1 Design-Built Permanent Soil Nail Retaining Wall and Building Foundations at the University of Connecticut Health Center Ulrich La Fosse, P.E. GeoDesign, Inc. Middlebury, CT New York, NY Windsor, VT September 13, 2013

04 LaFosse PPT Final

Embed Size (px)

DESCRIPTION

LaFosse PPT Final

Citation preview

Page 1: 04 LaFosse PPT Final

1

Design-Built Permanent Soil Nail Retaining Wall and Building Foundations at the University of

Connecticut Health Center

Ulrich La Fosse, P.E. GeoDesign, Inc.

Middlebury, CTNew York, NYWindsor, VT September 13, 2013

Page 2: 04 LaFosse PPT Final

2

Site Locus

SITE

Bridging Documents –Foundations and Wall Types

ACC Building – Drilled Shafts

Garage – Spread Footings

Site Wall Behind Garage• Temporary SOE• Buttress Type – Concrete Gravity Wall• Heights up to 55 feet & 450 feet long

Page 3: 04 LaFosse PPT Final

3

Bridging Docs Retaining Wall - Plan

Section 15-Ft24-Ft500-Ft

GRAVITY WALL

c

Bridging Docs Retaining Wall - Section

GRAVITY WALL

Page 4: 04 LaFosse PPT Final

4

Bridging Docs Temporary SOE & Wall

CONCRETEGRAVITY

WALL

TEMPORARYSOE WALL

Alternate Design Goals

Accelerate Construction

Eliminate work

Achieve economies

Meet Owner Criteria

Page 5: 04 LaFosse PPT Final

5

Alternate Design Concept

Combine Temporary & Permanent Support of Excavation

Replace Drilled Shafts with shallow Foundations (ACC)

Maximize Foundation Pressures (Garage & ACC)

Retaining WallDesign Considerations

Sparse Subsurface Data Very Tight Schedule for Design Tall Wall (up to 55 feet High) Wall Surcharge (1.5H:1V slope and

Road) Bridge Abutment Loading Combine Temporary & Permanent

Support of Excavation

Page 6: 04 LaFosse PPT Final

6

Surficial Geology

SITE

Retaining WallConstruction Considerations

Sparse Subsurface Data Tall Wall (up to 55 feet) Wall Surcharge (1.5H:1V slope and

Road) Bridge Abutment Loading Combine Temporary & Permanent

Support of Excavation

Page 7: 04 LaFosse PPT Final

7

Page 8: 04 LaFosse PPT Final

8

EXISTING 2H:1V SLOPE

Page 9: 04 LaFosse PPT Final

9

Main Road and Traffic Surcharge

STEEP SLOPE ABOVE WALL

Page 10: 04 LaFosse PPT Final

10

Retaining WallPerformance Considerations

Must Limit Movement

Permanent Wall Considerations

Wall Finish – Varying Opinions

Alternate Design ConsiderationsACC Building

High Bearing Pressures Desirable Variable Soil Conditions

• Unsuitable Fill, over• Moderately dense Glacial Till, over• Dense to very Dense Till

Reworked Site – Possible unexpected variations and organics

Page 11: 04 LaFosse PPT Final

11

Permanent Soil Nail Wall Design

Partial Soil Wall Nail Plan

Page 12: 04 LaFosse PPT Final

12

Typical Soil Nail Wall - Section

Typical Soil Nail Wall - Section

Page 13: 04 LaFosse PPT Final

13

Typical Soil Nail Wall - Section

Typical Soil Nail Wall - Section

Page 14: 04 LaFosse PPT Final

14

Typical Soil Nail Wall - Section

Partial Soil Nail Wall – Elevation

Page 15: 04 LaFosse PPT Final

15

Soil Nail Wall – Detailed Section

CAPACITY OF TEMPORARYFACING IS NEGLECTED IN FINAL DESIGN

Start of Wall Construction

Page 16: 04 LaFosse PPT Final

16

Page 17: 04 LaFosse PPT Final

17

Page 18: 04 LaFosse PPT Final

18

DCP Soil Nailsand Temporary Shotcrete

Wall Facing

Page 19: 04 LaFosse PPT Final

19

Page 20: 04 LaFosse PPT Final

20

Page 21: 04 LaFosse PPT Final

21

IT IS IMPERATIVE TO BE ABLE TO CONTROL WATER and SOILS MUST BE ABLE TO STAND UNTIL SHOTCRETE HAS BEEN APPLIED

SLOUGHING SOILS

DRAINAGE, DRAINAGE, AND MORE DRAINAGE!

Page 22: 04 LaFosse PPT Final

22

A DCP SURPRISE!

A SIMPLE SOLUTION TO THE VEXINGPROBLEM OF LACK OF DCP AT TOP OF NAIL

Page 23: 04 LaFosse PPT Final

23

ANOTHER SURPRISEAN UNEXPECTED STUMP DUMP!

Page 24: 04 LaFosse PPT Final

24

Installation of Reinforcement for Final Shotcrete Wall Facing

Page 25: 04 LaFosse PPT Final

25

Page 26: 04 LaFosse PPT Final

26

Page 27: 04 LaFosse PPT Final

27

Page 28: 04 LaFosse PPT Final

28

Application of Final Shotcrete Wall Facing

Page 29: 04 LaFosse PPT Final

29

Night Work to MeetProject Schedule

Page 30: 04 LaFosse PPT Final

30

Completed Wall

Page 31: 04 LaFosse PPT Final

31

Page 32: 04 LaFosse PPT Final

32

Page 33: 04 LaFosse PPT Final

33

Page 34: 04 LaFosse PPT Final

34

Page 35: 04 LaFosse PPT Final

35

Page 36: 04 LaFosse PPT Final

36

Micropile-Supported Bridge AbutmentDirectly Behind

Permanent Soil Nail Wall

Page 37: 04 LaFosse PPT Final

37

Page 38: 04 LaFosse PPT Final

38

Page 39: 04 LaFosse PPT Final

39

Footing Preparationat ACC Building

Page 40: 04 LaFosse PPT Final

40

Page 41: 04 LaFosse PPT Final

41

Thank You!

Questions?