Upload
avca65
View
221
Download
0
Embed Size (px)
Citation preview
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
1/37
Construction of a Cut-off Wall
through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
2/37
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
3/37
Project Location
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
4/37
Project Location
Mine Camp
Main Dam
Runway
Tailings
ImpoundmentOverburden
Stockpile
Waste Dump
Ore Pit
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
5/37
Design Criteria
Reduce or prevent seepage from tailings impoundment into
downstream watershed (Bons Creek)
Crest elevation of 292.6 m (revised to 295.6 m) and final crest
elevation of 300.5 m
Key into low permeability bedrock Average annual temperature of
- 4ºC with an AFI = 2,628 ºC-days
Design for perpetuity
(consider total thawed condition)
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
6/37
Site Characteristics
Overburden Stockpile constructed over permafrost that averages about - 1° C Overburden Stockpile composed of mainly Kivalina Shale, having high ice content, low strength
Cofferdams constructed of end dumped waste rock.
Tailings placed over geotextile to reduce seepage.
Additional tailings placed on upstream face of north cofferdams to further reduce seepage.
Overburden Stockpile
Cofferdams with Tailings Between
Tailings
ImpoundmentDD2
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
7/37
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
8/37
Embankment SectionTailings
Impoundment
Tailings
Impoundment
Select fill composed of well-graded -2.5 cm crushed rock with less than10% fines
Rockfill composed of waste rock from mine operations (60 cm max with less than
10% fines)
Width of embankment must allow for cut-off wall equipment
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
9/37
Alignment and Excavation LimitsTailings
Impoundment
Tailings
Impoundment
Dewater about 151,000 m³
Excavate about 91,746 m³ of organics and ice-rich materials
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
10/37
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
11/37
Plastic Concrete Mix Design
Performance criteria:
Max permeability of 10-8 m/sec
Min 28-day unconfined compressive strength
of 0.7 MPa at 5% strain
Final mix design: 22.8% water, 6.8% cement,
1.8% bentonite, 68.5% aggregate
Same water/bentonite ratio as slurry during
excavation
Average permeability achieved 5x10-9 m/sec
Average 28-day strength of 0.83 MPa
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
12/37
Cut-Off Wall Panel Construction
Construction began in 2007 and was completed in 2010 (instrumentation in 2011)
Golder Associates Innovative Applications (GAIA) main contractor for cut-off wall
construction (assisted by AIC)
Excavation and earthworks by
TAK and Paw River
Construction season – May 15 to
October 5
Deep excavation using BAUERTrench Cutter
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
13/37
Cut-Off Wall Panel Construction
Guide Wall Installation
The Guide Wall provides:
Guidance to ensure alignment of excavation
Stability to the upper portion of the trench
Reservoir to maintain slurry level
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
14/37
Cut-Off Wall Panel ConstructionTailings
Impoundment
Tailings
ImpoundmentPre-Excavate Trench about 3 m
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
15/37
Cut-Off Wall Panel ConstructionTailings
Impoundment
Tailings
ImpoundmentAdd Slurry to Trench and Excavate Panel
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
16/37
Cut-Off Wall Panel Construction
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
17/37
Cut-Off Wall Panel Construction
Cutting of the first “bite”
2.8 m, 1st bite
Guide Wall
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
18/37
Cut-Off Wall Panel Construction
Cutting of the second “bite”
2.8 m 1st bite 2.8 m 2nd bite
Guide Wall
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
19/37
Cut-Off Wall Panel ConstructionCutting of the third “bite”
1.5 m 3rd bite
Guide Wall
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
20/37
Cut-Off Wall Panel Construction
7.9 m Triple Primary Panel
Excavated primary panel
Guide Wall
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
21/37
Cut-Off Wall Panel Construction
„Working
Slurry“
1st Primary Panel
Guide Wall
Fresh Slurry
To Desanding Plant
2nd Primary Panel Secondary
Replacing of Working Slurry by Fresh Slurry
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
22/37
Slurry Recycled Through Desander
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Cut-Off Wall Panel Construction
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
23/37
Tailings
Impoundment
Tailings
ImpoundmentBackfill Panel with Tremied Plastic Concrete
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Cut-Off Wall Panel Construction
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
24/37
Concreting
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Cut-Off Wall Panel Construction
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
25/37
A p p r o x .
4 0
’
BC 40
Distinguishing features of BAUER-Cutter (BC)
robust cutter frame (number indicates cutterweight)
steering flaps to control verticality
pressure balance for major components
(2 x gearbox, 1 x mud pump) 6" mud pump (up to 450 m³/h mud flow) max.
diameter of cobbles 80 mm
powerful cutter gear boxes with shock absorbers(BC 32 with 81 kNm; BC 40 with 100 kNm)
appropriate cutter wheel sets for different soilconditions; free cut of the gear box shield due topatented flipper tooth
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
26/37
B-Tronic Cutter Control System
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Distinguishing features of BAUER-Cutter (BC)
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
27/37
Construction Issues – Resolved!
Rock cutter replaced clay cutter toimprove trenching productivity
7H:1V slopes used to mobilize
carrier with cutter along alignment
Embankment widened for safety
berms required by MSHA
Sodium bicarbonate used todecrease viscosity of working slurry
when cutting secondary panels
Secondary pumps used to transport
slurry farther away from mixing
tanks (didn’t have to relocate mixing
tanks)
Realigned (offset) cut-off wall to
avoid geologic obstruction
Developed termination criteria (at
abutments) based on cutting rates
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
28/37
Tailings
Impoundment
Tailings
ImpoundmentEmbankment Construction
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Construction Photos
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
29/37
Tailings
Impoundment
Tailings
ImpoundmentEmbankment Construction
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Construction Photos
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
30/37
Construction Photos
Ice-rich Materials During Excavation
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
31/37
Mixing Tanks and Desander
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Construction Photos
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
32/37
Tailings
Impoundment
Tailings
ImpoundmentClay Cutter Wheels
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Construction Photos
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
33/37
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
34/37
Maintenance
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Construction Photos
C i f C ff W ll h h W P f
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
35/37
Tailings
Impoundment
Tailings
ImpoundmentSlurry Loss Through Fractured Rock
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Construction Photos
C t ti f C t ff W ll th h W P f t
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
36/37
Good Job, Good Team, Good People
Construction of a Cut-off Wall through Warm Permafrost,
Red Dog Mine, Alaska
Construction Photos
8/9/2019 S2_11_10_Franz_Gerressen_rev.pdf
37/37
Thank You for Your Attention
Questions?