Luanshya Akatiti Dam

Embed Size (px)

Citation preview

  • 7/28/2019 Luanshya Akatiti Dam

    1/6

    LUANSHYA, AKATITI DAM TAILINGS LEACH PROJECT

    INTRODUCTION:

    Akatiti dam was the second tailings dam in Luanshya to be built. It was constructed when:

    The feed grade of the ore from the mine was very high, and

    The processing in the plant was not efficient.Because of these two factors, the grade of copper in the dam is extremely high, equivalent to ore

    grade in many countries. Because of the age of the copper minerals in the dam, they are heavily

    oxidised, and amenable to leaching and solvent extraction. It is recommended that 12 auger

    samples be taken diagonally from the four corners of the dam to:

    Establish the grade of the copper, and the acid soluble content of the tailings.

    The thickness of the tailings, for tonnage estimation purposes. and

    Establish the price to pay ZCCM-IH for the dam. They will want to charge based on total

    copper content, the investor will only pay for recoverable copper acid soluble copper,

    content.The financial plan was based on memory, as the author was in charge of rehabilitating this dam

    from 1989 to 1992. The financial model, attached, shows a very lucrative. Using conservative

    figures, a profit of $10-$12m per year is anticipated. A capital expenditure of $10m is required.

    Treatment rate is estimated at about 4,500 tonnes per day. The infrastructure in the area is

    excellent with roads and housing nearby. There are two independent power lines bordering the

    property, to the East and South. The Chonga dam is less than 5 kilometres away, this dam will be

    used to take the tailings effluent.

    PROCESSING:

    It is proposed to slurry the tailings using hydraulic monitors and pump the tailings to

    Leaching tanks. Leaching will be carried out using sulphuric acid, most of which will be generated

    from within the system. Leached tailings will be thickened and washed by counter current

    decantation before discarding of the residue in Chonga dam. Pregnant leach solution (PLS) will be

    fed to extraction mixer-settlers where the copper laden PLS will be contacted with solvent

    extraction reagents to make a loaded organic (Figures 1 and 2).

    Figure 1: Diagrammatic representation of the solvent extraction process

  • 7/28/2019 Luanshya Akatiti Dam

    2/6

    Figure 2: Solvent

    extraction reagent

    The loaded organic will then be fed to the strip-mixer settler in which the copper will be extractedwith spent electrolyte coming from the electrowinning section to make a strong electrolyte

    (Figure 3).

    Figure 3: Block diagram showing the solvent extraction process

    The raffinate generated is used to leach new copper. This might need topping up with fresh acid;

    the amount of acid needed is controlled by the gangue acid consumption of the tailings. In this

    case, it is not expected to exceed 40gt-1. That strong electrolyte (advance electrolyte) will be fed

    to the electrolytic tankhouse where a DC current will be used to plate to copper onto stainless

    steel cathodes (Figure 4 and 5).

    Figure 4: DC rectiformer

  • 7/28/2019 Luanshya Akatiti Dam

    3/6

    The whole process from leaching to harvesting plated copper is expected to take 28 days.

    Figure 5: Electrolytic tankhouse showing busbar, anodes and cathodes

    There is a plethora of such processing skill within Zambia, as at least four plants are using this

    technology within the country.

    Luanshya is one of the more attractive towns in Zambia and many workers will cherish the

    opportunity to live and work there.

    The property will be located only 25 kms from Ndola, the export hub.

    The limited access to the property will enhance security.

    Figure 6: Harvested

    copper cathodes, ready

    for sale

  • 7/28/2019 Luanshya Akatiti Dam

    4/6

    Sulphuric acid will constitute a major cost component; since it is made as a by-product from

    copper smelting, astute negotiations can secure it at a bargain price. The feasibility study was

    done using world market price.

    CAPITAL BUDGET:

    Leaching/Solvent Extraction $800,000

    Electrowinning $1,200,000

    Purchasing the Dam $6,000,000

    Environmental licence $100,000

    Construction $500,000

    Chemicals $850,000

    Ponds construction and lining $475,000

    Acid $115,000

    Contingency $150,000

    TOTAL $10,190,000

    OPERATING COST:

    Assuming a 15-year life of the

    project

    TNS TAILS23,595,000

    AS Cu GRADE 0.45

    TNS Cu CONTAINED 106,178

    PLANT RECOVERY 60

    TNS COPPER

    RECOVERED63,707

    COPPER PRICE ($/t) 6,500

    OPS COST ($/t) 3,694

    SALES $414,092,250

    EXPENSE $235,360,125PROFIT $178,732,125

    Profit per year $11,915,475

    Payback period (years) 0.9

  • 7/28/2019 Luanshya Akatiti Dam

    5/6

    ORGANISATION STRUCTURE:

    The proposed organisation structure is shown below.

    RECOMMENDATIONS:

    It is recommended that the following be carried out:

    A full reconnaissance of the area is conducted to establish the possible location of

    the processing plant in relation to the power supply. The service of a person

    knowledgeable in the area and with the tailings dam should be sought

    12 auger samples be taken across the dam to accurately assess the leachable

    copper content and the thickness of the deposit (Figure 7)

    Figure 7: Proposed sampling

    General Manager 1

    Metallurgical Manager 1

    Receptionist (1) 1

    HR Superintendent Process Superintendent Maintanance Superintendent 3

    General Foreman Sectional Engineer 2

    Maintenance Foreman Electrical Foreman Instrumentation Foreman Boilermaker Foreman 4

    Shift Foreman A Shift Foreman Swing Shift Foreman B 3

    Accountant Storekeeper Security Officer Payroll Clerk Fitter Artisans (6) Electricians (2) Instrument Artisans (2) Boilermakers (2) 16

    Reclaim (4) Reclaim (4) Reclaim (4) 12

    Clerk (1) Issuer (1) Guards (4) Clerk (1) Leaching (1) Leaching (1) Leaching (1) Helper (1) Helper (1) Helper (1) Helper (1) 14

    Solvent Extraction (2) Solvent Extraction (2) Solvent Extraction (2) 6

    Driver (1) Ponds/Utilities (2) Ponds/Utilities (2) Ponds/Utilities (2) Driver (1) 8

    CCD/Tailings (3) CCD/Tailings (3) CCD/Tailings (3) 9

    Electrowinning (1) Electrowinning (1) Electrowinning (1) 3

    Tails Dam (2) Tails Dam (2) Tails Dam (2) 6

    Reagents Mixing (2) Reagents Mixing (2) Reagents Mixing (2) 6

    Forklift Driver (1) Forklift Driver (1) Forklift Driver (1) 3

    Driver (1) Driver (1) Driver (1) 3

    TOTAL 101

    Old Dam

    N

    Reliable

    PowerSample Line

    Points

    AKATITI DAM

    Less Reliable Power Line

    To Masaiti

    Lake Success

    Proposed

    Plant

  • 7/28/2019 Luanshya Akatiti Dam

    6/6

    The dam be accurately measured to establish its area

    A suitable local contractor is taken to the site to establish logistics of working in the

    area. It is hoped that by working round the clock, the construction can be

    completed in 12 months

    The proximity to Chonga dam be established to calculate the pumpingrequirements of tailings effluent

    A full sensitivity analysis be carried out using the attached spreadsheet to establish

    how lucrative the project is

    Negotiations be opened with second-hand equipment suppliers, like Manhattan in

    South Africa, to establish the availability of such equipment

    A consortium of financiers be approached to provide funding

    The possibility of purchasing Old Dam. This dam is richer, but is geotechnically

    unstable, as it was built in a swamp to combat blackwater fever when the mine

    started in the 1930s. Should it break and block the Fisansa stream, the

    environmental council will shut down the operation. However, there is a judicious

    way of mining the tailings without causing breakage

    Establishing the above, will improve on the accuracy of this management brief,

    which is currently only 20%

    Figure 8: The ultimate objective of the proposed project

    Ramoutar (Ken) Seecharran

    Mining/Metallurgical Consultant