Upload
joju-johny
View
217
Download
0
Embed Size (px)
Citation preview
8/3/2019 Joju Johny - ADSCM - SPL Case Study
1/15
ADVANCED SUPPLY
CHAIN MANAGEMENT
Case Study
Improving DRP effectiveness in ERPenvironment
Karuna Jain & Sunil Phabiani
Joju Johny
Roll No 17
8/3/2019 Joju Johny - ADSCM - SPL Case Study
2/15
Company Profile The largest household insecticide player in the country and the
worlds largest producer of mosquito repellent mats.
SPL is now in the growth phase. Its three major bands SP1, SP2, SP3
command almost 70 percent share of the mosquito repellent mats
market, which is the largest category of household insecticides in
India.
Logistics Network: 4 manufacturing sites at Pondichery, Goa, Silvassa
and Nashik.4 regional offices in metros Delhi. Mumbai, Chennai,
Calcutta. Each regional office has CFAs under its jurisdiction.
Distribution Planning - distribution mainly constitutes of two types of
materials movements
factory to the depots directly
from the factory to the hub centers from which it is then sent
to the satellite depots
8/3/2019 Joju Johny - ADSCM - SPL Case Study
3/15
8/3/2019 Joju Johny - ADSCM - SPL Case Study
4/15
Problem Definition
SPL has implemented the distribution module of ERP - Rs 3 crore.
All CFAs have distribution module of ERP. Weekly sales and stocks
arrive from CFAs electronically through emails.
Inspite of that, the DRP functions were not being used by the logistics
department.
Only if DRP functionality is used, the benefits of having a common
platform for information exchange can be more successful
Thus the efficacy of the current manual dispatch plan was calculated
Observation - The manual distribution plan was not the best plan.Marginal improvement over the FY 1996 97. Transportation cost had
increased and the inventory turnover was poor.
All these showed that there was scope for improvement and it was
believed that DRP is one such tool which can improve this.
8/3/2019 Joju Johny - ADSCM - SPL Case Study
5/15
Objectives
The project was initiated
to draw the top management attention towards the need
for using DRP by showing its impact on the bottom line of
the organization
to develop confidence in the users about the DRP
functionality by demonstrating how it could improve the
performance of the logistics department
To achieve these objectives the study wasdivided into 2 phases namely Phase I and
Phase II
8/3/2019 Joju Johny - ADSCM - SPL Case Study
6/15
Phase I
Develop a frameworkfor benefitquantification.
Simulating thedistribution of SPL
using DRP.
Comparing thesimulated distributionplans with actual
distribution plans. Projecting the benefits
and its impact oncorporate profitability.
Phase II
Identifying issues incurrent DRP practices.
Reviewing inputs toDRP
Analyzing the problemareas
Recommending theimprovements
8/3/2019 Joju Johny - ADSCM - SPL Case Study
7/15
Proposed Comprehensive Modelfor DRP
The job of DRP is to manage the flow of materials fromsupply sites to demand sites.
this was accomplished in three distinct phases
Input Phase: forecast, customer orders, inventory records and
planning parameters for each SKU.
DRP process phase: DRP generates a time phased model of
resource requirements to support logistics strategy.
Output Phase: The DRP generates the planned order dictated
by the item order policies and align the order by due date with
demand which is known as planned order releases.
A good distribution model is the one which provides both
internal mechanisms of the process and its linkages with the
other processes of the organization.The proposed model of
DRP is one such model.
8/3/2019 Joju Johny - ADSCM - SPL Case Study
8/15
Measure for Quantification
A meaningful quantification would be one thatshows an impact on the bottom line of the
organization.
Return of Investment is one such measure, which takes
into consideration not only the impact on the bottom line
but also on the cash flows and asset utilization.
Logistics department is the one whose impact
could be seen in all the financial aspects of the
business and ROI could prove to be the right
platform to project the benefits of DRP.
8/3/2019 Joju Johny - ADSCM - SPL Case Study
9/15
Simulation Exercise In order to quantify the benefits of DRP, a simulation exercise was carried to
prove that if DRP was used instead of the current manual system, then benefits
like reduction in inventory, reduced transportation costs could be achieved.
Simulation Parameter: The simulations used for the study are:
Fixed Order Quantity (truckload).
Planning horizon (raw material procurement to receipt by CFAs eight
weeks)
Lead times as per contract agreement.
Data Requirement: The data required for the simulation exercise is as follows:
Opening stocks and goods in transit
Weekly sales and value of stocks.
Actual dispatches from factory to CFAs.
Analysis Parameter: Number of dispatches
Weekly inventory position.
Avoidable dispatches Inter CFA
8/3/2019 Joju Johny - ADSCM - SPL Case Study
10/15
Impact on CorporateProfitability
Reduction in cost: savings of 31.68
Lakhs
Reduction in assets: weekly inventoryhad reduced in each region.
Impact on ROI: 1.2 % increase in the ROI for
SPL from the use of DRP module of the ERP
system.
8/3/2019 Joju Johny - ADSCM - SPL Case Study
11/15
DRP Review Further to see the impact of forecast accuracy on
performance of DRP, a similar situation exercise was carriedout.
It was found that with 100 percent accuracy DRP can further
bring down the transportation and inventory carrying costs
by 15 %. Conclusion: the correctness of the system is entirely
dependent upon the correctness of parameters fed into the
system
Therefore, to improve effectiveness, those inputs that aredynamic, need to be identified and treated accordingly.
Using this methodology it was found that the dynamic inputs
to DRP are Safety Stock (SS), Lead time (LT), Bill of
Distribution (BOD) and ordering Policy (OP).
8/3/2019 Joju Johny - ADSCM - SPL Case Study
12/15
The Proposed Semi DynamicModel
Based on the parameters mapping results, it wasfound that parameters should be changed every
quarter.
To incorporate this dynamic feature in the
comprehensive model proposed by them, one had
to modify the model.
The model was renamed as Semi Dynamic Model
for DRP process (SDMD) generalized the findings
for SPL, where the planning parameter fed to DRP
are function of sales trend and/or time
8/3/2019 Joju Johny - ADSCM - SPL Case Study
13/15
Recommendations
Planning process: The distribution planning should be donecentrally by taking DRP run at every HO every week.
Using DRP to generate MPS to synchronize operations: The
integration of DRP with MPS gives a single, continuous
seamless system that uses one set of logic across theoperations.
Revising DRP parameters every quarterly:
Using safety stocks for demand uncertainties, calculated at
95 % service level. Using safety time for lead time uncertainties, calculated at 95
% service level.
8/3/2019 Joju Johny - ADSCM - SPL Case Study
14/15
Recommendations
Following periodic order quantity (POQ) dispatch policy,
where period shall be calculated for optimum total cost
from a trade off analysis between transportation cost and
inventory holding cost.
The time bucket of one week should be uniformly applied.
Dispatch variance report should be generated by factory,
giving reasons for any dispatches not done as per the
dispatch plan.
Provide the DRP summary information to depots so that
even the branch managers have the visibility of the system
and can suggest changes in the forecasts or lead times
which according to them are not correct.
8/3/2019 Joju Johny - ADSCM - SPL Case Study
15/15