Upload
ramoutar-ken-seecharran
View
226
Download
0
Embed Size (px)
Citation preview
7/28/2019 Luanshya Akatiti Dam
1/6
LUANSHYA, AKATITI DAM TAILINGS LEACH PROJECT
INTRODUCTION:
Akatiti dam was the second tailings dam in Luanshya to be built. It was constructed when:
The feed grade of the ore from the mine was very high, and
The processing in the plant was not efficient.Because of these two factors, the grade of copper in the dam is extremely high, equivalent to ore
grade in many countries. Because of the age of the copper minerals in the dam, they are heavily
oxidised, and amenable to leaching and solvent extraction. It is recommended that 12 auger
samples be taken diagonally from the four corners of the dam to:
Establish the grade of the copper, and the acid soluble content of the tailings.
The thickness of the tailings, for tonnage estimation purposes. and
Establish the price to pay ZCCM-IH for the dam. They will want to charge based on total
copper content, the investor will only pay for recoverable copper acid soluble copper,
content.The financial plan was based on memory, as the author was in charge of rehabilitating this dam
from 1989 to 1992. The financial model, attached, shows a very lucrative. Using conservative
figures, a profit of $10-$12m per year is anticipated. A capital expenditure of $10m is required.
Treatment rate is estimated at about 4,500 tonnes per day. The infrastructure in the area is
excellent with roads and housing nearby. There are two independent power lines bordering the
property, to the East and South. The Chonga dam is less than 5 kilometres away, this dam will be
used to take the tailings effluent.
PROCESSING:
It is proposed to slurry the tailings using hydraulic monitors and pump the tailings to
Leaching tanks. Leaching will be carried out using sulphuric acid, most of which will be generated
from within the system. Leached tailings will be thickened and washed by counter current
decantation before discarding of the residue in Chonga dam. Pregnant leach solution (PLS) will be
fed to extraction mixer-settlers where the copper laden PLS will be contacted with solvent
extraction reagents to make a loaded organic (Figures 1 and 2).
Figure 1: Diagrammatic representation of the solvent extraction process
7/28/2019 Luanshya Akatiti Dam
2/6
Figure 2: Solvent
extraction reagent
The loaded organic will then be fed to the strip-mixer settler in which the copper will be extractedwith spent electrolyte coming from the electrowinning section to make a strong electrolyte
(Figure 3).
Figure 3: Block diagram showing the solvent extraction process
The raffinate generated is used to leach new copper. This might need topping up with fresh acid;
the amount of acid needed is controlled by the gangue acid consumption of the tailings. In this
case, it is not expected to exceed 40gt-1. That strong electrolyte (advance electrolyte) will be fed
to the electrolytic tankhouse where a DC current will be used to plate to copper onto stainless
steel cathodes (Figure 4 and 5).
Figure 4: DC rectiformer
7/28/2019 Luanshya Akatiti Dam
3/6
The whole process from leaching to harvesting plated copper is expected to take 28 days.
Figure 5: Electrolytic tankhouse showing busbar, anodes and cathodes
There is a plethora of such processing skill within Zambia, as at least four plants are using this
technology within the country.
Luanshya is one of the more attractive towns in Zambia and many workers will cherish the
opportunity to live and work there.
The property will be located only 25 kms from Ndola, the export hub.
The limited access to the property will enhance security.
Figure 6: Harvested
copper cathodes, ready
for sale
7/28/2019 Luanshya Akatiti Dam
4/6
Sulphuric acid will constitute a major cost component; since it is made as a by-product from
copper smelting, astute negotiations can secure it at a bargain price. The feasibility study was
done using world market price.
CAPITAL BUDGET:
Leaching/Solvent Extraction $800,000
Electrowinning $1,200,000
Purchasing the Dam $6,000,000
Environmental licence $100,000
Construction $500,000
Chemicals $850,000
Ponds construction and lining $475,000
Acid $115,000
Contingency $150,000
TOTAL $10,190,000
OPERATING COST:
Assuming a 15-year life of the
project
TNS TAILS23,595,000
AS Cu GRADE 0.45
TNS Cu CONTAINED 106,178
PLANT RECOVERY 60
TNS COPPER
RECOVERED63,707
COPPER PRICE ($/t) 6,500
OPS COST ($/t) 3,694
SALES $414,092,250
EXPENSE $235,360,125PROFIT $178,732,125
Profit per year $11,915,475
Payback period (years) 0.9
7/28/2019 Luanshya Akatiti Dam
5/6
ORGANISATION STRUCTURE:
The proposed organisation structure is shown below.
RECOMMENDATIONS:
It is recommended that the following be carried out:
A full reconnaissance of the area is conducted to establish the possible location of
the processing plant in relation to the power supply. The service of a person
knowledgeable in the area and with the tailings dam should be sought
12 auger samples be taken across the dam to accurately assess the leachable
copper content and the thickness of the deposit (Figure 7)
Figure 7: Proposed sampling
General Manager 1
Metallurgical Manager 1
Receptionist (1) 1
HR Superintendent Process Superintendent Maintanance Superintendent 3
General Foreman Sectional Engineer 2
Maintenance Foreman Electrical Foreman Instrumentation Foreman Boilermaker Foreman 4
Shift Foreman A Shift Foreman Swing Shift Foreman B 3
Accountant Storekeeper Security Officer Payroll Clerk Fitter Artisans (6) Electricians (2) Instrument Artisans (2) Boilermakers (2) 16
Reclaim (4) Reclaim (4) Reclaim (4) 12
Clerk (1) Issuer (1) Guards (4) Clerk (1) Leaching (1) Leaching (1) Leaching (1) Helper (1) Helper (1) Helper (1) Helper (1) 14
Solvent Extraction (2) Solvent Extraction (2) Solvent Extraction (2) 6
Driver (1) Ponds/Utilities (2) Ponds/Utilities (2) Ponds/Utilities (2) Driver (1) 8
CCD/Tailings (3) CCD/Tailings (3) CCD/Tailings (3) 9
Electrowinning (1) Electrowinning (1) Electrowinning (1) 3
Tails Dam (2) Tails Dam (2) Tails Dam (2) 6
Reagents Mixing (2) Reagents Mixing (2) Reagents Mixing (2) 6
Forklift Driver (1) Forklift Driver (1) Forklift Driver (1) 3
Driver (1) Driver (1) Driver (1) 3
TOTAL 101
Old Dam
N
Reliable
PowerSample Line
Points
AKATITI DAM
Less Reliable Power Line
To Masaiti
Lake Success
Proposed
Plant
7/28/2019 Luanshya Akatiti Dam
6/6
The dam be accurately measured to establish its area
A suitable local contractor is taken to the site to establish logistics of working in the
area. It is hoped that by working round the clock, the construction can be
completed in 12 months
The proximity to Chonga dam be established to calculate the pumpingrequirements of tailings effluent
A full sensitivity analysis be carried out using the attached spreadsheet to establish
how lucrative the project is
Negotiations be opened with second-hand equipment suppliers, like Manhattan in
South Africa, to establish the availability of such equipment
A consortium of financiers be approached to provide funding
The possibility of purchasing Old Dam. This dam is richer, but is geotechnically
unstable, as it was built in a swamp to combat blackwater fever when the mine
started in the 1930s. Should it break and block the Fisansa stream, the
environmental council will shut down the operation. However, there is a judicious
way of mining the tailings without causing breakage
Establishing the above, will improve on the accuracy of this management brief,
which is currently only 20%
Figure 8: The ultimate objective of the proposed project
Ramoutar (Ken) Seecharran
Mining/Metallurgical Consultant