234
This document is downloaded from CityU Institutional Repository, Run Run Shaw Library, City University of Hong Kong. Title Innovative generation in cost management through BIM environment Author(s) Lin, Mushui (林木水) Citation Lin, M. (2013). Innovative generation in cost management through BIM environment (Outstanding Academic Papers by Students (OAPS)). Retrieved from City University of Hong Kong, CityU Institutional Repository. Issue Date 2013 URL http://hdl.handle.net/2031/7147 Rights This work is protected by copyright. Reproduction or distribution of the work in any format is prohibited without written permission of the copyright owner. Access is unrestricted.

This document is downloaded from CityU Institutional ...lbms03.cityu.edu.hk/oaps/ca2013-4513-lms979.pdf · technology. The steps in the pilot study include 3D model drawings, BIM

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • This document is downloaded from CityU Institutional Repository,

    Run Run Shaw Library, City University of Hong Kong.

    Title Innovative generation in cost management through BIM environment

    Author(s) Lin, Mushui (林木水)

    Citation

    Lin, M. (2013). Innovative generation in cost management through BIM environment (Outstanding Academic Papers by Students (OAPS)). Retrieved from City University of Hong Kong, CityU Institutional Repository.

    Issue Date 2013

    URL http://hdl.handle.net/2031/7147

    Rights This work is protected by copyright. Reproduction or distribution of the work in any format is prohibited without written permission of the copyright owner. Access is unrestricted.

  • Innovative Generation in Cost Management

    through BIM Environment

    By

    Mushui LIN

    Submitted in partial fulfillment of the requirements for

    the degree of Bachelor of Science (Honours) in Surveying

    Department of Civil and Architectural Engineering

    City University of Hong Kong

    March 2013

  • DECLARATION

    I declare that this thesis represents my own work, except where due acknowledgement

    is made, and that it has not been previously included in a thesis, dissertation or report

    submitted to this University or any other institution for a degree, diploma or other

    qualification.

    Signed _______________________________

    Mushui LIN

  • i

    ABSTRACT

    Construction cost management is essential for the success of a project. The

    procedures in the project cost management include pre-contract cost estimating and

    post-contract cost control. Cash flow forecasting, as one of the processes in the post-

    contract cost control, serves the functions of: 1) assisting project managers to

    anticipate the total planned budget, 2) illustrating a difference between anticipated and

    actual expenditure of the project in a monthly basis, and 3) timely reminding the

    client possible risks of overbudget and to take prompt remedial actions. Building

    Information Modeling (BIM) is a new innovative technology that allows relevant

    graphical and topical information related to the built environment to be stored in the

    database for access and management through a project lifecycle. With development of

    digital technology, data and information can be linked with 3D components in BIM to

    provide 4D, 5D and 6D BIM. It is predicted that BIM could have a marked impact on

    the construction industry and is regarded as a major challenge to conventional

    professionals in AEC industry including Quantity Surveyors.

    However, there is seldom research about what services can Quantity Surveyors

    provide to Client on the BIM projects. This research will establish a framework of 5D

    BIM construction cost management and evaluate the degree of feasibility and

    efficiency of using 5D BIM for Quantity Surveyors in preparing cash flow forecast

    for cost control. During the research process, the procedures for generating 5D BIM

    cash flow forecast are demonstrated. The benefits and difficulties encountered are

    described and analyzed. Solutions for some problems and recommendations for

    improvement are discussed.

    This research involves a pilot study to create cash flow forecast by using 5D BIM

    technology. The steps in the pilot study include 3D model drawings, BIM quantities

    takeoff and measurement, Bills of Quantities production and pricing, construction

    programme planning, cash flow forecast and 5D simulation.

    Through this research, it is found that 5D BIM is feasible to be used for construction

    cost management by Quantities Surveyors. The benefits of 5D BIM in cost

    management include 1) visualized communication; 2) fast response in model-based

    cost management; 3) leveraged integration of information; and 4) close monitor on

  • ii

    actual cash flow. However, there are some difficulties or loopholes revealed due to

    the contradictions between current cost management practices and BIM approach. It is

    recommended that the industry needs to redefine current standards in order to make

    BIM adoption and use easier. In addition, the university and the construction industry

    needs to work collaboratively to ensure that BIM modules are introduced into higher

    education curricula.

  • iii

    ACKNOWLEDGEMENTS

    This dissertation would not have been possible without the guidance and the help of

    several individuals who in one way or another contributed and extended their

    assistance in the preparation and completion of this study.

    First and foremost, I would like to express my sincere gratitude to my dissertation

    supervisor, Dr. Daisy K. L. YEUNG, for her valuable guidance, advice and

    continuous support throughout the production of this dissertation. She can always give

    me insightful comments and inspiration when I hurdle the obstacles in the completion

    of this research.

    Besides my supervisor, I would like to thank Mr. Calvin KEUNG, for his kind

    encouragement and assistance during the preparation of this dissertation. My sincere

    thanks also go to Mr. K.K. CHAN, for his insightful knowledge and kind support for

    this research.

    I thank Mr. Kelvin KUO of isBIM Limited, the Hong Kong Institute of Surveyors,

    BuildingSMART (Hong Kong) for their beneficial experience sharing.

    Last but not least, I thank my families and friends for their numerous love, care and

    support. Whenever I felt confused and pressured, they became my intimate audience.

    This work is dedicated to them.

  • iv

    TABLE OF CONTENTS

    Abstract i

    Acknowledgements iii

    Table of Contents iv

    List of Tables ix

    List of Figures x

    Page

    CHAPTER 1: INTRODUCTION 1

    1.1 Background to the Research 1

    1.2 Statement of the Problem 3

    1.3 Research Aims and Objectives 4

    1.4 Methodology 4

    1.5 Research Procedures 6

    1.6 Outline Structure of the Thesis 7

    CHAPTER 2: LITERATURE REVIEW-BIM 9

    2.1 Introduction 9

    2.2 Introduction to BIM 9

    2.3 Adoption of BIM in the Construction Industry 13

    2.4 BIM and Construction Planning 15

    2.5 Model-based Estimating and Quantity Takeoff 17

    2.6 BIM and Quantity Surveying Practice 20

  • v

    2.7 Adoption of BIM in Hong Kong 20

    2.8 Worldwide BIM Standards and Policies 21

    2.9 Future & Preparation for BIM 24

    CHAPTER 3: LITERATURE REVIEW-CONSTRUCTION COST MANAGEMENT 25

    3.1 Introduction 25

    3.2 Process of Construction Cost Management 25

    3.3 Cash Flow Forecast 26

    3.4 Cash Flow Curve 27

    3.5 Cumulative Cost Curve 28

    CHAPTER 4: RESEARCH METHODOLOGY 30

    4.1 Introduction 30

    4.2 Background of Research 30

    4.3 Research Framework 30

    4.4 Description of Research Framework 32

    4.5 Background of Pilot Study 34

    4.6 Descriptions of Adopted Softwares 35

    4.7 Declaration for Software Adoption 37

    CHAPTER 5: 3D MODEL DRAWING 38

    5.1 Introduction 38

    5.2 List of BIM Software Applications 38

    5.3 BIM Design Software Used in Pilot Study 40

    5.4 Principles of Model Drawing 40

  • vi

    5.5 Model Drawing By Floors 46

    CHAPTER 6: QUANTITIES TAKEOFF AND MEASUREMENT 51

    6.1 Introduction 51

    6.2 Concrete 51

    6.3 Formwork 57

    6.4 Reinforcement 63

    6.5 Door & Window 64

    6.6 Internal Finish 65

    6.7 External Finish 66

    CHAPTER 7: BILLS OF QUANTITIES AND PRICING 67

    7.1 Introduction 67

    7.2 BQ Production 67

    7.3 BQ Pricing 72

    7.4 Cost Summary 75

    CHAPTER 8: CONSTRUCTION PROGRAMME PLANNING 77

    8.1 Introduction 77

    8.2 Introduction to Construction Programme Planning 77

    8.3 Bar Chart 78

    8.4 Application of Computer in Construction Scheduling 79

    8.5 Introduction to Microsoft Project 79

    8.6 Construction Programme Planning for Pilot Study 79

  • vii

    CHAPTER 9: BIM CASH FLOW FORECAST 86

    9.1 Introduction 86

    9.2 Principles of BIM Cash Flow Forecast 86

    9.3 Cost for Breakdowns of Construction Programme 87

    9.4 Cost for Items Excluded in BQ 88

    9.5 Summary of Total Construction Cost 92

    9.6 Cost Distribution for Construction Activities 93

    9.7 Planned and Actual Construction Cost (Without Retention) 95

    9.8 Payment Arrangements for Preliminaries and Retention 101

    9.9 Planned Construction Cash Flow (With Retention) 102

    9.10 Actual Construction Cash Flow (With Retention) 104

    9.11 Final Cash Flow Curves and Forecasting (With Retention) 106

    CHAPTER 10: 5D SIMULATION 109

    10.1 Introduction 109

    10.2 Introduction to Navisworks Manage 109

    10.3 Process of Creating 5D BIM Simulation 109

    10.4 Applications of 5D BIM in Interim Payment 118

    10.5 Export to Video and Table Summary 118

    CHAPTER 11: FINDINGS DISCUSSIONS AND ANALYSIS 126

    11.1 Introduction 126

    11.2 Benefits 126

    11.3 Difficulties 128

  • viii

    CHAPTER 12: CONCLUSIONS, RECOMMENDATIONS AND SUGGESTIONS 136

    12.1 Introduction 136

    12.2 Review of Research Objectives 136

    12.3 Summary of Research 137

    12.4 Conclusions 141

    12.5 Recommendations 142

    12.6 Limitation of Research 146

    12.7 Suggestions for Further Research 148

    REFERENCES 153

    APPENDIX A – 3D Model Drawing 159

    APPENDIX B –Bills of Quantities with Pricing 195

  • ix

    LIST OF TABLES

    Page

    Table 3.1 Process of Construction Cost Management 26

    Table 4.1 Summary of Pilot Study Background 35

    Table 5.1 List of BIM Software Applications 38

    Table 5.2 Concrete Measurement Rules in HKSMM4 41

    Table 6.1 Formwork Measurement Rules in HKSMM4 57

    Table 6.2 Assumed Reinforcement Ratios 63

    Table 6.3 Example of Internal Finishing in G/F 65

    Table 6.4 Example of External Finish in G/F 66

    Table 7.1 Bill for Each Floor 67

    Table 7.2 Cost Summary of All Floors 76

    Table 9.1 Cost for each bill and total cost 89

    Table 9.2 Summary of Cost Estimation for All Items in Construction Programme 92

    Table 9.3 Payment Arrangement for Preliminaries and Retention 101

    Table 9.4 Payment Arrangement for Planned Construction Programme 103

    Table 9.5 Planned (Baseline) Construction Programme Cash Flow 104

    Table 9.6 Payment Arrangement for Actual Construction Programme 105

    Table 9.7 Actual Construction Programme Cash Flow 106

    Table 10.1 5D Cumulative Cash Flow and Monthly Interim Payment 119

  • x

    LIST OF FIGURES

    Page

    Figure 1.1 Process of 5D Simulation and cash Flow Forecast 5

    Figure 2.1 BIM Maturity Diagram 10

    Figure 2.2 Productivity of Construction Industry in U.S. 14

    Figure 4.1 Research Framework 31

    Figure 5.1 Concrete Measurement Rules in HKSMM4 42

    Figure 5.2 Example of R.C. Frame Elements 42

    Figure 5.3 Example of Column Properties 43

    Figure 5.4 Example of Window Family 44

    Figure 5.5 Example of Door Family 44

    Figure 5.6 Properties Dialogue of a Window Set 45

    Figure 5.7 Painting Function in Revit 45

    Figure 5.8 Floor Plan-G/F 46

    Figure 5.9 Floor Plan-1/F 47

    Figure 5.10 Floor Plan-2/F 47

    Figure 5.11 Floor Plan-3/F 48

    Figure 5.12 Floor Plan-4/F 48

    Figure 5.13 Floor Plan-5/F 49

    Figure 5.14 Floor Plan-6/F 49

    Figure 5.15 Floor Plan-Roof and Upper Roof 50

    Figure 5.16 Whole Building 3D Model 50

  • xi

    Figure 6.1 Example of Wall Concrete Takeoff 52

    Figure 6.2 Example of Column Concrete Takeoff 52

    Figure 6.3 Example of Beam Concrete Takeoff 53

    Figure 6.4 Example of Slab Concrete Takeoff 53

    Figure 6.5 Example of Model Tree 54

    Figure 6.6 Example of Model Schedule 55

    Figure 6.7 Example of Model Map 55

    Figure 6.8 3D Curved Surface Area Measurement 56

    Figure 6.9 Example of Workbook Function in CostX 56

    Figure 6.10 Live Linking in Workbook 57

    Figure 6.11 Example of Wall Formwork Area Measurement 59

    Figure 6.12 Example of Column Measurement in Revit 60

    Figure 6.13 Example of Beam Measurement in Revit 61

    Figure 6.14 Define Floor Level 62

    Figure 6.15 Automatic Takeoff and Sum up in Workbook 62

    Figure 6.16 Example of Door Schedule 64

    Figure 7.1 Structure of A Typical Bill in B.Q. 68

    Figure 7.2 Example of Bill 1 G/F (Concrete Works) 69

    Figure 7.3 Example of Bill 1 G/F (Brickwork & Blockwork, Internal and External

    Finishing) 70

    Figure 7.4 Example of Bill 1 G/F (Door Set, Steel & Metal Works, and Window Set)

    71

    Figure 7.5 Example of Priced BQ (Concrete Works) 72

  • xii

    Figure 7.6 Example of Priced BQ (Brickwork & Blockwork, Internal and External

    Finishing) 73

    Figure 7.7 Example of Priced BQ (Door Set, Steel & Metal Works, and Window Set)

    74

    Figure 7.8 Example of Cost Summary of Bill 1 in G/F 75

    Figure 8.1 Major Items in Construction Programme (Without Cost) 82

    Figure 8.2 Detailed Breakdown of Construction Programme (Without Cost) 85

    Figure 9.1 Relationship between Program Planning, Cost and Schedule 87

    Figure 9.2 Original Simplified Construction Program of R.C. Framing 87

    Figure 9.3 New Detailed Construction Programme of R.C. Framing 88

    Figure 9.4 Percentage for Calculating Items Excluded in BQ 90

    Figure 9.5 Simplied Version of R.C. Framing Planning 93

    Figure 9.6 Detailed Version of R.C. Frame Planning 93

    Figure 9.7 Simplified Program for Joiner and Alum. Window 94

    Figure 9.8 Detailed Construction Program of Joiner, Alum. Window 94

    Figure 9.9 Planned and Actual Construction Programme (With Cost) 97

    Figure 9.10 Baseline (Planned) Monthly Construction Cost (Without Retention) 98

    Figure 9.11 Actual Monthly Construction Cost (Without Retention) 99

    Figure 9.12 Planned (Baseline) & Actual Cumulative & Monthly Construction Cost

    (Without Retention) 100

    Figure 9.13 Comparison of Planned (Baseline) and Actual Cash Flow (With Retention)

    108

    Figure 10.1 Export Model to Navisworks Manage 110

    Figure 10.2 Example of Schedules and Costs in Navisworks Manage 111

  • xiii

    Figure 10.3 Model Elements Selection and Attachment to Task 112

    Figure 10.4 Example of inputting payment information of preliminaries, retention

    money in Navisworks Manage 114

    Figure 10.5 Simulation Settings 115

    Figure 10.6 5D Simulation Example 117

    Figure 11.1 Function for Team Collaboration in Revit 129

    Figure 11.2 Dimension of Staircase Shown in Revit 130

    Figure 11.3 Example of Window Family 131

    Figure 11.4 BIM Standard Manual by Hong Kong Housing Authority 132

    Figure 12.1 Revision to 3D BIM Model 150

    Figure 12.2 Example of Saw-tooth Diagram 151

  • Chapter 1: Introduction

    1

    1. CHAPTER 1: INTRODUCTION

    1.1 Background to the Research

    With the development of BIM technology, the adoption of the BIM in the

    construction cost management will become populous. In the following, the

    background of the research, including the techniques in the construction cost

    management, development of BIM, and the adoption of BIM in the Hong Kong and

    worldwide.

    1.1.1 Construction Cost Management

    Construction cost management is essential for the success of a project. The

    procedures in the cost management for a project include pre-contract stage and post-

    contract stage. The pre-contract cost management includes providing preliminary cost

    estimate, controlling design development within budget and measuring quantities in

    BQ. The post-contract cost management includes payment assessment, valuation of

    variations, cash flow forecasting, and settlement of final account. Cash flow

    forecasting is to assist the client early in the process with funding agreements and for

    procurement and contract choice. It can be applied in cost control by comparing the

    actual cash flow against the anticipated cash flow. The cash flow curve derived from

    the forecast is used as a guide to the Client as the predicated cash flow forecast, which

    enables to anticipate total construction cost as well as interim payments to the

    contractor. The cumulative cash flow curves are graphic representation for the

    planned expenditure for a project, which are usually in the shape of “S” and therefore

    are usually referred as “S-Curve”.

    1.1.2 BIM

    As suggested by Robert (2011), there are two ways to define BIM, i.e. Building

    Information Modeling and Building Information Management. Building Information

    Modeling is a technology that allows relevant graphical and topical information

    related to the built environment to be stored in a rational database for access and

  • Chapter 1: Introduction

    2

    management. Building Information Management is the collection, organization,

    analysis, and distribution of attributed data contained within a building project.

    BIM enables data and information to be linked with 3D components in the BIM

    model to provide 4D, 5D and 6D BIM. 4D BIM is to embed time into the 3D model,

    which can be used to simulate the construction process of the building. 5D BIM is to

    add cost to the 4D model. It allows quick cost estimation for different design options

    at the concept stage. 6D BIM is to incorporate data of facilities into the model which

    enables the facilities managers to have a powerful tool to manage the assets during the

    operating stage.

    With data of a construction project stored in the BIM model, the designers and

    constructors can simulate real life situations before commencing the project on site.

    Therefore conflicts in design and construction can be reduced. The automatic

    measurement function enables the Quantity Surveyors to run takeoffs and opt for the

    exact quantities used in estimating the pre-bid budget. Upon completion of the

    construction, the data-rich model can be delivered to the operator for facility

    management.

    Compared with the traditional approach of cost estimating, the model-based

    estimating of BIM enables automatically takeoff quantities from the model, which

    allows the project team to see the cost effects of their design options and proposed

    changes during all phases of the project. The benefits of model-based estimating

    include 1) consistent information with design, 2) efficient, cost effective and reduce

    human errors, and 3) enable estimators to focus on high value project factors.

    1.1.3 BIM Adoption in Hong Kong & Worldwide

    BIM has been adopted in several projects in Hong Kong. The Hong Kong Housing

    Authority has introduced BIM in its public housing projects since 2006. It is reported

    by Hong Kong Housing Authority (2011) that BIM has benefited the government

    organization in the construability analysis, clash detection and environmental analysis.

    It has also planned to apply BIM for facility management of the HA assets. As

    reported by HKBIM (2011), other organizations like MTR and some private

  • Chapter 1: Introduction

    3

    developers have also attempted the implementation of BIM in producing drawings in

    recent years.

    In the worldwide, some countries, like Singapore, United States and Korea, have

    move far in advance and lead the world in BIM implementation. The Singapore

    government is very encouraging the adoption of BIM. It mandates that all

    architectural, structural, mechanical and electrical plans for building works to be in e-

    submission for regulatory approval by 2015. It has also set up a BIM fund to

    encourage construction firms to implement BIM technology. In the US, BIM at the

    design stage is now a mandated requirement for public office building procured and

    maintained by the US General Services Administration. In UK, the Government’s

    chief construction adviser indicated in October 2010 that BIM will become obligatory

    on publicly procured projects in the near coming future.

    1.2 Statement of the Problem

    BIM could have a marked impact on the construction industry. It is regarded as a

    major challenge to the conventional professionals in the AEC industry including

    Quantity Surveyors. Quantity Surveying is regarded as an important discipline

    responsible for cost and contract within the construction industry. Measurement and

    preparations of Bills of Quantities are important functions underpinning quantity

    surveying practices. It is predicted that BIM will have the potential to revolutionize

    current practices of Quantity Surveying. It is also central to the contention that BIM’s

    potential in automatic measurement might threaten clients’ requirements for quantity

    surveying services.

    However, there is seldom research about what services can Quantity Surveyors

    provide to the Client on the BIM projects. In fact, the industry shall embrace the new

    opportunities and benefits provided by this new technology. With automatic quantities

    takeoff undertaken by BIM software applications, the Quantity Surveyors can focus

    on more valuable services such as construction cost management, contract

    administration, risk assessment, pricing, valuation and so on, which cannot be

    replaced by computer and software.

  • Chapter 1: Introduction

    4

    1.3 Research Aims and Objectives

    Although there are some case studies for using BIM in cost estimating of different

    design options, there is seldom research about using 5D BIM for construction cost

    management.

    This research aims to establish a framework of 5D BIM and evaluate the degree of

    feasibility and efficiency of using it for Quantity Surveyors in construction cost

    management in compliance with existing Hong Kong Standard Method of

    Measurement. During the research process, the procedures for generating 5D BIM

    cash flow forecast and simulation, the benefits and difficulties encountered will be

    described and analyzed. Solutions for some problems and recommendations for

    improvement will be discussed.

    This research aims to conduct a pilot study to investigate the production of

    construction cash flow forecast through the BIM environment. The following

    objectives are formulated for carrying out this study.

    1) To review the development of Building Information Modeling (BIM) and

    techniques for project cost management;

    2) To create BIM model with associated construction programme planning and cost

    in compliance with the Hong Kong Standard Methods of Measurement.

    3) To produce project cash flow and 5D BIM simulation under Quantity Surveying

    practices,

    4) To identify benefits and difficulties encountered for construction cost

    management through BIM environment; and

    5) To make recommendations for improving BIM application in cost management

    for Quantity Surveyors.

    1.4 Methodology

    As illustrated in Figure 1.1, 5D BIM is composed of three elements, i.e. 3D model,

    time and cost. In order to achieve 5D BIM simulation and cash flow forecast for use

    by Quantity Surveyors in the cost management, the 3D model drawing is produced in

    accordance with the principles laid down in the standards methods of measurement.

  • The in

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    “Cost” can

    create 5D BIM for simulation and cash flow forecast.

    `

    The following met

    aims and objectives.

    1)

    2)

    The information of “Time” is obtained by construction programme scheduling and the

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    “Cost” can be input into the 3D model by linking with the construction elements to

    create 5D BIM for simulation and cash flow forecast.

    Figure

    The following met

    aims and objectives.

    Literature Review

    literature review is conducted in order to establish a deep knowledge base and

    understanding abou

    construction cost management techniques. The literature

    books, journals, conference papers, seminars,

    Pilot Study

    drawing, 2) BIM quantities takeoff and measurement, 3) Bills of Quantities

    3D Model

    •Model

    Drawing

    Following

    HKSMM

    formation of “Time” is obtained by construction programme scheduling and the

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    be input into the 3D model by linking with the construction elements to

    create 5D BIM for simulation and cash flow forecast.

    Figure 1.1 Process of 5D Simulation and cash Flow Forecast

    The following methodologies are applied for the purpose of achieving the research

    aims and objectives.

    Literature Review: In the outset of this research study, a comprehensive

    literature review is conducted in order to establish a deep knowledge base and

    understanding about the current development and research of BIM technology and

    construction cost management techniques. The literature

    s, journals, conference papers, seminars,

    Pilot Study: The processes in the pilot study include the s

    drawing, 2) BIM quantities takeoff and measurement, 3) Bills of Quantities

    3D Model

    Model

    Drawing

    Following

    HKSMM

    Time

    •Construction

    Programme

    Scheduling

    formation of “Time” is obtained by construction programme scheduling and the

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    be input into the 3D model by linking with the construction elements to

    create 5D BIM for simulation and cash flow forecast.

    Process of 5D Simulation and cash Flow Forecast

    hodologies are applied for the purpose of achieving the research

    : In the outset of this research study, a comprehensive

    literature review is conducted in order to establish a deep knowledge base and

    t the current development and research of BIM technology and

    construction cost management techniques. The literature

    s, journals, conference papers, seminars,

    The processes in the pilot study include the s

    drawing, 2) BIM quantities takeoff and measurement, 3) Bills of Quantities

    Time

    Construction

    Programme

    Scheduling

    5

    formation of “Time” is obtained by construction programme scheduling and the

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    be input into the 3D model by linking with the construction elements to

    create 5D BIM for simulation and cash flow forecast.

    Process of 5D Simulation and cash Flow Forecast

    hodologies are applied for the purpose of achieving the research

    : In the outset of this research study, a comprehensive

    literature review is conducted in order to establish a deep knowledge base and

    t the current development and research of BIM technology and

    construction cost management techniques. The literature

    s, journals, conference papers, seminars,

    The processes in the pilot study include the s

    drawing, 2) BIM quantities takeoff and measurement, 3) Bills of Quantities

    Construction

    Cost

    •Automatic

    Quantity

    Takeoff and

    measurement

    •Pricing in Bills

    of Quantities

    formation of “Time” is obtained by construction programme scheduling and the

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    be input into the 3D model by linking with the construction elements to

    create 5D BIM for simulation and cash flow forecast.

    Process of 5D Simulation and cash Flow Forecast

    hodologies are applied for the purpose of achieving the research

    : In the outset of this research study, a comprehensive

    literature review is conducted in order to establish a deep knowledge base and

    t the current development and research of BIM technology and

    construction cost management techniques. The literature

    s, journals, conference papers, seminars, workshops

    The processes in the pilot study include the s

    drawing, 2) BIM quantities takeoff and measurement, 3) Bills of Quantities

    Automatic

    Quantity

    Takeoff and

    measurement

    Pricing in Bills

    of Quantities

    Chapter 1

    formation of “Time” is obtained by construction programme scheduling and the

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    be input into the 3D model by linking with the construction elements to

    Process of 5D Simulation and cash Flow Forecast

    hodologies are applied for the purpose of achieving the research

    : In the outset of this research study, a comprehensive

    literature review is conducted in order to establish a deep knowledge base and

    t the current development and research of BIM technology and

    construction cost management techniques. The literature review ranges from

    workshops etc.

    The processes in the pilot study include the steps of 1)3D model

    drawing, 2) BIM quantities takeoff and measurement, 3) Bills of Quantities

    5D BIM

    Simulation

    &Cash Flow

    Forecast

    1: Introduction

    formation of “Time” is obtained by construction programme scheduling and the

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    be input into the 3D model by linking with the construction elements to

    Process of 5D Simulation and cash Flow Forecast

    hodologies are applied for the purpose of achieving the research

    : In the outset of this research study, a comprehensive

    literature review is conducted in order to establish a deep knowledge base and

    t the current development and research of BIM technology and

    review ranges from

    teps of 1)3D model

    drawing, 2) BIM quantities takeoff and measurement, 3) Bills of Quantities

    5D BIM

    Simulation

    &Cash Flow

    Forecast

    : Introduction

    formation of “Time” is obtained by construction programme scheduling and the

    information of “Cost” is achieved by automatic quantity takeoff and measurement as

    well as pricing of the Bills of Quantities. After that, the information of “Time” and

    be input into the 3D model by linking with the construction elements to

    hodologies are applied for the purpose of achieving the research

    : In the outset of this research study, a comprehensive

    literature review is conducted in order to establish a deep knowledge base and

    t the current development and research of BIM technology and

    review ranges from

    teps of 1)3D model

    drawing, 2) BIM quantities takeoff and measurement, 3) Bills of Quantities

  • Chapter 1: Introduction

    6

    production and pricing, 4) construction programme planning, 5) cash flow

    forecasting, and 6) 5D simulation. The progress of this pilot study starts with the

    3D model drawings in accordance with the 2D drawings of a completed simple

    project. After the model drawings, the quantities of materials can then be taken off

    from the 3D model by Revit’s inherent functions and other third party softwares.

    The Bills of Quantities are produced by abstracting and billing those quantities

    measured. After pricing of the BQ, the cost for construction works can then be

    obtained. Together with the construction programme scheduling, the time and

    schedule for the construction activities can then be linked with the associated cost.

    By inputting data of schedule and cost into the 3D model, a 5D BIM model can be

    created to simulate the construction progress and coinstantaneous cash flow. The

    monthly and cumulative cash flows for planned and actual construction programs

    can then be plotted and deduced in the graph to produce the “S” curve. With the

    assistance of BIM construction management software, the 5D BIM simulation

    with visualization of construction activities, programme schedules and cash flows

    can therefore be produced for the whole project for construction cost control and

    interim payment.

    1.5 Research Procedures

    The following are research procedures in order to achieve the research aims and

    objectives.

    1) To conduct literature review on BIM and construction cost management;

    2) To draw a 3D BIM model of a simple project in compliance with the Hong Kong

    Standard Methods of Measurement;

    3) To generate automatic quantity takeoff and measurement from the BIM model;

    4) To produce Bills of Quantities and then to obtain prices of items in the Bills of

    Quantities for construction cost;

    5) To generate planned and actual construction program to obtain schedules for

    construction activities;

    6) To embed schedule(time) and cost into 3D model and generate the 5D

    construction cash flow forecast;

  • Chapter 1: Introduction

    7

    7) To create integrated 5D BIM simulation and compare actual cash flow against

    planned cash flow;

    8) To analyze benefits of 5D BIM cash flow forecast and describe difficulties

    encountered;

    9) To suggest possible solutions and recommendations for improvement.

    1.6 Outline Structure of the Thesis

    This thesis is separated into 12 chapters in order to provide a clear and concise

    account of the content. The outline structure of the thesis is summarized in the

    following.

    Chapter 1 introduces the background to the study, statement of the research problems,

    research aims and objectives, and explanation of the research methodology. It is the

    foundation of this thesis.

    Chapter 2 develops the theoretical basis of the thesis by reviewing the literature

    relating to Building Information Modeling (BIM). The current development of BIM

    technology and its applications in the construction planning, model-based estimating

    are examined. The adoption of BIM in Hong Kong and worldwide BIM standards and

    policies are investigated and reviewed.

    Chapter 3 is to overview the process of construction cost management and the

    techniques for producing cash flow forecast.

    Chapter 4 sets out the research design and methodology adopted in this research. The

    primary research methodology adopted for this study is pilot study. The research

    framework is designed for this study.

    Chapter 5 is to demonstrate the principles and process of drawing 3D model in

    accordance with the principles laid down in the Hong Kong Standard Methods of

    Measurement.

    Chapter 6 is to demonstrate the procedures of quantity takeoff and measurement from

    the 3D model.

  • Chapter 1: Introduction

    8

    Chapter 7 is to describe the process of producing Bills of Quantities floor by floor in

    the 3D model and pricing on the bills of quantities to obtain the construction cost.

    Chapter 8 is to describe the procedures to create planned and actual construction

    programme planning and scheduling in accordance with the 3D model drawing.

    Chapter 9 is to demonstrate the process of creating planned and actual cash flow

    forecasting by linking elements in the 3D model with associated time and cost.

    Chapter 10 is to demonstrate the procedures to create 5D BIM simulation with

    visualization of construction activities together with simultaneous construction

    schedule and cost.

    Chapter 11 is to discuss the findings of this study including the benefits of 5D BIM in

    construction cost management and the difficulties encountered during this study.

    Chapter 12 is to present the conclusions of the research result, research limitations,

    recommendations for applying 5D BIM for construction cost management and

    suggestions for further study.

  • Chapter 2: Literature Review-BIM

    9

    2. CHAPTER 2: LITERATURE REVIEW-BIM

    2.1 Introduction

    This chapter presents a summary of the literature reviews relating to Building

    Information Modeling (BIM). The topics of the literature reviews about BIM can be

    summarized into eight categories including 1) introduction to BIM, 2) adoption of

    BIM in the construction industry, 3) BIM and construction planning, 4) model-based

    estimating and quantity takeoff, 5) BIM and Quantity Surveying practices, 6)

    adoption of BIM in Hong Kong, 7) worldwide BIM standards and policies, and 8)

    future and preparations for BIM. In the following, the literature reviews about these

    topics are discussed in detail.

    2.2 Introduction to BIM

    In the following, the introduction to BIM includes 1) definition of BIM, 2) BIM

    maturity diagram, 3) BIM vs. 2D drawings, 4) 4D, 5D and 6D BIM and 5)

    applications of BIM.

    2.2.1 Definition of BIM

    BIM is widely used as the acronym for ‘Building Information Modeling’. As provided

    by Schwegler (2001), BIM is defined as the process of creating an information

    database for a project in which lifecycle information is expressed in an interoperable

    manner to create, engineer, estimate, illustrate and construct a construction project.

    The Department for Business Innovation and Skills of the United Kingdom (2012)

    defined BIM as a collaborative way of working, underpinned by the digital

    technologies which unlock efficient methods of designing, creating and maintaining

    the assets. It embeds key product and asset data into the 3D model for effective

    management of information throughout a project lifecycle, i.e. from the earliest

    concept through to operation.

  • Chapter 2: Literature Review-BIM

    10

    2.2.2 BIM Maturity Diagram

    As suggested by the Royal Institute of British Architects (RIBA) (2012), the most

    effective way to understand BIM is to refer the BIM Maturity Diagram which is

    prepared by Mark Bew and Mervyn Richards, as shown in Figure 2.1. In accordance

    with this diagram, the maturity of BIM can be categorized into Level 0, Level 1,

    Level 2 and Level 3.

    Figure 2.1 BIM Maturity Diagram (Bew and Richards, 2008)

    1) Level 0-CAD: The Level 0 is to use 2D Computer Aided Design (CAD) files

    for producing information, which has been used by majority of the design

    practices for many years.

    2) Level 1- 2D and 3D: In this level, the uses of 2D and 3D information are both

    increased. However, 3D software is only used as a conceptual design tool

    during the early project stages and for visualization of the finished project. In

    this level, BIM is also referred to as ‘Lonely BIM’ because it cannot be shared

    with other members of the team.

    3) Level 2- BIM: In level 2, 3D models are collaboratively produced by all key

    members of the integrated team. But they need not co-exist in a single model.

    Therefore the full potential of the intelligent data contained in the models may

    not be realized at this level.

    4) Level 3 – iBIM: The move from Level 2 BIM to Level 3 Integrated BIM

    (iBIM) is the most challenging one. In the Level 3, the integrated BIM model

    provides shared data for information in the facility management and lifecycle

  • Chapter 2: Literature Review-BIM

    11

    costing. As illustrated by RIBA (2012), the Level 3 BIM will make it possible

    to:

    • Implement early design analysis on environmental performance and

    minimize iterative design time;

    • Quickly derive cost from the model using new costing interfaces;

    • Analyze health and safety associated with the construction and

    maintenance of the building; and

    • Align asset management, key performance indicators, and other

    feedback information with intelligent briefing, and to inform and

    improve future projects.

    2.2.3 BIM vs. 2D Drawing

    As stated by K. Pramod Reddy (2011), the 2D drawing only enabled the coordination

    in two dimensions and did not validate the space in any other dimension. This results

    in inconsistent and repeatable outcomes from meeting to meeting and project and

    project. BIM provides a much greater level of accuracy, which benefits all of the

    trades and builders involved in the coordination process.

    2.2.4 4D, 5D and 6D BIM

    As illustrated in the “BIM Overlay to the RIBA Outline Plan of Work” issued by the

    RIBA (2012), data and information can be linked with 3D components or assemblies

    in the BIM model to provide 4D, 5D and 6D BIM.

    1) 4D BIM

    4D BIM is to add time to the project 3D model. It is useful to simulate the

    construction process of the project in order to identify issues such as critical path

    activities, logistical delivery and refining the construction process. It can also be used

    to examine ways to make up time. The contract administrator can also use the

    programme to assess delays and applications for Extension of Time (EOT) raised by

    the contractor. A 4D enhanced model enables a diverse team of project participants to

    evaluate and comment on the project scope and corresponding schedules in a very

    proactive and timely manner (K. Pramod Reddy, 2011).

  • Chapter 2: Literature Review-BIM

    12

    2) 5D BIM

    5D BIM is to incorporate programme schedules and cost information into the project

    3D model. It will allow cost estimation of design options to be produced faster. It also

    makes different design options to be assessed accurately at the concept stage and

    makes the design to be more aligned with a client’s budget.

    3) 6D BIM

    6D BIM is to add data of facilities into the model. It enables the facilities management

    teams to have a powerful tool to manage the assets. For example, if a door is damaged,

    the FM team can click the door tag in the model and find its supplier and then order or

    repair the door in accordance with the supplier’s data.

    2.2.5 Applications of BIM

    The applications of BIM can be demonstrated in the following aspects, which include

    construability analysis, automatic measurement, facility management, as well as

    energy analysis.

    1) BIM & Construability Analysis

    Latham (1994) reported that design deficiencies and associated constructability

    constraints are the largest factors responsible for the poor performance of the

    construction industry. With data of the project stored in the BIM model, designers and

    constructors can simulate real life situations before commencing project on site.

    Therefore it is likely that conflicts in design and construction can be reduced by BIM.

    2) BIM & Automatic Measurement

    BIM has the powerful function of automatic measurements. The Cooperative

    Research Centre for Construction Innovation has reported successful attempts to

    produce Bills of Quantities automatically using the Industry Foundation Class (IFC)

    data (O.A. Olatunji et al, 2010). A data-rich BIM contains all of the potential building

    information, including the specifications and quantities, which allow the Quantity

    Surveyors to run takeoffs and opt for the exact quantities used in estimating the pre-

    bid budget (K. Pramod Reddy, 2011).

    3) BIM & Facility Management

  • Chapter 2: Literature Review-BIM

    13

    BIM enables an organization to virtually build the building before the actual

    construction start. This helps to eliminate many of the inefficiencies of the

    construction process. Upon completion, the data-rich model can be delivered to the

    owner or the facility manager for operating the building throughout its entire life

    cycle (K. Pramod Reddy, 2011). As reported by Hong Kong Housing Authority

    (2011), it has planned to apply BIM technology to streamline the maintenance, repair

    and management of HA facilities.

    4) BIM & Energy Analysis

    BIM can analyze and predict energy cost during the early design phase. It will help

    architects to understand how their design would impact energy consumption and costs

    during the building’s life cycle. Facility managers can also use data in BIM to

    benchmark a building’s energy consumption (K. Pramod Reddy, 2011). As reported

    by the Hong Kong Housing Authority (2011), BIM enables them to simulate the time

    of sunrise and sunset at a site and the direction the sun travels. This enables to

    determine the best location for sitting buildings and for planting greenery. Therefore

    the design can be enhanced by leveraging natural resources like sunlight and airflow,

    which eventually reduces the use of air-conditioning and consumption of energy.

    2.3 Adoption of BIM in the Construction Industry

    In the following, the discussions about the adoption of BIM in the construction

    industry include the issues about 1) construction industry and technology, and 2) the

    slow adoption of BIM in the construction industry.

    2.3.1 Construction Industry and Technology

    The construction economy is important to the society in terms of employment and

    economies contribution. However, it is well recognized that construction industry is

    conservative to technology adoption (O.A. Olatunji et al, 2010). In accordance with

    the research undertaken by the Center for Integrated Facility Engineering in Stanford

    University, U.S., the productivity of construction industry relative to all non-farm

    industries in the U.S., during the period from 1964 to 1998, showed that the

    construction productivity had declined slightly while productivity in all other

  • Chapter 2: Literature Review-BIM

    14

    industries had almost doubled in this period, as shown in Figure 2.2 (Benedict et al,

    2001).

    Figure 2.2 Productivity of Construction Industry in U.S. (Stanford University, 2001)

    2.3.2 Slow adoption of BIM in Construction Industry

    As reported by Phillip G. and Jon H. Pittman (2004), the productivity and economic

    benefits of BIM were widely and increasingly acknowledged and well understood.

    The technology of BIM is also readily available and rapidly maturing. However, the

    adoption of BIM is slower than anticipated. Although lack of interoperability between

    software applications is one significant point of friction, it is neither the singular nor

    most important factor impeding BIM adoption. As suggested by Phillip G. and Jon H.

    Pittman (2004), there are three interrelated barriers to BIM adoption as:

    1) the need for well-defined transactional business process models;

    2) the requirement that digital data be computable; and

    3) the need for well-developed practical strategies for the purposeful exchange of

    meaningful information between the many tools applied to industry processes

    today.

  • Chapter 2: Literature Review-BIM

    15

    2.4 BIM and Construction Planning

    In the following, the discussions about the applications of BIM in the construction

    planning include 1) introduction to BIM construction planning, 2) functions of BIM

    construction planning, 3) applications of BIM in construction planning, 4) benefits of

    BIM construction planning and 5) the examples of applying BIM construction

    planning in Hong Kong.

    2.4.1 Introduction to BIM Construction Planning

    It is claimed that by using the BIM platform together with the construction process

    management software like Autodesk Navisworks Manage, the workflow of the

    construction process can be simulated to effectively plan construction operations,

    identify potential problems, and explore and evaluate alternatives (Autodesk, 2012).

    2.4.2 Functions of BIM Construction Planning

    The functions of BIM construction planning include simulating planned sequences of

    construction activities, identifying clashes and interference problems, finding

    opportunities for improving construction schedules, tracking materials and managing

    the supply chain (Autodesk 2012).

    2.4.3 Applications of BIM in construction planning

    As reported by Autodesk (2012), BIM can be applied in the construction planning in

    terms of the following areas.

    1) 4D Modeling

    The 4D modeling can simulate the planning sequence of construction activities and

    space requirements on site, provide powerful visualization and identify the problems

    well in advance of construction activities.

    2) Site Utilization Planning

    The use of BIM can help to evaluate the locations of facilities on site during multiple

    phases of the construction process.

    3) 3D Coordination and Clash Detection

  • Chapter 2: Literature Review-BIM

    16

    It is to identify potential conflicts by comparing all building systems and thus to

    reduce field conflicts.

    4) Identify Time-Based Clashes

    By using the time-based clash testing, BIM can be used to verify the planned

    sequence of construction operations on the constrained sites.

    5) Construction System Design (Virtual Mockups)

    BIM can be used to create a model and conduct analysis on the construction of a

    complex building system for the detailed construction planning.

    6) Materials Planning and Management

    By linking the building elements in the project model and the associated task schedule,

    the dates when elements are needed on site for installation can be forecasted.

    2.4.4 Benefits of BIM Construction Planning

    As claimed by Autodesk (2012), traditional scheduling methods, such as bar charts or

    critical path method network diagrams, can be difficult to address the spatial aspect

    and they are not linked to the design or building model. The advantages of using 4D

    simulations include:

    1) informing design decisions by considering the impact on construction of

    proposed design features;

    2) identifying and resolving problems earlier;

    3) accessing and managing project risks; and

    4) improving project schedules and bringing facilities to client sooner.

    2.4.5 Example of BIM Construction Planning in Hong Kong Housing Authority

    As reported by the Hong Kong Housing Authority (2011), BIM enabled them to

    monitor the construction progress closely and ensure a six-day construction cycle for

    a typical floor. One example of using BIM for site planning is the Kwai Chung Tai

    Pak Tin Street project in which the site is very congested and has slopes on its three

    sides. BIM has assisted to define the best routes for site workers and trucks, the best

    location for soil disposal, as well as the optimum works sequence for transporting

  • Chapter 2: Literature Review-BIM

    17

    formworks and steel bars. The detailed programme and workflow simulated by BIM

    have enhanced both work efficiency and site safety.

    2.5 Model-based Estimating and Quantity Takeoff

    The discussion for model-based estimating and quantity takeoff includes the issues

    about 1) traditional cost estimating, 2) definition of model-based estimating, 3)

    functions of model-based estimating, 4)benefits of model-based estimating, 5) model-

    based estimating in stages, and 6)methods for exporting BIM to cost estimating

    system.

    2.5.1 Traditional Cost Estimating

    In the traditional approach, the estimators will typically begin cost estimating by

    digitizing the architect’s drawings, or importing their CAD drawings into a cost

    estimating software, or manual takeoff from the drawings. However, human errors

    will be introduced and inaccuracies in the original drawings will be propagated in

    such traditional process (Autodesk, 2007).

    2.5.2 Definition of Model-based Estimating

    Model-based estimating is to use features in the BIM model to create conceptual

    estimates. It can be used to compare the cost of proposed alternatives and prepare

    preliminary estimates to confirm cost feasibility and evaluate proposed design

    changes (Autodesk, 2012).

    2.5.3 Functions of Model-based Estimating

    As claimed by Autodesk (2012), model estimating can be used to accurately generate

    quantity takeoffs and assist in the creation of cost estimates throughout the lifecycle

    of a project. It enables the project team to see the cost effects of their design decisions

    and proposed changes during all phases of the project. It will also support better

    design decision-making and can help curb excessive budget overruns due to project

    modifications.

  • Chapter 2: Literature Review-BIM

    18

    2.5.4 Benefits of Model-based Estimating

    As reported by Autodesk (2007), the benefits of BIM Cost Estimating include the

    following aspects:

    1) consistent information with design:

    By using BIM, measurements and quantity takeoff can be generated directly from the

    model. Changes in the design can automatically ripples to all related measurement,

    schedule and documentation.

    2) Efficient, Cost Effective and Reduce Human Error

    BIM cost estimating can enable estimators to save time, cost and reduce the potentials

    of human errors.

    3) Enable focusing on high value project factors

    With quantities takeoff and measurement automatically done by BIM, estimators can

    focus on high value project-specific factors such as identifying construction

    assemblies, generating pricing, factoring risks and so forth.

    2.5.5 Model-based Estimating in Stages

    As reported by Autodesk (2012), model-based cost estimates are very valuable to

    project teams at every stage of the design process, as shown in Table 2.1.

    Table 2.1 Stages of Model-based Estimating (Autodesk, 2012)

    Stage Action Purpose

    1) Early Design

    Stage Cost estimates based on area or

    volume of a proposed conceptual

    design and comparison to

    historical data.

    To confirm that the design is

    feasible and in alignment

    with budget.

    2) Design being

    developed Material takeoff and quantify

    key building elements to

    compute real-time preliminary

    cost estimates.

    To confirm that the evolving

    design is staying on-track

    and evaluate the cost impact

    of proposed design

  • Chapter 2: Literature Review-BIM

    19

    enhancements.

    3) Design

    matures with

    construction

    details

    accurately

    modeled

    Precise quantity takeoffs

    extracted from BIM model to

    compute very detailed cost

    estimates.

    To analyze factors in the

    planned construction process

    and consider labor, materials,

    equipment, and subcontractor

    costs for all building

    elements.

    4) Increased

    detail level of

    each element

    in BIM model

    Increase level of costing detail. To make more precise cost

    estimates.

    2.5.6 Methods for Exporting BIM to Cost Estimating System

    The approaches to export quantities and descriptions from BIM into a cost estimating

    system include Application Programming Interface (API), Open Database

    Connectivity (ODBC) and Output to Excel. The selection of approach to be adopted

    shall be in accordance with the estimating workflow, the costing solutions, the pricing

    database and other factors of the organization (Autodesk, 2007).

    1) Application Programming Interface

    This approach is using a direct link between the costing system and BIM software like

    Revit. The user can export the building model from BIM software using the costing

    program’s data format and send it to the estimator. The estimator can then open it

    with the costing solutions to begin the costing process.

    2) Open Database Connectivity

    It typically uses the ODBC database to access the attribute information and dimension

    data in the building model. Such kind of estimating software applications include

    CostX and ITALSOFT.

    3) Output to Excel

    This method is to take off quantity within Revit and then output to an Excel program.

    It is most suitable for some projects with simple costing workflow.

  • Chapter 2: Literature Review-BIM

    20

    2.6 BIM and Quantity Surveying Practice

    The topic about BIM and Quantity surveying practices will cover the discussion about

    1) role of Quantity Surveyors, and 2) effect of BIM on Quantity Surveying practices.

    2.6.1 Role of Quantity Surveyors

    Quantity surveying is regarded as an important discipline responsible for cost and

    contract within the construction industry. The conventional services provided by the

    Quantity Surveyors include preliminary estimates, feasibility studies, cost plans, and

    bills of Quantities preparation. They are also responsible for construction contract,

    tender analysis, contractor selection and financial management of all construction

    works. In addition, some quantity surveying firms provide other services such as

    value management, management contracting, construction dispute resolution and so

    on (Nkado, 2000).

    2.6.2 Effect of BIM on Quantity Surveying Practices

    As reported by Masidah and Khairuddin (2005), while some professional services

    provided by Quantity Surveyors might be unnecessary, measurement and preparations

    of Bills of Quantities are important functions underpinning quantity surveying

    practices. It is predicted that BIM will have the potential to revolutionize current

    practices of quantity surveying. It is central to the contention that BIM’s potential in

    automatic measurement might threaten clients’ requirements for quantity surveying

    services (O.A. Olatunji et al, 2010).

    2.7 Adoption of BIM in Hong Kong

    BIM has been adopted in several projects in Hong Kong. In 2011, the Hong Kong

    Institute of Building Information Modeling (HKIBIM) has issued a report about the

    use of BIM in Hong Kong since 2005. It was reported that projects in MTR and other

    private developments have attempted the implementation of BIM in producing

    drawings in recent years (HKIBIM, 2011).

  • Chapter 2: Literature Review-BIM

    21

    In the public sector, the Hong Kong Housing Authority claimed that it had introduced

    BIM in its public housing projects since 2006. In fact, BIM system has been adopted

    in more than 19 public housing projects by the Hong Kong Housing Authority at

    various project stages for identifying and resolving construction and demolition

    difficulties. As reported by the Hong Kong Housing Authority (2009), it had set up

    plans for BIM as:

    1) starting from 2014-2015, use BIM as a standard design tool for housing

    projects;

    2) from 2006, pilot BIM for more than 19 public housing projects at various

    project stages;

    3) prepare in-house BIM standards, user guide, library component design guide

    and references;

    The projects utilizing BIM technology include So Uk Demolition, So Uk

    Redevelopment, Kwai Chung Area 9H, and Kai Tak Site 1B. It is reported that the

    application of BIM enabled the Hong Kong Housing Authority to perform building

    analysis to avoid clashes in design and improve communication among project teams,

    contractors and the public. It has also pilot several projects using BIM environmental

    analysis, 4D construction planning and it has planned to apply BIM technology to

    streamline the maintenance, repair and management of HA facilities (Hong Kong

    Housing Authority, 2011).

    2.8 Worldwide BIM Standards and Policies

    The discussion about the worldwide BIM standards and policies will cover the

    adoptions of BIM in countries of Singapore, China, Korea, the United States and the

    United Kingdom.

    2.8.1 Singapore

    The Singapore Government is encouraging the adoption of BIM technology in the

    construction industry. The Singapore Building and Construction Authority (BCA)

    mandates that all architectural, structural, mechanical and electrical plans for building

    works shall be in e-submission for regulatory approval by 2015. It is expected by the

  • Chapter 2: Literature Review-BIM

    22

    Singapore BCA that 80% of the organizations in the construction industry will use

    BIM by then. The BCA has also set up a BIM fund in order to encourage construction

    firms to implement BIM technology in actual projects (Singapore BCA, 2012).

    2.8.2 China

    In the Twelfth Five Years Plan released in 2011, the Chinese Government has realized

    the importance of using information system to improve the qualities and standards in

    the construction industry. In a report issued by the Ministry of Housing and Urban-

    rural Development of the People’s Republic of China (2011), the government planned

    to:

    1) encourage application of BIM technology for clash analysis in the construction

    projects;

    2) apply information management in the construction industry to improve

    productivity and management standards.

    3) use BIM to visualize design in the design stage and to reduce errors in

    information transmission during construction stage.

    4) investigate possibilities of implementing BIM in complex and large projects.

    5) incorporate BIM to synchronize information in architecture, structure and

    mechanics.

    2.8.3 Korea

    The Korean government agencies including the Korean Public Procurement Service

    and the Korea’s Ministry of Land, Transport and Maritime Affairs, are encouraging

    the adoption of BIM. In January 2010, the Korean Ministry of Land, Transport and

    Maritime Affairs has compiled a BIM application guide for architectural and civil

    engineering works which include detailed descriptions of methods and conditions for

    using BIM technology for owners, architects and engineers (Korean Ministry of Land,

    2012).

    2.8.4 The United States

    As reported by K. Pramod Reddy (2012), some government agencies and building

    owners in the United States such as the General Services Administration (GSA) and

  • Chapter 2: Literature Review-BIM

    23

    the U.S. Army Corps of Engineers have taken extreme steps regarding mandating the

    use of BIM. They believe the adoption of BIM will have benefits for every key player

    in the construction process, from design to construction to facility management.

    2.8.5 The United Kingdom

    In May 2011, the Cabinet Office of the United Kingdom announced its Government

    Construction Strategy for BIM. In accordance with this report, the Cabinet Office will

    coordinate with the industry stakeholders to develop standards for BIM. As outlined

    in this report by the Cabinet Office of U.K. (2011), the major BIM strategies set by

    the Government are to:

    1) allow time for industry stakeholders to prepare for new standards and training

    for BIM;

    2) complete agreed pilot projects using BIM;

    3) starting from March 2012, post BIM to the completion process such as facility

    management;

    4) starting from April 2012, define and mandate BIM standards for Government

    projects;

    5) starting from summer 2012, roll out BIM to all government projects;

    6) by July 2012, achieve goal of fully collaborative delivery via 3D models for

    trial projects in multiple departments;

    7) by 2016, require fully collaborative 3D BIM with all data and documentation

    being electronic;

    8) use BIM to integrate design and construction with facility management.

    From the summer of 2012, the UK government has made commitments to have all of

    its projects utilizing BIM based on the “Government Construction Strategy - UK

    Government Cabinet Office, May 2011” as well as “BIM overlay to the RIBA Outline

    Plan of Work” (Department for Business Innovation and Skills of U.K., 2012).

  • Chapter 2: Literature Review-BIM

    24

    2.9 Future & Preparation for BIM

    In the discussion for the future and preparation for BIM, the two issues will be

    discussed, i.e. 1)the future impacts of BIM and 2)the suggested preparations for BIM.

    2.9.1 Future Impacts of BIM

    As reported by O.A. Olatunji et al (2010), BIM could have a marked impact on the

    pre-construction processes, however, complying BIM with the relevant Standard

    Methods of Measurement could be one of the chief challenges. BIM is regarded as a

    major challenge to the conventional professionals in the AEC industry including

    Quantity Surveyors, which may redefine the traditional professional boundaries.

    2.9.2 Preparations for BIM

    AEC industry will face a great challenge as the shift from Level 0 BIM to Level 3

    BIM as described in the BIM maturity diagram is more significant compared with the

    shift from drafting on tracing paper to CAD. The following are some approaches as

    suggested by RIBA (2012) as to:

    • provide training, especially in relation to teamwork and collaborative approaches

    in design and construction to embrace new working methods;

    • examine current successful private sector integrated team models and set out how

    different models might be appropriate depending on the client’s aspirations and

    risk profile;

    • adopt industry-wide process;

    • consider ways to build and manage successful project teams; and

    • contribute to the debate on the best forms of procurement which will truly

    encourage collaboration and innovation.

    Therefore, the Quantity Surveyors and other construction professionals need to have

    some preparations for BIM, e.g. reviewing quantity surveying curricula in education

    (O.A. Olatunji et al, 2010).

  • Chapter 3: Literature Review-Construction Cost Management

    25

    3. CHAPTER 3: LITERATURE REVIEW-CONSTRUCTION COST

    MAN AGEMENT

    3.1 Introduction

    This chapter presents a summary of the literature reviews about construction cost

    management. The topics covered in the literature reviews for construction cost

    management include 1) process of construction cost management, 2) cash flow

    forecast, 3) cash flow curve, and 4) cumulative cost curve. In the following, the

    literature reviews about these topics are discussed in detail.

    3.2 Process of Construction Cost Management

    In Hong Kong, the normal processes of construction cost management include the

    procedures as in the following:

    1) providing preliminary cost estimate;

    2) controlling the design development within budget;

    3) measuring the quantities of construction works in the Bills of Quantities;

    4) controlling cost in post-contract stage, including

    a. payment assessment

    b. valuation of variation

    c. cash flow forecasting

    d. settlement of final account

    The process of construction cost management in different stages can be summarized

    in Table 3.1.

  • 3.3

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    cash flow forecast, 4) reten

    format of cash flow forecast.

    3.3.1

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    company, and 2) cash flow forecast of a particular projec

    study, only

    BIM technology

    3.3.2

    Generally, the approach adopted by the employer for producing cash flow for

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    some issues differ between one party and another,

    In this

    Cash Flow Forecast

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    cash flow forecast, 4) reten

    format of cash flow forecast.

    3.3.1 Types of Cash Flow Forecast

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    company, and 2) cash flow forecast of a particular projec

    study, only the cash flow of a project, i.e.

    BIM technology

    3.3.2 Employer’s

    Generally, the approach adopted by the employer for producing cash flow for

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    some issues differ between one party and another,

    In this dissertation

    Chapter

    Table 3.1

    Cash Flow Forecast

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    cash flow forecast, 4) reten

    format of cash flow forecast.

    Types of Cash Flow Forecast

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    company, and 2) cash flow forecast of a particular projec

    the cash flow of a project, i.e.

    BIM technology.

    Employer’s vs. Contractor’s Cash Flow Forecast

    Generally, the approach adopted by the employer for producing cash flow for

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    some issues differ between one party and another,

    dissertation, only the cash flow for the

    Chapter 3: Literature Review

    1 Process of Co

    Cash Flow Forecast

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    cash flow forecast, 4) retention percentage and period, and 5) accurate graphical

    format of cash flow forecast.

    Types of Cash Flow Forecast

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    company, and 2) cash flow forecast of a particular projec

    the cash flow of a project, i.e.

    Contractor’s Cash Flow Forecast

    Generally, the approach adopted by the employer for producing cash flow for

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    some issues differ between one party and another,

    , only the cash flow for the

    : Literature Review

    26

    Process of Construction C

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    tion percentage and period, and 5) accurate graphical

    Types of Cash Flow Forecast

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    company, and 2) cash flow forecast of a particular projec

    the cash flow of a project, i.e. project cash flow

    Contractor’s Cash Flow Forecast

    Generally, the approach adopted by the employer for producing cash flow for

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    some issues differ between one party and another,

    , only the cash flow for the client

    : Literature Review-Construction Cost Management

    nstruction Cost Management

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    tion percentage and period, and 5) accurate graphical

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    company, and 2) cash flow forecast of a particular project (RICS, 2012). In this pilot

    project cash flow

    Contractor’s Cash Flow Forecast

    Generally, the approach adopted by the employer for producing cash flow for

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    some issues differ between one party and another, e.g. retention money (RICS, 2005)

    client will be discussed.

    Construction Cost Management

    ost Management

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    tion percentage and period, and 5) accurate graphical

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    t (RICS, 2012). In this pilot

    project cash flow, will be

    Contractor’s Cash Flow Forecast

    Generally, the approach adopted by the employer for producing cash flow for

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    retention money (RICS, 2005)

    will be discussed.

    Construction Cost Management

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    tion percentage and period, and 5) accurate graphical

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    t (RICS, 2012). In this pilot

    will be created using

    Generally, the approach adopted by the employer for producing cash flow forecast is

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    retention money (RICS, 2005)

    Construction Cost Management

    In the discussion for cash flow forecast, the following issues are discussed as 1)types

    of cash flow forecast, 2) employer’s vs. contractor’s cash flow forecast, 3) function of

    tion percentage and period, and 5) accurate graphical

    There are mainly two types of cash flow forecast, i.e. 1) cash flow forecast of a

    t (RICS, 2012). In this pilot

    created using

    ecast is

    different from the approach adopted by the contractor. It is due to different

    considerations in terms of payment dates, presentation of the cash flow forecast, and

    retention money (RICS, 2005).

  • Chapter 3: Literature Review-Construction Cost Management

    27

    3.3.3 Function of cash flow forecast

    The function of cash flow forecast is to assist the employer early in the process with

    funding agreements and for procurement and contract choice. The cash flow profiles

    may also be affected by the different procurement routes and contracts (RICS, 2012).

    3.3.4 Retention Percentage and Period

    The provision of retention is usually included in the construction contract. It is usually

    10% of certified value excluding Nominated Subcontractors’ values, plus retention

    retained for each Nominated Subcontractor. The limit of retention is usually 5% of

    main contract sum excluding Nominated Subcontractors’ sub-contract sums, plus

    limit of retention for each Nominated Subcontractor. Half of the total retained sum

    shall be released upon the issue of the Practical Completion Certificate. The

    remaining half shall be released upon the issue of Making Good Certificate which is

    usually 12 months (or otherwise months agreed in contract) after the Practical

    Completion Certificate (Ramus, 1996).

    3.3.5 Accurate Graphical Format of Cash Flow Forecast

    The retention shall be taken account of in the accurate cash flow forecast. There will

    also be a long period between practical completion and the final certificate where the

    cash flow is static with a final jump at the end which signals the return of the final

    part retention (RICS, 2005).

    3.4 Cash Flow Curve

    In the following, the topics about 1) definition of cash flow curve, 2) function of cash

    flow curve, and 3) preparations of the cash flow curve are discussed.

    3.4.1 Definition of Cash Flow Curve

    The cash flow curve is produced by a detailed estimate combined with a detailed

    construction schedule. It is a graphical estimate of when the contractor expects to

    have work in place and the estimated cost of that work. It is often one of the first

    things the employer will ask the project manager (Len et al., 2005).

  • Chapter 3: Literature Review-Construction Cost Management

    28

    3.4.2 Function of cash flow curve

    In the design process, cash flow cures are often used as a guide to the employer for

    the predicted cash flow forecast (RICS, 2005). The cash flow curve serves the

    function of a forecast to the employer of anticipated monthly payment to the

    contractor for the completed work.

    3.4.3 Preparation of cash flow curve

    The cash flow curve is prepared by applying the estimated costs across the schedules

    of activities. For example, if an activity has a value of $100,000 and takes five months

    to complete, then $20,000 is spread over each of the five months. The other costs such

    as the administration, taxes, and fees should be distributed proportionately over the

    entire project. The cost data are summed at the bottom of the schedule for each month

    to develop the anticipated monthly expenses (Len et al., 2005).

    3.5 Cumulative Cost Curve

    The discussion about cumulative cost curve will cover 1) the definition of cumulative

    cost curve, and 2) the function of S-curve.

    3.5.1 Definition of Cumulative Cost Curve

    The cumulative cost curves are graphic representation for the planned expenditures

    for a project. In the cumulative cost curve, x-axis represents the time periods and the

    y-axis represents the cumulative costs expended at any particular time. The curve is

    created by connecting the cumulative cost points of a project during each time period

    over the entire duration of the project. The cumulative cost curve is usually in the

    shape of a somewhat flattened “S” due to the higher expenditures during the middle of

    the project and the lower expenditures in the beginning and end of the project. Thus,

    the curve is also usually referred as “S-Curve” (James, 2008).

    3.5.2 Function of S-Curve

    As reported by James (2008), the S-Curve has many valuable functions in the

    construction project management as to:

  • Chapter 3: Literature Review-Construction Cost Management

    29

    1) Help project manager see the total planned budget and communicate it in a

    shorthand way;

    2) Serve as an excellent briefing tool and easily to be read;

    3) Serve as an excellent way of summarizing progress including both planned

    and actual cost curves on the same graph for comparison; and

    4) Analyze the earned value.

  • Chapter 4: Research Methodology

    30

    4. CHAPTER 4: RESEARCH METHODOLOGY

    4.1 Introduction

    The fundamental knowledge of the Building Information Modeling, cost management

    and quantity surveying practices has been discussed in the literature review. With the

    established knowledge, a pilot study about the innovative generation of cost

    management using the 5D BIM technology will be carried out in order to find out

    whether BIM can be used by the Quantity Surveyors for the cost management in the

    cash flow forecasting.

    4.2 Background of Research

    With the development and maturing of BIM technology, the adoption of BIM

    technology in the construction industry is inevitable. In fact, the Hong Kong Housing

    Authority has set the targets to apply BIM to all new projects from design stage by

    2014/2015 (Fung, 2011). BIM is expected to have a marked impact on the existing

    practices for professionals in the AEC industry including the Quantity Surveyors. In

    this dissertation, a pilot study of applying 5D BIM technology in the cost management

    will be conducted to investigate the feasibility and efficiencies of using 5D BIM by

    Quantity Surveyors. The difficulties encountered during the study will be discussed.

    Some solutions for the problems will be suggested, while for some problems which

    cannot be solved will be considered as the limitations of BIM adoption.

    4.3 Research Framework

    In order to fulfill the research objectives, a comprehensive research process including

    literature review, pilot study, discussion and analysis of findings, conclusions and

    recommendations are programmed at the outset of the research. The framework of the

    research process is illustrated in Figure 4.1.

  • Analysis of Findings

    •Benefits

    •Difficulties and Problems

    •Suggested Solutions

    Recommendations &

    Suggestions for Further

    Literature Review

    •BIM (development of BIM, 4D, 5D,

    model-based estimating, standards

    and policies worldwide, etc.)

    •Construction Cost Management

    flow forecast, cumulative cost curve,

    etc.)

    Discussion and

    Analysis of Findings

    Benefits

    Difficulties and Problems

    Suggested Solutions

    Conclusions,

    Recommendations &

    Suggestions for Further

    Study

    Literature Review

    (development of BIM, 4D, 5D,

    based estimating, standards

    and policies worldwide, etc.)

    Construction Cost Management

    flow forecast, cumulative cost curve,

    Discussion and

    Analysis of Findings

    Difficulties and Problems

    Suggested Solutions

    Conclusions,

    Recommendations &

    Suggestions for Further

    Study

    Literature Review

    (development of BIM, 4D, 5D,

    based estimating, standards

    and policies worldwide, etc.)

    Construction Cost Management (cash

    flow forecast, cumulative cost curve,

    Analysis of Findings

    Difficulties and Problems

    Recommendations &

    Suggestions for Further

    Figure 4.1

    31

    (development of BIM, 4D, 5D,

    based estimating, standards

    (cash

    flow forecast, cumulative cost curve,

    •3D Model Drawing

    measurement rules )

    •BIM Quantities Takeoff and

    Measurement

    CostX; Measure by floor)

    •BQ Production and Pricing

    Use current tender price of related BQ to

    reflect true price level)

    •Construction Programme Planning

    (Planned and actual construction

    programme planning by assumption)

    •Cash Flow Forecast

    model with schedule and cost; Formulate

    schedule for retention money deduct and

    release; Create planned and actual cash

    flow)

    •5D Simulation

    activities and simultaneous schedule and

    cash flow)

    1 Research Framework

    Chapter 4

    Data Collection

    and Viability

    Checking

    Conduct Pilot Study

    3D Model Drawing

    measurement rules )

    BIM Quantities Takeoff and

    Measurement(Use Revit schedule and

    CostX; Measure by floor)

    BQ Production and Pricing

    Use current tender price of related BQ to

    reflect true price level)

    Construction Programme Planning

    (Planned and actual construction

    programme planning by assumption)

    Cash Flow Forecast

    model with schedule and cost; Formulate

    schedule for retention money deduct and

    release; Create planned and actual cash

    flow)

    5D Simulation (Visulation of construction

    activities and simultaneous schedule and

    cash flow)

    Research Framework

    4: Research Methodology

    Data Collection

    and Viability

    Checking

    Conduct Pilot Study

    3D Model Drawing (Follow HKSMM 4

    measurement rules )

    BIM Quantities Takeoff and

    (Use Revit schedule and

    CostX; Measure by floor)

    BQ Production and Pricing (Bills by floor;

    Use current tender price of related BQ to

    reflect true price level)

    Construction Programme Planning

    (Planned and actual construction

    programme planning by assumption)

    Cash Flow Forecast (Link elements in

    model with schedule and cost; Formulate

    schedule for retention money deduct and