
heritage
35 300.5 English oak Botanic 0 1979 Object of local natural
heritage
36 303.3 Tryby Reserved Area Botanic 5 1979 Object of local natural
heritage
37 313.7 Kulykivsky 25 1975 Local Landscape Heritage
Park
38 320.5 Vilkhivshchynsky Landscape 1,030 1980 National sanctuary
39 324.6 Storozhovy Hydrological 502 1989 Local sanctuary
40 346.3 Lyzniana Balka Landscape 60 1993 Local sanctuary
41 349 Iskrivsky Forest 2,243 1993 Local sanctuary
The maps of forests and protected areas in Poltava Oblast are shown below:
12
13
Therefore, with one exception, the protected areas located in the zone affected by the road
belong to the local category. No impacts additional to the existing ones are expected on the protected areas from construction works and further operation of the motorroad.
3. General Description of the Project
M-03 Motorroad is an important component of Ukraine’s highway network:
In accordance with the predictive estimates, by the year 2026 the traffic volume in the designed section of M-03 Motorroad will increase by almost a factor of three. The largest traffic volume is expected within Boryspil Rayon (almost 47 thousand units reduced to a conditional vehicle/day) and within Poltava detour (almost 65 thousand units reduced to a conditional vehicle/day).
Therefore, if M-03 Motorroad is not overhauled and renovated to conform to Category I and if no new sections are built, the environmental impact of mobile sources of pollution may increase.
The traffic accident rate is another important factor which accounts for the need to renovate the motorroad.
Development of the motorroad includes:
14
- motorroad: a linear system of engineering and auxiliary structures designed for uninterruptible, safe, and convenient traffic of vehicles with standard specifications and proof loads, for provision of national and international passenger and freight transportation;
- engineering structures: overpass bridges, drain pipes, water treatment works, battering walls, etc.;
- auxiliary structures: protective structures and shelter plantations, ramps, etc.
Motorroad Engineering Data (as per DBN В.2.3-4-2000 „Motor Roads”):
L/I Descripiton UOM Critical Parameters Parameters for
Irregular terrain
1. Design speed km/hr 140 110
2. Number of lanes ea. 4.6 4
3. Width of lane m 3.75
4. Width of carriageway m 7.50 – 11.25 7.50
5. Width of verge m 3.90
6. Width of reinforced verge strip m 0.75
7. Width of centre mall m 2.75 - 6 5 - 6
8. Width of reinforced strip on centre mall
m 1.0
9. Width of roadbed m 28.8 – 36.3 28.8
10. Minimum seeing distance:
- for stop 300 250 - for oncoming vehicle
m
500 450
11. Least curve radii horizontal 1,100 700
vertical convex 25,000 13,000 concave
m
7,000 4,000
12. Type of pavement Capital breakstone-mastic bituminous
concrete
13. Design loads on engineering structures А-15, НК-100
Estimations of the sizes of land plots to be alienated for placement of the roadbed will be
based on the designed vertical alignment of the road and the cross profile of the roadbed as accepted in standard and individual designs. The permanent right-of-way will include areas for road interchanges, redevelopment of service lines, and other structures included in the construction documentation. On the plots where the surface drainage systems will be constructed, the right-of-way will be widened appropriately.
The land area of temporary withdrawal is estimated subject to the conditions of accepted construction methods.
The plots of land to be transferred for temporary use include territories allotted for development of roadside reserves, places for stockpiling of vegetation soil and turf and for creation of bypasses, and areas for passage of construction vehicles.
The areas of permanent and temporary alienation must correspond to the standards of land allotment for motorroads (SN (Building Specificaitons) 467-74).
During repair and construction works the territory of allotted lands needs to be cleared from the trees and shrubs of existing forest shelter belt. The quantity and quality parameters of green plantations to be cut down are determined by the Certificates of Green Plantations Inspection. The design includes restoration of green plantations with the quantity parameters not lower than those of
15
the existing ones. The feasibility study includes planting of greenery during architectural styling by landscape group method and compensation planting along the sections laid on the new route.
In order to protect the slopes of roadbed and the centre mall from erosion, they shall be
anchored by sowing grass throughout 0.15 m thick layer of fertile soil. A surface drainage system with gutters, water channels, and chutes will be installed along the
roadbed. In the places where culverts will be installed, the roadbed slopes will be reinforced with concrete slabs near the culvert heads to prevent scour at the points of entry and exit.
Significant amounts of ground for roadbed landfilling will be collected from explored roadside reserves.
The excavated ground suitable for construction of the roadbed will also be used for embankment landfilling.
The vertical alignment is designed to provide for the least restrictions and changes of speed subject to the principles of stitching the elements of horizontal and vertical alignment,
recommendations on architectural and landscape engineering, and preservation, to the maximum extent practicable, of the roadbed elevations of the existing motorroad.
Based on the estimations, nonrigid types of pavement design were recommended. A unified type of three layers of road concrete mix, 23 cm thick in total, was accepted to
renovate the existing pavement.
The skim of pavement shall be recycled to reinforce the pavement, the verges, and the slopes.
Pavement design of the new passage: surface course of bituminous concrete, 5 cm thick, and two bottom courses: the first one of hot dense fine bituminous concrete, Grade I, Type B, 8 cm thick,
and the second one of hot blown-out coarse bituminous concrete, Grade I, 10 cm thick. The verges will be reinforced with two layers of bituminous concrete covering 1.75 m width
from the edge of carriageway under DSTU (State Standard of Ukraine) БВ.2.7-75-98. The remaining part of the verge, 1.25 m wide (1.40 m if a barrier fence is installed and on a road of Category Ib) will be anchored by sowing grass throughout 15 cm thick layer of fertile soil.
In order to provide dependable surface drainage from the carriageway, the cross profile of curb is accepted on the sections which have vertical alignment over 30 ‰ on the embankments higher than 3.0 m and on the sections of concave curves at a distance of 50 m from each side of the vertex.
Water will be drained from the carriageway by means of reinforced concrete water channels
with installation of wasteway channels on the slopes and dashpots near the embankment bed. The designs of aforesaid works are included in the respective bills of work volume and
drawings. Construction of new and rehabilitation of existing engineering structures is planned, including
two-level interchanges and crossings at grade, bridges, overpass bridges, pedestrian crossings, and rectangular and circular culverts of reinforced concrete.
Location and geometry of the engineering structures are determined by the general route of the road, the local hydrological and topographical conditions, and the accepted design at crossings and junctions in different levels.
16
The design includes the following treatment facilities:
Location km, plus
UOM Quantity Water Body
Kyiv Oblast
70+190 ea. 2 the Trubizh River
74+554 ea. 2 the Nedra River
102+432 ea. 2 the Supiy River
117+131 ea. 2 brook
Poltava Oblast
133+538 ea. 2 the Gnyla Orzhytsia River
204+1,091 ea. 2 the Sula River
211+216 ea. 2 brook
242+578 ea. 2 the Khorol River
Detour of Pokrovska Bagachka Village
1+000 ea. 2 brook
Total: ea. 18 —
and noise screens:
Screen length, m Settlement
on the left on the right Total
Location km, plus
Kyiv Oblast
Olexandrivka Village 1,000 — 1,000 km 0+200 – km 1+200
Ivankiv Village 2,800 200 3,000 km 45+000 – km 48+000
Bzov Village 150 150 300 km 58+250 – km 58+400
Borshchiv Village — 1,500 1,500 km 67+200 – km 68+700
Semenivka Village — 500 500 km 81+150 – km 81+650
Snizhkiv Village 1,000 1,000 2,000 km 100+100 – km 101+100
Poltava Oblast
Olexiyivka Village 1,000 100 2,000 km 133+000 – km 134+000
Olexandrivka Village 1,500 1,500 3,000 km 146+000 – km 147+500
Mohylivshchyna Village
– 500 500 km 148+500 – km 149+000
Pyriatyn Town 1,000 – 1,000 km 155+720 – km 156+720
Vyly Village 500 500 1,000 km 183+500 – km 184+000
Pyshne Village 500 500 1,000 km 187+300 – km 188+000
Vilshanka Village 5,000 5,000 10,000 km 199+200 – km 204+200
Voinykha Village 1,700 1,700 3,400 km 210+100 – km 211+800
Kovtuny Village 1,200 1,200 2,400 km 229+000 – km 230+200
Khorol Town 500 2,000 2,500 km 237+000 – km 239+000
Chapayivka Village – 800 800 km 260+220 – km 261+020
Total: 17,850 17,150 35,900 –
The Feasibility Study includes construction of 34 interchanges in two levels, including three interchanges on Poltava detour.
17
The design approaches include stationary lamplight at the road interchanges in different levels.
In view of envisaged increase of traffic, the design approaches accept an automated highway traffic control system, which includes automated highway access control system, traffic condition control, including speed limits depending on natural conditions, control of traffic emergency service and the services of regular and winter road maintenance, etc.
The production residue and construction waste will be stockpiled in specially assigned places for temporary storing and then removed from the construction site.
In order to ensure the proper level of traffic safety, the design includes a number of measures and structural concepts which will contribute to better operation of the road and vehicles.
Rehabilitation of M-03 Motorroad will result in the following benefits:
- the traffic capacity will increase, the traffic handling costs will go down, and the travel time of passengers and cargoes will be reduced;
- the local, regional, and national transport infrastructure will be improved and conditions will be created to improve operating characteristics of vehicles;
- transport, economic, and trade links among the oblasts and across Ukraine as a whole and international links will be intensified;
- negative impact on the natural and technological environment will be reduced and environmental safety will be enhanced due to improvement of the riding qualities, provision for optimal traffic speed, and implementation of nature-conservative measures included in the project;
- traffic safety will be increased; - new jobs will be created both during construction and during further operation of the
motorway, its infrastructure, and the appropriate service facilities. After completion of the rehabilitation and commissioning of the road, all the negative
environmental impacts will be reduced significantly in comparison with the present status due to implementation of nature-conservative (protection, restoration, compensation, preservation) measures included in the design, which is corroborated by the predictive estimates described in the following section.
4. ASSESSMENT OF ENVIRONMENTAL IMPACTS FROM THE PROJECT
The estimates of noise, emissions, and pollutant dispersal caused by the traffic flow on the
designed road were made by means of specialized software and GIS technologies based on the data on local conditions and envisaged future traffic volume.
The pollutant dispersal was estimated for open territory and the obtained values are the
highest concentrations of the pollutants in the most adverse weather conditions: wind speed: 0.5 m/c, wind direction: frontal from the road towards the assessed point.
18
Averaged predictive estimates of emissions in Kyiv Oblast:
Motor Transport Emissions (predictive estimate)*
at the border of affected area (3,000 m) at the border of safety buffer zone (300
m)
2006 2026 2006 2026 Section of Road km-km
without rehabilita
tion
after rehabilita
tion
without rehabilita
tion
after rehabilita
tion
without rehabilita
tion
after rehabilita
tion
without rehabilita
tion
after rehabilita
tion
СО, mg/m3 (single MPC: 5.0 mg/m
3)
End of Boryspil detour (R-03) to junction of Zgurivka-Berezan
Motorroad
45+000 -
76+015 0.0028 0.0025 0.0080 0.0072 0.0359 0.0323 0.1035 0.0931
Junction of Zgurivka-Berezan Motorroad to road towards Yagotyn
76+015 -
103+690
0.0025 0.0022 0.0073 0.0066 0.0319 0.0287 0.0942 0.0848
Road towards Yagotyn to Poltava Oblast border
103+690 -
126+160
0.0022 0.0020 0.0067 0.0060 0.0285 0.0256 0.0866 0.0780
NОх, mg/m3 (single MPC: 0.085 мg/m3)
End of Boryspil
detour (R-03) to junction of Zgurivka-Berezan Motorroad
45+000 -
76+015
0.0002 0.0002 0.0005 0.0005 0.0024 0.0022 0.0069 0.0062
Junction of Zgurivka-Berezan Motorroad to road towards Yagotyn
76+015 -
103+690
0.0002 0.0001 0.0005 0.0004 0.0021 0.0019 0.0063 0.0057
Road towards Yagotyn to
Poltava Oblast border
103+690 -
126+160
0.0001 0.0001 0.0004 0.0004 0.0019 0.0017 0.0058 0.0052
SО2, mg/m3 (single MPC: 0.15 мg/m3)
End of Boryspil detour (R-03) to
junction of Zgurivka-Berezan Motorroad
45+000
- 76+015
0.000009 0.000008 0.000027 0.000024 0.000120 0.000108 0.000345 0.000310
Junction of Zgurivka-Berezan
Motorroad to road towards Yagotyn
76+015 -
103+690
0.000008 0.000007 0.000024 0.000022 0.000106 0.000096 0.000314 0.000283
Road towards Yagotyn to Poltava Oblast
border
103+690 -
126+16
0
0.000007 0.000007 0.000022 0.000020 0.000095 0.000085 0.000289 0.000260
CxHy, mg/m3 (single MPC: 1.0 мg/m3)
End of Boryspil detour (R-03) to junction of
Zgurivka-Berezan Motorroad
45+000 -
76+015
0.0005 0.0004 0.0013 0.0012 0.0060 0.0054 0.0172 0.0155
19
Junction of Zgurivka-Berezan Motorroad to road towards Yagotyn
76+015 -
103+690
0.0004 0.0004 0.0012 0.0011 0.0053 0.0048 0.0157 0.0141
Road towards Yagotyn to Poltava Oblast border
103+690 -
126+160
0.0004 0.0003 0.0011 0.0010 0.0047 0.0043 0.0144 0.0130
Carbon black, µg/m3 (single MPC: 300 µg/m3)
End of Boryspil detour (R-03) to junction of Zgurivka-Berezan
Motorroad
45+000 -
76+015
0.0172 0.0155 0.0494 0.0445 0.2217 0.1995 0.6383 0.5744
Junction of Zgurivka-Berezan Motorroad to road towards Yagotyn
76+015 -
103+690
0.0152 0.0137 0.0450 0.0405 0.1969 0.1772 0.5812 0.5231
Road towards
Yagotyn to Poltava Oblast border
103+69
0 - 126+16
0
0.0136 0.0123 0.0414 0.0373 0.1757 0.1582 0.5343 0.4809
Benzpyrene, µg/m3 (average daily MPC: 0.001 µg/m3)
End of Boryspil
detour (R-03) to junction of Zgurivka-Berezan Motorroad
45+000 -
76+015
0.00000116
0.00000104
0.00000334
0.00000301
0.00001498
0.00001348
0.00004312
0.00003881
Junction of
Zgurivka-Berezan Motorroad to road towards Yagotyn
76+015
- 103+69
0
0.00000103
0.00000093
0.00000304
0.00000274
0.00001330
0.00001197
0.00003927
0.00003534
Road towards Yagotyn to
Poltava Oblast border
103+690 -
126+160
0.00000092
0.00000083
0.00000280
0.00000252
0.00001187
0.00001069
0.00003610
0.00003249
Pb (intensity of atmospheric emission), µg/m3 (single MPC: 1.0 µg/m
3)
End of Boryspil detour (R-03) to
junction of Zgurivka-Berezan Motorroad
45+000
- 76+015
0.0033 0.0030 0.0096 0.0087 0.0431 0.0388 0.1242 0.1118
Junction of Zgurivka-Berezan Motorroad to road towards Yagotyn
76+015 -
103+690
0.0030 0.0027 0.0088 0.0079 0.0383 0.0345 0.1131 0.1018
Road towards Yagotyn to Poltava Oblast
border
103+690 -
126+16
0
0.0026 0.0024 0.0081 0.0072 0.0342 0.0308 0.1040 0.0936
20
Averaged predictive estimates of emissions in Poltava Oblast:
Motor Transport Emissions (predictive estimate)*
at the border of affected area (3,000 m) at the border of safety buffer zone (300 m)
2006 2026 2006 2026 Section of Road km-km
without rehabilita
tion
after rehabilita
tion
without rehabilita
tion
after rehabilita
tion
without rehabilita
tion
after rehabilita
tion
without rehabilita
tion
after rehabilita
tion
СО, mg/m3 (single MPC: 5.0 mg/m3)
M-03 – Drabiv-Zolotonosha Motorroad (Т-24-15) (Kyiv Oblast
border) to crossing with Pyriatyn-Grebinka Motorroad
km 126+160 -
km 156+600
0.0022 0.0020 0.0067 0,0061 0,0285 0,0256 0,0868 0,0781
Crossing with Pyriatyn-Grebinka Motorroad to start of Lubny detour
km 156+600
– km 192+100
0.0022 0.0019 0.0067 0,0060 0,0280 0,0252 0,0861 0,0775
Lubny detour
km 192+100
– km 207+100
0.0019 0.0017 0.0059 0,0053 0,0243 0,0218 0,0756 0,0680
End of Lubny detour to start of
Khorol detour
km 207+100
– km
235+840
0.0020 0.0018 0.0064 0,0057 0,0262 0,0235 0,0821 0,0739
Khorol detour
km 235+840
– km 243+720
0.0019 0.0017 0,0061 0.0055 0.0243 0.0219 0.0784 0.0705
End of Khorol
detour to junction of (Lubny-Myrgorod-Opishnia) -
Shyshaky-Podil Motorroad (Т-17-20)
km 243+720
– km
286+285
0.0020 0.0018 0.0063 0.0057 0.0260 0.0234 0.0816 0.0734
Junction of (Lubny-Myrgorod-
Opishnia) - Shyshaky-Podil Motorroad (Т-17-20) to Dykanka-
Reshetylivka Motorroad (Т-17-21)
km 286+285
– km 306+628
0.0022 0.0020 0.0066 0.0060 0.0283 0.0254 0.0857 0.0771
Crossing with Dykanka-Reshetylivka Motorroad (Т-17-21) to Poltava City
km
306+628- km
336+873
0.0022 0.0020 0.0066 0.0060 0.0290 0.0261 0.0856 0.0770
Poltava City
km 336+873
– km 340+961
0.0042 0.0037 0.0111 0.0100 0.0537 0.0483 0.1433 0.1290
21
Poltava City to Poltava-Krasnograd Motorroad (R-11)
km 340+961
– km 362+500
0.0024 0.0022 0.0057 0.0052 0.0309 0.0278 0.0740 0.0666
Poltava-Krasnograd Motorroad (R-11) to Kharkiv Oblast
border
km 362+500
– km
395+064
0.0018 0.0016 0.0046 0.0042 0.0237 0.0213 0.0598 0.0538
NОх, mg/m3 (single MPC: 0.085 мg/m3)
M-03 – Drabiv-Zolotonosha Motorroad (Т-24-
15) (Kyiv Oblast border) to crossing with Pyriatyn-Grebinka
Motorroad
km
126+160 - km
156+600
0.0001 0.0001 0.0004 0.0004 0.0019 0.0017 0.0058 0.0052
Crossing with Pyriatyn-Grebinka Motorroad to start of Lubny detour
km 156+600
– km 192+100
0.0001 0.0001 0.0004 0.0004 0.0019 0.0017 0.0057 0.0052
Lubny detour
km
192+100 – km
207+100
0.0001 0.0001 0.0004 0.0004 0.0016 0.0015 0.0050 0.0045
End of Lubny
detour to start of Khorol detour
km 207+100
– km 235+840
0.0001 0.0001 0.0004 0.0004 0.0017 0.0016 0.0055 0.0049
Khorol detour
km 235+840
– km
243+720
0.0001 0.0001 0.0004 0.0004 0.0016 0.0015 0.0052 0.0047
End of Khorol detour to junction of (Lubny-Myrgorod-
Opishnia) - Shyshaky-Podil Motorroad (Т-17-20)
km 243+720
– km 286+285
0.0001 0.0001 0.0004 0.0004 0.0017 0.0016 0.0054 0.0049
Junction of (Lubny-Myrgorod-Opishnia) - Shyshaky-Podil Motorroad (Т-17-
20) to Dykanka-Reshetylivka Motorroad (Т-17-21)
km 286+285
– km 306+628
0.0001 0.0001 0.0004 0.0004 0.0019 0.0017 0.0057 0.0051
Crossing with
Dykanka-Reshetylivka Motorroad (Т-17-21) to Poltava City
km 306+628-
km 336+873
0.0001 0.0001 0.0004 0.0004 0.0019 0.0017 0.0057 0.0051
Poltava City
km
336+873 – km
340+961
0.0003 0.0002 0.0007 0.0007 0.0036 0.0032 0.0096 0.0086
22
Poltava City to Poltava-Krasnograd Motorroad (R-11)
km 340+961
– km 362+500
0.0002 0.0001 0.0004 0.0003 0.0021 0.0019 0.0049 0.0044
Poltava-Krasnograd Motorroad (R-11) to Kharkiv Oblast
border
km 362+500
– km
395+064
0.0001 0.0001 0.0003 0.0003 0.0016 0.0014 0.0040 0.0036
SО2, mg/m3 (single MPC: 0.15 мg/m3)
M-03 – Drabiv-Zolotonosha Motorroad (Т-24-
15) (Kyiv Oblast border) to crossing with Pyriatyn-Grebinka
Motorroad
km
126+160 - km
156+600
0.000007 0.000007 0.000022 0.000020 0.000095 0.000085 0.000289 0.000260
Crossing with Pyriatyn-Grebinka Motorroad to start of Lubny detour
km 156+600
– km 192+100
0.000007 0.000006 0.000022 0.000020 0.000093 0.000084 0.000287 0.000258
Lubny detour
km
192+100 – km
207+100
0.000006 0.000006 0.000020 0.000018 0.000081 0.000073 0.000252 0.000227
End of Lubny
detour to start of Khorol detour
km 207+100
– km 235+840
0.000007 0.000006 0.000021 0.000019 0.000087 0.000078 0.000274 0.000246
Khorol detour
km 235+840
– km
243+720
0.000006 0.000006 0.000020 0.000018 0.000081 0.000073 0.000261 0.000235
End of Khorol detour to junction of (Lubny-Myrgorod-
Opishnia) - Shyshaky-Podil Motorroad (Т-17-20)
km 243+720
– km 286+285
0.000007 0.000006 0.000021 0.000019 0.000087 0.000078 0.000272 0.000245
Junction of (Lubny-Myrgorod-Opishnia) - Shyshaky-Podil Motorroad (Т-17-
20) to Dykanka-Reshetylivka Motorroad (Т-17-21)
km 286+285
– km 306+628
0.000007 0.000007 0.000022 0.000020 0.000094 0.000085 0.000286 0.000257
Crossing with
Dykanka-Reshetylivka Motorroad (Т-17-21) to Poltava City
km 306+628-
km 336+873
0.000007 0.000007 0.000022 0.000020 0.000097 0.000087 0.000285 0.000257
Poltava City
km
336+873 – km
340+961
0.000014 0.000012 0.000037 0.000033 0.000179 0.000161 0.000478 0.000430
23
Poltava City to Poltava-Krasnograd Motorroad (R-11)
km 340+961
– km 362+500
0.000008 0.000007 0.000019 0.000017 0.000103 0.000093 0.000247 0.000222
Poltava-Krasnograd Motorroad (R-11) to Kharkiv Oblast
border
km 362+500
– km
395+064
0.000006 0.000005 0.000015 0.000014 0.000079 0.000071 0.000199 0.000179
CxHy, mg/m3 (single MPC: 1.0 мg/m3)
M-03 – Drabiv-Zolotonosha Motorroad (Т-24-
15) (Kyiv Oblast border) to crossing with Pyriatyn-Grebinka
Motorroad
km
126+160 - km
156+600
0.0004 0.0003 0.0011 0.0010 0.0047 0.0043 0.0145 0.0130
Crossing with Pyriatyn-Grebinka Motorroad to start of Lubny detour
km 156+600
– km 192+100
0.0004 0.0003 0.0011 0.0010 0.0047 0.0042 0.0144 0.0129
Lubny detour
km
192+100 – km
207+100
0.0003 0.0003 0.0010 0.0009 0.0040 0.0036 0.0126 0.0113
End of Lubny
detour to start of Khorol detour
km 207+100
– km 235+840
0.0003 0.0003 0.0011 0.0010 0.0044 0.0039 0.0137 0.0123
Khorol detour
km 235+840
– km
243+720
0.0003 0.0003 0.0010 0.0009 0.0041 0.0036 0.0131 0.0118
End of Khorol detour to junction of (Lubny-Myrgorod-
Opishnia) - Shyshaky-Podil Motorroad (Т-17-20)
km 243+720
– km 286+285
0.0003 0.0003 0.0011 0.0009 0.0043 0.0039 0.0136 0.0122
Junction of (Lubny-Myrgorod-Opishnia) - Shyshaky-Podil Motorroad (Т-17-
20) to Dykanka-Reshetylivka Motorroad (Т-17-21)
km 286+285
– km 306+628
0.0004 0.0003 0.0011 0.0010 0.0047 0.0042 0.0143 0.0129
Crossing with
Dykanka-Reshetylivka Motorroad (Т-17-21) to Poltava City
km 306+628-
km 336+873
0.0004 0.0003 0.0011 0.0010 0.0048 0.0043 0.0143 0.0128
Poltava City
km
336+873 – km
340+961
0.0007 0.0006 0.0018 0.0017 0.0089 0.0081 0.0239 0.0215
24
Poltava City to Poltava-Krasnograd Motorroad (R-11)
km 340+961
– km 362+500
0.0004 0.0004 0.0010 0.0009 0.0052 0.0046 0.0123 0.0111
Poltava-Krasnograd Motorroad (R-11) to Kharkiv Oblast
border
km 362+500
– km
395+064
0.0003 0.0003 0.0008 0.0007 0.0039 0.0035 0.0100 0.0090
Carbon black, µg/m3 (single MPC: 300 µg/m3)
M-03 – Drabiv-Zolotonosha Motorroad (Т-24-
15) (Kyiv Oblast border) to crossing with Pyriatyn-Grebinka
Motorroad
km
126+160 - km
156+600
0.0136 0.0122 0.0415 0.0373 0.1756 0.1580 0.5354 0.4819
Crossing with Pyriatyn-Grebinka Motorroad to start of Lubny detour
km 156+600
– km 192+100
0.0134 0.0120 0.0411 0.0370 0.1725 0.1552 0.5310 0.4779
Lubny detour
km
192+100 – km
207+100
0.0116 0.0104 0.0361 0.0325 0.1496 0.1346 0.4659 0.4193
End of Lubny
detour to start of Khorol detour
km 207+100
– km 235+840
0.0125 0.0112 0.0392 0.0353 0.1613 0.1452 0.5065 0.4559
Khorol detour
km 235+840
– km
243+720
0.0116 0.0104 0.0374 0.0337 0.1499 0.1349 0.4834 0.4350
End of Khorol detour to junction of (Lubny-Myrgorod-
Opishnia) - Shyshaky-Podil Motorroad (Т-17-20)
km 243+720
– km 286+285
0.0124 0.0112 0.0390 0.0351 0.1606 0.1446 0.5032 0.4529
Junction of (Lubny-Myrgorod-Opishnia) - Shyshaky-Podil Motorroad (Т-17-
20) to Dykanka-Reshetylivka Motorroad (Т-17-21)
km 286+285
– km 306+628
0.0135 0.0122 0.0409 0.0368 0.1744 0.1569 0.5283 0.4755
Crossing with
Dykanka-Reshetylivka Motorroad (Т-17-21) to Poltava City
km 306+628-
km 336+873
0.0138 0.0125 0.0409 0.0368 0.1787 0.1609 0.5278 0.4750
Poltava City
km
336+873 – km
340+961
0.0256 0.0231 0.0684 0.0616 0.3310 0.2979 0.8836 0.7952
25
Poltava City to Poltava-Krasnograd Motorroad (R-11)
km 340+961
– km 362+500
0.0148 0.0133 0.0353 0.0318 0.1907 0.1717 0.4562 0.4106
Poltava-Krasnograd Motorroad (R-11) to Kharkiv Oblast
border
km 362+500
– km
395+064
0.0113 0.0102 0.0286 0.0257 0.1459 0.1313 0.3689 0.3320
Benzpyrene, µg/m3 (average daily MPC: 0.001 µg/m3)
M-03 – Drabiv-Zolotonosha Motorroad (Т-24-
15) (Kyiv Oblast border) to crossing with Pyriatyn-Grebinka
Motorroad
km
126+160 - km
156+600
0.00000092
0.00000083
0.00000280
0.00000252
0.00001186
0.00001068
0.00003617
0.00003256
Crossing with Pyriatyn-Grebinka Motorroad to start of Lubny detour
km 156+600
– km 192+100
0.00000090
0.00000081
0.00000278
0.00000250
0.00001165
0.00001049
0.00003588
0.00003229
Lubny detour
km
192+100 – km
207+100
0.00000078
0.00000070
0.00000244
0.00000219
0.00001011
0.00000910
0.00003148
0.00002833
End of Lubny
detour to start of Khorol detour
km 207+100
– km 235+840
0.0000008
4
0.0000007
6
0.0000026
5
0.0000023
9
0.0000109
0
0.0000098
1
0.0000342
2
0.0000308
0
Khorol detour
km 235+840
– km
243+720
0.0000007
8
0.0000007
1
0.0000025
3
0.0000022
8
0.0000101
3
0.0000091
1
0.0000326
6
0.0000293
9
End of Khorol detour to junction of (Lubny-Myrgorod-
Opishnia) - Shyshaky-Podil Motorroad (Т-17-20)
km 243+720
– km 286+285
0.0000008
4
0.0000007
6
0.0000026
3
0.0000023
7
0.0000108
5
0.0000097
7
0.0000340
0
0.0000306
0
Junction of (Lubny-Myrgorod-Opishnia) - Shyshaky-Podil Motorroad (Т-17-
20) to Dykanka-Reshetylivka Motorroad (Т-17-21)
km 286+285
– km 306+628
0.00000091
0.00000082
0.00000277
0.00000249
0.00001178
0.00001060
0.00003570
0.00003213
Crossing with
Dykanka-Reshetylivka Motorroad (Т-17-21) to Poltava City
km 306+628-
km 336+873
0.00000094
0.00000084
0.00000276
0.00000249
0.00001208
0.00001087
0.00003566
0.00003209
Poltava City
km
336+873 – km
340+961
0.00000173
0.00000156
0.00000462
0.00000416
0.00002237
0.00002013
0.00005970
0.00005373
26
Poltava City to Poltava-Krasnograd Motorroad (R-11)
km 340+961
– km 362+500
0.0000010
0
0.0000009
0
0.0000023
9
0.0000021
5
0.0000128
9
0.0000116
0
0.0000308
3
0.0000277
4
Poltava-Krasnograd Motorroad (R-11) to Kharkiv Oblast
border
km 362+500
– km
395+064
0.00000076
0.00000069
0.00000193
0.00000174
0.00000986
0.00000887
0.00002493
0.00002243
Pb (intensity of atmospheric emission), µg/m3 (single MPC: 1.0 µg/m3)
M-03 – Drabiv-Zolotonosha Motorroad (Т-24-
15) (Kyiv Oblast border) to crossing with Pyriatyn-Grebinka
Motorroad
km
126+160 - km
156+600
0.0026 0.0024 0.0081 0.0073 0.0342 0.0308 0.1042 0.0938
Crossing with Pyriatyn-Grebinka Motorroad to start of Lubny detour
km 156+600
– km 192+100
0.0026 0.0023 0.0080 0.0072 0.0336 0.0302 0.1033 0.0930
Lubny detour
km
192+100 – km
207+100
0.0023 0.0020 0.0070 0.0063 0.0291 0.0262 0.0907 0.0816
End of Lubny
detour to start of Khorol detour
km 207+100
– km 235+840
0.0024 0.0022 0.0076 0.0069 0.0314 0.0282 0.0986 0.0887
Khorol detour
km 235+840
– km
243+720
0.0023 0.0020 0.0073 0.0066 0.0292 0.0262 0.0941 0.0847
End of Khorol detour to junction of (Lubny-Myrgorod-
Opishnia) - Shyshaky-Podil Motorroad (Т-17-20)
km 243+720
– km 286+285
0.0024 0.0022 0.0076 0.0068 0.0313 0.0281 0.0979 0.0881
Junction of (Lubny-Myrgorod-Opishnia) - Shyshaky-Podil Motorroad (Т-17-
20) to Dykanka-Reshetylivka Motorroad (Т-17-21)
km 286+285
– km 306+628
0.0026 0.0024 0.0080 0.0072 0.0339 0.0305 0.1028 0.0925
Crossing with
Dykanka-Reshetylivka Motorroad (Т-17-21) to Poltava City
km 306+628-
km 336+873
0.0027 0.0024 0.0080 0.0072 0.0348 0.0313 0.1027 0.0924
Poltava City
km
336+873 – km
340+961
0.0050 0.0045 0.0133 0.0120 0.0644 0.0580 0.1719 0.1547
27
Poltava City to Poltava-Krasnograd Motorroad (R-11)
km 340+961
– km 362+500
0.0029 0.0026 0.0069 0.0062 0.0371 0.0334 0.0888 0.0799
Poltava-Krasnograd Motorroad (R-11) to Kharkiv Oblast
border
km 362+500
– km
395+064
0.0022 0.0020 0.0056 0.0050 0.0284 0.0256 0.0718 0.0646
* - The estimates are made without taking into account any natural (relief, plants) and artificial (buildings) obstacles in the way of emissions.
Therefore, the estimates show that during the next 20 years emissions will grow (with the growth of traffic concentration), but they will not reach the MPC, be it with or without rehabilitation. It is also obvious that all the emissions will be lower if the rehabilitation is performed than if it is not.
In adverse weather conditions (calm, low inversions, etc.) concentrations of pollutants in the atmosphere of roadside plots may rise above the estimated mean values.
The estimates of noise load caused by the traffic flow on the designed road were made by means of specialized software. The input parameters of estimates are described in the previous section.
Averaged predictive estimates of noise intensity in Kyiv Oblast:
Noise, decibel (permissible equivalent level for inhabited area: 55 decibel)*
at the border of affected area (3,000 m) at the border of safety buffer zone (300 m)
2006 2026 2006 2026 Section of Road
without rehabilitat
ion
after rehabilitati
on
without rehabilitati
on
after rehabilitati
on
without rehabilitati
on
after rehabilitati
on
without rehabilitati
on
after rehabilitati
on
End of Boryspil detour (R-03) to
junction of Zgurivka-Berezan Motorroad
45.2 42.7 54.2 46.7 56.5 54.0 65.5 58.0
Junction of Zgurivka-Berezan
Motorroad to road towards Yagotyn
44.7 42.2 53.9 46.4 56.0 53.5 65.1 57.6
Road towards Yagotyn to Poltava Oblast
border
44.3 41.8 53.6 46.1 55.6 53.1 64.8 57.3
Averaged predictive estimates of noise intensity in Poltava Oblast:
Noise, decibel (permissible equivalent level for inhabited area: 55 decibel)*
at the border of affected area (3,000 m) at the border of safety buffer zone (300 m)
2006 2026 2006 2026 Section of Road without
rehabilitation
after
rehabilitation
without
rehabilitation
after
rehabilitation
without
rehabilitation
after
rehabilitation
without
rehabilitation
after
rehabilitation
M-03 – Drabiv-
Zolotonosha Motorroad (Т-24-
44.3 41.8 53.6 46.1 55.6 53.1 64.8 57.3
28
15) (Kyiv Oblast border) to crossing with Pyriatyn-Grebinka Motorroad
Crossing with Pyriatyn-Grebinka Motorroad to start
of Lubny detour
44.2 41.7 53.5 46.0 55.5 53.0 64.8 57.3
Lubny detour 43.7 41.2 53.0 45.5 54.9 52.4 64.3 56.8
End of Lubny detour to start of Khorol detour
44.0 41.5 53.4 45.9 55.2 52.7 64.6 57.1
Khorol detour 43.7 41.2 53.2 45.7 55.0 52.5 64.4 56.9
End of Khorol detour to junction of (Lubny-Myrgorod-
Opishnia) - Shyshaky-Podil Motorroad (Т-17-20)
44.0 41.5 53.3 45.8 55.2 52.7 64.6 57.1
Junction of
(Lubny-Myrgorod-Opishnia) - Shyshaky-Podil
Motorroad (Т-17-20) to Dykanka-Reshetylivka Motorroad (Т-17-21)
44.3 41.8 53.5 46.0 55.5 53.0 64.8 57.3
Crossing with Dykanka-Reshetylivka Motorroad (Т-17-
21) to Poltava City
44.4 41.9 53.5 46.0 55.6 53.1 64.8 57.3
Poltava City 46.7 44.2 55.5 48.0 58.0 55.5 66.7 59.2
Poltava City to Poltava-
Krasnograd Motorroad (R-11)
44.6 42.1 53.0 45.5 55.9 53.4 64.2 56.7
Poltava-Krasnograd Motorroad (R-11) to Kharkiv Oblast border
43.6 41.1 52.1 44.6 54.9 52.4 63.4 55.9
* - The estimates are made without taking into account any natural (relief, plants) and artificial (buildings) obstacles in the way of noise.
As we can see from the estimates, in 2026, if the traffic concentration corresponds to the predictions and if no special noise protection is applied (noise screens, forest shelter belts, etc.), the
levels of acoustic load at the border of safety buffer zone will exceed the MPC (55 decibel) to some extent. The noise levels will be lower if the rehabilitation is performed than if it is not.
29
It is noteworthy that the settlements along the road are mostly rural-type developments established quite long ago. The survey revealed that actually all the homesteads near the road have natural protection against noise, such as perennial plants (fruit- and other trees). Therefore, the actual
noise levels will be quite lower than the estimated ones. Moreover, the outskirts of settlements located at a distance of less than 100 m from the road must have additional protection in a form three-row forest shelter belt with several rows of bushes.
Noise barrier panels will be installed in the places specified in the design. Such system of protection will allow to reduce noise nuisance of the road to the limits permissible by the sanitary code.
The table below includes estimated noise intensity at the borders of developed areas in Kyiv Oblast settlements with the specified places of obligatory noise-protection measures:
2006 2026
at the border of developed area
Settlement
Ray
on
Are
a, k
m2
D
ista
nce
fro
m t
he
beg
inn
ing o
f ro
ad,
m
without rehabilitation
after rehabilitation
without rehabilitation
after rehabilitation
Ivankiv 9.19457 600 61.4 58.9 70.4 62.9
Bziv 3.46603 13,500 60.8 58.3 69.8 62.3
Borshchiv 1.84954 25,100 61.4 58.9 70.4 62.9
Berezan 36.3423 31,300 61.4 58.9 70.4 62.9
Semenivka
Bory
spil
3.21992 37,000 60.9 58.4 70.1 62.6
Panfyly 2.45766 56,100 60.9 58.4 70.1 62.6
Yagotyn 8.62092 58,400 60.9 58.4 70.1 62.6
Nychyporivka 4.62062 58,800 55.2 52.7 64.3 56.8
Bogdanivka
Yag
oty
n
3.29562 72,700 59.9 57.4 69.2 61.7
Installation of noise screens – reduction of noise to 30 decibel *
70.0
59.0 Protective green plantations (forest shelter belts: 3-4 rows of trees with
bushes) – reduction of noise by 8-10 decibel
The table below includes estimated noise intensity at the borders of developed areas in Poltava Oblast settlements with the specified places of obligatory noise-protection measures:
2006 2026
at the border of developed area
L/I
Settlement
Ray
on
Are
a, k
m2
D
ista
nce
fro
m t
he
beg
inn
ing o
f ro
ad,
m
without rehabilitation
after rehabilitation
without rehabilitation
after rehabilitation
1 Olexiyivka Grebinka 2.47008 87,800 60.5 58.0 69.8 62.3
9 Victoria 1.52891 94,100 56.2 53.7 65.4 57.9
10 Olexandrivka 0.835162 101,400 60.5 58.0 69.8 62.3
11 Mohylivshchyna 0.250748 104,000 60.5 58.0 69.8 62.3
14 Pyriatyn 9.64031 113,000 60.5 58.0 69.8 62.3
16 Velyka Krucha
Pyriatyn
2.34882 115,900 60.4 57.9 69.7 62.2
22 Vyly Lubny 0.514207 138,800 60.4 57.9 69.7 62.2
30
29 Лубни 21.6658 151,400 54.2 51.7 63.5 56.0
31 Vilshanka 1.58223 154,800 59.9 57.4 69.2 61.7
36 Voinykha
1.08804 165,300 60.2 57.7 69.6 62.1
44 Pokrovska
Bagachka 4.04123 177,900 60.2 57.7 69.6 62.1
45 Nastasivka 0.79673 181,200 60.2 57.7 69.6 62.1
47 Kovtuny 1.37346 184,300 60.2 57.7 69.6 62.1
52 Lobkova Balka 0.868585 186,700 60.2 57.7 69.6 62.1
57 Khorol 12.449841 193,400 59.9 57.4 69.4 61.9
61 Vyshniaky
Khorol
3.75246 198,500 54.4 51.9 63.8 56.3
72 Chapayivka 1.670900 215,000 60.2 57.7 69.5 62.0
77 Shyroke 0.580100 220,700 60.2 57.7 69.5 62.0
81 Sydorivshchyna 0.596820 227,700 60.2 57.7 69.5 62.0
83 Morozivshchyna 0.633754 229,500 60.2 57.7 69.5 62.0
85 Krasnogorivka 2.109023 231,100 60.2 57.7 69.5 62.0
87 Bilotserkivka 4.769026 233,500 60.2 57.7 69.5 62.0
92 Konoplianka 0.582707 239,800 60.2 57.7 69.5 62.0
93 Podil
Vel
yka
Bag
ach
ka
3.107003 241,100 60.2 57.7 69.5 62.0
96 Lobachi 1.958733 248,400 60.5 58.0 69.7 62.2
100 Glyboka Balka 2.419821 253,500 60.5 58.0 69.7 62.2
103 Reshetylivka 10.717196 259,600 60.5 58.0 69.7 62.2
113 Nova Dykanka
Reshetylivka
0.764894 269,200 60.6 58.1 69.7 62.2
115 Tsyganske 0.936365 273,700 60.6 58.1 69.7 62.2
122 Karpusi 0.766161 277,700 56.2 53.7 65.4 57.9
124 Abazivka 1.732628 278,900 60.6 58.1 69.7 62.2
134 Myltsi 2.837861 287,600 62.9 60.4 71.7 64.2
137 Govtvianchyk 0.153447 289,800 60.2 57.7 69.0 61.5
138 Gorbanivka 0.585691 291,200 62.9 60.4 71.7 64.2
140 Poltava 77.131748 294,500 62.9 60.4 71.7 64.2
145 Nyzhni Mlyny 0.710739 297,800 62.9 60.4 71.7 64.2
146 Kopyly 1.285953 299,500 62.9 60.4 71.7 64.2
148 Tereshky 2.006194 300,000 58.6 56.1 67.4 59.9
158 Davydivka 0.600306 308,000 55.1 52.6 63.4 55.9
165 Male Ladyzhyne
Polt
ava
0.951129 320,000 59.8 57.3 68.3 60.8
169 Zelenkivka 2.947691 329,700 59.8 57.3 68.3 60.8
170 Voinivka 1.984649 331,700 59.8 57.3 68.3 60.8
173 Novofedorivka 2.220956 336,800 59.8 57.3 68.3 60.8
175 Chutove
Chutove
10.281613 341,900 59.8 57.3 68.3 60.8
Installation of noise screens – reduction of noise to 30 decibel *
70.0
59.0 Protective green plantations (forest shelter belts: 3-4 rows of trees with bushes) –
reduction of noise by 8-10 decibel
In accordance with the current standards (VBN В.2.3-218-007-98), the right-of-way shall be 30 m for Category I roads. Within the right-of-way, sanitary standards of environmental pollution are always exceeded and any agricultural activity is excluded. The design parameters of pollution in the right-of-way at different predictive volumes of traffic at present and in 20 years show that noise and pollution of air and ground with lead compounds may exceed the MPC (average daily and single).
Emissions within the right-of-way in Kyiv Oblast:
Density of Traffic, conditional vehicle/day
Traffic Noise, decibel CO, mg/m3
31
2006 2006 prognosis for 2026 2006 prognosis for 2026
prognosis for 2026 Noise exposure equivalent limit for inhabited
area: 55 decibel (day), 45 decibel (night) MPC: 5.0 mg/m3 (single); 3 mg/m3 (average daily). Hazard Class: 4
16,270 46,850 63.4 72.5 0.1580 0.4549
14,450 42,660 63.0 72.1 0.1403 0.4142
12,900 39,220 62.6 71.8 0.1253 0.3808
NOx, mg/m3 SO2, mg/m
3 CxHy, mg/m
3
2006 prognosis for
2026 2006 prognosis for 2026 2006
prognosis for
2026
MPC: 0.085 mg/m3 (single); 0.04 mg/m3 (average daily). Hazard Class: 2
MPC: 0.15 (single); 0.05 mg/m3 (average daily). Hazard Class: 3
MPC (single) – 1.0 mg/m3. Hazard Class: 4
0.010532 0.030327 0.000527 0.001516 0.02633 0.07582
0.009354 0.027615 0.000468 0.001381 0.02338 0.06904
0.008350 0.025388 0.000418 0.001269 0.02088 0.06347
Carbon black, µg/m3 Benzpyrene, µg/m
3
Pb (intensity of atmospheric emission), µg/m3
2006 prognosis for
2026 2006
prognosis for 2026
2006 prognosis for 2026
MPC: 150 µg/m3 (single); 50 µg/m
3
(average daily). Hazard Class: 3 MPC (average daily) – 0.001 µg/m3. Hazard Class: 1
MPC: 1.0 µg/m3 (single); 0.3 µg/m
3
(average daily). Hazard Class: 1
0.9742 2.8053 0.00015892 0.00045763 0.18957 0.54588
0.8652 2.5544 0.00014115 0.00041670 0.16837 0.49706
0.7724 2.3484 0.00012601 0.00038310 0.15031 0.45698
Atmospheric emission of solid Pb, mg / m x day
Pb in ground (due to road operation during next 20 years), mg/kg
2006 prognosis for
2026 prognosis for 2026
MPC: 32 mg/kg
0.154 0.444 116.128
0.137 0.404 105.071
0.122 0.371 95.890
In Poltava Oblast:
Density of Traffic, conditional vehicle/day
Traffic Noise, decibel CO, mg/m3
2006 prognosis for 2026 2006 prognosis for 2026
2006 prognosis for 2026 Noise exposure equivalent limit for inhabited
area: 55 decibel (day), 45 decibel (night) MPC: 5.0 mg/m3 (single); 3 mg/m3 (average daily). Hazard Class: 4
12,890 39,300 62.6 71.8 0.1252 0.3816
12,660 38,980 62.5 71.8 0.1229 0.3785
10,980 34,200 61.9 71.3 0.1066 0.3321
11,840 37,180 63.8 72.2 0.1745 0.4173
11,000 35,480 61.9 71.4 0.1068 0.3445
11,790 36,940 62.2 71.6 0.1145 0.3587
12,800 38,780 62.5 71.8 0.1243 0.3765
13,120 38,740 62.6 71.8 0.1274 0.3762
24,300 64,860 65.0 73.7 0.2359 0.6298
14,000 33,490 62.9 71.2 0.1359 0.3252
10,710 27,080 61.8 70.4 0.1040 0.2629
32
NOx, mg/m3 SO2, mg/m
3 CxHy, mg/m
3
2006 prognosis for
2026 2006
prognosis for 2026
2006 prognosis for
2026
MPC: 0.085 mg/m3 (single); 0.04 mg/m3 (average daily). Hazard Class:
2
MPC: 0.15 (single); 0.05 mg/m3 (average daily). Hazard Class: 3
MPC (single) – 1.0 mg/m3. Hazard Class: 4
0.008344 0.025440 0.000417 0.001272 0.02086 0.06360
0.008195 0.025232 0.000410 0.001262 0.02049 0.06308
0.007108 0.022138 0.000355 0.001107 0.01777 0.05535
0.011632 0.027822 0.000582 0.001391 0.02908 0.06955
0.007120 0.022967 0.000356 0.001148 0.01780 0.05742
0.007632 0.023912 0.000382 0.001196 0.01908 0.05978
0.008286 0.025103 0.000414 0.001255 0.02071 0.06276
0.008493 0.025077 0.000425 0.001254 0.02123 0.06269
0.015730 0.041985 0.000786 0.002099 0.03932 0.10496
0.009062 0.021679 0.000453 0.001084 0.02266 0.05420
0.006933 0.017529 0.000347 0.000876 0.01733 0.04382
Carbon black, µg/m3 Benzpyrene, µg/m3 Pb (intensity of atmospheric emission),
µg/m3
2006 prognosis for 2026 2006 prognosis for
2026 2006 prognosis for 2026
MPC: 150 µg/m3 (single); 50 µg/m3 (average daily). Hazard Class: 3
MPC (average daily) – 0.001 µg/m3. Hazard Class: 1
MPC: 1.0 µg/m3 (single); 0.3 µg/m3 (average daily). Hazard Class: 1
0.7718 2.3532 0.00012591 0.00038388 0.15019 0.45791
0.7580 2.3340 0.00012366 0.00038075 0.14751 0.45418
0.6575 2.0478 0.00010725 0.00033406 0.12794 0.39849
1.0760 2.5735 0.00017553 0.00041983 0.20938 0.50079
0.6587 2.1244 0.00010745 0.00034657 0.12817 0.41340
0.7060 2.2119 0.00011516 0.00036083 0.13737 0.43041
0.7664 2.3220 0.00012503 0.00037880 0.14914 0.45185
0.7856 2.3196 0.00012816 0.00037841 0.15287 0.45139
1.4550 3.8836 0.00023736 0.00063355 0.28314 0.75573
0.8383 2.0053 0.00013675 0.00032713 0.16312 0.39022
0.6413 1.6215 0.00010461 0.00026452 0.12479 0.31553
Atmospheric emission of solid Pb, mg / m x day Pb in ground (due to road operation during next 20
years), mg/kg
2006 prognosis for 2026 prognosis for 2026
MPC: 32 mg/kg
0.122 0.372 96.019
0.120 0.369 95.007
0.104 0.324 83.122
0.170 0.407 112.136
0.104 0.336 85.514
0.112 0.350 89.653
0.121 0.367 94.897
0.124 0.367 95.412
33
0.230 0.614 164.036
0.133 0.317 87.372
0.101 0.256 69.526
The accepted design approaches include the following measures for prevention of landslips and ablation along all the road:
1. Leveling of roadside territory within the right-of-way, which allows to prevent stagnation of
surface water. 2. Installation of culverts in low places with transverse gradient. 3. Strengthening of the surface drainage system (water channels, chutes, ditches, etc.) in order to
prevent scour and infiltration of ground water. 4. Damp-course and reinforcement of water-storage grounds near inlets and outlets of the
culverts. 5. Selection of a proper opening for the culvert to ensure free flow. 6. Installation of slopes with appropriate angles of dip, taking into account their height and
composition of the ground. 7. Installation of lateral drainage on landslide-prone sections (on the slopes and in the places
with close groundwater).
Potential impacts on surface water from rehabilitation and operation of the motorroad: 1) Ingress of contamination into water bodies from the pavement surface. Possible negative
impact: additional pollution of surface water. 2) Disruption of hydraulic conditions of water flow at cross-section wih the motorroad due to
constriction of water course bottomlands with road embankments and drainage structures. Posible negative impacts: a) increased velocities of water flows and more intensive erosive processes; b) disruption of natural state of water levels and overdrying or overwetting of the territories in the headrace canals of drainage structures and water
checks. 3) Disruption of conditions of surface flow formation. Possible negative impacts: more
intensive erosive processes and less stable slopes.
Estimated concentrations of pollutants in surface flows from the motorroad in Kyiv Oblast:
River, basin Catchment area,
km2 Length of road in encatchment, km
including Category I (15 m wide), km
including Category ІІ (7.5 m wide), km
the Trubizh + the Oster 5,698.03
39.650 39.650 0.000
the Trubizh 2,276.12 39.650 39.650 0.000
the Nedra 1,035.62 15.630 15.630 0.000
the Supiy 528.883 22.830 22.830 0.000
(continued)
Pollutants washed off the roadway, concentration in the water course,
g/m3
Area of road
in encatchment,
km2
Dilution factor Suspensions Chemical
oxygen demand (COD)
Biological
oxygen demand -5 (BOD-5)
Petrochemicals
34
0.5948 0.0001044 0.15657 0.05219 0.00783 0.00125
0.5948 0.0002613 0.39195 0.13065 0.01960 0.00314
0.2345 0.0002264 0.33958 0.11319 0.01698 0.00272
0.3425 0.0006475 0.97125 0.32375 0.04856 0.00777
(end)
Annual rainwater flow quantity from the basin, m3
Annual discharge of pollutants from the roadway, t/year
Annual layer of
precipitations, mm
Runoff coefficient
Flow quantity, thousand m3
Suspensions
COD BOD-5 Petrochemi
cals
550 0.09 282,052.49 44.16 14.72 2.21 0.35
550 0.09 112,667.94 44.16 14.72 2.21 0.35
550 0.09 51,263.19 17.41 5.80 0.87 0.14
550 0.09 26,179.71 25.43 8.48 1.27 0.20
In Poltava Oblast:
River, basin Catchment area,
km2 Length of road in encatchment, km
including Category I (15 m wide), km
including Category ІІ (7.5 m wide), km
the Gnyla Orzhytsia 549.302 34.030 34.030 0.000
the Sula 14,272.24 75.060 75.060 0.000
the Khorol 2,634.03 40.700 40.700 0.000
the Psel 9,814.33 46.900 46.900 0.000
the Vorskla 11,019.65 71.420 71.420 0.000
the Kolomak 630.962 29.980 29.980 0.000
(continued)
Pollutants washed off the roadway, concentration in the water course,
g/m3
Area of road
in encatchment,
km2
Dilution factor Suspensions COD BOD-5 Petrochemicals
0.5105 0.0009293 1,39391 0.46464 0.06970 0.01115
1,1259 0.0000789 0.11833 0.03944 0.00592 0.00095
0.6105 0.0002318 0.34766 0.11589 0.01738 0.00278
0.7035 0.0000717 0.10752 0.03584 0.00538 0.00086
1,0713 0.0000972 0.14583 0.04861 0.00729 0.00117
0.4497 0.0007127 1,06908 0.35636 0.05345 0.00855
(end)
Annual rainwater flow quantity from the basin,
m3
Annual discharge of pollutants from the roadway,
t/year
Annual layer
of precipitations
, mm
Runoff coefficient
Flow quantity, thousand m3
Suspensions
COD BOD-5 Petrochemi
cals
525 0.15 43,257.53 60.30 20.10 3.01 0.48
525 0.15 1,123,938.90 133.00 44.33 6.65 1.06
525 0.15 207,429.86 72.12 24.04 3.61 0.58
35
525 0.15 772,878.49 83.10 27.70 4.16 0.66
525 0.15 867,797.44 126.55 42.18 6.33 1.01
525 0.15 49,688.26 53.12 17.71 2.66 0.42
The aforesaid estimation of impact on surface water is conservative, because it does not take
into account the designed measures for water treatment at treatment facilities.
Therefore, excess of the MPC is not expected even under strict regulation of pollutional load in wastewater.
The Feasibility Study includes design of treatment facilities described in the respective sections for drainage of water to the areas located beyond water protection zones and its treatment. Besides, a scheme of bioengineering treatment facilities (bioplato) is developed for water treatment as a separate volume of the design. Such facilities use microorganisms for biochemical degradation of organic matters.
5. DESCRIPTION OF SOCIAL ENVIRONMENT AND THE IMPACT ASSESSMENT
Kyiv Oblast is located in the northern part of Ukraine, in the basin of the Dnipro River. In
terms of political subdivision, Kyiv Oblast includes 25 rayons. The area is 28.4 thousand km2 (4.7%
of Ukraine’s area). Population: 1,808.3 thousand persons (3.7% of Ukraine’s residents). Boryspil Rayon.
Area: about 1,460 sq. km, 43 settlements, 53,485 residents. Baryshivka Rayon. Area: 957.6 sq. km (3.46% of the oblast area), 38 settlements, 41.5 thousand residents. Yagotyn Rayon. Area: 793.3 sq. km (2.8% of the oblast area). Poltava Oblast is located on the left bank in the middle Dnipro River and covers the area of
28.8 thousand sq. km. Pyriatyn Rayon.
Area: 863.5 sq. km, population: 36.6 thousand persons. Lubny Rayon. Area: 1,378 sq. km, population: 40.8 thousand persons. Khorol Rayon. Area: 1,062.33 sq. km. Velyka Bagachka Rayon.
Area: 1,044 sq. km, population: 31.3 thousand persons.
Poltava Rayon.
Area: 1,259.89 sq. km (4.4% of the oblast area). Population: 66,850 persons. Reshetylivka Rayon. Area: 1,001 sq. km. Chutove Rayon. Area: 861 sq. km, population: 27.1 thousand persons.
36
The area affected by the road in Kyiv Oblast includes 30 settlements with 14.4 thousand residents. The affected area in Poltava Oblast includes 178 settlements with about 550 thousand residents.
Parameters of settlements in the area affected by M-03 Motorroad: Kyiv Oblast:
L/I Settlement Rayon Area, km2 Number of residents
Distance from the beginning of
road, m
Distance from the road, m
1 Ivankiv 9.19457 360 600 less than 50
2 Liubartsi 9.49246 390 10,100 over 2,440
3 Bziv 3.46603 500 13,500 50-70
4 Selychivka 1.93197 250 16,700 over 2,440
5 Ustynkova Greblia 0.249834 260 19,500 1,120-1,650
6 Shovkove 0.488635 3,000 20,000 1,650-2,440
7 Voloshynivka 1.83329 160 21,300 370-530
8 Borshchiv 1.84954 340 25,100 less than 50
9 Berezan 36.3423 590 31,300 less than 50
10 Semenivka 3.21992 2,100 37,000 less than 50
11 Leliaky 2.93881 510 38,700 770-1120
12 Khmeliovyk
Bo
rysp
il
1.36394 330 40,500 over 2,440
13 Kozliv Pereyaslav- Khmelnitskiy
3.72468 940 41,900 1,120-1,650
14 Zhovtneve 7.02109 680 44,700 530-770
15 Grygorivka Yagotyn 0.44238 2,000 48,700 1,650-2,440
16 Somkova Dolyna 2.05799 60 50,000 1,120-1,650
17 Radianske
Pereyaslav-
Khmelnitskiy 0.418191 280 52,600 1,650-2,440
18 Panfyly 2.45766 100 56,100 less than 50
19 Panfyly 0.141071 30 56,300 1,650-2,440
20 Yagotyn 8.62092 110 58,400 less than 50
21 Nychyporivka 4.62062 70 58,800 180-260
22 Nychyporivka 0.189423 30 60,800 530-770
23 Yagotyn 0.645171 50 62,600 over 2,440
24 Yagotyn 0.252105 510 63,100 1,650-2,440
25 Voronivshchyna 0.644359 80 63,700 370-530
26 Dvirkivshchyna 0.77692 270 64,600 1,120-1,650
27 Cherniakhivka 4.38463 40 67,600 260-379
28 Cherniakhivka 0.592058 230 70,200 1,120-1,650
29 Koptevychivka 1.75932 80 71,300 530-770
30 Bogdanivka
Yag
oty
n
3.29562 50 72,700 50-70
Total: 14,400
Poltava Oblast:
L/I Settlement Rayon Area, km2 Number of residents
Distance
from the beginning of road, m
Distance from the road, m
1 Teplivla Pyriatyn 2.68333 490 85,300 1,120-1,650
2 Olexiyivka 2.47008 30 87,800 less than 50
3 Natalivka Grebinka
0.922789 580 88,400 over 2,440
4 Arkhemivka 0.399791 3,000 89,300 770-1,120
5 Maliutyntsi
Pyriatyn
3.1706 190 89,300 770-1,120
37
6 Victoria 1.52891 200 94,100 130-180
7 Olexandrivka 0.835162 200 101,400 less than 50
8 Mohylivshchyna 0.250748 50 104,000 less than 50
9 Verkhoyarivka 0.75649 319 106,500 1,650-2,440
10 Rivna 0.669609 1,268 106,600 1,650-2,440
11 Pyriatyn
9.64031 10,100 113,000 less than 50
12 Tarasivka Grebinka 4.71729 700 114,000 over 2,440
13 Mala Krucha 0.518922 290 114,500 770-1,120
14 Velyka Krucha Pyriatyn
2.34882 1,330 115,900 less than 50
15 Novoselivka 0.185012 846 119,600 1,650-2,440
16 Ulianovka Grebinka
1.1353 3,600 120,900 over 2,440
17 Povstyn Pyriatyn 1.67188 1,900 124,400 1,120-1,650
18 Karpylivka Lubny 1.79351 1,800 126,300 1,120-1,650
19 Ivanivka Orzhytsia 0.524312 880 130,700 530-770
20 Stepuri 0.450987 1,700 138,500 1,120-1,650
21 Bogodarivka 0.810544 170 138,500 over 2,440
22 Vyly 0.514207 350 138,800 less than 50
23 Gubske 2.73838 220 139,200 over 2,440
24 Ostapivka 2.47958 1,300 141,000 1,650-2,440
25 Tarandyntsi 1.97591 190 141,700 1,650-2,440
26 Pyshne 0.606063 4,400 142,300 less than 50
27 Vyshchyi Bulatets 2.11119 540 146,000 1,120-1,650
28 Novaky 3.54543 710 149,300 370-530
29 Lubny 21.6658 80 151,400 180-260
30 Klepachi 2.1148 790 151,500 770-1,120
Vilshanka 1.58223 90 154,800 less than 50
31 Mgar 1.47435 70 158,800 530-770
32 Pisky 1.9663 270 160,600 1,120-1,650
33 Zasullia 2.90619 1,800 161,900 770-1,120
34 Solonytsia 2.96598 10 162,400 770-1,120
35 Voinykha 1.08804 320 165,300 less than 50
36 Kupyevakha 0.226593 510 165,400 770-1,120
37 Nazarivka
Lubny
0.637729 120 169,100 530-770
38 Ivantsi Khorol 0.492924 950 173,900 770-1,120
39 Krevelivka Lubny 0.56376 1,370 174,500 1,650-2,440
40 Zaporozhchyne Khorol 0.371857 940 175,000 over 2,440
41 Totchyne 0.350846 210 175,300 over 2,440
42 Shynkivshchyna Lubny
0.653348 810 176,000 1,120-1,650
43 Pokrovska Bagachka 4.04123 3,500 177,900 less than 50
44 Nastasivka 0.79673 1,860 181,200 less than 50
45 Bochky 0.924928 40 183,200 1,650-2,440
46 Kovtuny 1.37346 0 184,300 less than 50
47 Vazhnyna Dolyna 0.270148 0 184,800 1,120-1,650
48 Shtompelivka 1.19893 140 184,800 over 2,440
49 Pavlivka 1.2723 200 185,800 1,120-1,650
50 Padusi 0.438894 370 186,400 over 2,440
51 Lobkova Balka 0.868585 360 186,700 less than 50
52 Lisianshchyna 0.103153 320 186,800 over 2,440
53 Stavky 0.350139 90 187,300 1,120-1,650
54 Radky 0.897135 60 189,700 530-770
55 Glyboka Dolyna 0.612057 60 192,600 1,120-1,650
56 Khorol 12.4498 50 193,400 less than 50
57 Prystan 0.680092 150 194,400 1,120-1,650
58 Popivka
Khorol
1.93281 310 196,500 770-1,120
38
59 Mala Popivka 0.728908 70 198,200 370-530
60 Vyshniaky 3.75246 100 198,500 180-260
61 Kostiuky 0.677176 140 199,300 1,650-2,440
62 Demyna Balka 0.948551 200 202,500 530-770
63 Verbyne 1.12979 40 203,100 1,650-2,440
64 Pavlenky 0.495554 70 206,100 1,120-1,650
65 Novoivanivka 3.28986 130 206,600 260-379
66 Roplianske 0.212775 60 207,300 1,120-1,650
67 Yalosovetske 2.42041 150 208,200 260-379
68 Chervone 0.499029 40 210,000 770-1,120
69 Lagodivka 0.89815 90 210,500 1,650-2,440
70 Brygadyrivka
2.23764 120 210,700 530-770
71 Chapayevka 1.6709 150 215,000 less than 50
72 Semenivka 1.27816 70 215,900 over 2,440
73 Radyvonivka 2.69959 110 217,400 over 2,440
74 Pushkareve 1.09196 110 218,000 1,120-1,650
75 Bagachka Persha 1.44034 320 219,900 1,650-2,440
76 Shyroke 0.5801 110 220,700 less than 50
77 Mostovivshchyna 1.92677 100 223,200 1,120-1,650
78 Stefanivshchyna 0.910384 730 226,500 770-1,120
79 Vyshari 0.464803 80 227,600 1,650-2,440
80 Sydorivshchyna 0.59682 90 227,700 less than 50
81 Shyposhi 0.165788 150 228,500 over 2,440
82 Morozivshchyna 0.633754 130 229,500 less than 50
83 Dziubivshchyna 0.798442 80 230,300 1,650-2,440
84 Krasnogorivka 2.10902 90 231,100 less than 50
85 Gerusivka 0.310568 270 231,800 770-1,120
86 Bilotserkivka 4.76903 60 233,500 less than 50
87 Lugove 0.744542 200 233,900 1,120-1,650
88 Birky 1.30065 160 236,100 over 2,440
89 Balandy 0.333283 180 238,000 1,650-2,440
90 Ogyrivka 3.77931 170 238,400 1,650-2,440
91 Konoplianka 0.582707 1,000 239,800 less than 50
92 Podil
Velyka Bagachka
3.107 200 241,100 less than 50
93 Krokhmaltsi 0.796324 3,100 246,800 1,120-1,650
94 Lyman Drugyi 3.07172 90 247,100 1,650-2,440
95 Lobachi 1.95873 110 248,400 less than 50
96 Tryvaily 0.550594 110 248,900 370-530
97 Gryshky 0.794989 1,100 251,300 over 2,440
98 Bakay 1.45034 510 252,100 1,120-1,650
99 Glyboka Balka 2.41982 120 253,500 less than 50
100 Korzhivka 0.641986 860 254,800 770-1,120
101 Goluby 0.6356 130 255,000 over 2,440
102 Reshetylivka 10.7172 1,700 259,600 less than 50
103 Khoruzhi 0.368364 800 260,800 1,650-2,440
104 Prokopivka 0.91004 60 261,200 530-770
105 Bilokoni 1.6692 310 262,800 1,650-2,440
106 Shkurupiyivka 1.22467 330 263,000 530-770
107 Lytvynivka 1.3517 300 264,400 1,120-1,650
108 Kukobivka 1.12315 10 266,200 1,650-2,440
109 Liutivka 0.643363 700 266,400 530-770
110 Demydivka 2.54884 130 267,200 1,120-1,650
111 Dolyna 0.815856 570 269,100 770-1,120
112 Nova Dykanka
Reshetylivka
0.764894 1,600 269,200 less than 50
39
113 Keleberdivka 1.14712 1,100 272,600 770-1,120
114 Tsyganske 0.936365 810 273,700 less than 50
115 Vasky 1.81631 560 274,300 1,650-2,440
116 Kostochky 0.530005 1,400 274,300 770-1,120
117 Kirove 1.76787 100 274,600 1,650-2,440
118 Gutyrivka 0.551219 64 275,500 1,650-2,440
119 Umantsivka 0.22133 190 275,800 over 2,440
120 Vytivka 1.26736 80 277,500 530-770
121 Karpusi 0.766161 250 277,700 130-180
122 Chervona Dolyna 0.255828 80 278,600 1,120-1,650
123 Abazivka 1.73263 300 278,900 over 50
124 Solomakhivka 0.441295 740 280,000 1,650-2,440
125 Lavryky 0.433781 660 280,200 1,120-1,650
126 Rozhayivka 0.552949 630 281,600 1,650-2,440
127 Mazurivka 0.285651 790 282,400 1,650-2,440
128 Kovanchyk 1.16375 107 283,100 over 2,440
129 Ivashky 2.44568 368 284,600 370-530
130 Bayrak 0.569566 607 285,000 1,650-2,440
131 Suprunivka 3.4247 273 286,600 less than 50
132 Gozhuly 3.77876 5,900 287,100 1,650-2,440
133 Myltsi 2.83786 6,200 287,600 less than 50
134 Shostaky 1.53337 100 288,400 770-1,120
135 Kuklyntsi 0.71482 38 289,100 1,650-2,440
136 Govtvianchyk 0.153447 47 289,800 90-130
137 Gorbanivka 0.585691 115 291,200 less than 50
138 Rozsoshentsi 2.31532 9,800 292,100 770-1,120
139 Poltava 77.1317 660,000 294,500 less than 50
140 Shcherbani 1.97809 18,300 295,700 1,120-1,650
141 Shmygli 0.679321 7,500 296,500 1,120-1,650
142 Tiutiunnyky 0.44493 3,600 296,600 1,650-2,440
143 Gora 1.19066 3,300 297,100 770-1,120
144 Nyzhni Mlyny 0.710739 12,800 297,800 less than 50
145 Kopyly 1.28595 16,300 299,500 less than 50
146 Zintsi 1.14895 1,500 300,000 770-1,120
147 Tereshky 2.00619 110 300,000 130-180
148 Makukhivka 1.05227 2,500 303,100 1,650-2,440
149 Mykilske 1.65981 15,700 303,300 over 2,440
150 Andrushky 0.475433 303,900 1,650-2,440
151 Markivka 0.693945 304,200 770-1,120
152 Sosnivka 0.363431 305,200 over 2,440
153 Verkholy 0.96366 305,500 770-1,120
154 Vatsi 1.11406 305,900 1,650-2,440
155 Grabynivka 0.568601 306,200 770-1,120
156 Kovalivka 2.18614 307,300 1,650-2,440
157 Davydivka 0.600306 308,000 180-260
158 Yizhakivka 0.433659 308,100 260-379
159 Zaliznychne 1.58629 309,300 over 2,440
160 Kulykove 2.44237 313,000 370-530
161 Dudnykove 1.93885 316,800 770-1,120
162 Stepanivka 0.768685 317,700 1,650-2,440
163 Velyke Ladyzhyne 0.599053 320,000 1,650-2,440
164 Male Ladyzhyne 0.951129 320,000 less than 50
165 Vasylivka 3.10393 322,200 260-379
166 Burty
Poltava
0.46145
22,800
322,600 over 2,440
40
167 Storozhove 2.8268 328,000 1,120-1,650
168 Zelenkivka 2.94769 329,700 less than 50
169 Voinivka 1.98465 331,700 less than 50
170 Vynomynivka 0.723018 334,100 1,120-1,650
171 Lysycha 1.26744 335,500 1,650-2,440
172 Novofedorivka 2.22096 336,800 less than 50
173 Stinka 1.1377 340,800 1,650-2,440
174 Chutove 10.2816 341,900 less than 50
175 Kochubeyivka 3.0524 345,400 over 2,440
176 Cherniakivka 3.93491 347,900 1,650-2,440
177 Verkhni Rivni 0.36668 348,800 over 2,440
178 Nyzhni Rivni
Chutove
0.913572
22,800
349,700 260-379
Total: 548,132
The estimates show that though a lot of residents will be affected by operation of the road, quite fewer residents will be affected along its route in comparison with other motorways in Ukraine.
6. ASSESSMENT OF IMPACT ON TECHNOLOGICAL ENVIRONMENT
The technological environment in the area affected by the motorroad includes power lines,
adjacent local roads, and residential development. The project will have additional impact on civil residential and industrial buildings, above-ground structures, and social organization of the territory (including recreational areas and cultural landscapes) at the stage of rehabilitation due to temporary impairment of the infrastructure and passage and also because of environmental pollution. On the contrary, after the road is commissioned, it will have a positive impact on the technological
environment. The world practice shows that motorroads of Category I and II extend their socio-economic impact on hundreds of kilometres and contribute to business activity, investment appeal of the territory, creation of new jobs, etc.
7. MEASURES FOR MAINTENANCE OF ENVIRONMENTAL STANDARDS AND ENVIRONMENTAL SAFETY
The environmental impact of the project will be reduced to noise and air pollution with dust and aerosol emissions from internal-combustion engines. The mitigation measures will include:
- prevention of landslide and ablation effects (strengthening of surface water drainage systems to prevent washouts and groundwater seepage, installation of a drainage system, and other measures to prevent landslip on safe sections with high water table);
- reduction of atmospheric emissions (proper control of compliance with work technique and leveling of horizontal alignment in order to ensure steady traffic);
- noise reduction measures (installation of noise screens and prohibition of pile-driving at night);
- protection of soil (removal and stockpiling of vegetation soil on specially assigned grounds with its further use for improvement of fertility);
- reduction of impact on flora and fauna (prohibition to cut trees beyond the borders of zone alloted for rehabilitation of the road and road structures, prohibition to cover with earth the root collars and the trunks of the trees growing near the rehabilitation site, and provision for migration of animals in the places of passages, bridges, overhead roads, culverts, etc.);
41
- waste management (regular transportation of building materials in the course of rehabilitation without stockpiling the large lots at the construction sites, temporary stockpiling of building refuse at the construction site in specially assigned places, availability of transportable
containers for metal rejects, oiled rags, petrochemicals, etc. at the construction sites, and obligatory removal of building refuse from the construction site with its further utilization);
- prevention of negative changes in the hydrologic environment (prevention of pollutant ingress into the aquatic environment due to pollution of ground, installation of mimimum number of footings in water courses during rehabilitation of bridges, etc.).
Key measures accepted for environmental protection: - the road shall be rehabilitated with the maximum use of existing right-of-way; - the fertile layer of soil shall be removed along all the road, stockpiled in the right-of-way and
then used for consolidation of the roadbed, reclamation of ground-pits, and improvement of low-yield soils in other locations;
- the culverts are designed to provide for for free flow and fully equipped with chutes for water drainage to protect the ground in the roadside territories against erosion processes;
- the water courses shall be reinforced with concrete slabs and dashpots near the culvert heads to prevent scour at the points of entry and exit;
- the pavement structure shall not include toxic materials, either in the carpet, or in the bottom layers;
- in order to reduce dust formation in cases when vehicles drive down to the verges, the design includes reinforcement of the verges with asphalt coat;
- the lands disrupted temporarily during construction shall be reclaimed after completion of the construction and returned to their users for further economic activities;
Special measures are also planned, including treatment facilities at the sections of active water courses and noise screens on the road near inhabited localities.
In the places of animal migration, special biopassages shall be installed in a form of artificial structures: droves, bridges, tunnels, and corrugated-metal pipes.
The list of additional design approaches to be taken into account in order to observe the
environmental protection requirements during construction of M-03 Motorroad:
1. Provide compensations to and come to agreements with the users of forest plots to be cut down. The size of compensation shall not be lower than the value of material assessment of the green plantations specified in the certificates of inspection.
2. In the cases when roadside forest shelter belts are cut down, arrange alternative green plantations in coordination with the State Department of Ecological Resources and, if necessary, with the oblast forestries.
3. On all the bridges, install water drainage from the roadway to treatment facilities: of physical and mechanical treatment, filled with filter medium (fine-grained crushed rock), and bioplato.
8. COMPREHENSIVE ASSESSMENT OF ENVIRONMENTAL IMPACTS
After analyzing the factors of environmental impacts, we have to note that the motorroad will
have a negative impact only in its zone of influence (affected zone) and within the limits of minimum atmospheric air pollution. The levels of atmospheric air pollution in the affected zone will not exceed the permissible limits.
42
The estimated impact on surface and ground water is minimal. The system of design approaches to rainwater and meltwater drainage and organization of roadway cutting includes drainage both from the roadway and from the engineering structures.
The impact on flora and fauna will be insignificant. No impact is expected on protected areas.
In general, if the motorroad is operated properly, the estimated integral impact on most of the environmental components will be insignificant, provided that all the designed protective measures are applied.
This project will have explicit positive social outcomes. The impact on technological environment is qualified as positive.
Due to better riding qualities of the new road, as compared with the old one, the general effect of rehabilitation is expected to be rather positive than negative.
The residual effects will include:
- levels of noise, which will not exceed the current maximum permissible limits for inhabited localities, provided that the proposed protective measures are applied;
- pollutant emissions, which will not exceed the MPC; - runoffs from the roadway surface, in which pollutant concentrations will be lower than the
MPC and will not have any impact on the water quality in water bodies, provided that protective measures (channeling of the runoffs to treatment facilities) are applied.
9. ASSESSMENT OF ENVIRONMENTAL IMPACTS FROM CONSTRUCTION
The construction works for rehabilitation of the road and bridgeworks will be performed by
the general contractor which will win the tender. The plan is to start the construction works in 2006 and to complete them in 2013. All the materials, their transportation and storage, methods of construction works, and quality
assurance of the materials and the construction works shall correspond to the technical specifications
included in the tender documents. Provision for occupational safety shall be ensured by the construction management and
include, without limitation, the following key measures:
- provide personal and collective protective gear (overalls, footwear, goggles, etc.) to all the workers under the effective regulations;
- communicate the road-building safety code to all the workers; - provide the appropriate safety code briefing before commencement of the works; - equip the work sites with bright posters on safety codes for respective operations;
- arrange for transportation of the workers to their work sites only by the vehicles specially equipped for such purposes;
- install night-time lighting and appropriate fencing of the work sites; - provide amenity premises and structures for building sites in accordance with requirements
of normative documents on safety code, industrial sanitation, etc.
The contractors shall include the specific engineering decisions on occupational safety and hygiene and sanitary conditions of the workers in the designs of construction works.
The fire safety measures shall include the following:
- ensure that the workers observe fire safety requirements; - develop the schemes of personnel and machinery evacuation and communicate such schemes
to the workers;
43
- install fire safety shields with equipment (chemical extinguishers, boxes with dry sand, buckets, spades, gaffs, etc.) at the sites;
- equip the premises with fire extinguishers with instructions and placards including the names
of persons in charge of fire safety; - assign special places for smoking and equip them with appropriate fire fighting equipment
and Smoking Place placards; - provide for possible passage of fire engines to each building and structure and ensure proper
maintenance of such passages; Only the personnel familiar with the procedures and briefed on occupational and fire safety
shall be admitted to the work.
In order to ensure high riding qualities and durability of the road and create appropriate traffic
conditions, the construction documentation includes application of state-of-the-art technologies, materials, machines, and mechanisms during adaptation of the road to motorway requirements.
The feasibility study includes milling of the existing bituminous concrete pavement, cold recycling technique of pavement layers, and application of geotextiles, synthetic layers, and rubbly-mastic bituminous concrete.
The roadbase layers shall be made of materials reinforced with cement, and the layers of
carpet shall be made of bituminous concrete on cementic polymer bituminous material.
The design documents include antirust metal fencing.
For the engineering structures:
- application of Spolimost S weldup damp-course;
- application of hermetic rubbly-mastic isolation joints; - extension of superstructure dimensions with a cast-in-block overhead slab; - application of durable antirust zinc-plating and three-coat painting on metal structures, with
each layer of paint at least 220 micron thick; - anticorrosive protection of concrete surfaces with paints based on acrylic compositions; - application of damp-course carpet made of poured (modified) asphalt concrete; - application of fine rubbly-mastic bituminous concrete for floors of structures; and - application of repair materials based on polymer concrete compositions to renovate concrete
surfaces.
The main nature-conservative measures at the stage of construction include:
- mandatory observation of safety code and occupational safety regulations; - separation of dangerous areas and worksites with special multiple-use fencing - installation of caution signs and placards in the necessary places; - stockpiling of building materials and structures on the vacant grounds within the right-of-
way in order to avoid passage blocking; - exclusion of pollution caused by machinery and mechanisms to carriageways of
communication roads and the places where ground and building refuse is handled; - prevention of technological vehicles from driving beyond the right-of-way; - bulk building materials and mixes shall be delivered packed to the construction site, and
solutions and concrete shall be transported in concrete haulers; - installation of night-time lighting for the passages; - exclusion of continuous idling operation of vehicle and machinery engines; - disposal of building refuse, garbage, and ground in strict compliance with the
permissions obtained in accordance with the established procedures; - control of engineering equipment, mechanisms and machinery operation, prompt repair
and prevention of defective mechanisms from operation;
44
- prohibition to cut down trees beyond the strip allotted for construction of the road and road structures;
- strict compliance with effective fire safety norms and regulations;
- the garbage shall be localized and then removed in a centralized way by a specialized organization. The following measures shall be ensured:
- regular transporting of building materials in the course of works, without stockpiling of their large lots at the construction sites;
- temporary stockpiling of building refuse in specially assigned places at the construction sites;
- availablility of transportable containers for metal waste, oiled rags, petrochemicals, etc.
45