Prepared by M/s Udaipur Min-Tech. Pvt .Ltd 23 Sh. Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT

PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

23 Sh. Satyendra Singh Bijasana Masonry Stone Mine

.

PRE – FEASIBILITY

REPORT

Page 2: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

24 Sh. Satyendra Singh Bijasana Masonry Stone Mine

TTTTABLE OF CONTENTABLE OF CONTENTABLE OF CONTENTABLE OF CONTENT

Sr. Sr. Sr. Sr.

No.No.No.No.

ContentContentContentContent Page Page Page Page

No.No.No.No.

1.01.01.01.0 Executive SummaryExecutive SummaryExecutive SummaryExecutive Summary 25

2.02.02.02.0 Introduction of Project and Background Introduction of Project and Background Introduction of Project and Background Introduction of Project and Background

InformationInformationInformationInformation 26

3.03.03.03.0 Project DescriptionProject DescriptionProject DescriptionProject Description 28

4.04.04.04.0 Site AnalysisSite AnalysisSite AnalysisSite Analysis 33

5.05.05.05.0 Planning BriefPlanning BriefPlanning BriefPlanning Brief 37

6.06.06.06.0 Proposed InfrastructureProposed InfrastructureProposed InfrastructureProposed Infrastructure 41

7.07.07.07.0 Rehabilitation & ResettlementRehabilitation & ResettlementRehabilitation & ResettlementRehabilitation & Resettlement 42

8.08.08.08.0 Project ScheduleProject ScheduleProject ScheduleProject Schedule 42

9.09.09.09.0 Analysis of ProposalAnalysis of ProposalAnalysis of ProposalAnalysis of Proposal 43

Page 3: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

25 Sh. Satyendra Singh Bijasana Masonry Stone Mine

EXECUTIVE SUMMARYEXECUTIVE SUMMARYEXECUTIVE SUMMARYEXECUTIVE SUMMARY

ParticularsParticularsParticularsParticulars DetailsDetailsDetailsDetails Location Bijasana Masonry Stone Mine

Tehsil –Pahari, District –Bharatpur, Rajasthan

Total lease area 1.0 ha. Mineable Reserves 8,50,915 MT Capacity Proposed production – 1,26,000TPA (ROM) Life of Mine 7 years Ultimate depth of mining 220mRL Estimated project cost 35.0/-lacs EMP Cost 50,000

DG Set No

Highest and Lowest Elevation Almost Hilly having elevation 295-247mRL

Land use Govt. Waste land

Nearest Habitation/ Town Bijasana 0.05km By Road Nearest Airport Gurgaon 92 km By Road Nearest Highway SH-13, 14.0 Km & SH-22, 7.0 Km from the lease area Nearest Railway Station Deeg 46.0 km by Road Power Supply Bijasana Nearest Dispensary and Govt. Hospital

Hospital is at Pahari.

Educational Facility Primary School is at Bijasana and Higher School is at Pahari.

Nearest Telephone Facility Bijasana Water Demand and Supply 4.0 KLD, Source: through Water Tanker Nearest Tourist Places None within the study area Defense Installations None within the study area Archeological Features None within the study area Ecological Sensitive Zones None within the study area Nearest Streams/ Rivers/ Water Bodies (from mine boundary)

--

Seismic Zone Seismic zone – II.

Page 4: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

26 Sh. Satyendra Singh Bijasana Masonry Stone Mine

1.1.1.1. INTRODUCTION OF PROJECT /BACKGROUND INFORMATIONINTRODUCTION OF PROJECT /BACKGROUND INFORMATIONINTRODUCTION OF PROJECT /BACKGROUND INFORMATIONINTRODUCTION OF PROJECT /BACKGROUND INFORMATION

Mining project for Masonry Stone with M.L. No. 266/09. The project is located near

village – Bijasana, Tehsil – Pahari and District – Bharatpur, Raj. Lease area – 1.0

hect. Proposed production – 1,26,000TPA (ROM).

2.1 2.1 2.1 2.1 Identification of the project and project proponentIdentification of the project and project proponentIdentification of the project and project proponentIdentification of the project and project proponent

Name of the ProjectName of the ProjectName of the ProjectName of the Project Bijasana Masonry Stone Mine Name of theName of theName of theName of theLesseeLesseeLesseeLessee Sh. Satyendra Singh S/o Sh. Shivram Singh

Location of the projectLocation of the projectLocation of the projectLocation of the project Near Village – Bijasana Tehsil –Pahari, District– Bharatpur (Raj.),

Proposed ProductionProposed ProductionProposed ProductionProposed Production 1,26,000TPA (ROM).

Lease AreaLease AreaLease AreaLease Area 1.0 ha. (Govt. Waste land) Mob. No.Mob. No.Mob. No.Mob. No. +919587429553 EmailEmailEmailEmail [email protected]

Status of the Status of the Status of the Status of the FirmFirmFirmFirm An Individual

2.22.22.22.2 Brief description of the nature of the projectBrief description of the nature of the projectBrief description of the nature of the projectBrief description of the nature of the project::::

• Grant Order has been issued on dated 17/08/2010 having vide letter no. 2268 in

the favor of Sh. Satyendra Singh.(Annexure 1)(Annexure 1)(Annexure 1)(Annexure 1)

Nature of the Project:Nature of the Project:Nature of the Project:Nature of the Project:

Mining of Masonry Stone is Proposed in the Lease Area 1.0 Ha. (Govt. Waste

land) which will be done by Open cast semi-mechanized method of mining, Near

Village–Bijasana, Tehsil – Pahari, District – Bharatpur, Rajasthan. Proposed

Production is 1,26,000TPA(ROM).

2.3 2.3 2.3 2.3 Need for the project and its importance to the country and or region:Need for the project and its importance to the country and or region:Need for the project and its importance to the country and or region:Need for the project and its importance to the country and or region:

The Mining project falls in the area of the district Bharatpur, Rajasthan

devoid of sufficient agriculture activities and other industrial growth. The

earning sources of the region are limited. The region has scarcity of water.

Mineral wealth of the state Rajasthan provides the employment

opportunity to the people of the state. Mining is one of the major core

Page 5: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

27 Sh. Satyendra Singh Bijasana Masonry Stone Mine

sector industries which play a crucial role in the process of country

economic development.

2.4 2.4 2.4 2.4 DemandsDemandsDemandsDemands----supply gapsupply gapsupply gapsupply gap::::

The demand of building Masonry Stone depends on the level of development

and the rate of growth of the economy. However, there is a persistent demand

for this commodity.

Rajasthan being the largest producer is an important Masonry Stone producing

state of India.

� It is useful for building Stone Material Etc.

2.52.52.52.5 Imports vs. Indigenous ProductionImports vs. Indigenous ProductionImports vs. Indigenous ProductionImports vs. Indigenous Production

There will be no import for the project. There will be indigenous inputs in the

entire mining activity.

2.62.62.62.6 Export PossibilityExport PossibilityExport PossibilityExport Possibility

The mining activity is not prospecting exports.

2.72.72.72.7 Domestic/Export MarketsDomestic/Export MarketsDomestic/Export MarketsDomestic/Export Markets

Lessee would like to sale out the mineral in domestic market as per

requirement. No export is proposed.

2.82.82.82.8 EmployEmployEmployEmployment Generation (Direct or Indirect)ment Generation (Direct or Indirect)ment Generation (Direct or Indirect)ment Generation (Direct or Indirect)

The mining project will generate direct & indirect employment. About 42

people will get direct employment and 2-3 people will also be affected

indirectly and employed with allied and related industries, such as

transportation, maintenance, etc.

Page 6: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

28 Sh. Satyendra Singh Bijasana Masonry Stone Mine

3.03.03.03.0 PROJECT DESCRIPTIONPROJECT DESCRIPTIONPROJECT DESCRIPTIONPROJECT DESCRIPTION

3.1 3.1 3.1 3.1 Type of project including interlinked and interdependent projects:Type of project including interlinked and interdependent projects:Type of project including interlinked and interdependent projects:Type of project including interlinked and interdependent projects:

The proposed project is mining unit of Masonry Stone in the area of 1.0 ha.

Situated at N/v-Bijasana, Tehsil – Pahari & District – Bharatpur, Rajasthan.

Proposed Production is 1,26,000TPA (ROM).

No Interlinked or Interdependent project.

3.2 3.2 3.2 3.2 Location Location Location Location (Location map & Key plan is attached as Plate no. I & II respectively).

Village : Bijasana Tehsil : Pahari District : Bharatpur State : Rajasthan The entire project area is 1.0 hectares. (Govt. waste land).

The highest elevation of the lease area is 295mRL and lowest being 247mRL.

3.3 3.3 3.3 3.3 Details of Alternate Site Considered and the Basis of Selecting the Proposed Details of Alternate Site Considered and the Basis of Selecting the Proposed Details of Alternate Site Considered and the Basis of Selecting the Proposed Details of Alternate Site Considered and the Basis of Selecting the Proposed

Site, Particularly theSite, Particularly theSite, Particularly theSite, Particularly the Environmental Considerations Gone Into Should Be Environmental Considerations Gone Into Should Be Environmental Considerations Gone Into Should Be Environmental Considerations Gone Into Should Be

Highlighted:Highlighted:Highlighted:Highlighted:

Mining is site specific project hence no alternate site is considered.

3.43.43.43.4 Size/Magnitude of OperationSize/Magnitude of OperationSize/Magnitude of OperationSize/Magnitude of Operation

It is proposed to produce 1,26,000TPA (ROM) of Masonry Stone from the area

of 1.0 hectares by Open cast semi-mechanized method of mining.

3.53.53.53.5 Project Project Project Project description with process details:description with process details:description with process details:description with process details:

It is a mining project of Masonry Stone from the lease area 1.0 ha, situated at

near village –Bijasana, Tehsil – Pahari, District – Bharatpur, Rajasthan.

Proposed production is 1,26,000TPA (ROM).The material generated from this

mine will be used mainly as building stone for construction.

Page 7: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

29 Sh. Satyendra Singh Bijasana Masonry Stone Mine

Ground Water TableGround Water TableGround Water TableGround Water Table

Proposed working will not intersect Ground water.

Proposed Mining MethodProposed Mining MethodProposed Mining MethodProposed Mining Method

The Masonry Stone Mine shall be developed by Semi-Mechanized open cast

mining by forming benches each of 6m height 3m width in a four pits. The

masonry stone is being broken by blasting. This broken material is further

drilled by jack hammer and then blasted to form masonry stone lumps which

are being loaded by excavator into the hired trucks/dumpers.

Extent of MechanizationExtent of MechanizationExtent of MechanizationExtent of Mechanization

Type of MachineryType of MachineryType of MachineryType of Machinery Nos.Nos.Nos.Nos. CompanyCompanyCompanyCompany Capicity

Jack HammersJack HammersJack HammersJack Hammers 4 Atlas Copco 32mm

CompressorCompressorCompressorCompressor 1 Local 62.5HP

D.G.SetD.G.SetD.G.SetD.G.Set 1 Local 15KVA

DumperDumperDumperDumper 3 Ashoka Leyland 75HP

Water TankerWater TankerWater TankerWater Tanker 1 Ford 5000lit

PokleanPokleanPokleanPoklean 1 Hitechi 148HP

Wagon Drill m/cWagon Drill m/cWagon Drill m/cWagon Drill m/c 1 Atlas Copco 30m

Loading EquipmentLoading EquipmentLoading EquipmentLoading Equipment

JCB are available in the area on hire basis.

180-175mRL (20-25m bgl)

WATER TABLE

200mRL LOWEST LEVEL

220mRL (20m agl)

ULTIMATE DEPTHOF MINING

Page 8: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

30 Sh. Satyendra Singh Bijasana Masonry Stone Mine

Haulage and Transport EquipmentHaulage and Transport EquipmentHaulage and Transport EquipmentHaulage and Transport Equipment

Haulage of the Masonry Stone within the mining area will be done by small

excavator.

Transport from Transport from Transport from Transport from minemineminemine head to destinationhead to destinationhead to destinationhead to destination

Transport from mine head to destination will be done by the trucks.

SourceSourceSourceSource----Approved Mining PlanApproved Mining PlanApproved Mining PlanApproved Mining Plan

ProductionProductionProductionProduction/Year/Year/Year/Year

Per YearPer YearPer YearPer Year

ROM in volumeROM in volumeROM in volumeROM in volume

(Tones)(Tones)(Tones)(Tones)

RejectedRejectedRejectedRejected

First YearFirst YearFirst YearFirst Year 28275 Nil

Second YearSecond YearSecond YearSecond Year 57820 Nil

Third YearThird YearThird YearThird Year 81884 Nil

Fourth YearFourth YearFourth YearFourth Year 103869 Nil

Fifth YearFifth YearFifth YearFifth Year 1,26,000 Nil

TotalTotalTotalTotal 3,97,8483,97,8483,97,8483,97,848 NilNilNilNil

SourceSourceSourceSource----Approved Mining PlanApproved Mining PlanApproved Mining PlanApproved Mining Plan

3.6 3.6 3.6 3.6 Raw material required along with estimated quantity, likely source, marketing Raw material required along with estimated quantity, likely source, marketing Raw material required along with estimated quantity, likely source, marketing Raw material required along with estimated quantity, likely source, marketing

area of final products, mode of area of final products, mode of area of final products, mode of area of final products, mode of transport of raw material and finished product:transport of raw material and finished product:transport of raw material and finished product:transport of raw material and finished product:

Raw material i.e. Masonry Stone will be produced by Opencast Semi

Mechanized method of mining, proposed production is 1,26,000TPA (ROM); it

will be transported to users by using trucks.

3.73.73.73.7 Resource optimization/ recycling and reuse envisaged in the project, if any, Resource optimization/ recycling and reuse envisaged in the project, if any, Resource optimization/ recycling and reuse envisaged in the project, if any, Resource optimization/ recycling and reuse envisaged in the project, if any,

should be briefly outlined. should be briefly outlined. should be briefly outlined. should be briefly outlined.

Not applicable.

Page 9: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

31 Sh. Satyendra Singh Bijasana Masonry Stone Mine

3.3.3.3.8888 Availability of water its source, energy/power requirement and sourceAvailability of water its source, energy/power requirement and sourceAvailability of water its source, energy/power requirement and sourceAvailability of water its source, energy/power requirement and source ::::

The total water requirement for the project is estimated 4.0 KLD. Water for

mining operation (dust suppression) and for domestic & drinking purpose will

be arranged from tube well and Water Tanker.

Sr. No.Sr. No.Sr. No.Sr. No. PurposePurposePurposePurpose Total Requirement (Total Requirement (Total Requirement (Total Requirement (KLDKLDKLDKLD))))

1111 Dust Dust Dust Dust suppressionsuppressionsuppressionsuppression 1.00 2222 DrinkingDrinkingDrinkingDrinking 2.0 3333 Green beltGreen beltGreen beltGreen belt 1.00

TOTALTOTALTOTALTOTAL 4.04.04.04.0 Diesel for tippers/equipment – about 180 Lt. per day is assumed to be

consumed. Diesel will be brought from outside, from nearby diesel pumps.

3.93.93.93.9 Quantity of wastes to be generated (liquid Quantity of wastes to be generated (liquid Quantity of wastes to be generated (liquid Quantity of wastes to be generated (liquid and solid) and scheme for their and solid) and scheme for their and solid) and scheme for their and solid) and scheme for their

management /disposal:management /disposal:management /disposal:management /disposal:

There is no top soil in the area. As there is no generation of waste, (5% of total

minable reserve is considering as mining loss i.e. while transportation &

loading) hence no waste rock management required.

3.10 3.10 3.10 3.10 Schematic Representations Schematic Representations Schematic Representations Schematic Representations oooof f f f thethethethe Feasibility DrawiFeasibility DrawiFeasibility DrawiFeasibility Drawing Which Giveng Which Giveng Which Giveng Which Give

Information Information Information Information oooof ECf ECf ECf EC Purpose:Purpose:Purpose:Purpose:

Page 10: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Sh. Satyendra Singh

Prepared by M/s Udaipur

32 Bijasana Masonry Stone Mine

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

Bijasana Masonry Stone Mine

Page 11: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

33 Sh. Satyendra Singh Bijasana Masonry Stone Mine

4444.0 .0 .0 .0 SITE ANALYSISSITE ANALYSISSITE ANALYSISSITE ANALYSIS

4.1 4.1 4.1 4.1 ConnectivityConnectivityConnectivityConnectivity

Connectivity Connectivity Connectivity Connectivity Details Details Details Details from Project Site:from Project Site:from Project Site:from Project Site:

4.2 4.2 4.2 4.2 Land form, land use and land Land form, land use and land Land form, land use and land Land form, land use and land ownershipownershipownershipownership

The lease area under mining lease is a Hilly ground. The highest elevation of

the area is 295mRL and lowest elevation is 247mRL.

Sr. Sr. Sr. Sr.

No.No.No.No. ParticularsParticularsParticularsParticulars DetailsDetailsDetailsDetails

1.1.1.1. Road

Connectivity

The village Bijasana, nearest population center is 0.05km away from

the lease area & it is connected with other important towns and cities

through a good network of roads with regular public transport

services. The Tehsil Headquarters of Pahari is at a distance of 12.0

km by road & District Headquarter Bharatpur is 85.0 km connected by

road.

The nearest railhead is at Deeg at a distance of 46.0km from lease area.

2.2.2.2. Nearest

Highway

SH-13 at about 14.0 km

SH-22 at about 7.0 km

3.3.3.3.

Nearest

Railway

Station

The nearest railhead is at Deeg at a distance of 46.0 km from lease area

4.4.4.4. Nearest

Airport

The nearest civilian airport for regular commercial flights is at

Gurgaon the road distance from the lease area is around 92.0

km.

Type of LandType of LandType of LandType of Land Area in HectaresArea in HectaresArea in HectaresArea in Hectares

Govt. Waste land 1.0

Total:Total:Total:Total: 1.01.01.01.0

Page 12: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

34 Sh. Satyendra Singh Bijasana Masonry Stone Mine

4.3 4.3 4.3 4.3 TopographyTopographyTopographyTopography

The lease area is a Govt. Waste land. In general the area is having Hilly

topography. There is no nalla flowing within the area. There is no village or

human settlement in the lease area. The rain water spread out in the area &

nearby areas. The highest contour in the area is 295mRL and lowest is

247mRL.

4.4 4.4 4.4 4.4 Existing Land use PatternExisting Land use PatternExisting Land use PatternExisting Land use Pattern

The lease area is Govt. Waste land (1.0 hect.). There is no village or hutments

within the lease area. Existing land use pattern is given as below:

Sr. No.Sr. No.Sr. No.Sr. No. ParticularsParticularsParticularsParticulars PrePrePrePre----OperationalOperationalOperationalOperational

A)A)A)A) Mining ActivityMining ActivityMining ActivityMining Activity

1111 PitsPitsPitsPits 0.00

2222 Top Soil Storage Top Soil Storage Top Soil Storage Top Soil Storage 0.00

3333 DumpsDumpsDumpsDumps 0.00

4444 RoadRoadRoadRoad 0.00

5555 Mineral StackMineral StackMineral StackMineral Stack 0.00

6666 Infrastructure Infrastructure Infrastructure Infrastructure 0.00

7777 PlantationPlantationPlantationPlantation 0.00

8888 Reclamation & Reclamation & Reclamation & Reclamation & PlantationPlantationPlantationPlantation Backfilled Backfilled Backfilled Backfilled

0.00

9999 Water storage Water storage Water storage Water storage 0.00

B)B)B)B) Remaining Virgin. LandRemaining Virgin. LandRemaining Virgin. LandRemaining Virgin. Land 1.00

Total areaTotal areaTotal areaTotal area

1.01.01.01.0 Hect.Hect.Hect.Hect.

4.5 4.5 4.5 4.5 Existing InfrastructureExisting InfrastructureExisting InfrastructureExisting Infrastructure::::

All necessary infrastructures will be developed before mining operation

commenced. Site services as per Mines Rules 1956 will be developed. First-Aid

station with all necessary medical facilities, Toilets as per the provisions of

Mines Rules will be developed. Regular medical checkup of the mine employees

will be carried out as per the provisions of Mines Rules 1956.

Page 13: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

35 Sh. Satyendra Singh Bijasana Masonry Stone Mine

4.6 4.6 4.6 4.6 Soil classificationSoil classificationSoil classificationSoil classification::::

The Soil of the Bharatpur District are grayish brown and yellowish Brown with

wide variation in texture from sandy loam and clayey loam. The Soils at some

palaces are affected by salinity/alkalinity. The soil of Bharatpur Bayana and

Deeg Sub division are fertile. In northeastern part of the district, the soils are

compact and have low permability, which causes water to stangnat on the

surface during rainy season.

Regional geology & local geologyRegional geology & local geologyRegional geology & local geologyRegional geology & local geology::::

a)a)a)a) Regional geologyRegional geologyRegional geologyRegional geology::::----

The regional Geological settings of Bhartpur District show a wide variety of

rock type belonging to the Delhi Super group of Middle Proterozoic age. The

rock formations which outcrop in Bhartpur District are mainly Calc Gneiss,

Quartzite, Amphibolites, Mylonite, Dolomite, Migmatite, Gneisses, Cal schist,

marble, mica schist etc. The regional Geological Sequence of the region as

described by Geological Survey of India, Miscellaneous Publication No.30, Part

12, 2nd revised edition is as follows:

Super group Group Age Lithology

Recent

Post Delhi

Delhi Super

Group

Ajabgarh/ Kumbhalgarh

Group

Alwar- Gogunda Group

Lower- middle

Proterozoic

Soil, Sand dunes

Pegmatite, Granite

Muscovite-Biotite Group, Quartzite,

amphibolites, mylonite, dolomite,

migmatite, gneisses, Calc Gneiss, Cal

schist, marble, mica schist, calcite,

Biotite schist, Calc Biotite schist,

Quartzite

Page 14: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

36 Sh. Satyendra Singh Bijasana Masonry Stone Mine

b)b)b)b) Local GeologyLocal GeologyLocal GeologyLocal Geology

Massive Quartzite is outcropping in the entire mining lease area. Most of the

part of Quartzite is weathered and fractured. Geologically the Massive

Quartzite in the mining lease area belongs to Delhi Super group. The

stratigraphic sequence of the litho unit present in the area is as follows:-

Recent &sub recent - Alluvium & blown sand

Delhi Super Group Ajabgarh Group Massive Quartzite

Surface geological mapping has been done on a scale of 1:1000 and geological

cross section and long section is prepared accordingly.

4444.7 .7 .7 .7 Climatic detailsClimatic detailsClimatic detailsClimatic details

The area is characterized by semi arid with an average annual rainfall of

about 657 mm, which is mainly received during monsoon season of June to

September. There is a large variation of temperature in the area.

The minimum temp. recorded as 1.4º during winter whereas maximum

temp. recorded during summer is 47º C. General wind direction is south

west to north east.

4.8 4.8 4.8 4.8 Social InfrastructureSocial InfrastructureSocial InfrastructureSocial Infrastructure

� The infrastructure like, toilets, first aid stations etc. will be provided inside the

lease area.

� The nearest Hospital is available at Pahari & Educational facilities are at

Bijasana (in the form of primary schools) & at Pahari (in the form of Higher

schools) are available there.

� Medical facilities, Primary Health Centre are there in the area, imparting

services, for advance medical facilities. In each village one health worker has

been appointed by the Govt. to provide primary health facilities.

� The water required will be available by the local water well department in the

lease area and through water tanker.

Page 15: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

37 Sh. Satyendra Singh Bijasana Masonry Stone Mine

� Communication services like post office and telephones are available in the

nearby village. Some of the villagers are having mobile phones.

� An occupational health unit will be organized and the proposed measures will

be adopted:

• Pre &Periodical Medical Checkup program for all the workers.

• Compulsory medical checkup program and first-aid box with necessary

equipment will be provided.

• Training for workers.

• Safety equipment i.e. dusts mask, safety shoes, gloves etc.

5. 5. 5. 5. PLANNING BRIEFPLANNING BRIEFPLANNING BRIEFPLANNING BRIEF

5.1 5.1 5.1 5.1 Planning Planning Planning Planning conceptconceptconceptconcept

It is proposed to produce 1,26,000TPA(ROM) of Masonry Stone from the lease

area. It is situated in Bharatpur District of Rajasthan.

5.2 5.2 5.2 5.2 Population Population Population Population projectionprojectionprojectionprojection

Man power requirement for mining is estimated to be 42 Nos. Most of the

employees will be recruited from neighboring village depending upon the

availability of skilled & unskilled people. Migration of highly educated and

skilled person will take place but it will be on temporary basis. So there will no

permanent migration of people, hence there will be no population projection.

Page 16: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

38 Sh. Satyendra Singh Bijasana Masonry Stone Mine

5.35.35.35.3 Land use Planning:Land use Planning:Land use Planning:Land use Planning:

Land use pattern Land use pattern Land use pattern Land use pattern (Hects.)(Hects.)(Hects.)(Hects.)

Sr. No.Sr. No.Sr. No.Sr. No. ParticularsParticularsParticularsParticulars PrePrePrePre----OperationalOperationalOperationalOperational OperationalOperationalOperationalOperational PostPostPostPost----OperationalOperationalOperationalOperational

A)A)A)A) Mining ActivityMining ActivityMining ActivityMining Activity

1111 PitsPitsPitsPits 0.00 0.7225 0.7225

(Convert into Water Reservoir)

2222 Top Soil StorageTop Soil StorageTop Soil StorageTop Soil Storage - -

3333 PlantationPlantationPlantationPlantation 0.00

- 0.2775

4444 DumpsDumpsDumpsDumps 0.00 0.00 -

5555 RoadRoadRoadRoad 0.00 0.00 0.00

6666 Mineral StackMineral StackMineral StackMineral Stack 0.00 0.000 -

7777 Infrastructure Infrastructure Infrastructure Infrastructure 0.00 0.000 0.00

8888 Rain water storageRain water storageRain water storageRain water storage 0.00 0.00 -

9999 Reclamation & PlantationReclamation & PlantationReclamation & PlantationReclamation & Plantation Backfilled Backfilled Backfilled Backfilled

0.00 0.00 -

B)B)B)B) Remaining Virgin. LandRemaining Virgin. LandRemaining Virgin. LandRemaining Virgin. Land 1.00 0.2775 0.00

Total areaTotal areaTotal areaTotal area

1.01.01.01.0 Hect.Hect.Hect.Hect.

1.01.01.01.0 Hect.Hect.Hect.Hect.

1.01.01.01.0 Hect.Hect.Hect.Hect.

5.4 5.4 5.4 5.4 Assessment of Assessment of Assessment of Assessment of infrastructure demand infrastructure demand infrastructure demand infrastructure demand ((((physical physical physical physical and and and and socialsocialsocialsocial).).).).

Temporary office and stores will be provided in the mine lease area. Specified

first-aid box with all necessary facilities will be maintained at the site office and

the rest shelter as per Mines Act-1952. Medical facilities, Primary Health Centre

are there in the area, imparting services, for advance medical facilities.

Communication services like post office and telephones are available in the

nearby village. Some of the villagers are having mobile phones.

5.55.55.55.5 Facilities Facilities Facilities Facilities providedprovidedprovidedprovided::::

5.5.5.5.5555.1 .1 .1 .1 InfrastructureInfrastructureInfrastructureInfrastructure

Additional facilities will be made as per the requirement. Arrangements for

safe and healthy working conditions have been done. Provision of Drinking

water from nearby villages or through tankers in dry period.

Page 17: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

39 Sh. Satyendra Singh Bijasana Masonry Stone Mine

5.5.5.5.5555.2.2.2.2 Landscaping and Landscaping and Landscaping and Landscaping and green belt developmentgreen belt developmentgreen belt developmentgreen belt development

To improve the aesthetic environment of the area it is proposed to plant 50

saplings at Operational stage at statutory barrier. During the first five years

sapling of local species like Babool, Khejri, Neem, and Jaletc will be planted

over an area of 0.225 hect.

Plantation ProgrPlantation ProgrPlantation ProgrPlantation Prograaaammmmmemememe

Protection of Plants: Protection of Plants: Protection of Plants: Protection of Plants:

Following measures are proposed for protection of plants.

The expected rate survival is assumed at 80%. To improve the survival rate in

the adverse climate condition necessary consultation would be taken from the

Forest department. Proposed plantation area shall be fenced properly for

improving the survival rate. Plantation will be carried out in the lease area in

phased manner.

5.5.35.5.35.5.35.5.3 Health and safety SystemHealth and safety SystemHealth and safety SystemHealth and safety System

During the Opencast Semi Mechanized working, and allied activities, all the

precautionary measures shall be taken into account as per MMR 1961 and

MCDR 1988 for safety and security.

Following Safety & security measures will be enforced;

� Moving front of the quarry shall have temporary fencing.

� Permanent fencing will be provided where quarry has reached the

ultimate pit limit.

YearYearYearYear No. of saplingsNo. of saplingsNo. of saplingsNo. of saplings Year Wise Area (Hectare)Year Wise Area (Hectare)Year Wise Area (Hectare)Year Wise Area (Hectare)

IIII 50 0.045 IIIIIIII 50 0.045 IIIIIIIIIIII 50 0.045 IVIVIVIV 50 0.045 VVVV 50 0.045

At the End of five YearAt the End of five YearAt the End of five YearAt the End of five Year 100100100100 0.1050.1050.1050.105 TotalTotalTotalTotal 350350350350 0.33000.33000.33000.3300

Page 18: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

40 Sh. Satyendra Singh Bijasana Masonry Stone Mine

� Mine entrance will have a permanent check post and record shall be

maintained of all persons / vehicles entering the mine area.

� Round the clock security arrangement shall be provided to prevent

inadvertent entry of persons.

5.5.45.5.45.5.45.5.4 Disaster Management and Risk AssessmentDisaster Management and Risk AssessmentDisaster Management and Risk AssessmentDisaster Management and Risk Assessment

Inspite of following all the precautionary measures and following all safety

rules, regulations and procedures, in mining accidents cannot be ruled out

completely. The Project Proponent will formulate a Disaster Management Plan

with the approval of DGMS. Following are the accidents which can take place

in mechanised Opencast Semi Mechanized mining and measures proposed to be

taken.

� Fall of human beings or fall of machines from benches/ dumps/haul roads.

� Due to drilling / blasting and handling of explosives.

� Fire & Explosion in machinery

� Emergency situation due to social reason such as public unrest, terrorism

etc.

Preventive Measures: Preventive Measures: Preventive Measures: Preventive Measures:

� Creating beam on the side of benches / haul roads of height greater than or

equal to ½½½½ tyre radius. Minimum height of beam shall be 1.2 m and slope

450. Minimum clearance of 1.5 m will be maintained between outer tyre and

beam.

� All provisions of MMR 1961, conditions imposed in permission for Deep hole

drilling and blasting and use of HEMM, and conditions of explosive license

will be followed. . . .

� Fire fighting equipment in the machinery/ workshop/ office will be

maintained. Persons will be trained in the use of fire fighting equipment

and mock rehearsal will be conducted.

Page 19: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

41 Sh. Satyendra Singh Bijasana Masonry Stone Mine

� Training of security personnel.

� Procedures as laid down in Disaster Management Plan to be followed. . . .

Training;Training;Training;Training;

Persons will be trained in the following:

• Knowledge of Chemicals and use of protective equipment

• Procedures for reporting emergencies.

• Location and use of fire fighting equipment

• Knowledge of alarm system and siren

• Evacuation procedures.

• Training in first aid as per Mines Rules 1955

Emergency Equipment & Facilities:Emergency Equipment & Facilities:Emergency Equipment & Facilities:Emergency Equipment & Facilities:

• Mobiles.

• Fire fighting equipment’s

• Emergency medical supplies

Other protective equipment’s i.e. goggles, helmet, face shield, hand gloves,

safety belts, barricade tape. First Aid station as per the provisions of Mines

Rules 1955.

6.6.6.6. PROPOSED INFRASTRUCTUREPROPOSED INFRASTRUCTUREPROPOSED INFRASTRUCTUREPROPOSED INFRASTRUCTURE

S.S.S.S. No.No.No.No. DetailsDetailsDetailsDetails

1 Lease Area 1.0 hectares.

2 Residential Area Not Applicable

3 Connectivity The village Bijasana, nearest population center is 0.05 km

away from the lease area & it is connected with other

important towns and cities through a good network of roads

with regular public transport services. The Tehsil

Headquarters of Pahari is at a distance of 12.0 km by road &

District Headquarter Bharatpur is 85.0 km connected by road.

Page 20: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

42 Sh. Satyendra Singh Bijasana Masonry Stone Mine

The nearest railhead is at Deeg at a distance of 46.0 km from

lease area.

SH-13, 14.0 Km

SH-22, 7.0 Km

4 Green Belt During the first five years sapling of local species like

Babool, Khejri, Neem, Amal Tas etc will be planted over an

area of 0.225hect.

5 Social Infrastructure Social Infrastructure and other necessary other facilities will be

provided by mine’s proponent.

6 Water Management 4.0 KLD, Source: tube well and water tanker.

7 Sewerage System Domestic Effluent treated in soak pits and overflow used for

gardening

8 Industrial Waste

Management

N.A.

9 Solid Waste

Management

There are some subgrade mineral will be generated which will be

stacked separately.

10 Power requirement N.A.

7.7.7.7. REHABILITATION & RESETTLEMENT PLAN REHABILITATION & RESETTLEMENT PLAN REHABILITATION & RESETTLEMENT PLAN REHABILITATION & RESETTLEMENT PLAN

There is no human settlement within the mine lease area. No human

settlement will be disturbed due to the mining activity. So, no Rehabilitation

and Resettlement is proposed.

8.8.8.8. PROJECT SCHEDULEPROJECT SCHEDULEPROJECT SCHEDULEPROJECT SCHEDULE

8.1 8.1 8.1 8.1 Proposed Proposed Proposed Proposed schedule and schedule and schedule and schedule and approval for implementationapproval for implementationapproval for implementationapproval for implementation

The Proposed project shall be established after getting the Environmental

Clearance from SEAC, Jaipur.

Page 21: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

43 Sh. Satyendra Singh Bijasana Masonry Stone Mine

8.2 8.2 8.2 8.2 Project Project Project Project cost estimationcost estimationcost estimationcost estimation

Estimated Project Cost for the proposed project is Rs. 35.0/- Lacs.

(A)(A)(A)(A) Capital Capital Capital Capital investmentinvestmentinvestmentinvestment/-

Site facilities = Rs.... 30,000

Machineries & Tools = Rs 25, 20,000

Financial assurance = Rs. 1, 00,000

PMCP = Rs. 2, 00,000

Social fund & activities = Rs. 50,000

EMP = Rs. 50,000

Labour Skill Welfare Programme = Rs. 50,000

Total costTotal costTotal costTotal cost = = = = RsRsRsRs 33335555.00.00.00.00 Lacs/Lacs/Lacs/Lacs/----

(B) (B) (B) (B) Operational Operational Operational Operational costcostcostcost----

The mineral will be mined from the lease area and the cost of per ton of mining

will be approx. Rs. 125/- per ton.

8.3 8.3 8.3 8.3 ECONOMIC VIABILITYECONOMIC VIABILITYECONOMIC VIABILITYECONOMIC VIABILITY

The anticipated cost of mining is Rs. 125/- per ton cost. Average sale value is

assumed at Rs. 250-280/- ton of Masonry Stone. Hence the project will be

viable.

9.9.9.9. ANALYSIS OF PROPOSALANALYSIS OF PROPOSALANALYSIS OF PROPOSALANALYSIS OF PROPOSAL

• Project will create direct & indirect employment opportunities within the

surrounding region. Unit will use good faith efforts to employ local people

from the nearby villages depending upon the availability of skilled & un-

skilled man-power surrounding the project site.

• In the proposed project would require significant workforce of non-technical

and technical persons. Migration of highly education and skilled experience

will result in increase of literacy in the surrounding villages.

Page 22: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_19_Jan_2016... · Satyendra Singh Bijasana Masonry Stone Mine . PRE – FEASIBILITY REPORT . Prepared

Prepared by M/s Udaipur Min-Tech. Pvt .Ltd

44 Sh. Satyendra Singh Bijasana Masonry Stone Mine

• In addition, the proposed expansion of project shall enhance the prospects of

employment.

• Assessment of the potential socioeconomic benefits during mining

focused primarily on work force requirements, acquisition of supplies,

and the temporary increased demand for services related to the mining

project like food, housing, communications, law enforcement, medical care,

local transportation etc. Due to these, additional revenue to local suppliers

for required products and services related to the construction and operation

phases of the project will generate.

• Thus, mining activities will provide numerous new, although temporary, work

opportunities for both skilled and unskilled labor, as well as contribute

significantly to the local economy.

• Additional government revenue expected from royalty, taxes, duties and other

fees.

• An added benefit to the proposed project will result in considerable growth of

stimulating the industrial and commercial activities in the state. Small and

medium scale industries may be further developed as a consequence.