    IRPMU

    NORTH CENTRAL RAILWAY

    PROGRESS OF WORKS

    ON

    HATHRAS YARD

    AS ON 08-06-2013

  • 7/28/2019 HRS Presentation

    2/24

    Name of work

    The work of addition and alteration

    to signalling gears in connection with

    yard remodeling and provision ofSolid State Interlocking (SSI) at

    Hathras station

    Plan HeadPH 16 (Traffic Facility Plan Head)

    Allocation DF(3)

    First included in the PB2008-09

    PB Item No. (2012-13)

    46 (Traffic Facility-Yard remodelling

    and Others)

    Sanctioned Estimated CostRs.11.15 Cr.

    Date of award of Tenders/Contract

    SSI being done as part of KfW project

    alongwith Yard remodelling

    SSI WORK AT HATHRAS (HRS)

  • 7/28/2019 HRS Presentation

    3/24

    Sl. No. CabinsPresent No.

    of Levers

    Status of Cabins after

    introduction of SSI

    1 East Cabin 42 levers Cabin will not be required

    2 West Cabin 35 levers Cabin will not be required

    DETAILS OF HATHRAS STATION

    Hathras Jn. is a 'B' class station interlocked with Colour light signaling,

    having 2 cabins for train working along with automatic block working

    with adjoining stations Pora on East (Kanpur side), Sasni on West (Delhi)

    side and staff working .

  • 7/28/2019 HRS Presentation

    4/24

    Summary for Solid State Interlocking at HATHRAS(Routes- 103)

    Present

    working

    Hathras yard is operated through 2 cabins with lever frames

    Scope Complete Indoor & Outdoor works as per approved plans

    All Indoor works to be carried out in SER (ECU-36)

    Comparison of various existing gears with new plan

    Functions As per existing SIP As per SIP for SSI

    a. Main signals 15 20b. Shunt Signals 07 19

    c. Calling On Signals Nil 04

    d. Routing signals 03 04

    e Points Machines 26 32

    f Siding points Nil 01

    F Track Circuits 23 49

    g No of Routes Nil 103

    /

  • 7/28/2019 HRS Presentation

    5/24

    SSI/HRS

    Summary of the progress

    CRS sanction received on 20.03.13

    S&T works progress

    Indoor works All the Indoor work completed, All 8 Microlocks powered Up,

    Simulation wiring completed

    Testing

    Logic testing completed by IRPMU.

    2nd round of FAT testing by IRPMU completed.

    Outdoor work90% work completed.

    P. Way works - Total 28 new Points to be inserted in the work (15 in Before Pre NI,

    12 in Pre NI and 1 in Post NI). Total 22 points to be dismantled in the work (10in

    Before Pre NI, 12 in Pre NI)

    .OHE & Elect. Works Total 140 masts (including portals) to be erected.

    Out of these, 125 masts erected. Old masts 10 no to be dismantled which shall becarried out in Pre-NI/NI period.

  • 7/28/2019 HRS Presentation

    6/24

    SSI HRS working

    MAIN ITEMS

    FOR Pre Pre-NI

    Engg. works S&T works Elect. & OHEworks

    Before

    Pre NI

    Points /Turn-

    outs

    Insertion of 15 new

    points, Dismantlingof 10 points

    Fixing of 15 Point

    m/cs, dismantling ofmech fittings and DC

    track ckt

    Associated works

    like provision ofCatenary wires

    and Insulators

    Pre NI

    12 days

    Points /Turn-

    outs

    Insertion of 12 new

    points, Dismantling

    of 12 Points

    Fixing of 12 Pointm/cs,

    Associated works

    like provision of

    Catenary wiresand Insulators

    NI 01

    days

    Points /Turn-

    outs

    Nil Commissioning of

    SSI

    Nil

    Post NI

    07 days

    Points /Turn-

    outs

    Dismantling of

    West Cabin and

    Linking of line 3,4

    and misc works

    Insertion of 1 new

    Point

    Dismantling of

    existing mech fittings

    and DC track Ckt

    connections Insertion

    of 1 new Point

    Associated works

    like provision of

    Catenary wires

    and Insulators

  • 7/28/2019 HRS Presentation

    7/24

    Detailed Scope of work along with progress for Indoor activities

    Sl.

    No.Description Total Qty Qty done Remarks

    1 Installation of LCP TwoTwo (To be

    reprogrammed

    as per SSI)

    To bereprogrammed

    with SSI

    2Erection of relays racks, CT racks, M Lock

    racks13 racks 13 racks

    Completed

    3 Termination in CT rack, Wiring/jumpering ofrelays, Wiring of M Lock rack

    13 racks 13 racks Completed

    4Installation of power supply (IPS) along with

    AT1 set at ECU-36 Completed Completed

    5 Supply of Data Logger & installation One Maint. PC NilTo be done with

    SSI

    6 Block instrument installation & wiring N/A N/A

    Train Staff

    system between

    Hathras and

    Hathras Qila

    7 Fixing of Telecom Equipments 1 Set

    Completed

    with Auto

    Signalling

    Completed

  • 7/28/2019 HRS Presentation

    8/24

    Detailed Scope of work along with progress for Indoor activities

    Sl.No.

    Description Total Qty Qty done Remarks

    08 Simulation Testing (SAT) 01 Lot (103 routes)To be done

    after FAT

    To start on 10.06.13

    09 Testing by Operating Deptt. 01 Lot (103 routes)To be done

    after SAT

    To be done after SAT

  • 7/28/2019 HRS Presentation

    9/24

  • 7/28/2019 HRS Presentation

    10/24

    ADVANTAGES OF SSI

    The major advantages of commissioning of HRS SSI can be divided in the

    following parts:-

    Safety Benefits

    Manpower saving

    Operational Benefits

    Maintenance Benefits

    1. Safety Benefits

    Removal of worn out lever frames and mechanical rodding.

    After commissioning of SSI, existing East & West Cabins and SM

    Slide Frame will be removed completely and all the operations shall bedone from the LCPs provided in the ASM room of HRS station.

    After SSI complete yard and all the running will be DC track circuited

    from Home to Home. Presently Hathras Qila side branch line, line no 5

    and 6 are non- track circuited.

    2. Manpower saving

    Complete elimination of operation from the East and West cabins will

    result in saving of manpower involved in operation at these cabins

    round the clock.

  • 7/28/2019 HRS Presentation

    11/24

  • 7/28/2019 HRS Presentation

    12/24

    Maintenance Benefits

    After commissioning of SSI at HRS, all departments will bebenefitted from maintenance point of view.

    1. S&T Department

    Improvement in cable maintenance after laying of New cables in theentire yard.

    Improvement in maintenance of points after provision of point

    machines in place of old & worn out rod operated mechanical points.

    Replacement of steel/wooden turnouts by PRC turnouts having better

    reliability of points.

    Maintenance PC/Data logger for the entire system facilitating

    predictive maintenance & monitoring.

    Provision of Stabilised power supply in 1+1 configuration through IPS,

    having 100% standby.Provision of glued joints for track circuiting.

    2. Engg DepartmentReplacement of steel/wooden turnouts by PRC turnouts having betterreliability.

    3. TRD Department

    Change in sub section plan of OHE of the yard having more flexibility

    from operation and maintenance point of view.

  • 7/28/2019 HRS Presentation

    13/24

    Before Pre-Pre-NI( Blocking of line no 5

    and 6)

    Work involved

    Insertion of 8 points, fixing of point machines and its testing

    electrically by 110 V i.e. 213, 283, 285 A, 285 B, 287 A, 287 B,

    289 A, 289 B( As per proposed SIP)

    Dismantling of two points i.e. 33 E and 7 E ( As per existing

    SIP)

    Energization of 12 track circuits

  • 7/28/2019 HRS Presentation

    14/24

    Works done Before Pre Pre-NI

    (Blocking of line no . 5 and 6)Day Point (s)

    already

    inserted

    Point (s) already

    dismantled

    Track circuit

    already

    energized ( in

    nos)

    Signal already

    erected (in

    nos)

    Blockingof line

    no. 5

    and 6

    213, 283, 285A, 285 B, 287 A,

    287 B, 289 A,

    289 B (Total 8

    nos.)

    33E, 7E (Twonos.) C3T, 3T, CLT1,CLT2, CLT3,

    285T, 283T,

    289 AT, 297

    AT, 287T,

    CL3T2, CL3T3

    (12 nos.)

    14

  • 7/28/2019 HRS Presentation

    15/24

  • 7/28/2019 HRS Presentation

    16/24

    Works involved during Pre Pre-NI

    Day Point (s) to be

    inserted

    Point (s) to be

    dismantled

    Track circuit

    energized

    Signal

    erection

    D-23 291A 7E/Lock8 (east

    end)

    --

    D-22 209 B 28L27(E) CL2T1, CL2T2,CL2T3

    D-21 209A 11L10, 19L22 209 BT S-13

    D-20 211,296 11L10

    D-19 215 K-1/1-K 8T,215T

    D-18 207 21/Lock 20 205T

  • 7/28/2019 HRS Presentation

    17/24

  • 7/28/2019 HRS Presentation

    18/24

    During Pre NI ( 12 days)

    Work Involved

    Insertion of 8 point, fixing of point machines and its testing

    electrically by 110 V i.e. 201b, 299b on line no. 1 and 201a,

    203, 295a,295 b, 297b, 299a on line no. 2.

    Dismantling of 8 points i.e. Pt29E, Pt25WL29E on line no 1,

    Pt29EL22, Pt28EL32E, Pt25EL24E, Pt19WL18W, Pt28WL24W,

    Pt25WL20W on line no. 2.

    Energization of 17 no of track circuits.

  • 7/28/2019 HRS Presentation

    19/24

  • 7/28/2019 HRS Presentation

    20/24

    Day Point (s) to be

    inserted

    Point (s) to be

    dismantled

    Track circuit

    energized

    Signal

    erection

    D-6 295 B Pt 29 Trailing 295BT

    D-5 295 A, 203 -- 295AT, 203T

    D-4 25 W connected

    to line no. 1

    D-3 25 W connected

    to line no. 2

    297 BT

    D-2 28W connected

    to line no. 2

    298 BT

    D-1 -- Pt 25(line 2) eastend, Pt 28 (line

    2) east end, Pt

    28 (line 3) west

    end

    298 AT,202BT, 202AT

  • 7/28/2019 HRS Presentation

    21/24

  • 7/28/2019 HRS Presentation

    22/24

  • 7/28/2019 HRS Presentation

    23/24

    Post NI ( 7 days)

    Work Involved

    Dismantling of West Cabin building

    Dismantling of 35 levers and associatedroddings.

    Insertion of Point no. 291 A

  • 7/28/2019 HRS Presentation

    24/24

    Works involved during Post NIDay Point (s) to be inserted

    Point (s) to be dismantled

    Track circuit

    energized

    Remarks

    D+1 Dismantling of West Cabin,

    Dismantling of 32 levers and its

    associated rod dings, Linking of

    line no 3 and 4 at west end.

    Testing of line no. 3 , 4, 5 and 6.

    Line no. 4 will

    remain

    suspended

    due to

    obstruction

    of West cabin

    and levers,

    roddings etc

    D+2

    D+3

    D+4 291T,295BT

    D+5

    D+6

    D+7 Testing of Line no 4