Upload
phungcong
View
216
Download
0
Embed Size (px)
Citation preview
© Hitachi, Ltd. 2016. All rights reserved.
再生可能エネルギー大量導入時代を支える需給運用/計画技術
Oct. 19 2016 Hitachi, Ltd Toshiyuki Sawa
Generation scheduling technologies supporting large Introduction of Renewable Energy
25th CEE Symposium with NEDO
© Hitachi, Ltd. 2016. All rights reserved.
Contents
1. Backgrounds and Objectives 2. Overview of methods for Uncertainties 3. UC method using Quadratic Programming 4. Proposed method for Uncertainties 5. Results 6. Conclusions & Future works
© Hitachi, Ltd. 2016. All rights reserved.
Large introduction of PV and WG Reduce Generation costs
1. Backgrounds and Objectives
Central Load Dispatching Center
Generation
Substation
Transmission
Distribution Customer
PV
Back -grounds
Generation Scheduling considering - Low generation costs - Uncertainty renewable generations
Objectives
Fiscal Year
10
0
20
30
40
GW
Increasing rate
Increasing rate
Increasing rate
PV
WT Bio.
Small hydro
Renewable Energy Introduction In Japan
From METI web site 2
© Hitachi, Ltd. 2016. All rights reserved.
Contents
1. Backgrounds and Objectives 2. Overview of methods for Uncertainties 3. UC method using Quadratic Programming 4. Proposed method for Uncertainties 5. Results 6. Conclusions & Future works
© Hitachi, Ltd. 2016. All rights reserved. 4
2-1. Normal Method : Combination of UC and Demand
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
出力
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
出力
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
出力
[M
Wh]
時刻UC
①
②
③
Opt. Method - UC - ELD
Constraints
UC UC
UC for each demand Select Optimal Schedule: Estimate each UC for all demands
Opt. Method - ELD
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
UC
Cost
① ② ③
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
Opt. Schedule
①
②
③
Demands
①
②
③
© Hitachi, Ltd. 2016. All rights reserved. 5
2-2. Conventional Method : Fixed UC for base Demand
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
出力
[M
Wh]
時刻
②
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 3 5 7 9 11 13 15 17 19 21 23
需要
[M
Wh]
時刻
UC
Cost
②
UC
UC
Demand Opt. UC for demand
UC is optimal for base demand
Opt. Method - UC - ELD
Constraints
Opt. Method - ELD
© Hitachi, Ltd. 2016. All rights reserved.
2-3. Proposed Method : One Optimal UC for all demands
Thermal Gen.
Pumped Hydro Renewable generation
forecast Errors
Wind
Load forecast Error
Supply
時間 Time
Th
erm
al-A
T
he
rma
l-B
Pu
mp
ed
Hyd
ro
Time
・・・・
- One UC
- ELD for each load curve
Network
PV
high Base Low
Demand Curves Optimal Schedule
- UC; Unit Commitment
- ELD; Economic load Disp.
Simultaneous
Optimization
Central Load Dispatching Center
One optimal UC is calculated by Simultaneous Optimization method
MW
MW
MW
MW
6
© Hitachi, Ltd. 2016. All rights reserved.
Contents
1. Backgrounds and Objectives 2. Overview of methods for Uncertainties 3. UC method using Quadratic Programming 4. Proposed method for Uncertainties 5. Results 6. Conclusions & Future works
© Hitachi, Ltd. 2016. All rights reserved.
3-1. Simultaneous Optimization method for UC and ELD
時間
Th
erm
al-A
T
he
rma
l-B
Pu
mp
ed
Hyd
ro
Time
・・・・
Economic Load
Dispatching
Pu
mp
ed
Hyd
ro
Time
・・・・
Unit Commitment
時間
Th
erm
al-A
時間
Th
erm
al-B
On
On Off
Gen-Available
Pump-Available
MW
MW
MW
On: Generation
Off: Stop
then
Simultaneous Optimization using Quadratic Programming
8
© Hitachi, Ltd. 2016. All rights reserved.
3-2. Formulation for Integrated Unit Commitment
N
i
ii
T
t
N
i
ititi SCuPCuPF11 1
)(),(),(
itiitiitiiti ucPbPaPC 2
)( iiii SvSC )(
Thermal UC Variable uit 0≦uit≦1 relaxing binary to continuous Increasing UC Variable uit≦uit+1 when demand increasing Decreasing UC Variable uit≧uit+1 when demand decreasing
Fuel Cost Start-up Cost
- Generation Capacity and minimum generation - System demand and supply balance - Spinning Reserve - Minimum up and down times - Transmission Constraints - LNG Consumption - Hydro unit power, load limit and reservoir water level
・・・(1) Mixed integer programming problem
↓ Quadratic programming problem
Objective Function:Generation Costs → min
Newly added Constraints
Main constraints
9
© Hitachi, Ltd. 2016. All rights reserved.
3-3. Quadratic Programming to Apply Problems
Problem 1: Feasible Operational Unit Commitment ⇒ Thermal units start up or shut down more than once per day.
Problem 2: Converging UC Variables to 0 or 1 ⇒ Thermal UC variables are usually not 0 or 1.
Thermal UC variables are relaxed from binary to continuous. uit=0 or 1 ⇒ 0≦uit≦1 (Mixed Integer ⇒ (Quadratic Programming Problem) Programming Problem)
1 3 5 7 9 11 13 15 17 19 21 23 Time
uit 1 0 0 0 1 1 0 1 0 1
1 3 5 7 9 11 13 15 17 19 21 23 Time
uit 0.9 0.1 0.6 0.3 1.0 0.2 1.0 0.3 0.6 0.2
Constraints
Problem 1: Feasible Operational Unit Commitment
Problem 2: Converging UC Variables to 0 or 1
10
© Hitachi, Ltd. 2016. All rights reserved.
3-4. Measure against Problem 1
1. Adding New Constraints A) From minimum to maximum demand time, the value of uit
does not decrease, and from maximum to last demand time, that of uit does not increase.
B) In low demand periods, the value of uit is the same, and in the peak demand periods, that of uit is the same.
1 3 5 7 9 11 13 15 17 19 21 23 Time
Dem
and
No change
No change
UC variable available direction
1. Adding New Constraints
11
© Hitachi, Ltd. 2016. All rights reserved.
3-5. Measure against Problem 2
A) New Objective Function
Average Cost μitd
Generation Power
Pitd
Fuel
cos
t
T
t
N
i
d
it
d
it
ddddd uwuPFuPRF1 1
1),(),(
d is iteration number; wd is penalty weighting factor; μit
d is average cost of thermal unit i at time t with the d-th iteration.
・・・(2)
2. Adding New Penalty Costs to Objective Function
12
© Hitachi, Ltd. 2016. All rights reserved.
3-6. Flowchart for generation scheduling
Yes
No
Calculate dispatching power and unit commitment using QP in Eq. 29
Calculate initial dispatching power and unit commitment using QP in Eq. 29 (d=0, wd=0,)
d=d+1, wd=10d
Calculate per-unit fuel cost μ itk
at present dispatching power Pitd
k>kmax ?
Calculate dispatching power using QP in Eq. 1
Decide unit commitmentif uit
d >0 then uit=1(committed) else uit=0
Output final generation schedule
d > dmax ?
Yes
No
Calculate dispatching power and unit commitment using QP in Eq. 29
Calculate initial dispatching power and unit commitment using QP in Eq. 29 (d=0, wd=0,)
d=d+1, wd=10d
Calculate per-unit fuel cost μ itk
at present dispatching power Pitd
k>kmax ?
Calculate dispatching power using QP in Eq. 1
Decide unit commitmentif uit
d >0 then uit=1(committed) else uit=0
Output final generation schedule
d > dmax ?
d
it
13
© Hitachi, Ltd. 2016. All rights reserved.
Contents
1. Backgrounds and Objectives 2. Overview of methods for Uncertainties 3. UC method using Quadratic Programming 4. Proposed method for Uncertainties 5. Results 6. Conclusions & Future works
© Hitachi, Ltd. 2016. All rights reserved.
4-1. Mathematical Formation for generation scheduling (1)目的関数:発電コスト=燃料費+起動費 最小化
・・・・・・・・・・・・ (1)
(2)制約条件
(a) Balance (b) Reserves for increasing and decreasing powers (c) Generation Capacity and minimum generation (d) Minimum up and down times (e) LNG Consumption (f) Hydro unit power and load limit and reservoir water level
N
i
iNiPi
L
j
T
t
M
i
it
j
iti
j uuSuPCwuPF11 1 1
)(),(),(
functionn consunptio Fuel:),(2
iti
j
i
j
iit
j
i ucPbPauPCititit
jiP j
itcurve Demandfor UnitThermal of Generation:
variablestateOperation:itu
costupStart: iS
jw j curve demandfor t coefficienWeight : demandpeak and bottom of Times:, PN
jjK
k
jM
i
j
tktktitDLHGHP
)(11
jD j
t curvefor Demand: load Pump andpower Generation:, jj
ktktLHGH
t
K
k
j
kt
j
ktkit
N
i
j
i RLHGHGHuPPit
1
max
1
max
t
K
k
j
kt
j
ktkit
N
i
i
j QGHLHLHuPPit
1
max
1
min powersminimum andMaximun:, minmax ii PP
tQR tt TimeatreservesRequirment:,
Generation costs = Fuel costs + Start-up costs ⇒ min Objectives
Constraints
15
© Hitachi, Ltd. 2016. All rights reserved.
4-2. Conditions of Scheduling Problem
Horizontal time 24 Thermal
unit Num. 29 Capacity 12,529MW mdt 3 mut 5
Pumped-hydro
Num. 1 Capacity 1,000MW
Method Demand and Weight
coefficient Reserves
High Base Low Conventio
nal 0% 0.0
0% 1.0
0% 0.0
Base±15%
Proposed +10% 0.25
0% 0.5
-10% 0.25
Base±15%
Σ(Weight coefficient)=1.0 mdt : Minimum down-times mut : Minimum up-times
Use three demand curves, high, base and low Uncertainty renewable generation and demand, ±10% for Base demand Reserves for up and down power; ±15% for Base demand
Setting Conditions
16
© Hitachi, Ltd. 2016. All rights reserved.
Contents
1. Backgrounds and Objectives 2. Overview of methods for Uncertainties 3. UC method using Quadratic Programming 4. Proposed method for Uncertainties 5. Results 6. Conclusions & Future works
© Hitachi, Ltd. 2016. All rights reserved.
5-1. Conventional method : Using one curve for base demand
Unit N
um
ber
(Priority o
rder
)
時間 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 容量
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 7132 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 7293 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 4504 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6005 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6006 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2507 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6008 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 6009 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 250
10 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 25011 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60012 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 25013 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 25014 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 32515 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 32516 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 25017 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 25018 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 25019 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 25020 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25621 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 37522 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 0 0 0 0 0 0 0 60023 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60024 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 45025 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60026 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60027 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60028 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60029 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 156
Time
ON
OFF
Higher priority units are ON except Unit-11 and 20 Result
Capacity(MW) Capa
18
© Hitachi, Ltd. 2016. All rights reserved.
5-2. Proposed method : Simultaneous Optimization method using three demand curves
時間 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 容量
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 7132 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 7293 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 4504 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 600
5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6006 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 2507 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6008 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 6009 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 250
10 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 25011 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 60012 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 25013 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 25014 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 32515 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 32516 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 25017 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25018 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 25019 1 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 25020 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 25621 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 0 0 0 0 0 0 0 37522 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60023 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 600
24 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 45025 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 600
26 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60027 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60028 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 60029 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 156
Higher priority units are ON except Unit-17 Result
Unit N
um
ber
(Priority o
rder
)
Time
ON
OFF
Capacity(MW) Capa
19
© Hitachi, Ltd. 2016. All rights reserved.
5-3. Differences of Unit commitments
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 容量
6 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 2507 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 6008 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 6009 1 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 250
10 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 25011 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 60012 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 25013 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 25014 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 32515 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 32516 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 25017 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25018 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 25019 1 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 25020 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 0 0 0 0 25621 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 0 0 0 0 0 0 0 37522 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 600
Unit N
um
ber
(Priority o
rder
)
Time
ON by only Proposed method
Capacity(MW)
ON by only Conventional method
600MW Unit-11 ON 250MW Unit-12 ON
Bottom Peak
600MW-11+256MW-20 Units ON 600MW-22+250MW-17 Units ON
Proposed Conventional
Differences of UC are one and two units in bottom and peak times respectively Other differences are start-up and shut-down time
Difference
Capa
20
© Hitachi, Ltd. 2016. All rights reserved.
5-4. Results : In case of high demand, base + 10%
① All constraints are satisfied in case of 15 % reserve for base demand.
② Final water level < Target level Power[kW]can balance at each time but not energy[kWh]
③ Compensation costs are added to raise target water level Average unit cost × ΔWater Level [k¥/kWh] [kWh]
0
500
1000
1500
2000
2500
1 3 5 7 9 11 13 15 17 19 21 23
予備力[
M
W
h]
時刻
揚水 火力
0
500
1000
1500
2000
2500
1 3 5 7 9 11 13 15 17 19 21 23
予備力[
M
W
h]
時刻
揚水 火力
Proposed ① Satisfy all constraints
Conventional ② Violation of Water level
③ Lower than target Level
Time
Time
Res
erve
(M
W)
Res
erve
(M
W)
Pump Therm
Pump Therm
Thermal Units P
um
pe
d
Pu
mp
ed
21
© Hitachi, Ltd. 2016. All rights reserved.
5-5. Comparison of Generation costs
Costs Generation Fuel Start-up Conventional 100.000 99.249 0.751
Proposed 99.767 99.140 0.627 Reduction (%) 0.233 0.110 0.123
Costs are normalized by generation costs of Conventional method
Start-up Units Conventional 256MW, 600MW
Proposed 250MW, 600MW
Expected generation costs of proposed method are 0.233 % less than that of Conventional method.
22
© Hitachi, Ltd. 2016. All rights reserved.
Contents
1. Backgrounds and Objectives 2. Overview of methods for Uncertainties 3. UC method using Quadratic Programming 4. Proposed method for Uncertainties 5. Results 6. Conclusions & Future works
© Hitachi, Ltd. 2016. All rights reserved.
6-1. Conclusions
Generation Scheduling method has been developed for uncertainties such as large introduction of renewable energy. - Using Quadratic Programming - Solving simultaneously UC and ELD Simulation results from proposed method show - Satisfy all constraints - Reduce generation costs by 0.233%. Pumped-hydro as energy storage system is important for uncertainties to keep not only kW-power balance but also kWh-energy balance.
24
© Hitachi, Ltd. 2016. All rights reserved.
6-2. Future works
Simulate and estimate more realistic cases considering - Uncertainties for each time dependent - Network constraints
25