22
Produced by: Supported by: Use of Integration PM-PS for Effective Long-Term Planning Joseph Layani, PMP Société de Transport de Montréal Montreal Transit Commission

Plant Maint

Embed Size (px)

DESCRIPTION

Plant Maint

Citation preview

Page 1: Plant Maint

Produced by: Supported by:

Use of Integration PM-PS for Effective

Long-Term Planning

Joseph Layani, PMP

Société de Transport de Montréal –

Montreal Transit Commission

Page 2: Plant Maint

Introduction & Overview

Trigger points & Key challenges

Journey to Success

Integration Process and Achievements

Key points to Take Home

Questions

What I’ll Cover

Page 3: Plant Maint

Introduction & Overview

STM in numbers

• 405 million of transits per

years

• 9600 employees

• 2 main operational

branches: Buses and

Subway

• Total assets values:

> 14 billions US$

o Buses (1700 on 210 lines),

o Infrastructures ( > 200

locations all over the city of

Montreal)

o Subway fixed assets (5 lines,

68 stations)

o Rolling stocks ( >760 subway

cars)

Page 4: Plant Maint

Introduction & Overview

SAP-EAM at STM in numbers

• PM for the maintenance of :

o Buses (since 2002),

o Infrastructures (since 2006)

o Subway fixed assets (since 2010),

o Rolling stocks (on-going project)

• Portal is used by maintenance end-users

• BW and BI-BO for KPIs production

• PS for Infras. projects only (since December 2012)

Page 5: Plant Maint

Project Closing

Project Initialization

Project Planning

• Based on engineers estimates

• In a third party software by projects coordinators (Eng. Dept.)

Project execution

• External : PO to contractors in MM-SRV and Serv. entry

• Internal : PM work orders by maintenance planners

Project control

• Report in CO (Internal order) once a month

SAP-PS for Infrastructure projects lifecycle

Slide 5

Maintenance Planning

•In SAP-PM

•Based on

•Maint. Plans simulation,

•breakdown estimate

• & projects

•Use of Maintenance Work Centers

Page 6: Plant Maint

Long term planning process

Overall needed working

hours

Estimated projects work

hours for internal

resources

Preventive maintenance

backlog

(hours/WC)

Preventive maintenance

( hours / work centers)

Corrective maintenance (hours /WC)

based on historic data

Infrastructure

Projects planners

Infrastructure

Maintenance planners

Infrastructure

Maintenance Manager

PM work orders

PM task lists

PM work orders

Page 7: Plant Maint

Trigger points

Lack of integration : Maintenance vs. Engineering

• Impossible to compare project estimates, made in the

third party software, with the planning made in PM

o High level work area vs. PM work centers

o Annual Maint. team capacity allotted to projects : imprecise

• Impossible to adjust the planned vs. actual

o Only CO reporting, by the end of the posting period, for cost

reporting – no advancement calculations

Maintenance Engineering

Page 8: Plant Maint

Key challenges

Simplify the projects planning process

• Productivity improvement for the Eng. Group

Match the project resource plan with PM capacity

• More accurate human resource planning

Get a complete view of assets costs (by locations)

• Consolidation of project and maintenance costs per FL

Page 9: Plant Maint

Kick-off Blueprint(PS & BI)

Realization and tests

Conversion & user training

Support & BI deployment

SAP-PS project Roadmap

o Implement SAP-PS as a project planning tools

o Get rid of the 3rd party software

o Convert more than 400 active projects

o Develop a combined capacity management

o Create relevant reporting and KPIs

October 2011 May 2012

(6 months) September 2012

(5months) November 2012

(2 months) December 3rd 2012

Page 10: Plant Maint

Important Considerations

Change management

• Planning tool : Department for infra. projects PS

• Cost collectors : Finance department follow Infra. projects with

WBS instead of internal orders

• Work Centers usage: Maintenance planners have to share

“their” PM work centers with Project planners

Implication of High Management (communications)

Compose a Project team with Maintenance, Engineers and

Finance members

Page 11: Plant Maint

Technical considerations

Use of PM-PS integration points

• WBS elements are linked to the FL on which the project is

performed

• Project activities for internal resources are planned with a

control key that allows “capacity requirement”

• PM order affectation to projects leads to an automatic

replacement of the activity control key (no capacity req.)

• Work Centers usage must be changed from “Maintenance”

usage to “All task list types” usage

Page 12: Plant Maint

Results

Business process integration

Project Functional Location

Maintenance Order for projects

Work Centers

WBS

Network Activity (Internal labor)

Long term project planning Short term planning

Infrastructure project planners

Infrastructure Maintenance planners

Link

Page 13: Plant Maint

Results

Business process integration

Project

Functional Location

Maintenance Order for projects

Work Centers

WBS

Network Activity (Internal labor)

Short term planning Infrastructure project planners Infrastructure Maintenance planners

Capacity requirement is disabled

for project activity

Page 14: Plant Maint

Long term planning process - improvement

Total work hours

(Planned)

Estimated projects work

hours for internal work centers

Backlog for preventive

maintenance

(hours/WC)

Calculated PM work hours for

preventive maintenance

Estimated corrective work

hours /WC based on

historic data

Infrastructure Projects planners Infrastructure Maintenance planners

PM

PM

PM/BW

PS

BO

Infrastructure Maintenance Manager

Page 15: Plant Maint

More accurate Capacity estimate

Project planners

• Are able to give to the maintenance sections

o An estimate based on all project activities using the same work

centers as the maintenance dept. (Electricians, Mechanics,

Plumbers…)

• Are able to use PM historic data to plan new projects o Work centers utilization in PM orders related to projects

• Are able to adjust project plans according to

maintenance section work load capacity leveling

Page 16: Plant Maint

More effective decision making

Maintenance managers

• Are able to challenge their participation to projects in

regard to their preventive vs. curative objectives

o By using overall projects analysis and regular PM reporting

Maintenance planners

• Are able to react to change of project timeframe

o Overall work hours needed is adjusted once a month

Page 17: Plant Maint

Short term planning process

Slide 17

Project work orders are created at

the right time

no more “floating” orders in the

system

PM order capacity requirements

replace the initial PS activity

capacity requirement

No duplication of resources

requirement in the project

Page 18: Plant Maint

Configuration point

Slide 18

Page 19: Plant Maint

Our way to EAM consolidation

Use of Functional location in PS

• Complete Cost analysis per FLOC includes PS data

o Investment planning per location Maintenance deficit reduction

• Asset lifecycle evaluation Definition of an Asset “Health”

indicator

o based on BW data and BO reporting

Page 20: Plant Maint

Gap Reduction between 2 planning groups

• Integration leads to interactions Better Productivity

o Work centers resources integration

o Functional location object integration

More decision making tools

• Better project execution follow up

o Standard PS, BW and BO reporting and analysis

Change management consideration

o Communication and User training is the key of success

o Test team must involve a large panel of end-users

Key Points to Take Home

Page 21: Plant Maint

Questions

Thank you

Slide 21

Page 22: Plant Maint

Produced by: Supported by:

Joseph Layani, PMP

Société de Transport de Montréal

[email protected]