chap1-el

  • Upload
    rk

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

  • 8/9/2019 chap1-el

    1/5

    SECTION 1

    INTRODUCTION

    1.1 The sub transmission and distribution constitutes the final link between

    the utility and consumer and the utility is judged by the consumers on the

    performance of this segment of power utility. The funds required for system

    improvement schemes for primary distribution sector is so large that the

    present level of funding is grossly inadequate. Inadequacy of funds is

    contributing towards time and cost overrun of the sub -transmission and

    distribution projects resulting in lack of capacity addition in sub

    transmission and distribution network. Therefore, timely completion of

    schemes pertaining to sub transmission and distribution works within the

    budgeted cost is of vital importance as it directly reflects on the performance

    of the utility and revenue realisation from the ultimate customer.

    1.2 Monitoring is a continuous process to ensure timely implementation

    without time and cost overrun and in O & M stage covering performance

    (technical) and consumer satisfaction issues. The systematic approach to

    project monitoring and evaluation through computer based monitoring and

    information system will curtail avoidable delays which are taking place

    today in sub transmission and distribution project even after investment

    decision is done timely.

    1.3 In planning new sub-transmission and distribution system ,land

    encumbrances ,environmental interfaces and visual impact are features,

    which are receiving increasing importance. It is not only the planning cost

    but cost of construction is also to be minimised which rises due to delay in

    construction. Apart from compensation to be paid ,the very process of

    acquiring land is time consuming. The coordination with telecommunication

  • 8/9/2019 chap1-el

    2/5

  • 8/9/2019 chap1-el

    3/5

    Litigation

    1.6 Most of these can be minimised by organising and controlling post

    investment decision activities through adoption of meticulous monitoring

    techniques such as Bar Chart Method, Critical Path Method (CPM),or

    Programme Evaluation and Review Technique (PERT).The preference is

    given to adoption to Bar Chart Method due to its simplicity. The PERT is

    suitable to R & D projects.

    1.7 Monitoring is a control function. The objective is realised through the

    managerial techniques of Planning & Control. They are inter-

    dependent functions, for the one looses its significance without the other.1.8 The primary work arising under the planning elements is the

    determination of construction/implementation programme for the year

    and laying down the general principles on the basis of which it will

    operate. These general principles basically involves availability of the

    finances, land and various clearances to undertake construction work etc.

    Once the construction programme for the year is decided and distributed

    properly into the four quarters of the year, the control function comes

    into play.

    1.9 The control function is generally exercised by comparison of actual

    results with pre-determined programme or targets and taking corrective

    measures where deviation occurs.

    1.10 The basic objective of strengthening and improvement of sub

    transmission and distribution system is to ensure quality and reliability of

    supply to consumers, bring down technical losses to an optimal minimum

    value and phasing the system expansion to match the growing demand in

    the area.

  • 8/9/2019 chap1-el

    4/5

    1.11 The evaluation of a sub-Transmission and Distribution system can be

    done in terms of, reduction of T & D losses, reduction in overloading of

    feeders and transformers ,degree of improvement in the voltage profile

    vis--vis voltage regulation, reduction in number of trippings of

    distribution system due to overloading ,reduction in consumer

    interruption ,reduction in cost per consumer, increase in revenue,

    enhancement in peak demand, energy supplied,enhancement in number

    of consumer supplied, improvement in level of service, assessing cost of

    input energy to total sales and total collection etc. The computation of T

    & D losses in the real system is very difficult and accuracy of the

    computation and quantification depend on number of factors such as,

    accuracy of meters, type of billing system , thefts and tampering of

    meters, metering and billing supply interruptions, consumer complaint

    redressal etc.

    1.12 This documents provides guidelines for issues to be looked into in

    awarding contracts, implementation activities, monitoring of sub-

    transmission and distribution projects for timely completion, performance

    evaluation and O&M of the equipment.

    1.13 The performance evaluation of the new system needs comparison of

    performance after adding the new system with system prior to network

    elements added in the existing system. A data acquisition system is

    required for such evaluation due to large number of inputs.

    1.14 A computer based software is also required for project monitoring and

    reliability analysis.

    1.15 Another area in which no work has been done so far by any of the

    utility is Renovation and Modernisation (R & M ) and life assessment

    studies of the sub transmission and distribution equipment. This can

  • 8/9/2019 chap1-el

    5/5

    enhance the life to few more years if predictive maintenance in the form

    of R & M supported by residual life assessment studies, is done at proper

    time.