Upload
ngonhan
View
224
Download
0
Embed Size (px)
Citation preview
Supersonic Post-Combustion Inertial
CO2 Extraction System
Bench Scale Project Status Update
2014 NETL CO2 Capture Technology Meeting
Pittsburgh, PA
24 June 2015
Vladimir Balepin, Ph.D.
Anthony Castrogiovanni, Ph.D.
Andrew Robertson
Jason Tyll, Ph.D.
Project Overview
• Funding
• NETL: $ 2,999,673
• Cost Share: $ 749,918
• Total: $ 3,749,591
• Project Performance Dates
• 1 Oct 2014 - 30 Sep 2017
• Project Participants
• ATK & ACENT Laboratories
• Ohio State University
• EPRI
• NYSERDA and NYS-DED
• Project Objectives
• Demonstrate inertial CO2 extraction
system at bench scale
• Develop approaches to obtain condensed
CO2 particle size required for migration
• Demonstrate pressure recovery efficiency
of system consistent with economic goals
• Demonstrate CO2 capture efficiency
2
ICES Technology Background
• Supersonic expansion of compressed flue gas results in
CO2 desublimation (high velocity → low p & T)
• Inertial separation of solid particles instigated by turning
the supersonic flow
• CO2-rich capture stream is removed and processed
• CO2-depleted stream is diffused and sent to stack
3
Thermodynamics of ICES
0.0
2.0
4.0
6.0
8.0
10.0
12.0
0.001
0.01
0.1
1
10
100
50 100 150 200 250 300
Ma
ch N
um
be
r
Pre
ssu
re [
ba
r]
Temperature [K]
Isentropic Expansion of 14mol% CO2 in N2 Relative to Phase Diagram of CO2
Triple Point
Partial Pressure of CO2
during Isentropic Expansion in Supersonic Nozzle(p0=2bar, T0=300K)
Region of incipient condensation
Gas Phase
Liquid Phase
Solid Phase
Post Condensation
PathStatic pressure (p), static
temperature (T) and velocity (v)
in a converging-diverging
nozzle
Low static pressure and temperature in supersonic nozzle causes CO2 to precipitate as a
solid – need to remove before diffusing back to low speed 4
Key Advantages and Challenges
Advantages Challenges
No moving parts, chemicals/additives or
consumable media
Maximization of CO2 particle size with
limited residence time
Inexpensive construction (sheet metal,
concrete)
Minimization of “slip gas” removed with
solid CO2
Small footprint (current bench scale test
article is 250kW, 3” x 24” x 96”
CO2 purity (all condensable material will
be removed with CO2)
“Cold sink” availability in solid CO2
Solid CO2 processing
Costs primarily driven by flue gas
compression
Optimization of flowpath pressure
recovery
5
Gen1a
and 1b
(swirl)
Gen2 (2D)
Gen3
(2D - long)
Principal conclusion of this effort was that CO2 particles >2.5μm are required for efficient
operation - need to control particle size generated 6
Summary of ARPA-e IMPACCT
Activity
Program Plan for Current Effort
• Year 1
• Lab-scale tests (OSU) to develop understanding of factors controlling particle size and
methods to increase
• Bench scale tests at ATK to demonstrate capture efficiency and diffusion with surrogate CO2
injection (liquid throttle of CO2 to produce controlled particle size)
• Success criteria: Demonstrate 50% capture, show path to pressure recovery required
• Year 2
• Integrate methods to increase particle size in bench scale test article
• Test with surrogate flue gas (Air + CO2 + H2O)
• Success criteria: Demonstrate migration of 80% of CO2 to 20% of duct height and path to
full scale pressure recovery
• Year 3
• Integrated bench-scale testing with capture + diffuser
• Success criteria: 75% capture with path to 90%, path to full scale pressure recovery
7
Lab-scale Testing at Ohio State
University
• Test program completed at OSU supersonic aerosol facility to gain better understanding of
nucleation process, condensation rates, and particle size behavior
Initial test results proved that under our conditions, CO2 only condenses on
solid or liquid media in the flow (i.e. heterogeneous condensation)
8
H2O homogeneous nucleation
N2(g)
CO2(g)
H2O(g)
throat
H2O freezing CO2 heterogeneous nucleation and growth
H2O droplet growth
coagulation
Temperature (K)
50 100 150 200 250 300
Pre
ssure
(P
a)
1e-1
1e+0
1e+1
1e+2
1e+3
1e+4
1e+5
1e+6
1e+7
1e+8
1e+9
liquid
vapor
solid
l
s
v
H2O hom
CO2 hom
CO2 het on H2O
CO2
H2O
M =
2.2
M =
3.3
Lab-scale Testing at Ohio State
University (continued)
• Test and analysis matrix included methods of inducing
turbulent particle collisions to promote agglomeration
• These approaches proved to be too intrusive and
resulted in local temperature increase
• Attention focused on solid CO2 injection/seeding
Combination of test data and detailed modeling led to conclusion that solid
media (e.g. CO2) seeding is most viable path to 90%+ capture by causing
flue gas CO2 to condense on particles already >2.5μm
0.0
0.2
0.4
0.6
0.8
1.0
0
1 10-6
2 10-6
3 10-6
4 10-6
5 10-6
0 50 100 150 200
Nozzle ATK
r0 = 1.25 mm
r0 = 2.00 mm
r0 = 3.00 mm
r0 = 1.25 mm, T
CO2L = 225K
r0 = 1.25 mm, LongFlat nozzle
r0 = 1.25 mm, LongFast nozzle
Mas
s fr
actio
n ra
tio, g
CO
2S/ w
co2 (
-)
Rad
ius
of C
O2
drop
let, r (
m)
Distance from throat, z (cm)
wco2
= 0.2 kg/kg
p0 = 2 atm
zinject
= -1 cm
gCO2S
/wCO2
r
Fig. 2 Mass fraction ratio of CO2 solid and radius of CO2 droplet
9
One CO2 Recirculation Approach
Solid/Liquid CO2 ProcessingSupercritical
CO2 Processing
Flue gas fromcompressor
Liquid CO2recirculation
Flue gas to the stack
Slip gas recirculation
Solid particle capture
Cyclone separator
CO2 to pipeline
Melting line
Triple point
Critical
point
Pipeline
Conditions
298K,153 barRecirculation CO2
@ 298K and 80 bar
Recirculation of liquid CO2 can achieve the
desired results of additional cooling + creation of
large particles to promote heterogeneous
nucleation capable of migration. Requirement to
inject very close to throat to mitigate evaporation.
10
Flow splitter plate
CO2-enriched capture flow
CO2- depleted
flow to diffuser
Current Bench Scale Test
Arrangement (250kW)
Plenum
Expansion
duct
Turning
duct
Capture
duct
Diffuser
liquid throttle solid CO2 injectors
Location of CO2
measurement probe
(NDIR and GC) 11
Laser Images of CO2 in Flow
Upper wall
Bottom wall
Air flow only
CO2 relatively uniform across
duct
Highest concentration of CO2
entering capture duct
Diffuser
Capture duct
CO2 depleted flow
CO2 enriched flow
12
CO2 Capture Data
Last year - goal of capture >50% of
CO2 achieved for short duration tests.
Cumulative measurement error due to
GC and NDIR sensor contamination
after first several seconds
This year – gas sample approach reworked to mitigate several sources
of error including time lag, pump oil contamination + added in-situ
calibration. Preliminary review of results indicate >50% capture of
solid CO2 in several recent tests – data still in detailed review
Gas samples taken from primary flow stream were processed with on-line gas
chromatograph (GC) and NDIR sensors to access CO2 mole fraction.
13
Full Scale Pressure Recovery Predictions
Current scale limits pressure recovery
performance due to thick boundary layer relative
to duct size. We have shown path to target
pressure recovery of 40% through:
• CFD benchmarking using subscale test
results and predictions of full scale
performance
• Definition of flowpath updates required to
improve performance from 31% to 40%
overall pressure recovery
10X Photo Scale
12 Units
CFD
Expansion
End
Curve
End
3” Duct 15” Duct
Component CFD Current
Configuration
Desired
Performance
Expansion
Duct
79 % 85%
Turning Duct 88% 95%
Diffuser Duct 45% 50%
Total 31% 40% 14
• A preliminary Techno-economic assessment by WorleyParsons (WP) was carried out in 2013
• Key efficiency/economic numbers are provided in the table below:
Resulting lower COE increase for ICES technology is based on lower capital and O&M costs and improvements in the overall plant efficiency
A path to the DOE research goal of 35% COE increase is being developed based on a more detailed capex/labor model and reduced flue gas compression (PR=2.0 vs 2.5 used in WP analysis)
Metric Case 11 Case 12, Amine
Plant ICES Plant
CO2 capture no yes yes
Net plant efficiency (HHV basis) 39.3% 28.4% 34.5%
COE % increase base 77% 42%
Parasitic Load 5.5% 20.5% 7.3%
Cost per tonne of CO2 captured NA US$ 62.8 US$ 41.8
Cost per tonne of CO2 avoided NA US$ 90.7 US$ 48.4
ICES Economic Impact
15
ICES Plant Layout and Footprint
Boiler Exhaust Stack
Flue Gas
Desulfurization
(FGD)
Continuous
Emission Monitors
(CEMs)
Precipitator
Axial Compressors (3)
Air Coolers Captured CO2
processing
ICES Units
Direct Contact Cooler
(DCC)
Unique Equipment
for ICES System
ICES footprint of ~8k m2 compares to 20k to 30k m2 for an amine plant of similar capacity.
ICES nozzle and compressor stacking can further reduce footprint by 30-40%.
17
Project Schedule
MS 1. Updated BP1 PMP – complete
MS 2. Kickoff meeting - complete
MS 3. Capture duct/diffuser demonstration – complete
MS 4. Updated BP2 PMP – complete
MS1 MS2 MS3
17
MS4
Tasks Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8 Q9 Q10 Q11 Q12 Q13
Task 1. Program Management
Task 2. Lab-scale Condensation/Growth Investigation
Task 3. Analytical and Computational Investigation
Task 4. Bench-scale Capture and Diffuser Testing
Task 5. Bench-scale Condensation/Growth Testing
Task 6. Integrated System
Task 7. Plant Integration and Techno-economic Analysis
Budget Period 1 Budget Period 2 Budget Period 3
Quarters
Summary
• ICES Technology holds considerable promise as an alternative to adsorbents and
membranes
• Current NETL effort focused on solving key technical challenge of particle size
• Testing and analysis results to-date support strategy of solid CO2 recirculation
as most viable approach
• Ongoing work to optimize CO2 injection arrangement to minimize
evaporation upstream of supersonic section and to redesign turning duct to
increase pressure recovery performance
18
Acknowledgements
• NETL • Andy O’Palko
• Lynn Brickett
• ATK • Bon Calayag
• Florin Girlea • Michele Rosado
• Dr. Daniel Bivolaru
• Kirk Featherstone
• ACENT Labs • Dr. Pat Sforza
• Randy Voland
• Robert Kielb
• Ohio State University • Professor Barbara Wyslouzil
• Dr. Shinobu Tanimura
• EPRI
• Dr. Abhoyjit Bhown
• Adam Berger
• NYSERDA
• NYS-DED
19