IZGRADNJA POSTROJENJA I
PROIZVODNJA ELEKTRINE/TOPLOTNEENERGIJE IZ HIDROGEOTERMALNIH IZVORAU REPUBLICI SRBIJI -VODI ZA INVESTITOREDr Branislava Lepoti Kovaevi, dipl.prav.Stanislav Milosavljevi, dipl.rud.in.Bojan Lazarevi, dipl.el.in.
CONSTRUCTION OF PLANTS ANDELECTRICITY/HEAT GENERATION FROMHYDROGEOTHERMAL RESOURCES INTHE REPUBLIC OF SERBIA -GUIDE FOR INVESTORS
Branislava Lepoti Kovaevi, PhD LawStanislav Milosavljevi, BSc M. Eng.Bojan Lazarevi, BSc El. Eng.
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
2/64
ENGLISH SERBIAN
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
3/64
1
CONSTRUCTION OF PLANTS ANDELECTRICITY/HEAT GENERATION FROMHYDROGEOTHERMAL RESOURCES INTHE REPUBLIC OF SERBIA -
GUIDE FOR INVESTORS
2 Introduction4 Energy from Geothermal Resources4 Hydrogeothermal Energy4 Power Plants for Electricity/Heat Generation from Hydrogeothermal Sources4 Investors Rights5 Relevant Legislation5 Competent Institutions5 From an Idea to Exploitation
6 Main Steps from an Idea to Exploitation (I)6 I Acquiring the Right to Survey and Exploitation of Geothermal Resources7 I-1 Geological Surveys
7 I-1 Approval of Geological Surveys
8 I-1 Feasibility Study of Geological Surveys - Contents
8 I-1 Feasibility Study of Ground Water Reserves
9 I-2 Exploitation of Hydrogeothermal Energy
9 I-2 Approval for Exploitation of Mineral Resources
10 I-2 Approval to Carry Out Mining Works
10 I-3 Mining Facilities
11 I-4 Exploitation of Hydrogeothermal Energy
12 Main Steps from an Idea to Exploitation (II)13 II-1 Location Selection, Perusal of Valid Planning Documents and the Information on Location
13 II-2 Energy Permit
14 II-2 Obtaining the Energy Permit
14 II-3 Location Permit
15 II-3 Requirements for Connection to the Electricity/District Heating Network15 II-3 Forming the Building Plot
16 II-3 Water requirements
16 II-3 Obtaining the Location Permit
17 II-4 Building Permit
17 II-4 Environmental Impact Assessment (1)
18 II-4 Environmental Impact Assessment (2)
18 II-4 Environmental Impact Assessment (3)
19 Technical Documentation
19 II-4 Water Approval and Technical Supervision of the Design
20 II-4 Construction Permit, Attachments to the Request
20 II-4 Obtaining the Construction Permit
21 II-5 Operating Permit
21 II-5 Construction of a Facility
22 II-5 Technical Inspection and the Operating Permit
23 Main Steps from an Idea to Exploitation (III)23 III Acquiring the Right to Generate Electricity/Heat24 III-1 The Right to Electricity Generation - Acquisition Method
24 III-1 Assigning the Engagement in an Activity of Public Interest
25 III-1 Assignment Agreement - Requirements
25 III-1 A ssignment Agreement - Contents/Provisions
26 III-2 Concession
26 III-2 Concession - Contents of a Concession Agreement
27 III-2 The Assignment Agreement vs. Concession - Main Differences
27 III-3 License - Acquiring the License
28 III-4 Approval for the Connection to the Electricity Network
28 III-4 Approval for the Connection to the District Heating Network
29 III-5 The Status of a Privileged Producer
29 III-5 Acquiring the Status of a Privileged Producer
30 III-6 Power Purchase Agreement
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
4/64
Renewable energy, such as biomass, wind, mini-hydro, and geothermal isreceiving greater attention from governments, potential investors, andconsumers worldwide. In 2007, the European Union (EU) set a combinedmember country target that 20% of overall energy consumption will comefrom renewable sources by 2020.
Serbia has significant renewable energy resources to meet this emergingdemand, and the Serbian Government has developed a strategy to leveragethis opportunity. To support sector growth and investment, and to meet theircommitment to the South East Europe Energy Community Treaty, the Serbiangovernment adopted several regulations by decree in November 2009,including:
Establishment of a Feed-in Tariff system whereby the Serbian governmentwill subsidize the cost of renewable electricity;
Dened the requirements of becoming a Privileged Electric PowerProducer who uses renewable energy sources to generate electricity;
With the Serbian governments adoption of feed-in tariffs and other keyregulation, GTZ Project Strengthening of the Local Self-Government(GTZ SLS) has been working with government ministries and the USAIDCompetitiveness Project private sector investors to encourage investment inrenewable energy projects.
2BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
5/64
A key activity has been to create definitive guides to the renewable energylicensing process aimed at encouraging investors and other market actorsto become active in the sector. Representatives of the Ministry of Mining andEnergy, Ministry of Environment and Spatial Planning and Ministry ofAgriculture, Forestry and Water Management together with the GTZ expertshave created four such roadmaps, which explain the licensing process for
developing projects in geothermal water, small hydro power, wind power andbiomass subsectors. The USAID Competitiveness Project has supportedGTZ SLS in the creation of investor roadmaps as part of its activities toencourage investment in the sector by providing technical assistance toprospective investors.
Each roadmap is created as a detailed document, which describes administrative procedures and identifies relevant institutions and necessary planning anddesign documents needed for investors. The roadmaps navigate the
legislative and regulatory framework and should be utilized as a baseline forfurther legislative and regulatory reform. GTZ SLS has also prepared shortversions of roadmaps, which are executive summaries that investors can usefor fact finding.
We hope that this effort will be a vehicle to facilitate dialogue between the pri-vate sector and the Government to identify and address barriers to the growthand financial viability of the sector.
3 BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
6/64
4
Energy fromGeothermalResources
- Geothermal energy is the heat accumulated in dry rocksand fluids of the lithosphere; this is a result of the continu-ous radiation of heat from the interior of the Earth
- Geothermal energy can be:
- Hydrogeothermal energy - accumulated in fluids (water and gases) and- Petro-geothermal energy - accumulated in hard rocks
Hydrogeo-thermalEnergy
- Hydrogeothermal energy is a form of a renewableenergy source
- Hydrogeothermal energy can be used directly, both forheat and electricity generation
Power Plantsfor Electricity/Heat Generationfrom Hydrogeo-
thermal Sources
- Hydrogeothermal power plants used for electricity and/orheat generation
- Small power plants - up to 10MW- Big power plants - 10 MW or more
Investorsrights
The investor must acquire the following rights:
- I The right of exploitation- II The right of construction- III The right to generate electricity/heat
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
7/64
5
- The Energy Law (Official Gazette of the RoS, No. 84/04)- The Mining Law (Official Gazette of the RoS, No. 44/95, 85/05-super-
seding law, 101/05- 85/05-superseding law, 34/06, and 104/09)- The Law on Geological Surveys (Official Gazette of the RoS, No. 44/95)
- The Law on Mineral Resource Reserve Establishing and Classificationand Presentation of Geological Survey Data (Official Gazette of the
FRY, Nos. 12/98 and 13/98)- The Law on Planning and Construction (Official Gazette of the RoS,
Nos. 72/09 and 81/09)- The Law on Environmental Protection (Official Gazette of the RoS,
Nos. 135/04 and 36/09)- The Law on Waters (Official Gazette of the RoS, No. 30/10)- The Law on Concessions (Official Gazette of the RoS, No. 55/03)- The Law on Public Companies and Performing Activities of Public Inter-
est (Official Gazette of the RoS, Nos. 25/00, 25/02, 107/05, and 108/05)
- The Law on Public Utility Companies (Official Gazette of the RoS, Nos.
16/97 and 42/98)
and other relevant laws and executive regulations.
RelevantLegislation
- The Ministry of Mining and Energy - MME- A Local Self-government Unit - LSU- The Energy Agency - EA
- The Republic Geodetic Authority - RGA- The Ministry of Agriculture, Forestry and Water Management - MAFWM- The Ministry of Environment and Spatial Planning - MESP- The competent secretariats of the Autonomous Province- The Republic Hydro-meteorological Service - RHMS- The Electric Grid of Serbia - EMS- The Electric Power Industry of Serbia - EPS
Other competent institutions in each concrete case
CompetentInstitutions
I Acquiring the right to survey and exploitation ofhydrogeothermal resources
II Acquiring the right to the construction of a power plantfacility
III Acquiring the right to electricity/heat generation
From an Idea toExploitation
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
8/64
6
Main Steps from an Ideato Exploitation (I)
IAcquiring the right to survey andexploitation of hydrogeothermalresources
I-1 Geological surveys
Geological survey projectApproval for geological surveys
Feasibility study of geological investigations Feasibility study of groundwater reserves
I-2 Exploitation of hydrogeothermal energy
Approval for exploitation of mineral resources Approval to carry out mining works
I-3 Mining facilities
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
9/64
7
Main Steps from an Idea to Exploitation (I)Acquiring the right to survey and exploitation of hydrogeothermal resources I
Geological surveys are undertaken with the aim ofestablishing the hydro-geological potential of a deposit I-1
GeologicalSurveys
I-1Approval ofGeological
Surveys
Basic geological surveys (undertaken for public interest andfinanced from the budget of the Republic of Serbia)
Feasibility study of the resultsof geological surveys
Detailed geological surveys (necessary for drawing up of geotechnical andhydro-geotechnical documents for the exploitation of geothermal energy)
The Request for approval of thesurvey
Approval of the survey (definesdeadlines for commencementand completion of the survey)
Geological survey project
The report and certification of thetechnical supervision
Approval of the Institute for NatureConservation of Serbia
Water requirements (Slide II-3/5)
Approval of the Intra-municipal Institutefor Protection of Cultural Monuments
Technical supervision - establishessupervision for (1) the implementation of
modern achievements and methods of thegeological science and engineering and
(2) for harmonization with technicalregulations, codes, and standards
Deadline:30 days
(maximum60 days)
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
10/64
8
Main Steps from an Idea to Exploitation (I)Acquiring the right to survey and exploitation of hydrogeothermal resourcesI
I-1FeasibilityStudy ofGeologicalSurveys- Contents -
I-1FeasibilityStudy ofGround WaterReserves
- Presentation and evaluation of former surveys
- Aim and method of investigation
- A systematic presentation of data obtained in field investigations
- Presentation and explanation of survey results
- Presentation of reserves of mineral resources, conditions forexploitation, and measures for protection of the environment
- Techno-economic assessment of survey results
A feasibility study of results of geological surveys has the characterarchival materials and it is kept permanently in line with the regulations
The party in charge of a survey is obliged to submit one copy of thefeasibility study to the authority that initially issued the approval forthe survey
- The economic entity undertaking the works (the party in charge of a
survey) must submit the feasibility study of the ground water reserveson an exploratory/exploitation field to the Ministry of Environment andSpatial Planning, or to the competent authority of the AutonomousProvince every fifth year, in order to establish and certify ground waterreserves
A feasibility study of results of geological surveys has the character ofarchival materials and it is kept permanently in line with the regulations
The party in charge of a survey is obliged to submit one copy of thefeasibility study to the authority that initially issued the approval for
the survey
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
11/64
9
Exploitation of hydrogeothermal energy is the process bywhich hydrogeothermal energy is used I-2
Exploitationof Hydro-
geothermalEnergy
I-2Approval forExploitation
of MineralResources
EXPLOITATIONPERMIT
Approval to CarryOut Mining Works
Water Permit
Approval forExploitation
Inspection
Certificate for
Mining Facilities
Request forthe Approval
for
Exploitation
Approval forExploitation
Site map (1:25000)
Evidence of ownership rights or of the right to use
Feasibility study of exploitation of mineral resource deposits
The decision of the Ministry of Agriculture, Forestry andWater Management, when exploitation is planned on
agricultural land
Approval from the Ministry of Environment and Spatial Planning
Water requirements, the Water approval, and the Waterpermit (Slides: II-3/5, II-4/6, and II-5/4)
The decision of the authority in charge of town planning
affairs on harmonization of exploitation of mineral resources
with the relevant spatial, or urban development plans
The decision on established and certified reserves of groundwater (verification of balance reserves of mineral resources),
issued for a maximum 2 years
Main Steps from an Idea to Exploitation (I)Acquiring the right to survey and exploitation of hydrogeothermal resources I
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
12/64
10
I-2Approval toCarry outMining Works
I-3MiningFacilities
The Request for the approvalfor carrying out mining works
(the Ministry of Mining andEnergy)
The approval to carry outmining works
Approval of the Ministry of Environmentand Spatial Planning
The mining design, including the report oncompleted technical supervision
Certificate of verified balance reserves
Evidence of ownership rights or of theright to use
Water approval (Slide II-4/6)
Approval of the Ministry of Agriculture,Forestry and Water Management
- Mining facilities are directly related to the technological process of the
surveys, exploitation, and transportation of ground waters in an
exploitation field
- The inspection certificate for mining facilities is an administrative
document issued by the Ministry of Mining and Energy, which approves
the use of a mining facility or of a part thereof
Main Steps from an Idea to Exploitation (I)Acquiring the right to survey and exploitation of hydrogeothermal resourcesI
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
13/64
11
I-4Exploitation
of Hydro-geothermal
Energy
Exploitation for electricity and/or heat generation
Acquiring the right to constructa power plant
Acquiring the rights to engagein electricity and/or heat
generation
Direct exploitation
Regulations on planning andconstruction
Construction of the facilitywhere hydrogeothermal
energy will be used directly
Main Steps from an Idea to Exploitation (I)Acquiring the right to survey and exploitation of hydrogeothermal resources I
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
14/64
12
Main Steps from an Ideato Exploitation (II)
IIAcquiring the right to construct andthe construction of a power plant facility
I-1 The information on location
I-2 Acquiring the energy permit
I-3 Obtaining the location permit
I-4 Obtaining the building permit
Construction of the facility
I-5 Acquiring the Operating Permit
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
15/64
13
II-1Location
Selection,Perusal of
Valid PlanningDocuments,
and theInformationon Location
II-2EnergyPermit
The location planned forconstruction of an energy facility
Request for obtaining theinformation on the location
A copy of the lot, the List of lot owners (RealEstate Cadastral Service of a municipality)
Obtaining the approval from theMinistry of Agriculture, Forestry and
Water Management
Selection of the location
The information on the location
Perusal of the valid planning document (a local self-government unit)
Deadline: 8 days
No
Yes
ENERGYPERMIT
Constructionfeasibility study
Bank statementshowing bank readiness to
support the Investor inthe financing
The informationon location
The opinion of the
energy system
operator concerning
the possibilities for
connection
The energy permit is a key element in acquiring the rightto construct an energy facility; it is obtained in accordancewith Serbias Program on Implementation of the EnergySector Development Strategy
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facility II
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
16/64
14
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facilityII
II-2Obtainingthe EnergyPermit
II-3Location
Permit
Request for the energypermit (Form O-1)
Request for the energy permit(Form O-2)
Requestfor theenergypermit(FormO-10)
Prefeasibility Study with theGeneral Design
Electricity generatingpower plant
(Ministry of Mining
and Energy)
> 10 MW
Heat generatingpower plant(a local self-
government unit)
Heat-and-power co-generatingplant(Ministry of Mining and
Energy + a local self-government
unit)
Power plant power > 1 MW
Energy permit (valid for 2 years and may be
extended at the request of the holder)
The energy permit is notrequired
The deadline for all the Requestsis 30 days (appealable within 7
days from receipt of the decision)
Yes
Yes
No
No
LOCATIONPERMIT
Requirementsfor designing
collected
The technical documentationfor a geothermal power plant
facility (data on the facility/thegeneral design)
Property-rightsissues resolved
The construction plot
formed (allotment/
re-allotment)
The location permit contains all the requirements and data
necessary for preparation of the technical documentation and
the main design, in accordance with a valid planning document
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
17/64
15
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facility II
II-3Requirementsfor Connection
to the Electri-city/District
Heating
Network
II-3Forming theBuilding Plot
The technical report specifies whether power and technicalconditions are in place for possible future connection of the
facility according to the submitted Request
Request for the requirements for connection to the system (to the energy entity towhich the producers facility will be connected)
Issuing of therequirements for connection
Deadline: 30 days (maximum 60 days), and
appealable within 15 days from receipt of
the decision
Preparation of the allotment/re-allotmentplan (it must include the Design ofGeodetic Survey Benchmarking)
Submitting the plan to the competent
authority in charge of town planningaffairs at the local self-government unit
Party that submittedthe plan receives
notification
The plan is inaccordance with
the valid planningdocument
The competentauthority verifies the plan
Complaint to the city/town/municipal council
Submitting the Request to beundertaken allotment/re-allotment(the Republic Geodetic Authority)
Decision on forming theCadastre Lot (s)
Deadline: 3 days
Deadline:
10 days
No
Yes
Deadline: 30 days (maximum 60 days),
and appealable within 15 days from
receipt of the decision
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
18/64
16
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facilityII
II-3WaterRequirements
II-3Obtaining the
LocationPermit
Deadline: 30 days (maximum 60 days)
Deadline: 30 days (maximum 60 days)
The opinion of the Republic
organization in charge of hydro-
meteorological affairs
Preliminary Feasibility Study, includingthe general design
The opinion of the public water-management company
A special opinion needsto be obtained
Obtaining the opinion
(the Ministry of Environ-
ment and Spatial Plan-
ning and/or a specialized
scientific institution)
Obtaining the opinion
(the ministry in charge
of tourism affairs)
The facility
is in the
territory
of a spa
The Request for an opinion of the
Republic organization in charge of
hydro-meteorological affairs (RHMS)
The Request for the opinion of apublic water-management
company (JVP Srbija vode/JVP VodeVojvodine)
The decision on issuing the Water
requirements
The Request for the Water require-ments (to the Ministry of Agriculture,
Forestry and Water Management)
Deadline: 30 days (maximum 60 days)
Yes
Yes
No
No
The Request for the location permit (10 MW, to the Ministry of Environment and Spa-
tial Planning or to the Autonomous Province,
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
19/64
17
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facility II
II-4Building
Permit
II-4Environmental
Impact
Assessment
(1)
After completing the the technical supervision of the main de-sign and the positive report on a completed technical supervi-
sion, the Request for the Building Permit must be submitted
to the competent authority at the local self-government unit
BUILDINGPERMIT
TheEnvironmental
Impact AssessmentStudy
Approvals for thedesign Documentation and the
Environmental ImpactAssessment Study
The design
documentation
(the preliminary design,
the main design)
Technicalsupervision of
the designdocumentation
The Environmental Impact Assessment Study maybe requested
Power plantpower > 1 MW
Power plantpower > 50 MW
Notification tothe investor and
to the publicabout thedecision
Notifications to the interested authorities and to the public
Obtaining the opinions from the interestedauthorities and the public
The competent authority makes the decision onthe request on the need for environmental impact
assessment
The request for deciding on the need to assess theimpact (10 MW, to the Ministry of Environment and
Spatial Planning or to the Autonomous Province,
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
20/64
18
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facilityII
II-4Environmental
Impact
Assessment
(2)
II-4Environmental
Impact
Assessment(3)
The decisiondefines the scope andcontents of the Study
The request for determining the scope and contentsof the impact assessment study (10 MW, to the
Ministry of Environment and Spatial Planning or to theAutonomous Province,
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
21/64
19
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facility II
TechnicalDocumentation
II-4Water
Approval and
Technical
Supervision of
the Design
Feasibility study with the preliminary design (containing the layout plan)
Feasibility study with the preliminary design (containing the layout plan)
Subject to review (expert supervision) by the committee (the review committee)
The review committee submits, to the investor, the report containingmeasures that must be applied when preparing the Main Design
The Main Design
Preliminary feasibility study, including the general design
Yes
No
Deadline: 30 days
The Water approval of the main design(valid for 2 years from the date of receipt,
time during which the Request for theConstruction Permit must be submitted)
Obtaining the approval from the Minis-try of Environment and Spatial Planning
on the Main Design
Request for the Water approval (to theMinistry of Agriculture, Forestry and
Water Management/to the competent
authority of the AP of Vojvodina)
Obtaining the approval of the Main
Design from authorities/organizations,
when specified in the requirements
contained in the location permit
Technical supervision of the design
Obtaining the approval fromthe Ministry of Health for the
Main Design
The Main Design
Deadline: 30 days, maximum 60
days, appealable within 15 daysfrom submitting the decision
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
22/64
20
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facilityII
II-4ConstructionPermit* -Attachmentsto theRequest
II-4Obtaining theConstructionPermit
Technical supervisionof the Main Design
The design has been preparedaccording to the codes of construction
contained in the location permit
Notification to the Investorto revise the design within
30 days
The design revised within 30 days
The report on the completed technical supervision of the Main Design
The request for the Construction Permit (10 MW, to the Ministry of Environment
and Spatial Planning or to the Autonomous Province,
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
23/64
21
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facility II
- The technical inspection determines the fitness of afacility for us
- A facility may be used after the Operating Permit hasbeen obtained
- It is necessary to submit the As-built Design in theprocess of obtaining the Operating Permit
II-5Operating
Permit
II-5Construction
of a FacilityThe Main Design contains detailsneeded to carry out the works
The Detailed Design
Registration of the commencement of construction of the facility
Marking of the building plot, regulation, leveling, and buildinglines, marking of the construction site with an adequate panel
The Main Design andthe Decision on theConstruction Permit
Construction of the facility
No
Yes
OPERATINGPERMIT
As-builtdesign
Water Permit
Constructionof a facility
Technical
inspection of
the constructed
facility
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
24/64
22
Main Steps from an Idea to Exploitation (II)Acquiring the right to construct and the construction of a power plant facilityII
II-5TechnicalInspectionand OperatingPermit
The request for the technicalinspection of the facility
Forming of the commission fortechnical inspection of the facility
Technical inspection
Fitness of the facility foruse needs to be
established
The commission proposes to approvesetting of the facility in test operation
to the competent authority
The request for theWater Permit
The decision on issuingthe Water PermitThe decision on approval to set
the facility into test operation
The commission verifies fulfillment of therequirements for issuing the operating permit
The Report/Finding of the commissionfor technical inspection
As-built design ofthe facility
Construction of thefacility
The OperatingPermit
Yes
No
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
25/64
23
Main Steps from an Ideato Exploitation (III)
IIIAcquiring the right to generate
electricity/heat
III-1 Acquiring the right to engage in an activity of public interest
III-2 License
III-3 Approval for connection
III-4 Acquiring the status of a privileged producer
III-5 Engaging in the activity of electricity/heat generation
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
26/64
24
Main Steps from an Idea to Exploitation (III)Acquiring the right to generate electricity/heatIII
- The precondition for pursuing electricity/heat generationand for acquiring a license
- Several models existIII-1The Right toElectricityGeneration- AcquisitionMethod
III-1Assigning theEngagementin an Activityof PublicInterest
Electricity generation
The Republic activity of publicinterest (competence: the
Ministry of Mining and Energy)
Heat generation
A public utility service(competence: a local
self-government unit)
Conclusion of the AssignmentAgreement that assigns the
activity of public interest:electricity generation
Conclusion of the AssignmentAgreement that assigns the
activity of public utility services(heat generation)
1. Investment in
affiliated companies
of a public
company
2. Assigning the
right to engage in
an activity of public
interest
3. Granting
concessions
- It involves clear and relatively short procedures
- A potential problem - a parent public company isreluctant to allow a major share of the Investor
- Risk - a high degree of discretionary power of the
founder of the public company
- The investor acquires the right only after conclusionof the Assignment Agreement, and the Agreement isconcluded only after the facility has been constructed
- In practice, a simpler procedure compared toconcessions
- Most often applied in practice
- The Investor acquires the right through a clearly
defined procedure at the very start- The obligation to set up a new economic operator
- The lengthiest procedure
or
or
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
27/64
25
Main Steps from an Idea to Exploitation (III)Acquiring the right to generate electricity/heat III
III-1The Assignment
Agreement -
Requirements
to be met
III-1The Assignment
AgreementAssigning the
Activity -
Contents/
Provisions
- Adequate technical prerequisites (the ownership right or the right to use the powerplant, which has been constructed in accordance with the law, technical and other
regulations)
- Staff capacity (that persons working in the power plant have the necessary
qualifications and other prescribed skills)
- Implementation of the prescribed safety at work
- Implementation of the prescribed requirements and method of protection and
improvement of the environment
- Operation and business of the economic operator to whom this activity is assigned
- Obligations of the economic operator to provide the conditions for continuous,
proper, and quality needs of the users of products and services
- Mutual rights and obligations of the parties to the Agreement in cases where
economic and other conditions for pursuing the activity of public interest are
not provided
- Rights and obligations in case of a disruption in the economic operators business
operation
- Other rights, obligations and important issues to protect the public interest
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
28/64
26
Main Steps from an Idea to Exploitation (III)Acquiring the right to generate electricity/heatIII
III-2Concession
III-2Concession- Contents ofa ConcessionAgreement
Proposal for adoptionof a concession deed
The concession deed
The report of the Commis-sion ot undertake the public
invitation for tenders
The decision designating theconcessionaire
Concession Agreement
Public invitation for tenders
Proposal forgranting a concession
Setting up of a concessionary enterprise
- The parties to the Agreement, the subject matter of the concession, including thedescription of the facility and equipment
- Duration of the concession period and conditions under which such terms may beextended
- Manner of and deadlines for securing the funds for financing the concessionbusiness (the financial plan) and the time line of their employment, the amount andmethod of providing guarantees for fulfillment of the concessionary obligation
- The requirements for conducting the concessionary business
- Standards of products and services, technology transfer
- Criteria for setting the end-user prices-tariffs for products and services
- The concession fee (the amount, deadlines, conditions, and the method of payment)
- Rights and obligations concerning the undertaking of measures to ensure generalsafety, protection of health and protection of the environment as well as liabilities forcompensation of damage caused by jeopardizing general safety and protection ofthe environment
- The rights to transfer the concession
- The time and method of handing over the immovables, the facility, equipment orplants and the condition in which they must be handed over
- Conditions for amendments or termination of the agreement and their consequences,
changed circumstances and force majeure
- The method of settling disputes and enforcement of applicable law, control, etc.
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
29/64
27
Main Steps from an Idea to Exploitation (III)Acquiring the right to generate electricity/heat III
- The license is a permit to engage in an energy-relatedactivity; it is issued by the Energy Agency of theRepublic of Serbia
- It is required only for power plants with a 1MW or higher
power
III-2The Assignment
Agreement vs.
Concession -
Main
Differences
III-3License
- Acquiringthe License
Heat or electricity generation for ownrequirements or for electricity generation
in power plants of up to 1 MW
Request for the License
(to the Energy Agency)
Acquiring the License
is not required
The decision on grantingthe License
(valid for 10 years)
Yes
No
Deadline: 30 days
- The tendering procedure is not prescribed
- The obligation to specify the place for engaging in electricity generation is not
stipulated (if it is not tied to a concrete facility by the agreement)
- The maximum time period for engaging in an activity of public interest is not
specified (if it is not defined in the agreement)
- The obligation to establish the scope of engaging in an activity is not prescribed
- The obligation to pay a fee for engaging in an activity of public interest is
not prescribed
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
30/64
28
Main Steps from an Idea to Exploitation (III)Acquiring the right to generate electricity/heatIII
III-4Approvalfor theConnection tothe ElectricityNetwork
III-4Approvalfor theConnection
to the DistrictHeatingNetwork
The decision on approval of the conne-ction (valid for 2 years, appealable within
15 days to the Energy Agency)
The Request for the approval to connect thefacility to the electric power grid
The technical report for issuing theDecision on approval of connection
to the electric power grid
Electricitygenerating power
plant
The Electricity Purchase Agreement
CHP plant
Deadline: 30 days
The Request for approval for a power plantconnection to the heat distribution system
Verification of fulfillment of the requirements: whether the equipment andinstallations of the facility that are to be connected meet the requirementsprescribed under the law, technical, and other regulations governing the
conditions and the method of exploitation of such facilities
CHP plant
The decision on approval of the connection (appealablewithin 15 days from submitting the decision)
Heat production facility
Deadline: 30 days
A Precondition for electricity and/or heat to be suppliedto consumers
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
31/64
29
Main Steps from an Idea to Exploitation (III)Acquiring the right to generate electricity/heat III
III-5The Status of
a PrivilegedProducer
III-5Acquiring
the Status ofa Privileged
Producer
The Request for the status ofa privileged producer
Electricitygenerating power
plant
Heat generatingpower plant
Heat-and-powerco-generating plant
The decision on acquiringthe status of a privileged
electricity producer(valid for 12 years)
It is possible to acquire the status of aprivileged producer on the local
self-government unit level if it enactsrelevant regulationsDeadline: 30 days
- The priority right in an organized market with respectto other producers offering electricity under equalterms and conditions
- The right to subsidies (tax, customs, and other relieves/facilities)
Incentives - Feed-in tariffs:
Power Plant Type Installed power (MW) Incentive - feed-in tariff
(cEUR/1 kWh)
Power Plant Type 7,5
Co-generation plants usingfossil fuels
Up to 0,2 MW Co=10,4
Co-generation plants usingfossil fuels
from 0,2 MW to 2 MW Co=10,667-1,333*P
Co-generation plants usingfossil fuels
from 2 MW to 10 MW Co=8,2
Co-generation plants using
fossil fuels
from 2 MW to 10 MW Co=8,5
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
32/64
30
Main Steps from an Idea to Exploitation (III)Acquiring the right to generate electricity/heatIII
III-6PowerPurchaseAgreement
EPS
The Power Purchase AgreementTerm. 12 years
The Request to sign the Power PurchaseAgreement
BACK TO CONTENT
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
33/64
31
IZGRADNJA POSTROJENJA IPROIZVODNJA ELEKTRINE/TOPLOTNEENERGIJE IZ HIDROGEOTERMALNIHIZVORA U REPUBLICI SRBIJI -
VODI ZA INVESTITORE
32 Uvodna re34 Energija iz geotermalnih izvora34 Hidrogeotermalna energija34 Elektrane za proizvodnju energije iz hidrogeotermalnih izvora34 Prava investitora35 Izvori prava35 Nadlene institucije
35 Od ideje do korienja36 Osnovni koraci od ideje do korienja (I)
36 I Sticanje prava na istraivanje i ekploataciju geotermalnih izvora37 I-1 Geoloka istraivanja
37 I-1 Odobrenje za geoloka istraivanja
38 I-1 Elaborat o geolokim istraivanjima - Sadraj
38 I-1 Elaborat o rezervama podzemnih voda
39 I-2 Eksploataci ja hidrogeotermalne energije
39 I-2 Odobrenje za eksploataciju mineralnih sirovina
40 I-2 Odobrenje za izvoenje rudarskih radova
40 I-3 Rudarski objekti
41 Korienje hidrogeotermalne energije
42 Osnovni koraci od ideje do korienja (II)43 II-1 Izbor lokacije, uvid u vaee planske dokumente i informacija o lokaciji
43 II-2 Energetska dozvola
44 II-2 Pribavljanje energetske dozvole
44 II-3 Lokacijska dozvola
45 II-3 Uslovi za prikljuenje na elektroenergetsku i/ili mreu daljinskog grejanja45 II-3 Formiranje graevinske parcele
46 II-3 Vodni uslovi
46 II-3 D obijanje lokacijske dozvole
47 II-4 Graevinska dozvola
47 II-4 Procena uticaja na ivotnu sredinu (1)
48 II-4 Procena uticaja na ivotnu sredinu (2)
48 II-4 Procena uticaja na ivotnu sredinu (3)
49 Tehnika dokumentacija
49 II-4 Vodna saglasnost i tehnika kontrola projekta
50 II-4 Graevinska dozvola, prilozi uz zahtev
50 II-4 Dobijanje graevinske dozvole
51 II-5 Upotrebna dozvola
51 II-5 Izgradnja objekta
52 II-5 Tehniki pregled i upotrebna dozvola
53 Osnovni koraci od ideje do korienja (III)53 III Koraci za sticanje prava na obavljanje proizvodnje elektrine/toplotne energije
54 III-1 Pravo na obavljanje proizvodnje elektrine energije - nain sticanja
54 III-1 Poveravanje obavljanja delatnosti od opteg interesa
55 III-1 Ugovor o poveravanju delatnosti - uslovi koji moraju biti ispunjeni
55 III-1 Ugovor o poveravanju delatnosti - sadraj/odredbe
56 III-2 Koncesija
56 III-2 Koncesija - Sadraj koncesionog ugovora
57 III-2 Ugovor o poveravanju u odnosu na.koncesi ju - osnovne razlike
57 III-3 Licenca - Pribavljanje licence
58 III-4 Odob renje za prikljuenje elektrane na elektroenergetsku mreu
58 III-4 Odobrenje za prikljuenje elektrane na mreu za distribuciju toplotne energije
59 III-5 Status povlaenog proizvoaa
59 III-5 Sticanje statusa povlaenog proizvoaa
60 III-6 Ugovor o otkupu elektrine energije
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
34/64
Obnovljiva energija iz biomase, vetra, malih hidroelektrana i geotermalnihizvora je u centru panje drava, potencijalnih investitora i potroaa u celomsvetu. U 2007. godini, Evropska Unija (EU) postavila je cilj zemljama lanicamada, do 2020. godine, 20% energije u svakoj od zemalja treba da potekne izobnovljivih izvora energije.
Srbija ima znaajne izvore obnovljive energije kojima bi mogla da zadovoljinovonastale zahteve. Vlada Srbije je razvila strategiju kako bi iskoristila ovupriliku. Da bi podstakla razvoj i investicije u ovaj sektor i ispunila obavezu poUgovoru o energetskoj zajednici Jugoistone Evrope, Vlada Srbije je usvojilanekoliko propisa po direktivi od novembra 2009, ukljuujui:
Uspostavljanje sistema podsticajnih tarifa u kom e Vlada Srbije
subvencionisati troak obnovljive struje;
Denisanje zahteva za sticanje statusa Povlaenog proizvoaa
elektrine energije koji koristi obnovljive izvore energije za proizvodnjustruje;
Od usvajanja podsticajnih tarifa i ostalih kljunih propisa od strane VladeSrbije, GTZ Projekat Jaanje lokalne samouprave (GTZ JLS) je saraivao sa
relevantnim ministarstvima, USAID Projektom za razvoj konkurentnosti iinvestitorima u privatni sektor, kako bi podstakao investicije u obnovljiveizvore energije.
32IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
35/64
Kljuna aktivnost je bila kreiranje konanih vodia za proces izdavanjadozvola za obnovljive izvore sa ciljem podsticanja investitora i drugih trinihuesnika da postanu aktivni u ovom sektoru. Predstavnici Ministarstvarudarstva i energetike, Ministarstva zatite ivotne sredine i prostornogplaniranja i Ministarstva poljoprivrede, umarstva i vodoprivrede zajedno sastrunjacima GTZ-a su kreirali etiri takva vodia, koji objanjavaju
proces dobijanja dozvola za razvijanje projekata za podsektore geotermalnevode, malih hidroelektrana, energije vetra i biomase. USAID Projekat zarazvoj konkurentnosti je podrao GTZ JLS u kreiranju vodia za investitore kaodeo svojih aktivnosti vezanih za podsticanje investicija u sektor kroz pruanjetehnike pomoi perspektivnim investitorima.
Svaki vodi je kreiran u vidu detaljnog dokumenta, koji opisuje administra-tivne procedure i identifikuje institucije od znaaja i dokumenta vezana zaplaniranje i izradu projekata koja su neophodna za investitore. Vodii
obuhvataju i zakonski i regulatorni okvir i treba da se koriste kao osnova zadalje zakonske i regulatorne reforme. GTZ JLS je takoe pripremio krau
verziju vodia, koji predstavljaju saetke vodia koje investitori mogu dakoriste za nalaenje podataka.
Nadamo se da e ovaj korak biti podstrek za dalji dijalog izmeu privatnog
sektora i Vlade kako bi se identifikovale i uklonile prepreke razvoju ifinansijskoj odrivosti sektora.
33 IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
36/64
34
Energija izgeotermalnihizvora
- Geotermalna energija predstavlja toplotu akumuliranuu suvim stenama i fluidima Zemljine kore, kao posledicaneprekidnog zraenja toplote iz unutranjosti Zemlje
- Geotermalna energija, moe biti:
- hidrogeotermalna energija - akumulirana u fluidima (vodi i gasovima) i- petrogeotermalna energija - akumulirana u vrstim stenama
Hidrogeo-termalnaenergija
- Hidrogeotermalna enegija je jedan od oblika obnovljivihizvora enegije
- Hidrogeotermalna energija moe da se koristi direktno, amoe da se koristi i za proizvodnju toplotne energije i zaproizvodnju elektrine energije
Elektrane zaproizvodnjuenergije izhidrogeotermal-
nih izvora
- Elektrane na hidrogeotermalnu energiju koje slue zaobavljanje delatnosti proizvodnje elektrine i/ili toplotneenergije
- Male elektrane - snage do 10MW- Velike elektrane - snage od 10 MW i vie
Pravainvestitora
Investitor mora da stekne sledea prava:
- I Pravo na eksploataciju- II Pravo na izgradnju- III Pravo na obavljanje proizvodnje elektrine/toplotne energije
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
37/64
35
- Zakon o energetici (Sl. Glasnik RS br. 84/04)- Zakon o rudarstvu (Sl. glasnik RS br. 44/95, 85/05-dr.zakon,
101/05-dr.zakon, 34/06 i 104/09)- Zakon o geolokim istraivanjima (Sl.glasnik RS, br. 44/95)- Zakon o utvrivanju i razvrstavanju rezervi mineralnih sirovina i
prikazivanju podataka geolokih istraivanja (Sl.list SRJ br. 12/98 i
13/98)- Zakon o planiranju i izgradnji (Sl. glasnik RS br. 72/09 i 81/09)- Zakon o zatiti ivotne sredine (Sl. glasnik RS br. 135/04 i 36/09)- Zakon o vodama (Sl. glasnik RS br. 30/10)- Zakon o koncesijama (Sl. glasnik RS br. 55/03)- Zakon o javnim preduzeima i obavljanju delatnosti od opteg
interesa (Sl. glasnik RS br. 25/00, 25/02, 107/05 i 108/05)- Zakon o komunalnim delatnostima (Sl. glasnik RS br. 16/97 i 42/98)
i ostali pratei zakoni i podzakonska akta...
Izvori prava
- Ministarstvo rudarstva i energetike - MRE- Jedinica lokalne samouprave - JLS- Agencija za energetiku - AE- Republiki geodetski zavod - RGZ- Ministarstvo poljoprivrede, umarstva i vodoprivrede - MPV- Ministarstvo ivotne sredine i prostornog planiranja - MSPP- Nadleni sekretarijati Autonomne pokrajine
- Republiki hidrometeoroloki zavod - RHMZ- Elektromrea Srbije - EMS- Elektroprivreda Srbije - EPS
i ostale nadlene institucije u konkretnom sluaju
Nadleneinstitucije
I Sticanje prava na na istraivanje i eksploataciju
hidrogeotermalne izvora
II Sticanje prava na izgradnju objekta elektrane
III Sticanje prava na obavljanje proizvodnjeelektrine/toplotne energije
Od ideje
do korienja
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
38/64
36
Osnovni koraciod ideje do korienja (I)
ISticanje prava na istraivanje ieksploataciju hidrogeotermalnih izvora
I-1 Geoloka istraivanja
Projekat geolokih istraivanjaOdobrenje za geoloka istraivanja
Elaborat o geolokim istraivanjima Elaborat o rezervama podzemnih voda
I-2 Eksploatacija hidrogeotermalne energije
Odobrenje za eksploataciju mineralnih sirovina Odobrenje za izvoenje rudarskih radova
I-3 Rudarski objekti
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
39/64
37
Osnovni koraci od ideje do korienja (I)Sticanje prava na istraivanje i eksploataciju hidrogeotermalnih izvora I
Geoloka istraivanja se sprovode u cilju da se utvrdihidrogeoloki potencijal leita I-1
Geolokaistraivanja
I-1Odobrenjeza geolokaistraivanja
Osnovna geoloka istraivanja(posao od opteg interesa i finansira se iz budeta Republike Srbije)
Elaborat o rezultatimageolokih istraivanja
Detaljna geoloka istraivanja (neophodna za izradu geotehnikih ihidrogeotehnikih podloga za korienje geotermalne energije)
Zahtev za izdavanje odobrenjaza istraivanje
Odobrenje za istraivanje(definie rokove za zapoinjanje
i zavravanje istraivanje)
Projekat geolokih istraivanja
Izvetaj i potvrda o tehnikoj kontroli
Saglasnost Zavoda za zatitu prirode Srbije
Vodni uslovi (Slajd II-3/5)
Saglasnost meuoptinskog Zavoda zazatitu spomenika kulture
Tehnika kontrola - utvruje kontroluprimene savremenih dostignua i metoda
geoloke nauke i tehnike i usklaenostisa tehnikim propisima, normativima i
standardima
Rok je30 dana
(najkasnije60 dana)
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
40/64
38
Osnovni koraci od ideje do korienja (I)Sticanje prava na istraivanje i eksploataciju hidrogeotermalnih izvoraI
I-1Elaborat ogeolokimistraivanjima- Sadraj -
I-1Elaborat orezervamapodzemnihvoda
- prikaz i ocena ranijih istraivanja
- cilj i nain istraivanja
- sistematizovani prikaz podataka dobijenih terenskim istraivanjima
- prikaz i objanjenje rezultata istraivanja
- prikaz rezervi mineralnih sirovina, uslova eksploatacije i merezatite ivotne sredine
- tehno-ekonomska ocena rezultata istraivanja
Elaborat o rezultatima geolokih istraivanja ima karakter arhivskegrae i uva se trajno, u skladu sa propisima
Nosilac istraivanja je duan da jedan primerak elaborata dostaviorganu koji mu je izdao odobrenje za istraivanje
- Svake pete godine privredni subjekt koji vri radove (nosilacistraivanja) dostavlja Ministarstvu ivotne sredine i prostornog
planiranja, odnosno nadlenom organu autonomne pokrajine, Elaborato rezervama podzemnih voda na istranom / eksploatacionom polju,radi utvrivanja i overavanja rezervi podzemnih voda
Elaborat o rezultatima geolokih istraivanja ima karakter arhivskegrae i uva se trajno, u skladu sa propisima
Nosilac istraivanja je duan da jedan primerak elaborata dostaviorganu koji mu je izdao odobrenje za istraivanje
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
41/64
39
Osnovni koraci od ideje do korienja (I)Sticanje prava na istraivanje i eksploataciju hidrogeotermalnih izvora I
Eksploatacija hidrogeotermalne energije je postupakkorienja hidrogeotermalne energije I-2
Eksploatacijahidro-
geotermalneenergije
I-2Odobrenje zaeksploataciju
mineralnihsirovina
EKSPLOATACIJA
Odobrenje zaizvoenje rudarskih
radova
Vodna dozvola
Odobrenje zaeksploataciju
Upotrebna dozvoleza rudarske objekte
Zahtev zaizdavanje
odobrenja za
eksploataciju
Odobrenje zaeksploataciju
Situaciona karta (1:25000)
Dokaz o pravu svojine ili korienja
Studija izvodljivosti eksploatacije leita mineralnih sirovina
Akt Ministarstva poljoprivrede, umarstva i vodoprivrede,
kada se planira eksploatacija na poljoprivrednom zemljitu
Saglasnost Ministarstva ivotne sredine i prostornogplaniranja
Vodni uslovi, vodna saglasnost i vodna dozvola (Slajdovi:II-3/5, II-4/6 i II-5/4)
Akt organa nadlenog za poslove urbanizma u pogledu
usaglaenosti eksploatacije mineralnih sirovina, sa
odgovarajuim prostornim, odnosno urbanistikim planovima
Reenje o utvrenim i overenim rezervama podzemnih voda(potvrda o bilansnim rezervama mineralnih sirovina), koje
nije starije od 2 godine
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
42/64
40
Osnovni koraci od ideje do korienja (I)Sticanje prava na istraivanje i eksploataciju hidrogeotermalnih izvoraI
I-2Odobrenjeza izvoenjerudarskihradova
I-3Rudarskiobjekti
Zahtev za izdavanje odobrenjaza izvoenje rudarskih radova
(Ministarstvo rudarstva ienergetike)
Odobrenje za izvoenjerudarskih radova
Saglasnost Ministarstva ivotne sredine iprostornog planiranja
Rudarski projekat sa izvetajem oizvrenoj tehnikoj kontroli
Potvrda o overenim bilansnim rezervama
Dokaz o pravu svojine ili korienja
Vodna saglasnost (Slajd II-4/6)
Saglasnost Ministarstva poljoprivrede,umarstva i vodoprivrede
- Rudarski objekti su vezani neposredno za tehnoloki proces istraivanja,
eksploatacije i transporta podzemnih voda na eksploatacionom polju
- Upotrebna dozvola za rudarske objekte je administrativni (upravni)akt koji izdaje Ministarstvo rudarstva i energetike i kojim se odobravaupotreba rudarskog objekta ili njegovog dela
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
43/64
41
Osnovni koraci od ideje do korienja (I)Sticanje prava na istraivanje i eksploataciju hidrogeotermalnih izvora I
Korienjehidro-
geotermalneenergije
Korienje za proizvodnjuelektrine i/ili toplotne
energije
Sticanje prava na izgradnjuelektrane
Sticanje prava naobavljanje delatnosti
proizvodnje elektrine i/ilitoplotne energije
Direktno korienje
Propisi o planiranju i izgradnji
Izgradnja objekta u kome sedirektno koristi hidrogeo-
termalna energija
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
44/64
42
Osnovni koraciod ideje do korienja (II)
IISticanje prava na izgradnjui izgradnja objekta elektrane
I-1 Informacija o lokaciji
I-2 Pribavljanje energetske dozvole
I-3 Pribavljanje lokacijske dozvole
I-4 Pribavljanje graevinske dozvole
- Graenje objekta
I-5 Pribavljanje upotrebne dozvole
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
45/64
43
IIOsnovni koraci od ideje do korienja (II)
Sticanje prava na izgradnju i izgradnja objekta elektrane
II-1Izbor lokacije,uvid u vaee
planskedokumente iinformacija o
lokaciji
II-2Energetska
dozvola
Lokacija predviena za izgradnjuenergetskog objekta
Zahtev za dobijanje informacijeo lokaciji
Kopija parcele, Lista vlasnikaparcele (Sluba za katastar
nepokretnosti optine)
Pribavljanje saglasnosti Ministarstvapoljoprivrede, umarstva i vodoprivrede
Izbor lokacije
Informacija o lokaciji
Uvid u vaei planski dokument (jedinica lokalne samouprave)
rok 8 dana
Ne
Da
ENERGETSKADOZVOLA
Elaborato izgradnji
Izjava banke o spremnostida prati investitora
u finansiranju
Informacija olokaciji
Miljenje operatera
distributivnog sistema
o mogunostima
prikljuenja
Energetska dozvola je element sticanja prava naizgradnju energetskog objekta, koji se pribavlja u skladusa Programom ostvarivanja Strategije razvoja energetikeRepublike Srbije
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
46/64
44
IIOsnovni koraci od ideje do korienja (II)Sticanje prava na izgradnju i izgradnja objekta elektrane
II-2Pribavljanjeenergetskedozvole
II-3Lokacijska
dozvola
Zahtev za izdavanje ener-getske dozvole (Obrazac O-1)
Zahtev za izdavanje energetskedozvole (Obrazac O-2)
Zahtev zaizdavanje
energetske
dozvole(Obrazac
O-10)
Izrada prethodne studije oprav-danosti sa generalnim projektom
Elektrana zaproizvodnju
elektrine energije(Ministarstvo
energetike irudarstva)
> 10 MW
Elektranaza proizvodnju
toplotne energije(jedinica lokalne
samouprave)
Elektrana za kombinovanuproizvodnju elektrine i
toplotne energije(Ministarstvo energetike i
rudarstva + jedinica lokalnesamouprave)
Snaga elektrane > 1 MW
Energetska dozvola (vai 2 godine i moe se
produiti na zahtev imaoca)
Nije potrebnaenergetska dozvola
Rok za sve zahteve je 30 dana(alba se podnosi u roku od 7dana od prijema reenja)
Da
Da
Ne
Ne
ENERGETSKADOZVOLA
Prikupljeni usloviza projektovanje
Tehnika dokumentacijaza objekat elektrane na biomasu/
biogas (podaci o objektu/generalni projekat)
Reeniimovinsko-pravni
odnosi
Izvreno formiranje
graevinske parcele
(parcelacija/
preparcelacija)
Lokacijska dozvola sadri sve uslove i podatke potrebneza izradu tehnike dokumentacije, glavnog projekta, a uskladu sa vaeim planskim dokumentom
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
47/64
45
IIOsnovni koraci od ideje do korienja (II)
Sticanje prava na izgradnju i izgradnja objekta elektrane
II-3Uslovi za
prikljuenjena elektro-
energetsku i/ili mreu za
daljinskogrejanje
II-3Formiranje
graevinskeparcele
Tehniki izvetaj - utvruje da li postoje energetskii tehniki uslovi za eventualno budue prikljuenje
objekta prema podnetom zahtevu
Zahtev za izdavanje uslovaza prikljuenje korisnika na sistem (energetskom subjektu na
iji sistem se prikljuuje objekat proizvoaa energije)
Izdavanje akta o uslovima prikljuenjaRok je 30 dana (najkasnije 60 dana), a alba se
podnosi u roku od 15 dana od prijema reenja
Izrada projekta parcelacije/preparcelacije(obavezno sadri Projekat geodetskog
obeleavanja)
Predaja projekta nadlenom organu
za poslove urbanizma jedinice lokalnesamouprave
Obavetava sepodnosilac
projekta
Projekatje u skladu sa
vaeim planskimdokumentom
Nadleni organpotvruje projekat
Prigovor gradskomoptinskom veu
Podnoenje Zahteva za provoenjeparcelacije/preparcelacije
(Republiki geodetski zavod)Reenje o formiranju
katastarske(ih) parcele(a)
Rok je 30 dana
Rok je
10 dana
Ne
Da
Rok je 30 dana (najkasnije 60 dana),
a alba se podnosi u roku od 15 dana
od prijema reenja
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
48/64
46
IIOsnovni koraci od ideje do korienja (II)Sticanje prava na izgradnju i izgradnja objekta elektrane
II-3Vodni uslovi
II-3Pribavljanje
lokacijskedozvole
Rok je 30 dana (najkasnije 60 dana)
Rok je 30 dana (najkasnije 60 dana)
Miljenje republike organizacije
nadlene za hidrometeoroloke
poslove
Prethodna studija opravdanosti sageneralnim projektom
Miljenje javnog vodoprivrednogpreduzea
Potrebno je pribavljanjeposebnog miljenja
Pribavljanje miljenja
(Ministarstvo ivotne
sredine i prostornog
planiranja i/ili specijalizo-
vana nauna institucija)
Pribavljanje miljenja
(Ministarstvo nadleno
za poslove turizma)
Objekat je
na teritoriji
banjskog
mesta
Zahtev za dobijanje miljenjarepublike organizacije nadlene zahidrometeoroloke poslove (RHMZ)
Zahtev za dobijanje miljenja javnogvodoprivrednog preduzea (JVPSrbija vode/JVP Vode Vojvodine)
Reenje o izdavanju vodnih uslova
Zahtev za dobijanje vodnihuslova (Ministarstvu poljoprivrede,
umarstva i vodoprivrede)
Rok je 30 dana (najkasnije 60 dana)
Da
Da
Ne
Ne
Zahtev za dobijanje lokacijske dozvole (10 MW Ministarstvu ivotne sredine iprostornog planiranja ili Autonomnoj pokrajini,
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
49/64
47
IIOsnovni koraci od ideje do korienja (II)
Sticanje prava na izgradnju i izgradnja objekta elektrane
II-4Graevinska
dozvola
II-4Procena
uticaja naivotnu
sredinu (1)
Po izvrenoj tehnikoj kontroli glavnog projekta i pozitivnomizvetaju o izvrenoj tehnikoj kontroli, nadlenom organu
jedinice lokalne samouprave podnosi se zahtev za izdavanje
graevinske dozvole
GRAEVINSKADOZVOLA
Studija o proceniuticaja na
ivotnu sredinu
Saglasnosti naprojektnu dokumentaciju
i studiju uticaja
Tehnika kontrola
projektne
dokumentacije
Projektnadokumentacija(idejni projekat,glavni projekat)
Moe se zahtevati izrada studije uticaja na ivotnusredinu
Snaga elektrane> 1 MW
Snaga elektrane> 50 MW
Obavetavanjeinvestitora i
javnosti o odluci
Obavetavanje zainteresovanih organa i javnosti
Dobijanje miljenja zainteresovanih organa i javnosti
Nadleni organ donosi odluku po zahtevu o potrebiprocene uticaja
Zahtev za odluivanje o potrebi procene uticaja(10 MW Ministarstvu ivotne sredine i prostornog
planiranja ili autonomnoj pokrajini,
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
50/64
48
IIOsnovni koraci od ideje do korienja (II)Sticanje prava na izgradnju i izgradnja objekta elektrane
II-4Procenauticaja naivotnusredinu (2)
II-4Procenauticaja naivotnusredinu (3)
U odluci je definisanobim i sadraj studije
Zahtev za odreivanje obima i sadraja studije oproceni uticaja (10 MW Ministarstvu ivotne sredine i
prostornog planiranja ili autonomnoj pokrajini,
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
51/64
49
IIOsnovni koraci od ideje do korienja (II)
Sticanje prava na izgradnju i izgradnja objekta elektrane
Tehnikadokumentacija
II-4Vodna
saglasnost
i tehnika
kontrola
projekta
Studija opravdanosti sa idejnim projektom (sadri situaciono reenje)
Objekat iz lana 133. stav 2. taka 5), 9) i 20) Zakona o planiranju i izgradnji
Podlee reviziji (strunoj kontroli) komisije (reviziona komisija)
Reviziona komisija dostavlja investitoru izvetaj sa merama koje seobavezno primenjuju pri izradi glavnog projekta
Glavni projekat
Prethodna studija opravdanosti sa generalnim projektom
Da
Ne
rok 30 dana
Vodna saglasnost na glavni projekat (vai2 godine od dana dobijanja, u toku kojihmora da se podnese zahtev za izdavanje
graevinske dozvole)
Pribavljanje saglasnosti Ministarstvaivotne sredine i prostornog planiranja
na glavni projekat
Zahtev za dobijanje vodne saglasnosti(Ministarstvu poljoprivrede, umarstva i
vodoprivrede / nadlenom organu
AP Vojvodine)
Pribavljanje saglasnosti na glavniprojekat od organa/organizacija,kada je to predvieno uslovimasadranim u lokacijskoj dozvoli
Tehnika kontrola projekta
Pribavljanje saglasnostiMinistarstva zdravlja na
glavni projekat
Glavni projekat
rok 30 dana, najkasnije 60 dana,
alba u roku od 15 dana oddostavljanja reenja
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
52/64
50
II-4Graevinskadozvola* -prilozi uzzahtev
II-4Pribavljanjegraevinskedozvole
Tehnika kontrolaglavnog projekta
Projekat je uraen u skladu sapravilima graenja sadranim u
lokacijskoj dozvoli
Obavetavanje investitorada u roku od 30 dana uskladi
projekat
Projekat je usklaen u roku od 30 dana
Izvetaj o izvrenoj tehnikoj kontroli glavnog projekta
Zahtev za izdavanje graevinske dozvole (10 MW Ministarstvu ivotne sredine iprostornog planiranja ili autonomnoj pokrajini,
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
53/64
51
- Podobnost objekta za upotrebu utvruje se tehnikimpregledom
- Objekat se moe koristiti po prethodno pribavljenojupotrebnoj dozvoli
- U procesu dobijanja upotrebne dozvole potrebno jepriloiti projekat izvedenog stanja
II-5Upotrebna
dozvola
II-5Izgradnja
objektaGlavni projekat sadri razradu detaljapotrebnih za izvoenje radova
Izvoaki projekat
Prijava poetka graenja objekta
Obeleavanje graevinske parcele, regulacionih, nivelacionih igraevinskih linija, obeleavanje gradilita odgovarajuom tablom
Glavni projekati Reenje o
graevinskoj dozvoli
Izgradnja objekta
Ne
Da
UPOTREBNADOZVOLA
Projekatizvedenog
stanja
Vodna dozvola
Izgradnjaobjekta
Tehniki pregled
izgraenog
objekta
IIOsnovni koraci od ideje do korienja (II)
Sticanje prava na izgradnju i izgradnja objekta elektrane
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
54/64
52
IIOsnovni koraci od ideje do korienja (II)Sticanje prava na izgradnju i izgradnja objekta elektrane
II-5Tehnikipregled iupotrebnadozvola
Zahtev za izvrenje tehnikogpregleda objekta
Obrazovanje komisije za tehnikipregled objekta
Tehniki pregled
Potrebnoutvrivanje podobnosti
objekta za upotrebu
Komisija predlae nadlenomorganu da odobri putanje
objekta u probni rad
Zahtev za dobijanje vodnedozvole
Reenje o izdavanju vodnedozvoleReenje o odobravanju
putanja objekta u probni rad
Komisija proverava ispunjenost uslovaza izdavanje upotrebne dozvole
Izvetaj/Nalaz komisije zatehniki pregled
Projekat izvedenogobjekta
Izgradnja objekta
Upotrebna dozvola
Da
Ne
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
55/64
53
Osnovni koraciod ideje do korienja (III)
IIISticanje prava na
obavljanje proizvodnjeelektrine/toplotne energije
III-1 Sticanje prava na obavljanja delatnosti od opteg interesa
III-2 Koncesija
III-3 Licenca
III-4 Odobrenje za prikljuenje
III-5 Sticanje statusa povlaenog proizvoaa
III-6 Obavljanje delatnosti proizvodnje elektrine/toplotne energije
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
56/64
54
Osnovni koraci od ideje do korienja (III)Sticanje prava na obavljanje proizvodnje elektrine/toplotne energijeIII
- Preduslov za obavljanje delatnosti proizvodnje elektrine/toplotne energije i za pribavljanje licence
- Postoji vie modelaIII-1Pravo naobavljanjeproizvodnjeelektrineenergije
- nainsticanja
III-1Poveravanjeobavljanjadelatnosti odopteginteresa
Proizvodnja elektrineenergije republika delatnost od
opteg interesa(nadlenost: Ministarstvo
rudarstva i energetike)
Proizvodnja toplotne energije
komunalna delatnost(nadlenost: jedinica lokalne
samouprave)
Zakljuenje Ugovora opoveravanju delatnosti od
opteg interesa proizvodnjeelektrine energije
Zakljuenje Ugovora opoveravanju obavljanjakomunalnih delatnosti
(proizvodnja toplotne energije)
1. Ulaganje u
zavisna drutva
javnog
preduzea
2. Poveravanje
prava obavljanja
delatnosti od
opteg interesa
3. Dodeljivanje
koncesija
- Ima jasne i relativno kratke procedure
- Potencijalni problem - matino javno preduzee tekodozvoljava veinski udeo Investitora
- Rizik - velik stepen diskrecione vlasti osnivaa javnog
preduzea
- Investitor stie pravo tek po zakljuivanju ugovora opoveravanju, a ugovor se zakljuuje tek posleizgradnje objekta
- Jednostavnija procedura u praksi u odnosu na koncesije
- Najee primenjivano u praksi
- Investitor stie pravo kroz jasno definisanu proceduru
na samom poetku- Obaveza osnivanja novog privrednog subjekta
- Najdugotrajniji postupak
Ili
Ili
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
57/64
55
IIIOsnovni koraci od ideje do korienja (III)
Sticanje prava na obavljanje proizvodnje elektrine/toplotne energije
III-1Ugovor o
poveravanjudelatnosti
- uslovi kojimoraju biti
ispunjeni
III-1Ugovor o
poveravanjudelatnosti- sadraj/odredbe
- Adekvatna tehnika opremljenost (pravo vlasnitva ili pravo korienja elektrane,koja je izgraena u skladu sa zakonom, tehnikim i drugim propisima)
- Kadrovska osposobljenost (da lica koja rade u elektrani imaju neophodnu strunu
spremu i druga propisana znanja)
- Sprovoenje propisane zatite na radu
- Ostvarivanje propisanih uslova i naina zatite i unapreenja ivotne sredine
- Rad i poslovanje privrednog subjekta kome se poverava ova delatnost
- Obaveze privrednog subjekta u pogledu obezbeivanja uslova za kontinuirano,
uredno i kvalitetno zadovoljavanje potreba korisnika proizvoda i usluga
- Meusobna prava i obaveze ugovornih strana u sluaju kada nisu obezbeeni
ekonomski i drugi uslovi za obavljanje delatnosti od opteg interesa
- Prava i obaveze u sluaju poremeaja u poslovanju privrednog subjekta
- Druga prava i obaveze i pitanja koja su od znaaja za ostvarivanje zatite opteg interesa
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
58/64
56
Osnovni koraci od ideje do korienja (III)Sticanje prava na obavljanje proizvodnje elektrine/toplotne energijeIII
III-2Koncesija
III-2Koncesija -sadraj
ugovora okoncesiji
Predlog za donoenjekoncesionog akta
Koncesioni akt
Izvetaj Komisije osprovoenju javnog tendera Odluka o odreivanju koncesionara
Ugovor o koncesiji
Javni tender
Predlog za davanjekoncesije
Osnivanje koncesionogpreduzea
- Ugovorne strane, predmet koncesije, ukljuujui opis objekata i ureaja
- Rok trajanja koncesije i uslovima pod kojim se taj rok moe produiti
- Nain i rokovi obezbeivanja sredstava za finansiranje koncesione delatnosti (finansijski
plan) i dinamika njihovog ulaganja, visina i nain obezbeenja garancija za izvravanje
koncesione obaveze
- Uslovi obavljanja koncesione delatnosti
- Standardi proizvoda i usluga, transfer tehnologije
- Kriterijumi za odreivanje cena-tarifa proizvoda i usluga za krajnje korisnike- Koncesiona naknada (visina, rokovi, uslovi i nain plaanja)
- Prava i obaveze u pogledu preduzimanja mera obezbeivanja opte sigurnosti, zatite
zdravlja i zatite ivotne sredine kao i odgovornosti za naknadu tete prouzrokovane
ugroavanjem opte sigurnosti i zatite ivotne sredine
- Prava na prenos koncesije
- Vreme i nain predaje nepokretnosti, objekta, ureaja ili postrojenja i stanje u kome se
oni moraju predati
- Uslovi izmena ili raskida ugovora i njihove posledicae, promenjene okolnosti i via sila
- Nain reavanja sporova i primena merodavnog prava, kontrola i sl.
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
59/64
57
IIIOsnovni koraci od ideje do korienja (III)
Sticanje prava na obavljanje proizvodnje elektrine/toplotne energije
III-2Ugovor o
poveravanjuu odnosu
na koncesiju -osnovne
razlike
III-3Licenca
- Pribavljanjelicence
Obavljanje proizvodnjetoplotne ili elektrine energije za sopst-
vene potrebe ili za proizvodnju elektrineenergije u elektranama do 1 MW
Zahtev za dobijanje licence(Agenciji za energetiku)
Nije potrebnopribavljanje licence
Reenje o licenci(vai 10 godina)
Da
Ne
rok 30 dana
- Nije propisana tenderska procedura
- nije utvrena obaveza utvrivanja mesta obavljanja delatnosti proizvodnje elektrine
energije (ukoliko se ugovorom ne vee za konkretan objekat
- nije utvren maksimalan rok obavljanja delatnosti od opteg interesa (ukoliko se
ugovorom ne definie)
- nije propisana obaveza utvrivanja obima obavljanja delatnosti
- nije propisana obaveza plaanja bilo kakve naknade za obavljanje delatnosti od opteg
interesa
- Licenca je dozvola za obavljanje energetske delatnostikoju izdaje Agencija za energetiku Republike Srbije
- Potrebna samo za elektrane snage od 1MW i vee
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
60/64
58
Osnovni koraci od ideje do korienja (III)Sticanje prava na obavljanje proizvodnje elektrine/toplotne energijeIII
III-4Odobrenje zaprikljuenjeelektrane neelektroener-getsku mreu
III-4Odobrenje zaprikljuenjeelektrane na
mreu zadistribucijutoplotneenergije
Zahtev za izdavanje odobrenja za prikljuenjeobjekta na elektroenergetsku mreu
Tehniki izvetaj za izdavanjeReenja o odobrenju za prikljuenje
na elektroenergetsku mreu
Elektrana zaproizvodnju
elektrine energije
Reenje o odobrenju prikljuenja(vai 2 godine, alba u roku od 15
dana Agenciji za energetiku)Ugovor o otkupu
Elektrana za kombinovanuproizvodnju elektrine i toplotne
energije
rok 30 dana
Zahtev za odobrenje za prikljuenje elektranena distributivni sistem za toplotnu energiju
Provera ispunjenosti uslova - da ureaji i instalacije objekta koji seprikljuuje ispunjavaju uslove propisane zakonom, tehnikim i drugimpropisima kojima se ureuju uslovi i nain eksploatacije tih objekata
Elektrana za kombinovanuproizvodnju elektrine i
toplotne energije
Reenje o odobrenju prikljuenja(alba u roku od 15 dana od
dostavljanja reenja)
Elektrana za proizvodnjutoplotne energije
rok 30 dana
Preduslov da se elektrina i/ili toplotna energija dopremido potroaa
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
61/64
59
IIIOsnovni koraci od ideje do korienja (III)
Sticanje prava na obavljanje proizvodnje elektrine/toplotne energije
III-5Status
povlaenogproizvoaa
III-5Sticanje
statusapovlaenogproizvoaa
Zahtev za sticanje statusapovlaenog proizvoaa
Elektrana zaproizvodnju
elektrine energije
Elektrana zaproizvodnju
toplotne energije
Elektrana za kombinovanuproizvodnju elektrine i
toplotne energije
Reenje o sticanju statusapovlaenog proizvoaa
elektrine energije(vai 12 godina)
Status povlaenog proizvoaa mogueje ostvariti na nivou jedinice lokalnesamouprave ukoliko donesu propise
rok 30 dana
- Pravo prioriteta na organizovanom tritu u odnosu na dru-ge proizvoae koji nude energiju pod jednakim uslovima
- Pravo na subvencije (poreske, carinske i druge olakice)
Mere podsticaja - Feed-in tarife:
Vrsta elektrane Instalisana snaga (MW) Mera podsticaja -otkupna cena (cEUR/1 kWh)
na geotermalnu energiju 7,5
sa kombinovanomproizvodnjom na fosilnagoriva
do 0,2 MW Co=10,4
sa kombinovanomproizvodnjom na fosilnagoriva
od 0,2 MW do 2 MW Co=10,667-1,333*P
sa kombinovanomproizvodnjom na fosilnagoriva
od 2 MW do 10 MW Co=8,2
sa kombinovanomproizvodnjom na fosilnagoriva
od 2 MW do 10 MW Co=8,5
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
62/64
60
Osnovni koraci od ideje do korienja (III)Sticanje prava na obavljanje proizvodnje elektrine/toplotne energijeIII
III-6Ugovor ootkupuelektrineenergije
EPS
Ugovor o otkupu elektrine energijeRok vaenja 12 godina
Zahtev za potpisivanje Ugovora ootkupu elektrine energije
IDI NA SADRAJ
5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
63/64
See the detailed text of the Guide for Investors at the web site of the Ministry of Mining and Energy
Detaljno uputstvo za investitore moete pronai na web sajtu Ministarstva rudarstva i energetike
www.mre.gov.rs
http://www.mre.gov.rs/http://www.mre.gov.rs/5/24/2018 Hidrogeotermalna Elektronska- VODI ZA INVEST
64/64
Izrada ove publikacija omoguena je podrkom amerikog naroda kroz Ameriku agenciju zameunarodni razvoj (USAID) u saradnji sa Nemakom organizacijom za tehniku saradnju (GTZ), a podralisu je Ministarstvo rudarstva i energetike i Ministarstvo ivotne sredine i prostornog planiranja, i ona
ne mora nuno da odraava stavove USAID ili Vlade Sjedinjenih amerikih drava, niti GTZ ili Vlade SavezneRepublike Nemake
This publication is made possible by the support of the American people through the United States Agencyfor International Development (USAID) in cooperation with the German Development Agency (GTZ),supported by the Ministry of Mining and Energy and the Ministry of Environment and Spatial Planning, anddoes not necessarily reflect the views of USAID or the United States Government nor the views of GTZ or theGovernment of Federal Republic of Germany