Caterpillar Confidential Yellow
Optimizing Your Product Support
Solution
Caterpillar Confidential Yellow
Running the Power Station:
… costs, costs, costs
• Mobilization costs
• General Liability Insurance
• Machinery Breakdown Insurance
• Staff labor – Operations
– Maintenance
– Contracted & Plant security
– Administrative
– Training cost
– Vehicles
• Shop equipment & offices, – Hand tools cost
– Shop consumables
– Office supplies & communications cost
– Sewer and telephone connections
– Fuel, water or other consumables
– Non-hazardous waste disposal
– Equipment & Software
• Scheduled & Unscheduled Engine & Auxiliary Parts
• Strategic Spare Parts Inventory Cost – Unscheduled Repair Reserve
– On-Site Warehouse. Parts administration
• Emergency & Maint. Electrical Connections
• Building & Grounds Maintenance Cost
• Legal, HR & Accounting Services – Hiring/screening
– Payroll services
• Operating Licenses, Permits or Approvals – Facility Taxes and Fees Imposed or
Assessed
– Tariff and Import expenses
Caterpillar Confidential Yellow
Availability
Caterpillar Confidential Yellow
Factors Ensuring Equipment Up-time
Customer value equation
Cost / kW-hr (optimize)
Cost / Hour (minimize)
kW/ Hour (maximize)
REBUILD COSTS COMPONENT LIVES PRODUCT AVAILABILITY
% After failure
Repairs
Parts Reuse
Parts Salvage
Design
Application
Maintenance
Repair Quality
• MTBS
• MTTR
• Availability Index
• % Scheduled Down time
• Maintenance Ratio Labor Efficiency
Application
• Ambient condition
• Load factor
• Transient requirements
Operation
• Load management
• Peak shaving
• Ancillary equipment operations
MTBS – mean time between service
MTTR – mean time to repair
Caterpillar Confidential Yellow
Understanding the Customer
• Do it myself – Dealer provides parts and customer does all of the work.
– Dedicated PSSR meeting customer needs.
– Great parts opportunity but not really showing the value.
• Do it for me – Dealer technician develops relationship and provides 100% support.
Build a partnership with customer.
– Value driven opportunity but higher cost to customer.
– Great opportunity to negotiate “pay for performance”.
• Do it with me – Customer does the basics, dealer does the heavy lifting.
Caterpillar Confidential Yellow
Life Cycle Costs
“LCC”
Caterpillar Confidential Yellow
Life Cycle Cost – Principles
• LCC is the total cost of ownership of machinery and equipment,
including its cost of acquisition, operation, maintenance, conversion,
and/or decommission (International Electrotechnical Commission, IEC
60300-3-3).
• The primary objective of life cycle costing is to provide input to decision
making in any or all phases of a product’s life cycle.
• Simplified LCC analysis summarizes results in net present value (NPV)
format considering depreciation, taxes and the time value of money.
• ISO/IEC 15288:2008-System Life Cycle Processes establishes a
common framework for describing the life cycle of systems created by
humans.
Caterpillar Confidential Yellow
Inputs That Impact a LCC
Numerous inputs go into a Life Cycle Cost Analysis.
Fuel cost Electricity Price Wages
Fuel quality
Peak Hours
CSA Pricing Resale Value
Oil Cost Site Ambient
Labor Hours
Genset Price Heat Price
Interest Rate
Capacity - = Net Profit Energy
Value x Operating
Cost - Total
Owning
Cost
Availability x
Caterpillar Confidential Yellow
The CSA Teamwork Strategy Customer Service Agreements Are a Team Effort.
CSA Strategy
Caterpillar Confidential Yellow
• Contract Factors • Availability guarantees
• Redundancy
• Staffing levels
• Commercial • Margin & liquidated damages
• Contract term
• Customer / service provider financial stability
• Contract scope
• External • Ambient conditions
• Air & fuel quality
• Site access
• Environmental compliance
• Parts logistics & customs clearing
• Statutory restrictions & overall industry financial health
• Equipment • Product reliability
• BOP complexity
• Plant engineering & construction quality
• Critical spares & on-site tools
• Plant condition
• Operations • Application
• Redundancy
• Operating regime • Load duty
• Run hours
• Number of starts
• Service provider • Operation expertise
• Field response capability
Risk is Neither Created Nor Destroyed,
… Only Transferred. First Law of Customer Support Agreements
Caterpillar Confidential Yellow
Operating Costs … typically expressed in cents/ekW-hr or $/hr
For Power generating equipment:
• Fuel • Fuel consumption is the major portion of non-standby O&O costs for power
applications, whereas capital cost is the primary concern for backup generators.
• Fluids
• Oil, coolants, fluids analysis program.
• Scheduled preventive maintenance • Filters
• Parts
• Scheduled engine/systems overhauls • Top-end,
• In-Frame,
• Major
• Unscheduled repairs and overhauls
Caterpillar Confidential Yellow
Operating Costs – Prime Application
Fuel
Fluids
PM
Components
Overhauls
Fuel: 0,5 $/liter
2,3%
2,2% 1,1%
3,1%
91,3%
Having Fuel cost a main factors, makes Performance and Efficiency factors a dominant decision
driver!
Caterpillar Confidential Yellow
Fuel Quality
Caterpillar Confidential Yellow
Fuel Quality Impact on Engine M&R Costs
High Contaminant= 7k, 21k, 35k Hours
Low Contaminant= 18k, 54k, 90k Hours
Contaminants : Ammonia, Halides, Siloxanes, Hydrogen Sulfide
Cost / kWh
Assumed Overhaul Schedule (Top End, In Frame, Major)
Caterpillar Confidential Yellow
Fuel Contaminants & Bottom Line
G3520C 1600kW Genset
Caterpillar Confidential Yellow
Managing the Risk of the LCC
Caterpillar Confidential Yellow
B(x) life is the measure of time in
which (x)% of component population
will have failed.
• B10 Life - “No Fail Scenario”
– Cat Brand Standard (O&M), use for
low risk scenarios
• B50 Life - “Average Case”
– Industry Standard, use for any
competitive scenario
Operating Cost – B(x) Life Expectance
0
10
20
30
40
50
60
A
B
Line A = B10 Life
Line B = B50 Life
Operating Hours
Caterpillar Confidential Yellow
Preventative Maintenance (PM) Tasks
• The specific maintenance tasks are established based on manufacturer
recommendation (O&O manual), along with dealer experience.
• Each Maintenance Task has 3 major Cost Components
– Parts : ~80% of the cost, represents the parts being replaced in the service task
– Labor : ~15% of the cost, represents the time and labor cost to execute the service
– Travel : ~5% of the cost, represents travel costs to get tech to site
• Managing the frequency of these tasks is critical to minimizing your PM
Costs. Consider:
– Fuel Type
– Application
– Site Conditions
– Component life expectancy approach (B10 vs. B50)
Caterpillar Confidential Yellow
Repair Risk Management
• Scheduled repairs per service manual intervals
• Predictive repair scheduling – Use valve recession, oil consumption, other indicators
• LEXE0681-00 – Natural Gas Engines
• LEXE0682-00 - Landfill Gas Engines
Cat G3520C HV Low Energy Gas @ 1613 kW, 1200rpm
Cat G3520C HV Low Energy Gas @ 1613 kW, 1200rpm
Cost $289,416.97 $246,443.11
Revenue $1,338,064.96 $1,343,508.03
Profit $1,048,647.99 $1,097,064.92
$0.00
$200,000.00
$400,000.00
$600,000.00
$800,000.00
$1,000,000.00
$1,200,000.00
$1,400,000.00
$1,600,000.00
Pe
r Y
ea
r
Average Cost / Revenue Comparison
Cost
Revenue
Profit
Overhauls by Prediction Overhauls by Schedule
Caterpillar Confidential Yellow
Operating Cost – Overhauls
• Overhauls represent significant preventative maintenance events
– Involves the replacement or reconditioning of major ware components
– Requires additional service expertise beyond standard PM
– Represents the largest of the PM costs (4-6% of total Operating Cost)
– Cost often can be mitigated via rebuild or remanufactured components.
• Overhaul common terms
– Top End (E50) : Cylinder heads and Turbos - 12-25% of new Genset
– In Frame or Interim (E60): Adds main and rod bearings - 30-50% of new Genset
– Major (E70) : Adds cams, pumps, and gear train – 40-70% of new Genset
• Late life cycle overhauls are often excluded or optional to lower cost.
– Consider the impact on the Genset residual value.
Caterpillar Confidential Yellow
Unscheduled Maintenance…
Caterpillar Confidential Yellow
Operating Cost
… Unscheduled Maintenance
• Represents repair contingency
• Very difficult to assess accurately (estimate
from experience)
• Not always included in ‘Simplified Life Cycle
Cost’ analysis
• Results in downtime, which hurts availability
and could expose you to penalties
• Work with the service department to
understand this component
• Use oil sampling data to help define
maintenance intervals
Caterpillar Confidential Yellow
Addressing Unscheduled Maintenance Costs
• Unscheduled maintenance can be addressed by adding a % based
contingency to existing PM costs.
• Typical Unscheduled Maintenance costing includes:
– Parts : 2-4% adder to total parts, 4-15% for corrosive fuels
– Labor : 10-20% additional labor hours, depending on dealer experience
– Travel : 3-5 additional trip per year
Unplanned repair costs
are always higher
Caterpillar Confidential Yellow
Exhaust gas heat exchanger on a Ag Biogas cogen plant.
Caterpillar Confidential Yellow
Radiator at a landfill site-Pigeons found the radiators to be a nice place to
hang out in the winter
Caterpillar Confidential Yellow
Questions or Comments are
Encouraged!
Caterpillar Confidential Yellow
Thank You!