Tute -05.11.2011

Embed Size (px)

Citation preview

  • 7/27/2019 Tute -05.11.2011

    1/27

  • 7/27/2019 Tute -05.11.2011

    2/27

    In order to exempt a project from the use ofcompetitive bidding, the Contracting Agency mustadopt findings that support their resolution toexempt the project.

    1) Will not encourage favouritism2) Will result in substantial savings to the Agency3) Effect on the Operational Budget4) Public Safety5) Is there a Public Benefit

    6) Will Value Engineering be done7) What effect do Market Conditions have9) Technical Complexity10) What is the Funding Source and what effect

    will the exemption have

  • 7/27/2019 Tute -05.11.2011

    3/27

    Traditional delivery Design and buildsystem Turnkey, Package deal

    Client

    Designer

    Contractor

    Client

    Designer

    Contractor

    Inspector

    SupervisorQ.S.

    InspectorSupervisor

    Subcontractors

  • 7/27/2019 Tute -05.11.2011

    4/27

    Defined as an arrangement where onecontracting organisation takes soleresponsibility, normally on a lump sum fixedprice basis, for the bespoke design andconstruction of a clients project (e.g. D + B).

    The fundamental characteristics responsibility for the design and construction lies

    with one organisation reimbursement is generally by means of a fixed-

    price lump sum project is designed and built specifically to meet

    the need of the client

  • 7/27/2019 Tute -05.11.2011

    5/27

    A single contract between the project owner anda design-build contractor covering both thedesign and construction of a project.

    The design-builder performs design,construction engineering, and constructionaccording to design parameters, performancecriteria, and other requirements established bythe agency.

    Implemented in the highway construction

    industry in a variety of ways on how the state statutes are written

    how much responsibility is transferred to the design-builder for the design and other aspects of projectperformance.

  • 7/27/2019 Tute -05.11.2011

    6/27

    Modified Design-Build, also called Low Bid design-

    build or Draft/Detail-Build, where the agencycompletes a significant portion of the designbefore selecting the contractor using a low bidsolicitation or qualified low bid process.

    The design-builder then completes the remainderof the design work and constructs the projectunder a single contract.

    Primarily used in cases where state law prohibits

    the procurement of construction services using amethod other than low bid or before the design issubstantially complete, and the agency administersthe project using traditional practices and retains

    greater responsibility for project performance.

  • 7/27/2019 Tute -05.11.2011

    7/27

    Agency completes the conceptual design to alower level and then procures the design-builder under a two-step best-value proposalprocess.

    This two-step best-value approach allows formuch earlier involvement by the design-

    builder and shifts greater control andresponsibility for the design and projectperformance to the design-builder.

  • 7/27/2019 Tute -05.11.2011

    8/27

    D&B contract may also include responsibilities that extendbeyond the design and construction phases of a project,shifting more performance risk to the private sector.

    Design-Build-Warranty - A single entity designs, constructs,and warrants specified components over a prescribed timeperiod (e.g., 5, 10, or 20 years). Warranty requirements shift

    quality responsibility to the design-builder and reduce theagencys need to inspect during construction and maintainthe facility during its service life.

    Design-Build-Maintain - A single entity designs, builds, andmaintains the project works for a specified period of timeunder a single contract. Payment beyond completion ofconstruction is typically tied to meeting certain prescribedperformance-based standards for a period of years.

    Design-Build-Operate - A single entity designs, builds, andoperates the project (e.g., a toll road) for a specified periodof time under a single contract.

  • 7/27/2019 Tute -05.11.2011

    9/27

    Expanded to a PPP concept, where a private

    entity or developer takes part in financing andleasing a project in return for monetarycompensation based on contractualauthorization to collect revenues, or pursue

    development rights with the contractingagency. Private entity will be responsible for financing,design and construction, and often will operate

    and maintain the project for a specifiedduration. May give full or partial contracting authority to

    the private entity.

  • 7/27/2019 Tute -05.11.2011

    10/27

    A recent and fairly comprehensive study on design-build

    effectiveness focusing on design-build projects completedunder SEP-14 reported the following (SAIC, AECOM, andUniversity of Colorado 2006):

    An average 14 % time savings for design-build projectswhen compared to design-bid-build schedule estimates

    3 % reduction in total cost. An average reduction of 1 % between planned and actualtotal project duration No appreciable change in total cost. A comparable level of quality to design-bid-build delivery.

    For agency satisfaction as a quality measure, the use ofbest-value procurement, lower level of design, and largerprojects with design-build yielded higher satisfactionratings.

  • 7/27/2019 Tute -05.11.2011

    11/27

    Owner established budget and buildingcriteria

    Design and construction firm is selected asone team based on a predetermined list ofcriteria

    The design and construction are bothaccomplished by the selected team

  • 7/27/2019 Tute -05.11.2011

    12/27

    The owner contracts with a single entity toprovide the design and to construct theproject according to that design.

    The contract might be negotiated with asingle design-builder or result fromcompetitive proposals.

    The selection can be based on low price or

    on a set of value criteria (experience, staff,bonding capacity, etc.).

  • 7/27/2019 Tute -05.11.2011

    13/27

    Provides the owner with a single point ofcontact for project responsibilities,eliminating the need to assist inresolving designer-contractor disputes.

    With the contractor playing a major role

    in design, costs are typically defined andmaintained to a greater degree, and thecoordination of fast-track managementto achieve early completion is greatlysimplified.

    The design-builder makes manydecisions that owner would make underDBB, due to delegation of greatlyincreased authority.

  • 7/27/2019 Tute -05.11.2011

    14/27

    For many owners, delegation of responsibilitiesleads to satisfactory projects. However, if theparties are inexperienced and do notcooperate, the transfer of control and risk canbe disappointing.

    The owner may need to restructure his/herinternal procedures to accommodate design-build approach.

    Compared to DBB, this involves a significantlydifferent set of requirements and expectationsfor process, timelines and communications.

    A clear understanding and documentation ofdesign-build processes enhances the quality ofdesign-build projects.

  • 7/27/2019 Tute -05.11.2011

    15/27

    Specific use buildings Simple design criteria

    Repetitive function (open office space; hotel)

    Financed by others

  • 7/27/2019 Tute -05.11.2011

    16/27

    Characteristics

    Single pointresponsibility

    Can be overlapped

    Client can be sure ofmaximum cost before

    final commitment

    Integrated design andconstruction

    Improves buildability

    Fits to constructors

    expertise, workingcondition,organisation

    Preparation Design

    Tender ContractConstruction

    Cost

    costs should belower shorter timeon site

    Thus

    (Savings are not passed to the client in lower prices)

  • 7/27/2019 Tute -05.11.2011

    17/27

    Funding Option Variations Turnkey

    Developer Financed Projects

    Turnkey Variations

  • 7/27/2019 Tute -05.11.2011

    18/27

    Private capital and developer participationoffer private owners several variations ondesign-build.

    Lease-develop-operate arrangement:Theowner gives a private operator a long-term

    lease to use, operate, and expand an existingfacility. Public-private partnership or wrap around:

    Ownership of or fiduciary responsibility for a

    project is assigned to a private party. Thatparty designs, builds, and may even own,operate and maintain the new facility.

  • 7/27/2019 Tute -05.11.2011

    19/27

    Turnkey adds to the design-buildersresponsibilities the operation and/ormaintenance of the completed project.

    Turnkey delivery has the potential for

    bringing a new project on line more quickly. Three forms of turnkey project delivery:

    Design-build-operate-transfer Design-build-operate-maintain

    Design-build-own-operate-transfer

  • 7/27/2019 Tute -05.11.2011

    20/27

    For highly specialized projects andcircumstances, financing from a private orpublic developer or other third parties canoffer additional variations on design-build

    and turnkey project delivery, each with newroles for owners, designers, and contractors.

  • 7/27/2019 Tute -05.11.2011

    21/27

    Variations on turnkey add financing as a keycomponent. While financing arrangementsare unique for each project, developerfinanced projects generally resemble one ofthe turnkey delivery methods:

    FDBT (Finance, design, build, transfer) FDBOT (Finance, design, build, operate, transfer) FDBOOT (Finance, design, build ,own, operate,

    transfer)

    In each case, the transfer of the project

    occurs only after the developers interestsand financial obligations have beensatisfied.

  • 7/27/2019 Tute -05.11.2011

    22/27

    ECI is a hybrid design-build project delivery method from England

    involving qualifications-based design-builder selection and anopen-book target pricing system.

    Objective Align team goals through the early establishment of the

    contractors role in the project development process and through

    the rational and equitable sharing of project risks

    Qualifications-based approach to select a contractor early in theproject development process, when the agency has onlyconceptual plans and an approved budget price.

    Once the contractor has been selected, additional design andplanning is performed with the input of the entire delivery team to

    establish a target price for the project from that point forward. Various mechanisms are incorporated throughout the design and

    construction process for the contractor to share in savings, andparticipate in any losses, realized when actual costs are comparedto the target price.

  • 7/27/2019 Tute -05.11.2011

    23/27

    The agency compensates the contractor for actual costs, based on open-book accounts andrecords, plus a fee.

    In addition, an incentive structure, similar to that described below, is established to motivate thecontractor to design and construct the project within budget.

    Design Bonus If the contractor designs the project within the project budget, as indicated bycomparing the forecast total project cost to the project budget, the contractor is paid a designbonus. If the forecast costs are greater than the project budget, the contractor does not receive abonus, but likewise does not suffer any reduction in payment. If the agency elects to proceed withthe project, the contractor still has the opportunity to earn incentives during the constructionphase of the project.

    Construction Bonus During the construction phase, the contractor is paid actual construction costsplus a percent fee. If, at the end of construction, the total of actual costs plus the contractors feeis less than the estimated cost (i.e., initial target price adjusted for any additional compensationpaid out during design and construction), the contractor is paid a share of the savings, ascalculated using a formula set out in the contract. Similarly, the contractor would pay a share ofany cost overruns.

    Final Bonus At the completion of the project, the agency will calculate a final bonus based on acomparison of the contract budget to the total project expenditures incurred by the agency,including any design and construction bonuses already paid to the contractor, as well as an

    estimate of future costs not yet incurred. If the total expenditure is less than the contract budget,the contractor is paid a bonus percentage of the savings achieved on the contract budget. If thecontract budget is exceeded, no final bonus is payable to the contractor; however, the contractordoes not share in any additional cost overruns (other than what they may have already incurred inthe construction cost share).

  • 7/27/2019 Tute -05.11.2011

    24/27

    Pros ConsAllows contractors expertise to be

    introduced earlier in the projectdevelopment process

    Absence of direct price competition

    can lead to overly conservative andeasily achievable performance targets

    Bonus structure provides an incentivefor contractor to control costs andwork within the target priceestablished for the project

    Open-book accounting structure andthe risk of sharing in cost overrunsmay deter potential bidders

    Open book target pricing systemrequires contractor to operate in anopen and collaborative way

    Increased procurement costs

    Potential for overlapping design andconstruction phases may allow for

    faster project delivery

    Encourages better communicationbetween contractor and agency

  • 7/27/2019 Tute -05.11.2011

    25/27

    Compresses the schedule by sequencing the

    start of construction on underlying projectelements (e.g. foundation, basic supportingstructures) before final design is complete forinterior or adjacent elements.

    Is not a method of delivery, rather, its amanagement strategy within delivery methods. While often successful in achieving schedule

    reductions, problems on fast-track contractscan create a domino effect on follow-oncontracts for the project.

    More successful on projects that arestraightforward and have a high level ofpredictability.

  • 7/27/2019 Tute -05.11.2011

    26/27

    Pros ConsDesign E&O not responsibility of owner Owner has little or no input into design

    Initial cost is within budget Owner is at greater risk for owner initiated changes

    Other than owner, changes to initial design criteria is little to no

    risk

    Reduced opportunities for smaller, local construction firms

    Single point of contact between client and contractor Higher procurement costs

    If clients requirement is accurately specified, certainty of finalproject and cost would be then less when compared with otherprocurement methods

    Elimination of traditional checks and balances. Designer is nolonger agencys advocate. Quality may be subordinated by cost orschedule considerations.

    Design and construction is overlapped which results in improvedcommunications being establish between contractor and client.These two characteristics enable shorter, overall project periodsto be achieved and project management efficiency to be

    improved

    The absence of a bill of quantity makes the valuation of variationsextremely difficult and restricts the freedom of clients to makechanges to the design

    Single point responsibility for design and construction Less agency control over final design

    Accelerated project delivery by:- Fast-tracking design and construction- Close coordination between designer and contractor- Early contractor involvement to enhance constructability ofplans

    The clients control over the aspect of design and aesthetics ofthe building is less when compared with other methods ofprocurement

    Cost containment by minimizing owners exposure to design

    errors and omissions

    Fewer competitors and increased risk may result in higher initial

    costsEarlier schedule and cost certainty Accelerated construction can potentially overextend the

    workforce.

    Innovation and quality improvements through:- Alternative designs and construction methods suited to thecontractors capabilities- Flexibility in the selection of design, materials, andconstruction methods

    Traditional funding may not support fast-tracking construction ormay require accelerated cash flow.

    The clients brief is often ambiguous and does not convey exactlywhat he is proposing to the contractor.

  • 7/27/2019 Tute -05.11.2011

    27/27