04039447

Embed Size (px)

Citation preview

  • 7/29/2019 04039447

    1/5

    IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 22, NO. 1, JANUARY 2007 311

    Detrimental Effects of Capacitors in DistributionNetworks in the Presence of Harmonic Pollution

    Nicola Locci, Carlo Muscas, Member, IEEE, and Sara Sulis, Student Member, IEEE

    AbstractThe main goal of this paper is to analyze the behaviorof an electric power network in the presence of harmonic distor-tion, when capacitors are installed. The work starts from a casestudy, where failure and malfunctioning of an industrial plant aredescribed with the help of experimental measurements. The theo-retical and mathematical details of thephenomena involvedare an-alyzed by suitable computer simulations. The study is performedby considering some important electrical quantities, evaluated ac-cording to the definitions proposed by the standard IEEE 1459.The results put in evidence that using some typical quantities, suchas the power factor, could lead to ambiguous conclusions in evalu-ating the actual quality of the loads, and this can assume specialimportance in virtue of the economic relevance of such quantities.

    Index TermsCapacitors, harmonic distortion, power factor,power quality (PQ).

    I. INTRODUCTION

    CAPACITORS are widely used in distribution power net-

    works to obtain reactive compensation of the inductive

    loads. The root-mean-square (rms) value of the current in

    the power line feeding the customers loads is reduced by

    employing capacitors, so that both the generation capability of

    the power plant and the losses in the distribution network are

    minimized.However, the behavior of such compensation systems is op-

    timal only under sinusoidal conditions. These days, the actual

    operating conditions of power networks (in particular, distri-

    bution networks) may significantly differ from the pure sinu-

    soidal steady state, which is the reference condition for which

    the plants and the electrical devices are usually designed, real-

    ized, and applied.

    This paper focuses on some implications of the harmonic dis-

    tortion existing in modern distribution networks, when capaci-

    tors are installed in some of the nodes, since there is growing ev-

    idence that, under nonsinusoidal conditions, the presence of ca-

    pacitors is associated with the partial or overall malfunctioning

    of the plants (see, for instance, [1] and [2]).Furthermore, let us consider penalties for polluting loads and

    power-quality indexes needed to assign responsibility for dis-

    turbances in electric power systems. Doubts arise as to how the

    role of capacitors should be taken into account when such ac-

    knowledged indexes will be used to qualify the polluting be-

    havior of loads. In particular, there is a possibility that some in-

    dexes may penalize polluting consumers with capacitors in their

    Manuscript received April 1, 2005; revised February 13, 2006. Paper no.TPWRD-00185-2005.

    The authors are withthe Department of Electricaland ElectronicEngineering,University of Cagliari, Cagliari 9123, Italy (e-mail: [email protected]).

    Digital Object Identifier 10.1109/TPWRD.2006.877088

    plants [3][5], even if they are used for the reactive compensa-

    tion of the fundamental component of the current.

    In order to prove the relevance of these topics, we will con-

    sider a case study consisting of an industrial plant with signifi-

    cant harmonic pollution and the presence of capacitors.

    First, the drawbacks that arose during preliminary tests will

    be reported. It is shown that the nonsinusoidal conditions of the

    network seriously affect the performance of the portion of the

    plant where the capacitors are positioned, leading to interven-

    tion of the protection relays and, thus, inhibiting the normal

    plant operation. Then, the analysis of the network will be car-

    ried out by means of proper simulations in order to investigatedifferent possible configurations by evaluating, for each test,

    several electrical parameters defined in the IEEE 1459-2000

    trial-use standard [6]. In particular, a well known and commonly

    used parameter will be considered: the power factor, for which

    different definitions are proposed in [6], according to different

    measurement purposes and different network conditions. It is

    well known that the power factor has important economic im-

    plications since its value is related to the penalties applied by

    utilities to consumers. The results of this study show that, if the

    involved phenomena are not well understood and the proper pa-

    rameters are not considered, it is possible to make significant er-

    rors in the assignment of the responsibility for low-power factor.

    II. CASE STUDY

    A. Plant Layout

    The experimental investigation was performed on the

    network supplying the forge unit of a metallurgic plant for man-

    ufacturing steel pieces. Fig. 1 shows the general scheme of the

    plant. The industrial plant is supplied by two identical 1-MVA

    medium-voltage (MV)/low-voltage (LV) transformers (referred

    to as Tr1 and Tr2 in the following), having a common primary

    MV (15 kV) bus. In the studied situation, the low-voltage

    outputs of the transformers are independent of each other: the

    feeder leaving from Tr1 is dedicated to the forge division (bymeans of its distribution center, named DC1 in Fig. 1), while

    Tr2 supplies the other loads of the plant (distribution centers

    DC2 and DC3).

    The supply line from Tr1 to the distribution center of the forge

    unit is 140 m long and is made by an EPR cable ( mm

    for each phase plus the neutral conductor).

    The power supply to the forge is provided by a three-phase

    rectifier bridge, realized by thyristors, followed by a dc/ac high-

    frequencyconverter (10 kHz) realized by means of a high-power

    insulated-gate bipolar transistor (IGBT) inverter.

    The nominal current of the device is 870 A, with a rated

    voltage of 380 V. This nonlinear load is named Nlin in Fig. 1.

    0885-8977/$20.00 2006 IEEE

  • 7/29/2019 04039447

    2/5

    312 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 22, NO. 1, JANUARY 2007

    Fig. 1. Plant layout.

    From the same distribution center, a different feeder supplies

    a linear load (Lin) representing the service circuits of the unit.

    These circuits mainly include lighting circuits, consisting of

    groups of 400-W metal halide lamps, equipped with capacitors

    for reactive power compensation. The protection for the lighting

    circuits is guaranteed by automatic circuit breakers (CBs).

    During the preliminary tests, performed before starting the

    normal operation of the industrial process, overload conditions

    always occurred in the lighting circuit, thus causing the auto-

    matic CBs to open in less than a minute after the forge was

    triggered, even if CBs were designed and installed according to

    standard requirements. Such problems have prevented the plant

    from becoming operational.

    B. Voltage and Current Measurement

    To examine the nature and origin of the reported malfunc-

    tioning, both the voltages and the currents in the crucial points

    of the plant have been measured. A digital phosphor oscillo-scope Tektronix 3014 (sample rate 1.25 GSamples/s on each

    channel, 9 b for the vertical resolution) was used to acquire the

    waveforms. Voltage transduction is guaranteed by an active dif-

    ferential probe Tektronix P5200 with a bandwidth ( 3 dB) up

    to 25 MHz and accuracy 5%. Current transduction for currents

    up to 100 A is ensured by a Hall effect clamp-on probe Tek-

    tronix A622 with a frequency range up to 100 kHz and accu-

    racy . The current feeding the distribution center

    DC1 (whose rated value is 870 A) was directly measured on the

    output of transformer Tr1, acquiring the voltage at the output ter-

    minals of the current transformer installed in the power center.

    Theaccuracy of themeasurement systemis quite low, owingtothe uncertainty introduced by both the transducers and the ver-

    tical channels of the oscilloscope. According to Standard IEC

    61000-4-30 [6], the instrument specifications could be marked

    as class B performance.However, this accuracy class canbe con-

    sidered sufficient for the troubleshooting purpose of these mea-

    surementsand for the technical analysis reported in Section II-C.

    As for the evaluation of the power quantities described in [7] and

    discussed in Section III, more accurate data are necessary. To

    calculate such quantities, the experimental tests have been sub-

    stituted with suitable computer simulations that reproduce with

    good approximation theactual situation. In this way, thedata pro-

    cessed are not corrupted by any measurement uncertainty.

    Fig. 2 shows the acquired waveform of the current supplyingthe forge distribution center and its spectral content.

    Fig. 2. Current absorbed by the forge: (a) waveform and (b) frequency spec-trum.

    Fig. 3. Line-to-neutral voltage in the division distribution center.

    The significant distortion of the signal can be clearly ob-

    served. The relevant total harmonic distortion (THD) is about

    23%.

    Fig. 3 shows the line-to-neutral voltage waveform measured

    on the terminals of the feeder supplying the forge in the distri-

    bution center. We can observe the significant distortion arising

    fromthe highly distorted current absorbed by the nonlinear load.

    In particular, the sudden commutations occurring in the cur-

    rent cause voltage drops in the inductive impedance of the sup-

    plying network, thus leading to the noticeable voltage spikes in

    the waveform of Fig. 3. The THD of this waveform is 14%. Inorder to get a more exhaustive view over the voltage profile in

  • 7/29/2019 04039447

    3/5

    LOCCI et al.: DETRIMENTAL EFFECTS OF CAPACITORS IN DISTRIBUTION NETWORKS 313

    Fig. 4. Line-to-neutral voltage on the low-voltage terminals of the transformerTr1.

    Fig. 5. Line-to-neutral voltage on the low-voltage terminals of the transformerTr2.

    the overall plant, Fig. 4 shows the voltage waveform acquired

    directly on the low-voltage side of Tr1.

    The voltage distortion, caused by the harmonic current

    flowing into the equivalent series impedance of both trans-

    former Tr1 and supply network, is reduced with respect to the

    voltage at distribution center DC1, which was also affected by

    the voltage drop on the cable. This is confirmed by the fact that

    the THD of this waveform is 11.6%.

    Finally, Fig. 5 shows the voltage on low-voltage (LV) termi-

    nals of transformer Tr2. This waveform is even less disturbed

    than the one shown in Fig. 4, since it is not influenced by thedistorted voltage drop caused by the harmonic currents in Tr1.

    As a consequence, the voltage on the LV bars of Tr2 has a THD

    equal to 3%.

    C. Failure Report and Analysis

    In the distribution center DC1, as well as in the overall plant,

    the protection for the lighting circuits was designed following

    the usual rule of thumb. Malfunctioning and inefficiency of the

    protection plant occurred during the tests as untimely operation.

    The experimental acquisitions, along with the following consid-

    erations, allowed us to explain the situation. Each 400-W metal

    halide lamp of the lighting circuits is compensated with a 40- Fcapacitor and the combination absorbs 1.7-A rms line current

    Fig. 6. Current absorbed by the three lamps lighting circuit.

    with rated voltage 220 V. Each feeder supplies a group com-

    posed of six lamps directly from the division distribution center.

    The applied voltage is the one represented in Fig. 3.

    In order to perform the experimental survey without causingthe untimely intervention of the protection, three of the six

    lamps supplied by a single feeder where purposely bypassed.

    Fig. 6 shows the current absorbed by this reduced load. The

    rms current is 15 A, while the fundamental harmonic has an

    amplitude of 5 A. There are current peaks up to 50 A, with

    THD .

    Therefore, the actual current in the feeder with the original

    load (six lamps) is about 30 A rms, with peaks up to 100 A.

    These values should be compared to the rms current that would

    be absorbed by the same load under sinusoidal conditions,

    which is .

    One can notice that the ratio between the rms value of the dis-torted current and the nominal one

    is around three.

    Let us consider a thermal-magnetic CB, following the nor-

    malized curve C (according to [9]) for the modular CBs, with

    rated current . The same breaker in a polluted system

    works with a ratio and, therefore, in this condition,

    trips in 1 min. These considerations correspond perfectly with

    that which was experimentally observed.

    III. EVALUATION OF IEEE 1459 QUANTITIES

    A. Simulations

    The aim of this section is to closely examine the situation il-

    lustrated in Section II by evaluating a few significant parameters

    defined in the IEEE standard [7] in different realistic operating

    conditions. Therefore, different network configurations should

    be tested to compare the results. These tests were performed by

    simulating the distribution plant under examination by means of

    the PSCAD/EMTDC program, produced by Manitoba HVDC.

    As stated before, the use of simulations also allows possible

    problems arising from inadequate measurement accuracy to be

    avoided in the evaluation of the meaningful parameters.

    Nominal data from manufacturers, as well as experimental

    results, were used to obtain a realistic model of the actual

    system, so that a very good agreement exists between the ac-quired voltage and current waveforms and the simulated ones.

  • 7/29/2019 04039447

    4/5

    314 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 22, NO. 1, JANUARY 2007

    In particular, each lamp was modeled with a

    model (where , ,

    and F). The nonlinear load was modeled by means

    of an equivalent circuit consisting of a linear load shunted with

    harmonic current generators, whose values were extracted from

    the experimental waveforms.

    The IEEE Trial Use Standard 1459 provides definitions forthe measurement of electric power quantities under sinusoidal,

    nonsinusoidal, balanced, or unbalanced conditions. Besides

    the mathematical expressions that were used in the past, this

    standard defines new expressions aimed at accounting for the

    important changes that have occurred in the electric distribution

    network during the last decades. In the introductive note of

    the document, there is the claim that the new definitions

    were developed to give guidance with respect to the quantities

    that should be measured or monitored for revenue purposes,

    engineering economic decisions, and determination of major

    harmonic polluters.

    The power factor definitions used here are as follows, with

    the variables as defined in the Appendix:1) fundamental (50/60 Hz) power factor ;

    2) total power factor .

    To achieve the desired quantities, suitable signal processing has

    been performed in the LabVIEW software package. One period

    of the steady-state waveforms has been extracted from the simu-

    lations to avoid spectral leakage problems in the frequency anal-

    ysis performed by means of a discrete Fourier transform (DFT)

    [9].

    B. Results and Discussion

    As shown in Fig. 1, the network has a linear load (Lin),namely the lighting circuits, and a strongly nonlinear load

    (NLin), the forge, connected to the bus. In this specific situ-

    ation, both loads are managed by the same customer, but, for

    the purposes of this work, it is interesting to consider them as

    if they would be representative of different users supplied by

    the same bars, which could play the role of a point of common

    coupling (PCC).

    The measurement of both applied voltages and absorbed cur-

    rents has been achieved at the departure of the relevant feeders

    for each load.

    The first tests were conducted by considering only one load

    connected at a time.As for the linear lighting circuits, the two power factor defi-

    nitions lead, as was expected, to the same numerical result.

    In particular, when capacitors are not present, the inductive

    nature of the load is clearly evidenced by a low power factor

    , while the reactive compensation

    achieved with the capacitors increases this value up to 0.954

    for both indexes.

    As for the nonlinear load, it is characterized by the following

    values: and .

    These results should be compared to the ones obtained when

    both loads are supplied at the same time, which is the normal

    operating condition of the plant.

    When the forge is on, the noncompensated lighting circuitsfeature and . The similar values of

    the two quantities can be explained by the fact that the induc-

    tive lamps smooth the harmonic currents and, therefore, the har-

    monic powers have little effect on the total power quantities.

    In any case, the value is so low that the use of capacitors for

    power factor correction seems to be mandatory. However, this

    correction is valid for quantities at the fundamental frequency,

    whereas it can introduce dramatic collateral effects, dependingon the strong increase of the harmonic distortion on the network,

    as clearly shown in Section II-B. This is confirmed by the

    results: the fundamental power factor is increased again

    up to 0.954, whereas the total power factor falls down

    to 0.180.

    To complete the survey, it should be considered that on the

    forge side the effects of the reactive compensation on the lamps

    are significantly less noticeable: when the lighting circuit is not

    compensated, the forge features and ,

    while the introduction of the capacitors leads to

    and .

    The results achieved on this simple network emphasize the

    need for carefully stating the most suitable definitions to be im-plemented in measurement instruments designed to analyze the

    behavior of electric systems under nonsinusoidal conditions, es-

    pecially when such results are used to establish penalties for

    loads that contribute to the power-quality (PQ) degradation.

    IV. CONCLUSION

    This work focuses on an engineering problem related to the

    effects of the capacitors in electric power networks in the pres-

    ence of harmonic pollution. Starting from a real case in an ac-

    tual low-voltage industrial plant, the study remarks that, owing

    to the pervasiveness in the use of capacitors in such systems,

    strong nonlinear loads could have serious implications on theoperation of neighboring plants.

    In addition, by evaluating quantities purposely defined to be

    measured for either revenue purposes or determination of major

    harmonic polluters, it has been shown that customers with linear

    loads, besides suffering from malfunctioning of their plants,

    could also be penalized for the low-power factor, depending on

    the definition implemented in the utility measurement station.

    These considerations could be more complex when both linear

    and nonlinear consumers take responsibility for harmonic pollu-

    tion. In the assumption of sinusoidal conditions, the authorities

    enforce penalties to avoid the low-power factor in the network.

    Under nonsinusoidal conditions, the same penalties should be

    enforced according to parameters solidly acknowledged, whose

    recognized reliability would make the possible economical ef-

    fects acceptable from the customers point of view.

    APPENDIX

    Let us indicate the rms value of the line to neutral voltage

    as , the rms value of the line to line voltage as , the

    rms value of the line current as , and the rms value of the

    neutral current as , the fundamental positive-sequence voltage

    component as , the fundamental positive-sequence current

    component as , and the relevant phase angle as . On these

    base meanings, the standard IEEE 1459 provides the following

    definitions for power factors in three-phase nonsinusoidal andunbalanced four-wire systems.

  • 7/29/2019 04039447

    5/5

    LOCCI et al.: DETRIMENTAL EFFECTS OF CAPACITORS IN DISTRIBUTION NETWORKS 315

    1) Fundamental positive-sequence power factor

    where

    is the fundamental positive-sequence apparent power

    is the fundamental positive-sequence active power

    is the fundamental positive-sequence reactive power.

    2) Total power factor

    where is the total active power and

    is the effective apparent power.

    The rms effective current and voltage are defined as

    REFERENCES

    [1] M. Mamdouh Abdel Aziz, E. El-Din Abou El-Zahab, A. M. Ibrahim,and A. F. Zobaa, Effect of connecting shunt capacitor on nonlinearload terminals,IEEE Trans. Power Del., vol.18,no.4, pp. 14501454,Oct. 2003.

    [2] R. H. Simpson, Misapplication of powercapacitorsin distribution sys-tems with nonlinear loads-three case histories,IEEE Trans. Ind. Appl.,vol. 41, no. 1, pp. 134143, Jan./Feb. 2005.

    [3] D. Castaldo, A. Ferrero, S. Salicone, and A. Testa, An index for as-sessing the responsibility for injecting periodic disturbances, in Proc.6th Int. Workshop Power Definitions and Measurement Under Non-Si-nusoidal Conditions, Milano, Italy, Oct. 2003.

    [4] E. J. Davis, A. E. Emanuel, and D. J. Pileggi, Evaluation of single-point measurements method for harmonic pollution cost allocation,

    IEEE Trans. Power Del., vol. 15, no. 1, pp. 1418, Jan. 2000.[5] N. Locci, C. Muscas, and S. Sulis, On the measurement of power

    quality indexes for harmonic distortion in the presence of capacitors,in Proc. IEEE IMTC, Ottawa, ON, Canada, May 1719, 2005, pp.16001605.

    [6] Electromagnetic Compatibility ( EMC)Part 4: Testing and Measure-ment TechniquesSection 30: Power Quality Measurement Methods ,IEC Std. 61000-4-30, 2003.

    [7] Trial-Use Standard: Definitions for the Measurement of Electric PowerQuantities Under Sinusoidal, Nonsinusoidal, Balanced or UnbalancedConditions, IEEE Std. 1459-2000, Jan. 2000.

    [8] Electrical AccessoriesCircuit-Breakers for Overcurrent Protectionfor Household and Similar InstallationsPart 1: Circuit-Breakers fora.c. Operation, IEC 60898-1, 2003.

    [9] A. V. Oppenheim and R. W. Schafer, Digital Signal Processing. En-glewood Cliffs, NJ: Prentice-Hall, 1975.

    Nicola Locci received the Laurea degree in mechanical engineering from theUniversity of Cagliari, Cagliari, Italy, in 1974.

    Currently, he is Associate Professor of electrical measurements with the De-partment of Electrical and Electronic Engineering, University of Cagliari. Hewas Professor of communication systems and his research topics are coding,photovoltaic systems, losses measurement in power electronics, and high-fre-quency (HF) transformers, variable reluctance motor parameters measurement,

    and nonactive energy compensation. His research interests include measurementon power systems with distorted waveforms, transducers performance improve-ment, and accuracy evaluation in signal processing of data-acquisition systems.

    Carlo Muscas (M98) wasborn in Cagliari, Italy, in 1969. He received the M.S.degree in electrical engineering from the University of Cagliari, Cagliari, Italy,in 1994.

    He was Assistant Professor in the Electrical and Electronic MeasurementsGroup with the University of Cagliari from 1996 to 2001. Currently, he is Asso-

    ciate Professor of electrical and electronic measurement. His research activitymainly focuses on the study of power-quality phenomena, including the de fini-tion of electrical quantities used to characterize the behavior of power systemsunder nonsinusoidal conditions, along with the metrological qualification of therelevant measurement processes. He is author or co-author of many scientificpapers.

    Sara Sulis (S04) received the degree in electrical engineering from the Uni-versity of Cagliari, Cagliari, Italy, in 2002 and is currently pursuing the Ph.D.

    degree in industrial engineering at the University of Cagliari.Her main research activity is in the field of power-quality measurements, with

    particular attention to the definition and measurement of electrical quantities inpower systems under nonsinusoidal conditions and to the metrological qualifi-cation of the measurement processes involved.