    Construction of a Cut-off Wall

    through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    2/37

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    3/37

    Project Location

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    4/37

    Project Location

    Mine Camp

    Main Dam

    Runway

    Tailings

    ImpoundmentOverburden

    Stockpile

    Waste Dump

    Ore Pit

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    5/37

    Design Criteria

    Reduce or prevent seepage from tailings impoundment into

    downstream watershed (Bons Creek)

    Crest elevation of 292.6 m (revised to 295.6 m) and final crest

    elevation of 300.5 m

    Key into low permeability bedrock Average annual temperature of

    - 4ºC with an AFI = 2,628 ºC-days

    Design for perpetuity

    (consider total thawed condition)

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    6/37

    Site Characteristics

    Overburden Stockpile constructed over permafrost that averages about - 1° C Overburden Stockpile composed of mainly Kivalina Shale, having high ice content, low strength

    Cofferdams constructed of end dumped waste rock.

    Tailings placed over geotextile to reduce seepage.

    Additional tailings placed on upstream face of north cofferdams to further reduce seepage.

    Overburden Stockpile

    Cofferdams with Tailings Between

    Tailings

    ImpoundmentDD2

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    7/37

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    8/37

    Embankment SectionTailings

    Impoundment

    Tailings

    Impoundment

    Select fill composed of well-graded -2.5 cm crushed rock with less than10% fines

    Rockfill composed of waste rock from mine operations (60 cm max with less than

    10% fines)

    Width of embankment must allow for cut-off wall equipment

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    9/37

    Alignment and Excavation LimitsTailings

    Impoundment

    Tailings

    Impoundment

    Dewater about 151,000 m³

    Excavate about 91,746 m³ of organics and ice-rich materials

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    10/37

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    11/37

    Plastic Concrete Mix Design

    Performance criteria:

    Max permeability of 10-8 m/sec

    Min 28-day unconfined compressive strength

    of 0.7 MPa at 5% strain

    Final mix design: 22.8% water, 6.8% cement,

    1.8% bentonite, 68.5% aggregate

    Same water/bentonite ratio as slurry during

    excavation

    Average permeability achieved 5x10-9 m/sec

    Average 28-day strength of 0.83 MPa

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    12/37

    Cut-Off Wall Panel Construction

    Construction began in 2007 and was completed in 2010 (instrumentation in 2011)

    Golder Associates Innovative Applications (GAIA) main contractor for cut-off wall

    construction (assisted by AIC)

    Excavation and earthworks by

    TAK and Paw River

    Construction season – May 15 to

    October 5

    Deep excavation using BAUERTrench Cutter

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    13/37

    Cut-Off Wall Panel Construction

    Guide Wall Installation

    The Guide Wall provides:

    Guidance to ensure alignment of excavation

    Stability to the upper portion of the trench

    Reservoir to maintain slurry level

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    14/37

    Cut-Off Wall Panel ConstructionTailings

    Impoundment

    Tailings

    ImpoundmentPre-Excavate Trench about 3 m

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    15/37

    Cut-Off Wall Panel ConstructionTailings

    Impoundment

    Tailings

    ImpoundmentAdd Slurry to Trench and Excavate Panel

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    16/37

    Cut-Off Wall Panel Construction

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    17/37

    Cut-Off Wall Panel Construction 

    Cutting of the first “bite” 

    2.8 m, 1st bite

    Guide Wall

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    18/37

    Cut-Off Wall Panel Construction 

    Cutting of the second “bite” 

    2.8 m 1st bite 2.8 m 2nd bite

    Guide Wall

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    19/37

     

    Cut-Off Wall Panel ConstructionCutting of the third “bite” 

    1.5 m 3rd bite

    Guide Wall

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    20/37

     

    Cut-Off Wall Panel Construction 

    7.9 m Triple Primary Panel

    Excavated primary panel

    Guide Wall

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    21/37

    Cut-Off Wall Panel Construction 

    „Working

    Slurry“ 

    1st Primary Panel

    Guide Wall

    Fresh Slurry

    To Desanding Plant

    2nd Primary Panel Secondary

    Replacing of Working Slurry by Fresh Slurry

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    22/37

    Slurry Recycled Through Desander

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Cut-Off Wall Panel Construction 

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    23/37

    Tailings

    Impoundment

    Tailings

    ImpoundmentBackfill Panel with Tremied Plastic Concrete

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Cut-Off Wall Panel Construction 

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    24/37

    Concreting

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Cut-Off Wall Panel Construction 

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    25/37

       A   p   p   r   o   x .

       4   0

        ’

    BC 40

    Distinguishing features of BAUER-Cutter (BC)

    robust cutter frame (number indicates cutterweight)

    steering flaps to control verticality

    pressure balance for major components

    (2 x gearbox, 1 x mud pump) 6" mud pump (up to 450 m³/h mud flow) max.

    diameter of cobbles 80 mm

    powerful cutter gear boxes with shock absorbers(BC 32 with 81 kNm; BC 40 with 100 kNm)

    appropriate cutter wheel sets for different soilconditions; free cut of the gear box shield due topatented flipper tooth

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    26/37

    B-Tronic Cutter Control System

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Distinguishing features of BAUER-Cutter (BC)

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    27/37

    Construction Issues – Resolved!

    Rock cutter replaced clay cutter toimprove trenching productivity

    7H:1V slopes used to mobilize

    carrier with cutter along alignment

    Embankment widened for safety

    berms required by MSHA

    Sodium bicarbonate used todecrease viscosity of working slurry

    when cutting secondary panels

    Secondary pumps used to transport

    slurry farther away from mixing

    tanks (didn’t have to relocate mixing

    tanks)

    Realigned (offset) cut-off wall to

    avoid geologic obstruction

    Developed termination criteria (at

    abutments) based on cutting rates

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    28/37

    Tailings

    Impoundment

    Tailings

    ImpoundmentEmbankment Construction

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Construction Photos

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    29/37

    Tailings

    Impoundment

    Tailings

    ImpoundmentEmbankment Construction

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Construction Photos

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    30/37

    Construction Photos

    Ice-rich Materials During Excavation

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    31/37

    Mixing Tanks and Desander

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Construction Photos

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    32/37

    Tailings

    Impoundment

    Tailings

    ImpoundmentClay Cutter Wheels

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Construction Photos

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    33/37

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    34/37

    Maintenance

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Construction Photos

    C i f C ff W ll h h W P f

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    35/37

    Tailings

    Impoundment

    Tailings

    ImpoundmentSlurry Loss Through Fractured Rock

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Construction Photos

    C t ti f C t ff W ll th h W P f t

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    36/37

    Good Job, Good Team, Good People

    Construction of a Cut-off Wall through Warm Permafrost,

    Red Dog Mine, Alaska

    Construction Photos

  • 8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf

    37/37

    Thank You for Your Attention