Upload
lehuong
View
214
Download
1
Embed Size (px)
Citation preview
Title
© ABB Group November 5, 2012 | Slide 1
Ageing Assets - Managing Risk Rotating Machinery
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
Agenda
Introduction to ABB Consultancy
Why manage ageing assets?
UK Regulation and General Principles
Managing Risk of Ageing
Machines Failures
Electrical Motor Reliability
Obsolescence
People, Competence and Knowledge
Examples of Good Practice
Conclusions
© ABB Group November 5, 2012 | Slide 2
Title
© ABB Group November 5, 2012 | Slide 3
Background to ABB Consulting
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
ABB Group
130,000 employees in about 100 countries
$38 billion in revenue (2011)
Formed in 1988 merger of Swiss and Swedish engineering
companies - Asea and Brown Boveri
Predecessors founded in 1883 and 1891
Publicly owned company with head office in Switzerland
ABB Consulting Locations and Selected Clients
Title
© ABB Group November 5, 2012 | Slide 6
Why manage Ageing Assets?
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
Why do you need an Asset Life Strategy?
© ABB Group November 5, 2012 | Slide 7
Asset Life
Strategy and
Planning
Financial
Planning &
Budgets No
Surprises
Stakeholder
Governance
Reputation
Licence to
Operate
Due
Diligence &
Investment
Buying?
Selling?
Regulatory
Compliance
Compliance
with Law
Self
Regulation
Title
© ABB Group November 5, 2012 | Slide 8
Managing Ageing Assets UK Regulation and General Principles
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
Ageing – UK HSE definitions
“Ageing is not about how old the equipment is. It’s
about what is known about its condition, and how
that’s changing over time”
HSE Research Report RR509 - ‘The plant ageing
guide’
“Ageing is…where a component suffers deterioration
and damage (usually, but not necessarily, associated
with time in service) with an increasing likelihood of
failure….
HSE Research Report RR823 – ‘Plant Ageing Study’
© ABB Group November 5, 2012 | Slide 9 UK Health and Safety Executive
OSHA CFR 1910.119 (Process Safety Management)
Quotes from standard
An effective process safety management program requires a
systematic approach to evaluating the whole process
Operators need to develop the necessary expertise,
experiences, judgment and proactive initiative within their
workforce to properly implement and maintain an effective
process safety management program
Operators need to ensure that the design and construction along
with the testing, inspection and operation are still suitable for
the intended use. Where the process technology requires a
design which departs from the applicable codes and standards,
the employer must document that the design and construction is
suitable for the intended purpose.
© ABB Group November 5, 2012 | Slide 10
What reduces asset life?
© ABB Group November 5, 2012 | Slide 11
No. of Failures/
Accumulated
Damage
Time
Initial
Operation
Mature
Stage
Ageing
Stage
End of Life
Stage
Examples of factors that reduce asset life
Poor design quality
Poor standards
of installation
Poor control of
modifications
Operating outside
design limits
Obsolescence
Failure to manage
deterioration of
equipment and systems
Solving these problems is reactive!
Locations reflect
the impact, not
when initiated.
What extends asset life?
© ABB Group November 5, 2012 | Slide 12
No. of Failures/
Accumulated
Damage
Time
Initial
Operation
Mature
Stage
Ageing
Stage
End of Life
Stage
Examples of Factors that extend asset life
Maintenance
to quality
standards &
practices
Effective testing
& inspection of
equipment Quality of spare
parts & repairs
Correct control of
operating
parameters
Managing Deterioration
of Equipment &
Systems
Locations reflect
the impact, not
when initiated.
© ABB Group November 5, 2012 | Slide 13
UK Health and Safety Executive Key Performance Programmes
Key Programme 1 (KP1) - Run 2000 to 2001
Investigated all reported offshore hydrocarbon releases and analyzed the size, type and causes of the releases to identify ways of reducing the number of releases
Key Programme 2 (KP2) - Initiated in 2003
Addressing the unacceptable accident statistics from deck and drilling operations.
Key Programme 3 (KP3) - Run from 2004 to 2007
Focused on current standards of Asset Integrity defined as the ability of an asset to perform its required function effectively and efficiently while protecting health, safety and the environment
Key Programme 4 (KP4) – launched in July 2010
To determine the extent to which asset integrity risks associated with ageing & life extension are being managed effectively by duty holders
© ABB Group November 5, 2012 | Slide 14
Management
Reporting & Auditing
KPI’s Leading & Lagging
Indicators
Learning form Incidents &
Near Misses
Incident Investigation &
action tracking
Asset Performance
Monitoring
Defect Reporting System
Audit programme
Equipment Ageing
Assessment
Asset Integrity Management
Plan to identify critical plant
Risk assessment
Hazard Identification versus
Ageing
Technical Safety Review –
Critical equip
Justification for continued use,
obsolescence
Replacement Policy for
CRITICAL plant
Inspection – ageing
mechanisms
Focussed Inspection, RBI, RCM,
FMEA, etc
Corrective action plan and
tracking
Organisational &
Competence
Organisational Structure &
Responsibility
Communication –
internal/external
Regular reviews
Continuity Plans
Impact on organisation and
Human Factors
Contract 3rd party standard
setting
Competency In-house,
contractor
Organisational responsibility
for MOC.
Procedures /
Systems
Asset Integrity Management
Policy
Asset Register and actions at
correct intervals
Design Standards / Code of
Practice updates
Maintenance & Inspection
Systems interfacing with
Operations
Operational Procedures &
Maintenance Management
Interfaces
Operational Inspections
Management of Change (MOC)
ABB Ageing Plant Safety Management & Risk Control Summary
COMAH - Ageing Plant
Operational Delivery Guide
© ABB Group November 5, 2012 | Slide 15
UK HSE Managing Ageing Assets People, Systems and Organisation
UK Health and Safety Executive
Organisations
Demonstration that the organisation
is aware of ageing challenges at all
levels, incl. senior management
Demonstration that workforce has
adequate experience, competence
and training to manage ageing
issues
Definition of key responsibilities,
management structure,
communications and resources
Highlight of management measures
that differentiate life extension from
day-to to-day problem shooting
HSE KP4 Launch Ardoe House Aberdeen 28th July 2010
‘Successful Health and Safety Management’ HS(G)65
© ABB Group November 5, 2012 | Slide 16
Ageing Assets require an Integrated Approach
Co
nstru
ctio
n
Insp
ecti
on
Emergency
Response &
Preparedness
Process
Safety/
Integrity
Leadership
& Culture
Process
Hazard
Analysis &
Review
Operating
Procedures
& Practices
Pre Start-up
Safety
Management
of Change
Safe
Systems of
Work
Process
Safety
Indicators &
Information
Audit &
Review of
Integrity &
Compliance
Management
of
Contractors
Employee
Training &
Competence
Assurance
Incident
Investigation
Plant &
Equipment
Integrity
Effective
Systems
World
Class
Leadership
of Safety &
Integrity
© ABB Group November 5, 2012 | Slide 17
Topsides Asset Life Issues for an Offshore Installation Key items found during ABB Studies It’s the same Onshore as Offshore
Equipment projected as not fit for purpose
Increased congestion of equipment and removal of redundant equipment
Replacement of obsolete equipment
Operation outside original design or lack of turn down capacity
Reducing equipment and key system reliability
Need to upgrade Safety, Escape and Fire to meet latest standards
Newly emerging deterioration mechanisms, i.e.changes in process fluids, e.g. sand, H2S
Integrity of minor structures (handrails, walkways, ladders)
Integrity of utility systems (air, nitrogen, HVAC, cooling water etc.)
Electrical power limitations affecting current and future operations
Competencies as against ageing workforce retires
Leaner organisations with increased reliance on sub-contractors
Lack of clarity for ownership of knowledge between operator and sub-contractors
Loss of ‘Corporate Knowledge’ and ‘unfriendly’ documentation systems
Compliance with current and future environmental legislation
Dep
en
dab
le A
ssets
People
Systems
Title
© ABB Group November 5, 2012 | Slide 18
Managing Risk Machine Failures
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
Different Types of Equipment Different Ways of Managing Risk
© ABB Group November 5, 2012 | Slide 19
HIGH HAZARD, PRESSURE
CONTAINING EQUIPMENT
High Consequences
Low Likelihood
Fewer, but complex failure modes.
DETERIORATION MECHANISM LED
APPROACH
Risk Management by managing
deterioration (operations or
environment) and pre-failure detection
by inspection and monitoring (Focussed
Scheme of Examination)
Complex nature of most deterioration
mechanisms dictates bespoke solutions
OTHER EQUIPMENT ON HIGH HAZARD
DUTIES
Lower Consequences
Higher Likelihood
Wide range of complex failure modes.
FAILURE MECHANISM LED APPROACH
Risk Management by preventing failures
(quality control and operations) and pre-
failure detection by inspection,
performance and condition monitoring
(Maintenance Policy)
Risk from most failures can be managed
generically by following good practice
Age Related Failures of Rotating Machines Emerging Risks
Fatigue
Stress and Cyclical Load
Creep
Stress and Temperature
Corrosion
Mechanism and Materials
Potential Areas
Nozzles
Couplings
Rotor Blades
etc., etc.
© ABB Group November 5, 2012 | Slide 20
Compressors Failures due to Ageing
© ABB Group November 5, 2012 | Slide 21
Examples of Actions Failures Due to Ageing
© ABB Group November 5, 2012 | Slide 22
Scenario that requires no further action
Rotor blade failure – If failed would not breach containment, shutdown on
vibration trip. Protection system must be proven to have sufficient and
suitable integrity before disregarding the scenario.
Scenario that requires further action
Coupling failure – Potential failure mode fatigue. On failure could eject
debris causing secondary damage/personal injury. Investigate design,
operational history, maintenance/inspection history, etc. If failure credible
identify mitigation i.e. specific targeted inspection / change out policy.
Understanding how the equipment has been operated and maintained in the
past will be key to allowing it to operate into the future
Generally, understanding the cause rather than the effect is key
Bad misalignment leads to high nozzle stresses which ultimately leads to
fatigue failure. Bad misalignment could come from base plate corrosion.
Applying a Risk Matrix – Policy Decisions
LIKELIHOOD
C
O
N
S
E
Q
U
E
N
C
E
S 1
2
3
4
5
1 2 3 4 5
COMPRESSOR
FAILS AND
ROTOR
DESTROYED
Scales from
assessments using
word models,
categories and
similar quantified
assessments
BUY SPARE
ROTOR
COMPRESSOR
FAILS AND
ROTOR
DESTROYED
Business Risk
Both
INSTALL SIL 2
PROTECTION
COMPRESSOR
FAILS WITH
MINIMUM
DAMAGE
Safety Risk
Title
© ABB Group November 5, 2012 | Slide 24
Managing Risk from Ageing Electrical Motors
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
Motor Reliability
MOTORS FAILURES
POWER > 0.5 MW
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Bearings Stator Faults Rotor Faults Others
% F
AIL
UR
ES
Offshore Onshore
Failure Data from
Condition Monitoring Methods, Failure Analysis for High Voltage Motors in Petrochemical Industry - OV Thorsen & M Dalva - IEE 1997
A Survey of Faults on Induction Motors in Offshore Oil Industry, Petrochemical Industry, Gas Terminals and Oil Refineries - OV Thorsen & M Dalva - IEE 1995
Failure Impact = Failure Rate x Time to Repair
Minimum Impact assumes spares
Maximum Impact assumes no spares
Electric Motors - Impact of Failure
FAILURE IMPACT
MOTORS > 0.5 MW
0.00
0.05
0.10
0.15
0.20
0.25
0.30
Bearings Stator Faults Rotor Faults
FA
ILU
RE
IM
PA
CT
MINIMUM IMPACT MAXIMUM IMPACT
ALL FAILURES - EXCLUDING OTHERS
MOTORS > 0.5 MW
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Bearings Stator Faults Rotor Faults
% F
AIL
UR
ES
Failure Data from
Condition Monitoring Methods, Failure Analysis for High Voltage Motors in Petrochemical Industry - OV Thorsen & M Dalva - IEE 1997
A Survey of Faults on Induction Motors in Offshore Oil Industry, Petrochemical Industry, Gas Terminals and Oil Refineries - OV Thorsen & M Dalva - EE 1195
Title
© ABB Group November 5, 2012 | Slide 27
Managing Risk Obsolescence
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
Obsolescence
Mainly affects:
Rotating equipment
Electrical equipment - i.e. switchgear
Instrumentation
Control systems and software
© ABB Group November 5, 2012 | Slide 28
25 years old, but the design dates
from the early 1970s.
Obsolescence – do we really need to replace ?
How reliable is the equipment and is it getting less
reliable as time passes ?
What are failures costing in terms of lost production
and is this likely to get worse ?
Can the equipment be readily maintained ?
Are replacement parts and assemblies readily
available or are they easily reverse engineered ?
Are there companies supporting the aftermarket with
spares and overhaul capability ?
© ABB Group November 5, 2012 | Slide 29
$$$ Operating v $$$ Replacement
Title
© ABB Group November 5, 2012 | Slide 30
Managing Risk for Ageing Assets People, Competence and Knowledge
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
An Integrated Approach Some Big Issues that don’t appear in CAPEX
People and Competency
Knowledge Management
Use of 3rd Parties
© ABB Group November 5, 2012 | Slide 31
Age and competency of the workforce
Age profile - loss of highly experienced personnel.
Succession planning and knowledge retention for key
operating and maintenance roles.
Application of new technologies - investment in digital
infrastructure
Telemetry + high speed fibre optic links
Remote control of equipment and processes -
integrated control rooms.
Fewer persons + different competencies, de-manning &
relocation onshore, changes in working methods.
© ABB Group November 5, 2012 | Slide 32
More effective operation & reduction in operating costs.
Quality of historical records
Retaining corporate knowledge for the
extended life cycle.
30 year old information and data
needs to be kept for a further 30 +
years.
Incompatible and incomplete records
with significant gaps.
Moving to software based document
management systems.
Loss of data when systems are
changed.
No longer able to read electronic data
in old formats.
© ABB Group November 5, 2012 | Slide 33
A detailed understanding of what information needs
to be retained + a plan to assemble & maintain it.
Dependence upon 3rd Parties
Dependence upon on 3rd Parties seems
to be increasing
New operators - leaner organisations.
On-going operation increasingly
dependent upon sharing of information
with and between third parties.
Agreement on:
ownership of knowledge, records and
maintenance histories.
extends beyond the duration of the
contract.
© ABB Group November 5, 2012 | Slide 34
Title
© ABB Group November 5, 2012 | Slide 35
Some Examples of GoodPractice Managing Risks from Ageing
Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
© ABB Group November 5, 2012 | Slide 36
Core Best Practice Effective Management, Investment Profiles & Actions
Rotating Equipment Some Hidden Risks from Ageing
Key ‘Hidden’ Threats
Erosion and Corrosion
Operational Excursions – Pressure and Temperature
Fatigue
Creep
Understand the Risks and Manage/Mitigate them
Adopt modern standards for machine protection, monitoring and
control
‘Risk Based Inspection’ studies often deliver a more pragmatic
approach than FMEA or similar when looking at ageing issues.
Is the main driver safety or reliability or both?
The regulator can be harder to please than other
stakeholders.
© ABB Group November 5, 2012 | Slide 37
Rotating Equipment Good Practice for Ageing Assets
Look at the system – machine, ancillaries, such as lubrication or
seal support systems, surge protection etc. Are they all to current
best practice?
Vibration and Axial Position Alarms and Trips
Control of Operation Conditions – keep within design envelope
and record excursions – analyse past history, if you have it!
Beware of changes to the Process Fluids, past present and future
Fatigue and Creep relate to temperature and stress
Understand historical stresses and temperatures, if you can,
if not control the future!
Identify high stress or temperature areas and deterioration
mechanisms - Risk Based Inspection
Make sure that they are within limits now and will continue to
be so
Machine train alignment, Machine Nozzle Loads and
Pipework Supports
© ABB Group November 5, 2012 | Slide 38
Title
© ABB Group November 5, 2012 | Slide 39
Conclusion Brian G Hudson – ABB Consulting – OPERA– London October 30th 2012
Conclusions
Managing Ageing Assets
Its not just about Equipment and CAPEX
Its also about People, Organisation and Systems
Rotating Equipment
Its about understanding the risk and mitigating it.
Operations and Maintenance, now and in the past are critical
Electrical , Control and Instrumentation
Its about understanding what’s obsolete
But also is it cheaper to carry on maintaining it
© ABB Group November 5, 2012 | Slide 40
“The lucky man
is the one
who knows how much
to leave to chance.”
CS Forrester
“The Happy Return”
Risk Management
© ABB Group November 5, 2012 | Slide 42
Brian G Hudson
Principal Lead Consultant
ABB Consulting UK
Phone: +44 1642 372131
Mobile: +44 7711 771307
email: [email protected]