Earned Value Management Leading & misleading in Project Control Prepared by: Engr. Mohamed Maged, PMP Admin of: https://www.facebook.com/Prof .Planner ة ب س ت ك م ل ا ة م ي ق ل ا دارة ا روعات ش م ل ا ي ف م حك# ت ل ا ي ف ادعة ح م و دة ي ق م

Earned Value Management - Leading & Misleading in Project Control

Embed Size (px)

Citation preview

Page 1: Earned Value Management - Leading & Misleading in Project Control

Earned Value Management

Leading & misleading in Project Control

Prepared by:Engr. Mohamed Maged, PMP

Admin of: https://www.facebook.com/Prof.Planner

المكتسبة القيمة في– إدارة ومخادعة مفيدةالمشروعات في التحكم

Page 2: Earned Value Management - Leading & Misleading in Project Control

Instructor: Mohamed Maged

Senior Project Control Engineer, B.Sc. of Civil engineering – Ain Shams University, with experience in MENA region of (construction, infrastructure, and roads) Mega projects, in professions of Contract administration, Procurement,Tender estimating, Cost control, Planning & Claim analysis.   

Instructor of Planning & Project Management:- Construction Management Planning and Control (CMPC).- Delay, Claim and Dispute Resolution (DCDR) in PMBOK, FIDIC & SCL protocol.- Project Management Professional (PMP).- Free lectures with cooperation of Egyptian Engineers Association in Saudi:

- Product oriented construction management- Top 10 planning fundamentals- Scope creep – cases and preventive actions- Claims and dispute resolution in FIDIC

Page 3: Earned Value Management - Leading & Misleading in Project Control

Mohamed Maged (Prof. Planner)

Admin of the biggest online community of Arab Planners (10,000+)

(Facebook Page: to be prof. planner, related group: Best Advice for Planners – Public group) Achievements of 3 Years: http://www.slideshare.net/MohamedMaged8/3-years-acheivements

P P&C Academy (recently launched): http://prof.planner.teachable.com/

SlideShare: www.slideshare.net/MohamedMaged8/

YouTube Channel: https://www.youtube.com/ArabPlanners.

Arranged Two Annual Conferences of Planning and Project Management (Anniversary of Facebook Page: Prof.Planner)- American University in Cairo, August 2014 & 2015.

Page 4: Earned Value Management - Leading & Misleading in Project Control

References:1- A GUIDE TO THE PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK® Guide) – Fifth Edition.2- Practice Standard for EARNED VALUE MANAGEMET – PMI Global STANDARD.3- EARNED VALUE Project Management - QUENWT. FILEMNING and JOEL M. KOPPELMAN.4- Skills & Knowledge of Cost Engineering – AACE International.5- EARNED VALUE MANAGEMENT APM GUIDELINE FOR THE UK.6- Earned Value Professional (EVP) Certification Study Guide– AACE International.7- CMPC Course Material – Construction Management Planning & Control (Prof.Planner).8- Construction Project Scheduling and Control - Saleh Mubarak.9- Project Management, Planning, and Control - Albert Lester.10- Other posts and slide-shares from internet.

Page 5: Earned Value Management - Leading & Misleading in Project Control

Lecture TopicsProject ControlPerformance M.

BaselineWBS & Control

AccountsConcept of Cost ControlWhy Earned Value?Earned Value Analysis

Earned Value Forecasting

Earned ScheduleFinance & Cash flowSchedule Total FloatTricky or MisleadingStudy & Practice

Page 6: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

6

Project control is the continuous practice of

1.monitoring work progress,

2. comparing it to baseline budget and schedule,

3.detecting any deviations and their causes, and

4. taking a corrective action wherever and whenever necessary.

Also called Project tracking, Project monitoring & Follow up.

Project Control

Page 7: Earned Value Management - Leading & Misleading in Project Control

7

Create WBS. subdividing project deliverables and project work (including management work) into smaller, more manageable components, can be used as communications tool.

Tools & Techniques:Decomposition. A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts (e.g. by phase or by major deliverables).

Manageable Level of Control

Page 8: Earned Value Management - Leading & Misleading in Project Control

8WBS Dividing – Scope Baseline

- Lowest level in WBS called Work Package, then it can be decomposed to Schedule Activities.

Page 9: Earned Value Management - Leading & Misleading in Project Control

9

معن--ى • المعتم--د ؟ Baseline Programmeم--ا الزمن--ي ال--برنامج ه--وaccepted ،تأخي-ر أ-و مطالب-ة أ-ي دراس-ة عن-د الي-ه الرجوع يت-م مس-تند ويعت-بر

عمل يت-م الزمن-ي ال-برنامج عل-ى يؤث-ر م-ا تغيي-ر اعتماد حال-ة revisedوف-يbaseline. للمتابعة

Baseline Schedule

Page 10: Earned Value Management - Leading & Misleading in Project Control

10Cash Flow

Cost Baseline. The approved version of the time-phased project budget, excluding any management reserves.

Page 11: Earned Value Management - Leading & Misleading in Project Control

11Work Package - Control Account

Page 12: Earned Value Management - Leading & Misleading in Project Control

12

Cost Aggregation. Summing the lower-level cost estimates for a given cost control account.Planning Package. Control Account. A management control point to earned value.Reserve analysis. Budget reserve analysis can establish both the contingency reserves and the management reserves.Contingency Reserve. Allowance for identified risks that are accepted (known unknown).Management Reserve. for unforeseen work that is within scope (unknown unknown).Funding Limit Reconciliation. comparing the planned expenditure against any limits.

Cost Rolling-up

Page 13: Earned Value Management - Leading & Misleading in Project Control

13Control Account Responsibility

There are three main types of organizational structures: functional, matrix, and project

The above organizational process flow ofwork authorization is captured in Work Authorization Documents (WADs) that take many forms.

Page 14: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

14

- Cost control is related to cash out of Contractor most probably.

- It is the process of comparing the estimated to be spent for each (CA / activity / work package) and the actual.

- Therefore, You are comparing apple to apple.

Cost Control

Page 15: Earned Value Management - Leading & Misleading in Project Control

15

Scheduling and estimating are related and their relationships is probably one of the most important relationships in project management. These two areas intersected in many ways such as the following:

1) The estimator need to know how long the project will last in order to estimate certain cost , particularly overhead.

2) Scheduling and Estimating department collaborate to provide information to the procurement department. 3) Resource allocation and resource leveling may be cost related, although these are scheduling issues.

Proper Estimating (planning) is Very Important for Control

Page 16: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

16

What is an updated schedule?A living copy schedule reflecting project performance data at a given data date regarding completed activities, in progress activities, and change in the logic, cost, and resources and allocated at any level.

What is data date?The data date is the date as of which all progress on a project is reported. It is also called as- of date, cut-off date and status date .

Schedule Update

Page 17: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

17Output of Update

Baseline Cash Flow:

Time phased Budget Value of Planned

Work

Schedule Update: Up to date

Actual Value of Performed

Work & remaining

Page 18: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

18

Earned Value Management (EVM), started in 1800’s as a method for integrated project cost and schedule control, then in the 1960’s, was designed by the U.S. Air Force and named the Cost/Schedule Planning and Control System.

Earned Value History

Page 19: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

19Earned Value Terminology

Earned Value (EV) Analysis: Earned Value analysis is an integrated cost-schedule approach to monitor and analyze the progress in a project.

Page 20: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

20Earned Value Analysis

When EV is useless: If the WP = WS which happens for sure at the project completion if the scope is the same.

Page 21: Earned Value Management - Leading & Misleading in Project Control

21

Earned Value Management

This’s Why Earned Value…

EVM has been called “management with lights on”

Page 22: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

22Earned Value Reporting - Costs

ACWPBCWPCPI

ACWPBCWPCV

CPI = 1, on budgetCPI < 1, over budgetCPI > 1, under budget

Budgeted Cost of Work Performed (BCWP) = earned value Actual Cost of Work Performed (ACWP) = actual cost Cost Variance (CV): Difference between earned and actual

costs for the completed work Cost Performance Index (CPI or CI): as following

Page 23: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

23Earned Value Reporting - Schedule

Budgeted Cost of Work Performed (BCWP): earned value

Budgeted Cost of Work Scheduled (BCWS): planned value

Schedule Variance (SV): Difference between the value of work that was planned to be accomplished and the value of the work that was actually completed

Schedule Performance Index (SPI or SI): as following

BCWSBCWPSPI

BCWSBCWPSV

SPI = 1, on scheduleSPI < 1, behind scheduleSPI > 1, ahead of schedule

Page 24: Earned Value Management - Leading & Misleading in Project Control

24Earned Value - Forecasting

24

(earned)

(actual)

(budgeted)Forecasted cost variance (FCV) = CV ∕ % Complete = $400 ∕ 26.7% = $1, 500

Schedule variance in days (SV, days) = SV ($) ∕ Daily planned budget = $-1,067 ∕ $266.67 = - 4 daysForecasted schedule variance (FSV) = SV ∕ %Complete = -4 ∕ 26.7% = -15 days

Page 25: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

25

A simple problem will help to illustrate the application of the principles of earned value . A project has been defined that consist of 12 activities for which the estimated cost and duration have been defined see figure .After three and a half month , the activates 1,2,4,5,7 are completed and (6) is half complete and (8) is three–fourth complete and (3) is half complete. The incurred cost to date are 152000$ . What is the status of this project in terms of the schedule and the budget?

Example

Activity cost m1 m2 m3 m4 m5 m61 $220002 $100003 $180004 $300005 $500006 $400007 $60008 $160009 $1300010 $400011 $3400012 $14000

Page 26: Earned Value Management - Leading & Misleading in Project Control

26Solution

ACWP =152000$

BCWS=22000+30000+50000+10000+18000+0.5(40000+6000+16000)=161000$

BCWP=22000+30000+50000+10000+6000+0,5(40000)+0.75(16000)+0.5(18000)= 159000$

SV= BCWP-BCWS= -2000$ its behind schedule

CV=BCWP-ACWP= 7000$ under the budget

EAC=ACWP+(BAC-BCWP)=152000+(257000-159000) = 250000$

Page 27: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

27Earned Value: Cost and Time Status

Cost +CV

TimeSV

III

III IV

-

- +

Page 28: Earned Value Management - Leading & Misleading in Project Control

28

(Factors)

Earned Value Summary

Page 29: Earned Value Management - Leading & Misleading in Project Control

29

Page 30: Earned Value Management - Leading & Misleading in Project Control

30

(Forecast & TCPI)

-Magnify the cost variance.-Maintain the variance till end.-More accurate.-Time (SV) affect he cost as well as (CV).

Budget value of remaining work / Value of cost to spend (up to Budget or to Estimate)

Page 31: Earned Value Management - Leading & Misleading in Project Control

31

(EV)

Page 32: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

32Time-Based Measures: Earned Schedule

SPI(time) = PT / AT

AT: Actual Time of Work Performed (till Data date) (actual time expended to date (ATE) for a particular earned value)

PT: Planned Time of Work Performed (originally planned duration (OD) for that earned value)

Page 33: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

33Scope & Time

Forecast Time:EAC (t) = BAC (t) / SPI

Scope Control:Schedule factors based on cost.Time Control:Schedule factors based on time.

Estimated Duration

Page 34: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

34

- We can measure: Earned Quantity, Earned Workhours & Credit ($) WH of actual quantity as per budget unit rate, then Productivity Index (PI)= $ / unit.

Physical Units - Resources

- EVM requires the recording of resource utilization in resource units (i.e. labor, materials, and the like) for the work performed to compare with budget of resource units , and capture the actual costs.

- Lump Sum Projects Measurements

Page 35: Earned Value Management - Leading & Misleading in Project Control

35Cash flow: Cash-out vs Cash-in

Turnover: Inflation & interest

Economics, Estimating, Accounting & Finance

(EFCC – course)

Funding gap: budget overrun

Mon

th 0

1

Mon

th 0

2

Mon

th 0

3

Mon

th 0

4

Mon

th 0

5

Mon

th 0

6

Mon

th 0

7

Mon

th 0

8

Mon

th 0

9

Mon

th 1

0

Mon

th 1

1

Mon

th 1

2

Mon

th 1

3

Mon

th 1

4

Mon

th 1

5

Mon

th 1

6

Mon

th 1

7

Mon

th 1

8

Mon

th 1

9

Mon

th 2

0

PAC

FAC

0%

20%

40%

60%

80%

100% Cash in Received netadvance addedCash outCash in Invoice gross

Page 36: Earned Value Management - Leading & Misleading in Project Control

May 2, 2023

36Total Float Vs EVM Schedule Factors

Misleading in Each:

1- Out of sequence can disturb the results of EVM schedule factors specially if the progress of critical path is different.

2- Availability of resources and resource usage in remaining works can affect the rationality of the total float specially if many paths overlapped in the remaining duration.

Page 37: Earned Value Management - Leading & Misleading in Project Control

37

Some amount of knowledge brings more……

Earned Value Management - Tricky or Misleading

Page 38: Earned Value Management - Leading & Misleading in Project Control

38

Soon more courses in the regard at: http://prof.planner.teachable.com/

Economics, Estimating, Accounting, Finance & Cost Control Topics

Cost Engineering

Earned Value Basics - Arabic https://www.facebook.com/groups/prof.cost.engineers/

Page 41: Earned Value Management - Leading & Misleading in Project Control

Thank YouDon’t Hesitate to contact….