Upload
thavaselvan
View
217
Download
0
Embed Size (px)
Citation preview
8/13/2019 06672601
1/5
Modelling and Simulation of Reverse Power Relay for
Loss of Mains Protection of Distributed Generation in
Microgrids
C. Buque1, S. Chowdhury
2, S.P. Chowdhury
3
Department of Electrical EngineeringUniversity of Cape Town
Cape Town, South Africa
[email protected], [email protected]
3
Abstract Integration of distributed generation (DG) into theutility grid has led to a renewed emphasis on looking into novel
power system control and protection issues pertaining to DG
units. This paper focuses on loss of mains (LOM) detection and
protection for DG. Commonly used methods of detection fail to
effectively detect the loss of mains scenario when the local areanetwork load and generation are closely matched. The proposed
method of detection and protection is highly efficient when the
demand and supply are similar. For this reason it can be used
together with the present methods to provide a complete
solution to LOM protection.
Index TermsReverse Power Relaying, Loss of Mains,
Distributed Generation, Point of Common Coupling.
I. INTRODUCTION
Loss of mains occurs when the microgrid, formed by the
distributed generator and local load, become disconnected to
the utility source of electrical power but remain connected topart of the utility load [1][9]. Loss of mains is less apparent in
terms of system stability when the DG is large enough to
support the utility load to which it is connected, however it
can become a big challenge to system operators if the DG
does not have enough capacity to support the utility load.
Consequences related to LOM include frequency instability
and voltage dips.
There is no industry standard method for LOM detection
and protection, various literatures present different methods
of detection ranging from active methods, passive methods
and remote techniques. In this paper a passive method
(reverse power relaying) is explored in order to provide a
single and complete solution for loss of mains protection for
microgrids. This relaying system demonstrates the benefits of
active methods including speed of operation as well as
avoiding the difficulty presented in passive methods when
establishing detection thresholds.
The developed relay is installed on the utility side of thepoint of common coupling (PCC). This enables it to detect theLOM occurrence and signal the static switch (SS), which is apower electronics device at the PCC. Once the SS is open themicrogrid can safely operate in isolated mode. In this mode
the DG has enough capacity to support the local load withminimal negative effect on voltage levels and frequencystability.
II. LOSS OF MAINS
Loss of mains can occur due to faults in the utility grid,
maintenance in the system or even circuit breaker nuisance
trip. This event may have many negative effects on the
distributed generator and microgrid.
The real challenge faced by the system operators comes in
when the microgrid has a small distributed generator. This
can cause voltage dips and system instability. As a systems
engineer it is important to determine at design stage whether
the DG is suitable to support the utility load or not. In some
areas for example, the UK, the DG is by no means allowed to
support the utility load under a loss of mains scenario [2].
This is due to the lack of the reliability of the grid when
operating with a DG as its only source and the difficulties
encountered when attempting to reconnect the system. Loss
of mains, for whatever reason it may occur is a severe
situation which design engineers must take into account,
especially in terms of system control and protection during
the occurrence.
A. Loss of Mains Detection and ProtectionOver the years there have been many detection techniques
developed, each of these have their own advantages anddisadvantages.
Local detection means that long distance communication
is not required. The detection device is located close to the
The authors are grateful to the authority of the Electrical EngineeringDepartment, University of Cape Town for providing the support and
infrastructure necessary for carrying out this research.
978-1-4799-1303-9/13/$31.00 2013 IEEE
8/13/2019 06672601
2/5
switch. There are two types of local detection methods:
Active and Passive method.
In the active method the detection device functions by
directly interacting with the system under consideration.
Perturbations are purposely injected to the system. The
systems response to the perturbations determines whether
loss of mains has occurred or not. Examples of active
techniques are [3]: Reactive power export error detection
Impedance measurement method
Slip-mode frequency shift method
Active Frequency Drift method
Automatic phase-shift methodActive methods of detection have the disadvantage of
directly affecting the system to which they are applied. If the
injected signal is not adjusted correctly it may have a
significant effect on the magnitude of the frequency of the
voltage, current and power output of the DG, it can break the
power balance between the DG and the local loads. However,
it has a significant advantage in that it is cheaper than passive
means of detection.In passive techniques there is no added signal to the
system. This technique relies on the detection of certain
distinct patterns at the DG output when islanding occurs. A
difficulty faced when dealing with passive techniques is the
proper selection of detection thresholds. This technique
depends vastly on load condition. When there are local
balanced loads LOM detection becomes difficult. Examples
of these techniques are [3]:
Rate of change of output power
Rate of change of frequency (ROCOF)
Rate of change of frequency over power
Harmonics Detection
Reverse Power RelayingLastly there are remote techniques for LOM detection.These are based on communication systems between the
utility and the DG. These are expensive to implement,
especially when small DGs are involved. Examples of remote
detection include:
Power Line carrier communications
Supervisory Control and Data Acquisition systems
When implementing Passive techniques of detection, the
DG protection against LOM is provided for by the relays
used to detect LOM. Once they detect an occurrence they
send a signal to open the appropriate Circuit Breaker (CB)
and from those pre-determined actions, the DG andMicrogrids are guaranteed protection.
When implementing remote techniques, the
communication links can be used to communicate with the
PCC or the Static Switch to disconnect the microgrid from
the utility grid when LOM occurs. The communications
systems are usually reliable enough to provide effective
signaling.
However, when active detection techniques are
implemented depending on the infrastructure, not always are
appropriate protection mechanisms activated. Detectors will
merely warn that LOM has occurred, they will not necessarily
open any breakers or disconnect the microgrid at the point of
common coupling. An effective way of making use of the
information provided by the detector is to send it to relays
located at the microgrid. Based on pre-determined settings,
the relays can activate the SS at the PCC to open and leave
the microgrid to operate in isolated mode.
When the generation and load in a network area are closelymatched, it becomes difficult to detect a loss of grid supply at
the generator [4].
III. POWER SYSTEM MODEL
The power system model, as shown in Fig. 1, consists of a
utility source with impedance representing the estimated
impedance for a utility grid of that capacity. There are two
busbars with a reverse power relay between them. Once the
relay detects an abnormality the Static Switch is opened and
the microgrid becomes isolated. A normal installation would
have different types of relays triggering the various circuit
breakers due to certain events. For the purposes of this paper
only 1 relay is used so that its capabilities can be clearlydemonstrated. The System characteristics are shown in Table
1.
Due to the configuration of the power system, the sizes of
the generators and loads, it is expected that active power will
only flow from busbar A to busbar B. If active power flows
from busbar B to busbar A it is considered abnormal.
Fig. 1. Power System Model
TABLE 1
POWER SYSTEM CHARACTERISTICSSystem Voltage (ph-ph) 132kV
Nominal Frequency 50 Hz
Utility Source Capacity 100 MVA
DG Capacity 10MVA/ 10KVA
Utility Load 100MVA
Local Load 8MVA
IV. REVERSE POWER RELAY
Reverse power protection is generally applied to preventdamage to mechanical plant items in the event of failure of
the prime mover. Common generator damage includes
gearbox damage and mechanical damage to shafts.
Power relays currently used in industry are capable of
measuring system voltage and current. They also measure the
angle between these two signals, the angle . With this
information they can calculate real power which is as shown
in Equation 1.
8/13/2019 06672601
3/5
P = V I cos (1)
Under normal operation, real power flow is in a determined
forward direction and -90 < < 90, in the case of reverse
power flow 90 < < 270. The relay allows for
unidirectional flow of active power from A to B.
V. REVERSE POWER RELAY MODELThe reverse element of the relay is the most important in
identifying an abnormal condition, therefore it is the most
important in modelling the relay. In this paper the directional
component of the relay is adopted from [6], where a similar
relay is used for generator protection.
In this model, as depicted in Fig. 2, voltage and current
signals are modified to square waves, with maximum and
minimum values of 1 and -1. When the signal is positive, the
value is 1 and when the signal is negative it is represented by
-1. The two signals are then multiplied to give an output of 1
when the signals overlap and -1 when they dont. The product
is then integrated from 0 to L. The upper limit of the
integrator is 0 so that under normal power flow conditions theintegral remains less than 0. However, under reversed power
flow conditions the integral output tends to fall until it
reaches a threshold value of L. The value of L varies
according to the allowable reverse power, the higher the
value of L, the higher the amount of reverse power. Once
there is a reverse power flow in the location where the relay
is situated the relay identifies the abnormal condition and can
immediately react to it.
A time delay component is incorporated in the relay. This
ensures that the circuit breaker only trips if a prolonged fault
or abnormal event occurs. The relays shouldnt trip for
transient power swings.
The last 4 elements in the model are used to ensure a logic0 is sent to the CB when an abnormality is detected so that
the CB can open.
A.Definition of Reverse Power LevelWhen reverse power relaying is used to protect a generator
a relay setting is chosen based on the type of generator it is.
An example of this is protection of a Diesel Engine the
allowable motoring power is 5 to 25% of the rated generation
capacity. The relay setting is chosen based on Equation 2 [8]:
ratioratio VTxCT
(MVA)CapacityGeneratingxPower(%)MotoringSetting = (2)
For Loss of mains detection the method of determining
allowable reverse power flow is different because it is not the
generator that is primarily being protected. In this case -0.01
was chosen as the lower limit because this is the lowest
integral value during normal system operation. For other
systems this value would have to be chosen based on
modelling results as it depends on the size of the generation
capacity and the system loads.
B.Definition of Trip TimeReverse power relays with either built in timers or external
timers must be used to avoid spurious isolation under
transient reversal of power, which may arise following
synchronisation or in the event of a power transmission
system disturbance. The bigger the generating capacity, the
lower the time delay should be.
For loss of mains detection the delay time will essentially
be defined by breaker reclosing times. When using high
speed auto-reclosing, it is important to know the time for
which the line must be de-energised in order to allow
complete de-ionization of the arc, so that it will not strike
when the voltage is re-applied. The de-ionization time
depends on various factors, of these factors circuit voltage isthe most important. Utility reclosers usually reclose after
0.17s for a 132kV system as shown in Table 2. For this
reason loss of mains relays must activate before the circuit
breakers attempt to reclose and reconnect the utility power
source, this is to avoid reclosing on to unsynchronised
systems.TABLE2
ARC DE-ENERGISATION TIMES FOR DIFFERENT VOLTAGE LEVELS [8]
Transmission
Line Voltage (kV)
Minimum de-
energisation time
66 0.1110 0.15132 0.17220 0.28275 0.3
The trip signal time delay has to be long enough to not trip
for transient cases but fast enough to open the circuit breaker
before the recloser activates an unsynchronised circuit to be
reconnected. It is assumed that [7], at medium level voltage
it takes a relay 2 cycles to pick up the fault and the circuit
breaker another 3 to 5 cycles to open. Therefore, in addition
to the set trip time, it takes from 5 to 7 cycles (0.1s to 0.14s in
a 50Hz system) from the time the fault occurs to the time the
fault is cleared.
Based on the preceding argument the trip time delay
should be: 0.1s < t < 0.17s. The value chosen for t in this
paper is 0.14s, which corresponds to 7 cycles in a 50Hzsystem.
Trip1
VariableTime Delay
ToSwitch1
Switch
Product Integrator
1s
If ActionSubsystem
if { }In1 Out1
If
u1if(u1 < -0.01)
else
Gain
-1
Constant6
1
Constant5
0.06
Constant4
1
Constant3
-1
Constant2
1
Constant1
-1
Constant
1
Add1V_in
2
I_in1
Fig. 2. Reverse Power Relay Matlab Model
8/13/2019 06672601
4/5
VI. TEST CASES
A. Test Case 1: Loss of Mains due to open utility switch,large DG Capacity.
In Test Case 1, CB1 is opened after 2 seconds. This
represents a scenario where there is maloperation of a switch
or nuisance tripping. It causes reverse power flow into the
utility load from the 10MVA microgrid generator. It is
important that the reverse power relay detects this scenario
because it will prevent unsynchronized reconnection of the
utility power source with the microgrid. In this case the
reverse power relay is expected to cause the static switch at
the point of common coupling to open.
B. Test Case 2: Loss of Mains due to a 3-phase Fault,withlarge DG Capacity.
3-phase faults are the most severe faults in terms of the
levels of fault current. It is important to provide a protection
system that can handle such high currents. In this case the
Utility Source is lost due to a 3-phase fault between CB1 andbusbar A. After the fault has occurred, power will flow from
the DG towards the fault. This power in the reverse direction
should be detected by the reverse power relay and the fault is
expected to be cleared by the relay and switch combination in
between busbar A and busbar B.
C. Test Case 3: Loss of Mains due to open utility switch, withSmall DG Capacity.
This case is similar to test Case 1 but here it is expected
that there will be the least active power flow which might
make it more difficult for the reverse power relay to detect
the abnormality. This test is included in order to test the
sensitivity of the reverse power relay. Again the switch CB1will be opened at 2 seconds. This case will demonstrate the
impact on the size of the DG with regards to reverse power
relaying for loss of mains.
D. Test Case 4: Loss of Mains due to a 3-phase Fault, withSmall DG Capacity.
When it comes to reverse power flow with small DG,
detection is the main issue and sensitivity of the relay model is
of paramount importance. The reverse current is so small that
it makes it difficult to detect the reverse active power. In this
case the three phase fault will cause a relatively high reverse
power flow and the relay is expected to detect it.
In all of the test cases the relay setting is the same. The
relay plays the vital role of detecting reverse active power. For
all the tests the setting is as described in Section V.
VII. RESULTS
A. Test Case 1The results for this case indicate the relay detected the
reverse power at 2 s. The SS was signalled to open at 2.14 s,
after the 0.14 s time delay, as shown in Fig. 3. This was as
expected. The reverse current was 10A which was detected
by the relay, as shown in Fig. 4. The reverse active power can
be equated using the values in Table I, Equation 1 and the
measured reverse current.
Fig. 3. Relay status during Test Case 1
Fig. 4. Power System Current During Test Case 1
B. Test Case 2The results for Test Case 2 indicate that the reverse current
was 50A as shown by Fig. 6. This current was easily detected
by the relay. The SS was opened at 2.14 s, as can be seen in
Fig. 5.
Fig. 5. Relay status during Test Case 2
Fig. 6. Power System Current during Test Case 2
C. Test Case 3The lowest active reverse power was experienced in test
case as shown in Fig. 8. For this reason the relay did not
detect the reverse active power and the SS did not open, as
suggested by the Relay Status signal in Fig. 7. This result
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
0
0.2
0.4
0.6
0.8
1
Time (s)
TripSignal
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 50
50
100
150
200
250
Time (s)
Current(A)
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
0
0.2
0.4
0.6
0.8
1
Time (s)
TripSignal
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 50
50
100
150
200
250
Time (s)
Current(A)
8/13/2019 06672601
5/5
shows that reverse power relaying is ineffective when the
installed DG capacity is small. For this reason it cannot be
used as the only means of protection for loss of mains.
Fig. 7. Relay status during Test Case 3
Fig. 8. Power System Current during Test Case 3
D. Test Case 4In Test Case 4, where loss of mains occurs because of a
fault, the reverse power flow is slightly higher than when loss
of mains occurs due to a switch opening. The reverse current
witnessed by the relay is 3A, this can be seen in Fig. 10. The
relay detected this reverse in power flow and the SS was
opened after a 0.14 s delay, as displayed in Fig. 9.
Fig. 9. Relay Status during Test Case 4
Fig. 10. Power System Current during Test Case 4
VIII. CONCLUSIONS
It can be concluded from the test cases and results that
reverse power relaying is most effective in detecting loss of
mains when the DG capacity is large. This is useful because
most methods of loss of mains protection being used at the
moment are least effective when the DG capacity is large.
This reverse active power relaying method can be used to
compliment or as back-up to more traditional loss of mains
protection methods, such as ROCOF relaying, to provide a
complete solution which will detect all of the abnormalities
and protect the microgrid from all of the harms of Loss of
Mains. This scheme is useful when other methods such asROCOF and frequency drop relays are not sensitive enough
to detect an abnormal scenario. It is also better than active
systems because it is not intrusive and better than most
passive systems because it is reliable.
REFERENCES
[1] P. O'Kane and B. Fox, "Loss of mains detection for embeddedgeneration by system impedance monitoring," in Developments in
Power System Protection, Sixth International Conference on (Conf.
Publ. No. 434), 1997, pp. 95-98.
[2] P.D. Hopewell, N. Jenkins, A.D.Cross, Loss-of-mains detection forsmall generators, IEE Proc. Electr. Power Appl., Vol. 143, No. 3,May 1996.
[3] J. Yin, L.Chang and C. Diduch, Recent Developments in Islanding
Detection for Distributed Power Generation, Power Engineering,2004. LESCOPE-04. 2004 Large Engineering systems Conference, July
2004, pp.124 128.
[4] P. Crolla, A.J. Roscoe, A Dysko and G.M. Burt, Methodology fortesting loss of mains detection algorithms for microgrids and
distributed generation using real-time power hardware-in-the-loop
based technique, 8thInternational Conference on Power Electronics ECCE Asia, May 2011.
[5] Areva,Network Protection & Automation Guide, First Edition, July2001, pp.
[6] M.M. Aman, G.B. Jasmon, Q.A. Khan, A.H.B. Abu Bakar, J.J. Jamian,Modeling and Simularion of Reverse Power Relay for Generator
Protection, 2012 IEEE International Power Engineering and
Optimization Conference (PEOCO2012),Malaysia, June 2012.[7] S.Chowdhury, S.P.Chowdhury and P.Crossley, Microgrids and Active
Distribution Networks,UK: The IET(UK), 2009.[8] ABB,ABB Switchgear Manual, 10thEdition, 2001.[9] S.Chowdhury, S.P.Chowdhury and P.Crossley. Microgrids and Active
Distribution Networks, The IET(UK), July 2009.
IX. BIOGRAPHIES
C. Buque received his BSc in Electrical Engineering in 2011 and is currentlypursuing his MSc in Electrical Engineering at the University of Cape Town,
South Africa. Email: [email protected]
S.Chowdhury is currently the Senior Lecturer in the Electrical Engineering
Department of The University of Cape Town, South Africa. She became
Member of IEEE in 2003 and Senior member of IEEE in 2011. She haspublished three books and over 150 papers in power systems modeling and
simulation, power system protection, distributed generation and renewable
energy systems. She is Member of SAIEE, Member of the IET (UK) andIE(India) and Senior Member of IEEE(USA). Email:
S.P. Chowdhury is currently Associate Professor in Electrical Engineering
Department of the University of Cape Town, South Africa. He became
Member of IEEE in 2003 and Senior Member of IEEE in 2011. He has
published three books and over 200 papers in power systems, distributed
generation and renewable energy systems. He is a Member of SAIEE, Fellow
of the IET (UK) with C.Eng. IE (India) and the IETE (India) and SeniorMember of IEEE (USA). Email: [email protected]
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5-1
-0.5
0
0.5
1
Time (s)
T
ripSignal
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 50
50
100
150
200
250
Time (s)
Current(A)
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
0
0.2
0.4
0.6
0.8
1
Time (s)
TripSignal
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 50
50
100
150
200
250
Time (s)
C
urrent(A)