11
Programme and progress

Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Embed Size (px)

Citation preview

Page 1: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Programme and progress

Page 2: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Programme• Employer requirements

–Sectional completion• Pre-tender programme

–Use for ascertaining completion risk–Subcontractor activity periods–Temporary works–Enabling works

–Sequence cost study planning (see next slide)

• Master programme–Specified requirement under ICC and NEC3–Extent specified?–Content specified?–Measurement implications?–Work breakdown structure

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

2

Page 3: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Sequence study cost comparison

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

3

Page 4: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Contract stage programmes• Short-term programmes

–Monthly or weekly–Consider alternative methods

• Noncompliance with master programme–Effect?

• Types of programme–Precedence (activity on the node)–Arrow (activity on the arrow)–As planned–As Built

• Extensions of time–With costs–Without costs

• Mitigation of loss–An implied term???

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

4

Page 5: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Master programme

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

Page 6: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Baseline programme

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

6

Page 7: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Baseline programme (contd.)

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

7

Page 8: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Measuring progress

• S curve principles– Match budget with programme– Calculate a predicted cumulative total– Compare as built with predicted

• Possibility of EVA– Needs WBS– Metrics

• Acceleration© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

8

Page 9: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Progress measurement

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

9

Page 10: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Measuring progress-value envelope

10

Page 11: Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor

Acceleration• Short-term programmes

–Monthly or weekly–Consider alternative methods

• Noncompliance with master programme–Effect?

• Types of programme–Precedence (activity on the node)–Arrow (activity on the arrow)–As planned–As Built

• Extensions of time–With costs–Without costs

• Mitigation of loss–An implied term???

© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

11