PROGRAM : PENGEMBANGAN DESTINASI PARIWISATA
KEGIATAN : PENGEMBANGAN SARANA DAN PRASARANA PARIWISATA
PEKERJAAN : PEMBANGUNAN KONSTRUKSI KOLAM RENANG DAN TERAPI AIR PANAS
LOKASI : KOMPL. HWB PINANG AWAN, KEC. PAUH DUO KAB. SOLOK SELATAN
NO BBT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A. KOLAM RENANG 100
I PEKERJAAN PENDAHULUAN 0.947 0.947
II PEKERJAAN TANAH 0.611 0.306 0.306
III PEKERJAAN BETON 41.618 5.945 5.945 5.945 5.945 5.945 5.945 5.945
IV PEKERJAAN TRENCH PIPA 0.831 0.415 0.415
V PEKERJAAN SALURAN LIMPASAN 0.922 0.461 0.461
VI PEKERJAAN LANTAI SELASAR 1.339 0.446 0.446 0.446
VII PEKERJAAN KERAMIK LANTAI DAN GRILL BETON 12.618 2.524 2.524 2.524 2.524 2.524
VIII PEKERJAAN INSTALASI AIR BERSIH 1.159 0.290 0.290 0.290 0.290
B. BANGUNAN UTAMA
I PEKERJAAN PENDAHULUAN 0.267 0.267
II PEKERJAAN PONDASI 1.684 0.561 0.561 0.561
III PEKERJAAN BETON DAN STRUKTUR 8.608 1.230 1.230 1.230 1.230 1.230 1.230 1.230
IV PEKERJAAN DINDING DAN KUZEN 7.884 1.577 1.577 1.577 1.577 1.577
V PEKERJAAN KAP ATAP 5.833 0.833 0.833 0.833 0.833 0.833 0.833 0.833
VI PEKERJAAN PLAFOND 4.912 1.228 1.228 1.228 1.228
VII PEKERJAAN LANTAI 5.172 1.293 1.293 1.293 1.293
VIII PEKERJAAN PINTU DAN JENDELA 2.010 0.670 0.670 0.670
IX PEKERJAAN FINISHING 1.251 0.313 0.313 0.313 0.313
X PEKERJAAN INSTALASI LISTRIK 0.584 0.292 0.292
XI PEKERJAAN SANITAIR 0.874 0.437 0.437
XII PEKERJAAN RABAT KELILING BANGUNAN 0.878 0.293 0.293 0.293
0
BOBOT MINGGUAN 100.00 1.253 6.251 5.945 5.945 6.361 7.650 8.644 10.706 5.776 6.453 6.453 7.681 5.827 4.024 4.024 2.439 1.606 0.605 1.041 0.729 0.293 0.293
BOBOT KOMULATIF 0 1.253 7.504 13.450 19.395 25.756 33.406 42.050 52.756 58.533 64.986 71.439 79.120 84.947 88.971 92.995 95.434 97.039 97.644 98.685 99.415 99.707 100.000
BOBOT MINGGUAN
BOBOT KOMULATIF
Waktu Pelaksanaan Pekerjaan Selama 150 (Seratus Lima Puluh) Hari Kalender
Batusangkar, 28 Juni 2013
Penawar
CV. INDOMO RAJA SAKTI
ttd
Ir. FERRY ERIANDY
Wakil Direktur
RENCANA
REALISASI
DEVIASI LAMBAT/CEPAT ( +/- )
50
TIME SCHEDULE DILENGKAPI KURVA S DAN BOBOT
WAKTU PELAKSANAAN PEKERJAAN
URAIAN PEKERJAAN MINGGU KE - KET
SCHEDULE