COMMERCIAL AMENDMENT NO. A307/1022/CA-01
Page 1 of 3
COMMERCIAL AMENDMENT NO. A307/1022/CA-01
TO
BIDDING DOCUMENT NO.: SM/A307-IUE-PC-TN-8005/1022
EFFLUENT TREATMENT PLANT FOR INTEGRATED REFINERY EXPANSION PROJECT (IREP)OF M/s BPCL-KOCHI REFINERY, KOCHI, KERALA, INDIA
8/12/2019 A307_T-1022_8005_CA_1
2/3
COMMERCIAL AMENDMENT NO. A307/1022/CA-01
Page 2 of 3
SUBJECT: EFFLUENT TREATMENT PLANT FOR INTEGRATED REFINERY EXPANSION PROJECT (IREP) OF M/s BPCL-KOCHIREFINERY, KOCHI, KERALA, INDIA
BIDDING DOCUMENT NO.: SM/A307-IUE-PC-TN-8005/1022The terms, conditions and specifications of Bidding Document stand modified to the extent indicat ed under column MODIFICATIONS/ ADDITIONS/ DELETIONS.All other terms & conditions, stipulations, specifications etc. of Bidding Document issued earlier shall remain unaltered:
Sl.No.
Section(Document)
PageNo.
Clause /
Item No.Subject Modifications/Additions/Deletions
1. Notice InvitingTender
(NIT)
18 of2877
5.5.1 ExperienceCriteria-Technical
The Sign / appearing in 3rd
line of Clause 5.1.1 of NIT stands replaced by wordor.
2. Instructions toBidders
(ITB)
32 of2877
3.3.3 (xxiii)
(new)
Documentcomprising the bid
The following is added as Sub- clause 3.3.3 (xxiii):
MOU with Backup Consultant, if applicable shall be valid up to Defect Liability Period or up toDecember 2017, whichever occurs later.
3. Instructions toBidders
36 of2877
6.5.2(iii) Service Tax The clause 6.5.2 (iii) of ITB stands replaced by following :
Loading of 100% of Service Tax amount as quoted by the Bidder in Form SP -8.
4. Proposal Forms 56 of2877
Format- B(Page 1 of 2) -
The Word Annexure- D appearing in 1st line of Instructions: 3) of Format- B(page 1 of 2)
stands replaced by words Format-B
5. SpecialConditions of
Contract
(SCC)
149 of2877
9.2.7 Service Tax The 4th para of clause no. 9.2.7 stands replaced by following:
Cenvat credit against Service Tax is not available to OWNER. Hence loading of 100% of totalService Tax amount shall be considered for Price evaluation.
6. SpecialConditions of
Contract
181 of2877
73.0 Compensation forDelay
Following is added at the end of clause no. 73.0
Compensation for delay is applicable for delay in Mechanical Completion including precommissioning of Effluent Treatment Plant as per scope defined in the Bidding Document.
7. ` Annexure-IV toSCC
190 of2877
3.0 On AccountPayments
The following Para is added to Clause 3.0:
Payment shall be released by Owner within 30 days of receipt of Contractors monthlyRunning Account Bill/Invoice duly certified by Engineer-In-Charge.
8/12/2019 A307_T-1022_8005_CA_1
3/3
COMMERCIAL AMENDMENT NO. A307/1022/CA-01
Page 3 of 3
Sl.No.
Section(Document)
PageNo.
Clause /
Item No.Subject Modifications/Additions/Deletions
8. FORM SP-5 436, 437of 2877
Break-Up ofLumpsum Price for
Supply Portion
Read unit as LS against Sl. No. 1B. 1 (i) & (v)
9. FORM SP-6 439, 440& 441 of
2877
Break-Up of Lumpsum Price forConstruction/Installation Portion
a) Read unit as LS against Sl. No. 1C.1.1 (a), (c), (d), (e) and 1C.2.1 (a), (c)
b) Unit written as LS against Sl. No. 1C.2.1 stands deleted.
10. FORM SP8 443 of2877
Details ofCenvatable/Vatable Taxes &Duties
The words Service Tax at Sl. No. 5 is with respect to the FORM SP-7appearing in last line ofNotes: 1 stands deleted.
11. Schedule of
Rates
444 of
2877
5-b of FORM
SP-8
Service Tax The entire notes 5-b of Form SP-8 stands replaced by following :
Owner is not able to avail Cenvat credit on Service Tax. Hence, 100% of Service Tax amountindicated against Sl. No. 4 in Column (C) shall be loaded for Price evaluation. However, FullService tax shall be paid by Owner to Contractor subject to compliance with Clause No. 9.2.7of SCC.
Note:Please submit one copy of this Amendment along with enclosures, if any, duly signed & stamped along with Un-Priced Techno-Commercial Bid.