Joju Johny - ADSCM - SPL Case Study

Embed Size (px)

Citation preview

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    1/15

    ADVANCED SUPPLY

    CHAIN MANAGEMENT

    Case Study

    Improving DRP effectiveness in ERPenvironment

    Karuna Jain & Sunil Phabiani

    Joju Johny

    Roll No 17

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    2/15

    Company Profile The largest household insecticide player in the country and the

    worlds largest producer of mosquito repellent mats.

    SPL is now in the growth phase. Its three major bands SP1, SP2, SP3

    command almost 70 percent share of the mosquito repellent mats

    market, which is the largest category of household insecticides in

    India.

    Logistics Network: 4 manufacturing sites at Pondichery, Goa, Silvassa

    and Nashik.4 regional offices in metros Delhi. Mumbai, Chennai,

    Calcutta. Each regional office has CFAs under its jurisdiction.

    Distribution Planning - distribution mainly constitutes of two types of

    materials movements

    factory to the depots directly

    from the factory to the hub centers from which it is then sent

    to the satellite depots

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    3/15

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    4/15

    Problem Definition

    SPL has implemented the distribution module of ERP - Rs 3 crore.

    All CFAs have distribution module of ERP. Weekly sales and stocks

    arrive from CFAs electronically through emails.

    Inspite of that, the DRP functions were not being used by the logistics

    department.

    Only if DRP functionality is used, the benefits of having a common

    platform for information exchange can be more successful

    Thus the efficacy of the current manual dispatch plan was calculated

    Observation - The manual distribution plan was not the best plan.Marginal improvement over the FY 1996 97. Transportation cost had

    increased and the inventory turnover was poor.

    All these showed that there was scope for improvement and it was

    believed that DRP is one such tool which can improve this.

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    5/15

    Objectives

    The project was initiated

    to draw the top management attention towards the need

    for using DRP by showing its impact on the bottom line of

    the organization

    to develop confidence in the users about the DRP

    functionality by demonstrating how it could improve the

    performance of the logistics department

    To achieve these objectives the study wasdivided into 2 phases namely Phase I and

    Phase II

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    6/15

    Phase I

    Develop a frameworkfor benefitquantification.

    Simulating thedistribution of SPL

    using DRP.

    Comparing thesimulated distributionplans with actual

    distribution plans. Projecting the benefits

    and its impact oncorporate profitability.

    Phase II

    Identifying issues incurrent DRP practices.

    Reviewing inputs toDRP

    Analyzing the problemareas

    Recommending theimprovements

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    7/15

    Proposed Comprehensive Modelfor DRP

    The job of DRP is to manage the flow of materials fromsupply sites to demand sites.

    this was accomplished in three distinct phases

    Input Phase: forecast, customer orders, inventory records and

    planning parameters for each SKU.

    DRP process phase: DRP generates a time phased model of

    resource requirements to support logistics strategy.

    Output Phase: The DRP generates the planned order dictated

    by the item order policies and align the order by due date with

    demand which is known as planned order releases.

    A good distribution model is the one which provides both

    internal mechanisms of the process and its linkages with the

    other processes of the organization.The proposed model of

    DRP is one such model.

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    8/15

    Measure for Quantification

    A meaningful quantification would be one thatshows an impact on the bottom line of the

    organization.

    Return of Investment is one such measure, which takes

    into consideration not only the impact on the bottom line

    but also on the cash flows and asset utilization.

    Logistics department is the one whose impact

    could be seen in all the financial aspects of the

    business and ROI could prove to be the right

    platform to project the benefits of DRP.

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    9/15

    Simulation Exercise In order to quantify the benefits of DRP, a simulation exercise was carried to

    prove that if DRP was used instead of the current manual system, then benefits

    like reduction in inventory, reduced transportation costs could be achieved.

    Simulation Parameter: The simulations used for the study are:

    Fixed Order Quantity (truckload).

    Planning horizon (raw material procurement to receipt by CFAs eight

    weeks)

    Lead times as per contract agreement.

    Data Requirement: The data required for the simulation exercise is as follows:

    Opening stocks and goods in transit

    Weekly sales and value of stocks.

    Actual dispatches from factory to CFAs.

    Analysis Parameter: Number of dispatches

    Weekly inventory position.

    Avoidable dispatches Inter CFA

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    10/15

    Impact on CorporateProfitability

    Reduction in cost: savings of 31.68

    Lakhs

    Reduction in assets: weekly inventoryhad reduced in each region.

    Impact on ROI: 1.2 % increase in the ROI for

    SPL from the use of DRP module of the ERP

    system.

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    11/15

    DRP Review Further to see the impact of forecast accuracy on

    performance of DRP, a similar situation exercise was carriedout.

    It was found that with 100 percent accuracy DRP can further

    bring down the transportation and inventory carrying costs

    by 15 %. Conclusion: the correctness of the system is entirely

    dependent upon the correctness of parameters fed into the

    system

    Therefore, to improve effectiveness, those inputs that aredynamic, need to be identified and treated accordingly.

    Using this methodology it was found that the dynamic inputs

    to DRP are Safety Stock (SS), Lead time (LT), Bill of

    Distribution (BOD) and ordering Policy (OP).

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    12/15

    The Proposed Semi DynamicModel

    Based on the parameters mapping results, it wasfound that parameters should be changed every

    quarter.

    To incorporate this dynamic feature in the

    comprehensive model proposed by them, one had

    to modify the model.

    The model was renamed as Semi Dynamic Model

    for DRP process (SDMD) generalized the findings

    for SPL, where the planning parameter fed to DRP

    are function of sales trend and/or time

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    13/15

    Recommendations

    Planning process: The distribution planning should be donecentrally by taking DRP run at every HO every week.

    Using DRP to generate MPS to synchronize operations: The

    integration of DRP with MPS gives a single, continuous

    seamless system that uses one set of logic across theoperations.

    Revising DRP parameters every quarterly:

    Using safety stocks for demand uncertainties, calculated at

    95 % service level. Using safety time for lead time uncertainties, calculated at 95

    % service level.

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    14/15

    Recommendations

    Following periodic order quantity (POQ) dispatch policy,

    where period shall be calculated for optimum total cost

    from a trade off analysis between transportation cost and

    inventory holding cost.

    The time bucket of one week should be uniformly applied.

    Dispatch variance report should be generated by factory,

    giving reasons for any dispatches not done as per the

    dispatch plan.

    Provide the DRP summary information to depots so that

    even the branch managers have the visibility of the system

    and can suggest changes in the forecasts or lead times

    which according to them are not correct.

  • 8/3/2019 Joju Johny - ADSCM - SPL Case Study

    15/15