Managing Projects with ServiceNow at the University of San Francisco
Jim UominiService Level ManagerUniversity of San Francisco
John RobertsSenior Product ManagerServiceNow
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• PMO website includes overview and links to forms– www.usfca.edu/its/projects
• Project Lifecycle – PMO Toolkit– Initiation, Planning, Execution, Closing
• Show Project Management website – Open to public
Initiation• Sponsors use Initiate a Formal Project record producer• Project Managers use the Project form itself
Project Management Institute Methodology
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• High-Level Objective– SMART – Specific, Measurable, Achievable, Realistic, Time
• University Benefit• Alignment with strategic priorities
– Links to Vision, Planning, Priorities documents
• Project Classification– Compliance, Operational, Strategic– Discretionary or Non-Discretionary
• Priority• Risk/Reward Criteria – Look for low-risk, certain reward• Demonstrate Initiate a Formal Project record producer
Must Include
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
Risk / Reward Matrix
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• ITS Directors and VP/CIO meet every three weeks• Review Priority, Risk/Reward, Resource Requirements• Type classified• Approved projects changed to Planning/Design Status,
assigned an ITS director and project manager• Or given Status Under Review, On Hold or Cancelled
Project Portfolio Management Committee
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Project Type• Budget Status, Schedule Status, Scope Status, Overall
Status• Sponsor Approval• ITS Strategic Priority• Schedule tab
– On Time added for ease of reporting– Issues with Planned vs. Actual dates
• “Close Project” task; • Baseline End Date field – suggested by John Roberts
• Evaluation and Criteria tabs
Project Form Customizations
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Project Priorities tab– PM and sponsor agree to constraints related to Cost,
Quality/Performance, and Time– Values are Constrain, Enhance, or Accept
• Demonstrate Project form customizations
Project Form Customizations
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Reference fields tie to Requirements and Issues tables• Schedule Status• Phase• Deliverable• Non-ITS Assigned to
• Planned vs. Actual dates after task started• Setting correct Planned duration after task started - Schedule
• Demonstrate Project Task customizations
Project Task Form Customizations
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Submitted by PM from Requirements related list• Submitted by non-licensed team member using
Submit a Project Requirement record producer– Need to know the project Short description– Fit/Gap– Type– Solution Status– Status – Approved or Not Approved– Developer– Ties to Project Change Request
• Demonstrate Submit a Project Requirement record producer • Demonstrate Requirements table
Project Requirements
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Submitted by PM from Tests related list in Requirementstable
• Submitted by non-licensed team member usingSubmit a Project Test Scenario record producer– Need to know the project Short description and the Requirement
being tested
• Demonstrate Tests table
Project Tests
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Submitted by PM from Defects related list in Tests table• Submitted by non-licensed team member using
Report a Testing Defect record producer– Need to know the name of the Testing Scenario
• Demonstrate Defects table
Project Defects
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• We added Issues and Risks before SNC did in PM v2• Submitted by PM from Issues related list• Submitted by non-licensed team member using
Report a Project Issue record producer– Need to know the project Short description
• Demonstrate Issues table
Project Issues
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Submitted by non-licensed team member usingReport a Project Risk record producer– Need to know the project Short description
• Likelihood, Impact = Severity• Mitigation Strategy
– Control, Deflection, Retention, Avoidance
• Contingency Plan• Trigger
• Demonstrate Risks table
Project Risks
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Once in Build/Test phase, changes to Requirements/Scope require Project Change Request
• Submitted by Non-licensed team member usingSubmit a Project Change Request record producer– Need to know the project Short description– Auto assigned to VP for approval at PPM meeting
• Status– Decision Maker, Decision Date
• Priority• Change Type• Demonstrate Project Change Request table
Project Change Requests
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Link sent by PM to project team members/stake holders• Accessible from Provide Project Feedback record
producer– Need to know the project Short description
• Records viewed in Lessons Learned related list• Gather feedback on Project Management, Project Team
Dynamics, Recommendations
• Demonstrate Provide Project Feedback record producer
Lessons Learned Survey
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Accessed from Project Close tab• PM completes to debrief and begin project close out
– Replaced a doc form
• Demonstrate Project Close tab
Project Close
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Accessed from Transition tab• PM completes if project leads to a new service• New Service Needed – If “Yes”, following fields mandatory• New Service Name• New Service Description• Service Owner
– Additional questions related to support of new service– SOP doc – Creation of ServiceNow categorization, Business
Service and Application records, Service Portfolio record, web-based Service Portfolio listing, service web page
• Demonstrate Transition tab
Transition to Service
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• PPM uses homepages to give high-level views of project load and status
• CIO uses them to brief senior management– Dashboard
• Pipeline Project List– Trend Reports– Active Projects List– My Project Overview
• Demonstrate Homepages
Homepages
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
• Two-part course in Blackboard online learning environment• Two hours on project methodology• Two hours on managing projects with ServiceNow• Includes exercises and short quizzes• Pilot done with ITS staff• Plan to use feedback to revise course and offer it outside
department
Training
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
Training
LEAVE HEADER & FOOTER BLANK: SLIDE TREATMENT TO BE ADDED LATER BY SERVICENOW MARKETING
Thank YouService Level Manager
Jim UominiUniversity of San Francisco
Senior Product Manager
John RobertsServiceNow