41
1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

Embed Size (px)

Citation preview

Page 1: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

1

Welcome to the International Right of Way

Association’s

Course 303Managing the

Consultant Process

303-PT – Revision 3 – 01.30.08.USA

Page 2: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

2

Course Purpose

Government’s role is changing from…

staff to consultant

“doer” to manager

staff assignments to consultant contracting

…eventually, there will be a rebalancing.

Page 3: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

3

Introductions

Who we are…

What we do…

Where we do it…

How long we’ve been doing it…

Our goals for the course...

Page 4: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

4

Objectives (1) At the conclusion of the course,

you will be able to...

• Understand better the contracting process

• Avoid common mistakes and misunderstandings in proposal development

• Evaluate proposal submissions

Page 5: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

5

Objectives (2) At the conclusion of the course,

you will be able to...

• Monitor consultant work effort

• Understand better the issues and concernsof both agencies and consultants

• Engage in best practices

Page 6: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

6

Housekeeping

Page 7: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

7

Schedule (1)

8:00 - 9:00 Introductions, Etc.

9:00 - 12:00 Why and When to Use a Consultant

1:00 - 3:00 Proposal Elements

3:00 - 4:15 Consultant Proposal Evaluation

(start)

4:15 - 4:30 Recap Day One

Page 8: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

8

Schedule (2)

8:00 - 8:15 Recap Day One/Introduce Day Two

8:15 - 9:15 Consultant Proposal Evaluation (conclude)

9:15 - 10:30 Contract Execution Process

10:45 - 12:00 Consultant Monitoring (start)

1:00 - 2:00 Consultant Monitoring (conclude)

2:15 - 2:45 Invoicing and Auditing Issues

2:45 - 3:45 Process Evaluation

3:45 - 4:45 Post-Test

4:45 - 5:00 Summary and Review

Page 9: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

9

Fact or Fiction?(1)

Agency:“A consultant should only be used as a last resort.”

Consultant:“The agency only contracts out the impossible projects.”

Page 10: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

10

When to Use Consultants

• Project demands

• Staffing issues

• Political/other issues

Page 11: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

11

Wrong Reasons to Use Consultants

• Impossible timing

• No schedule

• No defined scope of work

Page 12: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

12

Agency Considerations

Will a consultant result in the best use of the agency’s staff?

Will a consultant result in the best use of the agency’s financial resources?

Does the agency have oversight capabilities?

Will a consultant affect the agency staff?

Page 13: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

13

Why Consultants arein Business

• Make money

• Offer a service and meet a need

• Provide staff flexibility

• Provide general and specialized expertise

Page 14: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

14

Contracting Methods

• Sole Source

• Special/Specific Task

• Turnkey

Page 15: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

15

Solicitation Methods

• LOI/SOI

• RFQ/SOQ

• RFP

Page 16: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

16

Developing a ProspectiveProposers’ List

• Scope of solicitation

• Solicitation methods• Established list

• Pre-qualified list

• Publication and Advertisement

Page 17: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

17

Fact or Fiction?(2)

Agency:“The scope of work can always bechanged if we overlook something.”

Consultant:“The scope of work is the most important part of the contract process.”

Page 18: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

18

Proposal Elements (1)

• Project description

• Scope of work

• Agency responsibilities

• Contractor responsibilities

• Project schedule

• Specific agency contracting requirements

Page 19: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

19

Proposal Elements (2)

• Subcontractor identificationand requirements

• Insurance

• Cost and pricing methods

• Interviews

• Evaluation criteria

• Pre-proposal meetings

Page 20: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

20

Proposal Elements (3)

• Timing issues for proposal issuance

• Proprietary information

• Appeals and protests

• Sampler contractes and forms

• Other elements

Page 21: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

21

Fact or Fiction?(3)

Agency:“The consultant will always use personnel in their proposal that look good – but they never show up on the project.”

Consultant:“The agency doesn’t read the proposal.”

Page 22: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

22

Day One Recap

Page 23: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

23

Recap Day OneIntroduce Day Two

Page 24: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

24

Case Study No. 2

Page 25: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

25

Fact or Fiction?(4)

Agency:“Starting a project without a signed contract is an acceptable process.”

Consultant:“There is so much ‘boilerplate’ in the contract that doesn’t apply to me.”

Page 26: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

26

Contracts

• Formal agreements

• Purchase orders

• Master contract with task orders

Page 27: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

27

Conflicts (1)

You have some concerns with the progress that a consultant is making and have discussed

it at progress status meetings.

A few days later, the consultant’s project manager calls and invites you to be his guest to

play golfat an exclusive local country clubto discuss the “progress issue.”

Page 28: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

28

Conflicts (2)

During the holiday season, a consultant sends you a basket of fruit,

candy and Napa Valley wine.

Page 29: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

29

Conflicts (3)

One of the consultants, with whom you do business, takes you and your staff to

lunch and picks up the tab.

Page 30: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

30

Conflicts (4)

You have a project that will eventually be contracted out. A consultant who is likely to submit a proposal

is in your office for a “cold call” visit. The consultant gives you several pens, a calendar

and a really nice traveling coffee mug. You accept the gifts and hand out the pens

to people in the office, you give the calendar to your

significant other and keep the coffee mug.

Page 31: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

31

Notice to ProceedYou ask one of your consultant appraisers to get a jump on an assignment. You believe and tell the appraiser that the notice to

proceed will be issued next week. Next week arrives with no authorization to proceed. You ask the consultant to continue

her work, which she does.

The following week, you receive a call from the project manager, who tells you that the project has been delayed

for a year and to stop all work. You are getting readyto telephone the appraiser.

What do you say?

The appraiser asks you how she will get paid for the work she has done on the appraisals.

What do you say?

Page 32: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

32

Fact or Fiction?(5)

Agency:

“We hired the best consultant available; why does he/she née so much oversight?”

Consultant:“ Why can’t we get answers to our questions/issues in a

timely manner?”

Page 33: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

33

Keys in Monitoring Projects

• Project staffing

• Reporting

• Schedule compliance

• Work product review

• Budget adherence

• Compliance

• Feedback

Page 34: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

34

Fact or Fiction?(6)

Agency:“The consultant is getting rich on this contract –

the claim for payment can wait a week or so.”

Consultant:“The proposal states that payment will be made in

30 days – it takes nearly 90 days to receive it.”

Page 35: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

35

Sixth Corollary

The sixth corollary to Murphy’s Law is:

The first invoice neverhas a chance.

Page 36: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

36

Fact or Fiction?(7)

Agency:“The consultant is only interested in moving

on to the next job.”

Consultant:“The agency doesn’t really want a critique

of its program.”

Page 37: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

37

Agency Complaints

• The consultant does the easy work…

• The consultant pulls the “bait and switch”...

• The consultant doesn’t follow up...

Page 38: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

38

Consultant Complaints

• The agency doesn’t provide the deliverables

• The agency doesn’t pay promptly

• The agency withholds forms and documents

Page 39: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

39

Objectives (1) Now, you are able to...

• Understand better the contracting process

• Avoid common mistakes and misunder- standings in proposal development

• Evaluate proposal submissions

Page 40: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

40

Objectives (2) Now, you are able to...

• Monitor consultant work effort

• Understand better the issues andconcerns of both agencies and consultants

• Engage in best practices

Page 41: 1 Welcome to the International Right of Way Association’s Course 303 Managing the Consultant Process 303-PT – Revision 3 – 01.30.08.USA

41

Thank you

303-PT – Revision 3 – 01.30.08.USA