Upload
buikhue
View
217
Download
3
Embed Size (px)
Citation preview
Strategic Approach to Recovery of FisheriesIndustry and Coastal Community
Affected by Great East Japan Disaster –
-Lessons learnt through Sumatra Earthquake and Great Indian
Ocean Tsunami Disaster in 2004 –1
食料生産管理学
Contents
Introduction
Impacts on fisheries industry and coastal community
caused by Great East Japan Disaster in 2011
How to obtain lessons learnt through recovery process of
Sumatra Earthquake and Indian Ocean Tsunami in 2004
Purpose and Contents of Symposium
2
Introduction
On March 11, 2011, a large earthquake measuring 9.0
on the Richter scale resulted from the two tectonic
plates’ movement in the Pacific Ocean floor along
coastlines of East Japan.
East Japan, especially northeast Pacific coast areas, are
the important pillars of food security of Japan, providing
the nations with agricultural and fisheries products.
Clusters of fisheries and their related industries had
extended production, processing and , with accumulated
capital, technologies, and knowledge.
3
Great East Japan Disaster: Damages to Fisheries ①
4
A fishing vessel dumped inland by
tsunami at Ayukawa fishing port
(Ishinomaki City)
Yoriiso fishing port covered with debris
(Ishinomaki City)
Yoriiso fish processing facility
damaged by tsunami (Ishinomaki
City)
Fishing
vesselsAbout 25,000 were damaged.
Fishing
Ports
319 fishing ports were damaged.
The estimation of damage is 8,230
billion yen.
Markets
Almost all markets adjacent to the
affected fishing ports were
damaged. 22 markets were
completely destroyed.
Fish
Processi
ng
Facilities
570 facilities were completely
destroyed. 113 facilities were
partially destroyed. 140 facilities
were flooded.
Damages in 7 prefectures
(Fishing vessels, Fishing Ports, Markets,
Fish Processing Facilities)
※The estimation of damages is as of May 5, 2011. (The damages are predicted to increase, as situations are more
comprehensively revealed.) ※Source: “Fishery Census 2008” (Source) Fisheries Agency
※7 prefectures
where the
earthquake
inflicted damages.
・Major damages in extensive areas mainly in 7 prefectures (Hokkaido, Aomori, Iwate, Miyagi,
Fukushima, Ibaraki, Chiba) which account for 50 percent of national fishery production. The number of
persons engaged in the fishery industry in the areas is 73,948 (1/3 of the nation’s total)
・The amount of damages to aquaculture facilities is 1312 billion yen (damages to aquaculture products
are included). The damages are severe, as the stricken areas are major producers of wakame
(seaweed) and oysters.
Great East Japan Disaster: Damages to fisheries ②
Catastrophic damages to wakame (seaweed) and oyster
aquaculture, which are among the major products of the
stricken areas (especially Iwate and Miyagi Prefecture)
Damages to aquaculture
facilities were
recognized in the
following 15 prefectures.
(Hokkaido, Aomori,
Iwate, Miyagi,
Fukushima etc.)
A damaged oyster processing
facility (Ishinomaki City).
* The estimation of damages is as of May 5, 2011.
(The damages are predicted to increase, as situations are more
comprehensively revealed)
* Share of stricken areas in national production of
seaweeds and oysters.
5
Other
stricken
prefectures:
13 %
Others:
8 %
Others
67 % Other stricken
prefectures :
4 %
Iwate prefecture
Miyagi
pref.
35%
Production of
cultured
oysters
(2009 fiscal
year)
Miyagi
prefecture Production of
cultured
wakame
(seaweeds)
(2009 fiscal
year)
Iwat
e
pref.
35%
(Source) Fisheries Agency
For Strategic Approach
How to rehabilitate and reconstruct those affected
society and people is still a controversial issue.
What strategic and comprehensive approaches are
appropriate to fit in with local reality?
6
Suggestions and Recommendations:
1) "Towards Reconstruction: Hope beyond the Disaster” The
Reconstruction Design Council (25 June)
2) "Master Plan for Reconstruction of Fisheries" Fisheries Agency
(28 June), etc
Experiences and lessons learnt through the recovery process
in Sumatra Earthquake and Indian Ocean tsunami may
provide a profound insight
Our questions
Tremendous efforts and donations have been put into
the rebuilding and restore of tsunami-affected coastal
society.
Is “Building back better” achieved?
Rehabilitation and rebuilding programs effectively
worked for those who survived in order to empower to
reshape the future and redevelop their way of life ?
(BRR 2009)
Lessons learnt can be adopted in the recovery of Great
East Japan Disaster in 2011
7
Damage and Loss by Sumatra Earthquake and Great Indian
Ocean Tsunami
8
Community center for evacuation, Aceh in Sumatra
Seven years have passed!
On 26th December 2004, a Sumatra earthquake
and a series of great tsunamis heavily struck to
many parts of Asian coastal communities.
This disaster caused an unprecedented loss of
life, and damaged a foundation of coastal
communities.
In the wake of disaster, an enormous number of
affected people lost their livelihood, society, and
culture. 9
Coastal communities were seriously damaged
Major parts of coastal area affected were fishing
communities, and many of the victims were fishers and
their families.
Economic loss in fisheries industry was massive.
Livelihood of fishing village was been destroyed.
Sustainable resource management was lost or
damaged.
FAO (2005) declared that fishers and local people have
rights to access marine resources as it was always in the
past. 10
Damage and loss
11
Unit: person
Nation Dead Victems
Indonesia 167,540 566,898
Sri Lanka 35,322 519,063
India 16,269 647,599
Thailand 8,212 n/a
Others (10 countries) 555 34,700
Total 227,898 1,768,260
Table 1 Lost of Life and Victems
(source)Jayasuriya, S. & McCawley, P. 2008. Reconstruction after a Major Disaster; Lessons fromthe Post-Tsunami Experience in Indonesia, Sri Lanka, and Thailand, ADB Institute Working PaperNo.125
Towards Sustainable Growth of Fisheries Industries and Coastal
Community
12
Toward Self-reliance
Most of tsunami-affected countries had an emergency
support and a 2~5 year recovery plan. Most of supports
have already terminated.
First stage: emergency support was provided.
Second stage: temporary housing or reconstruction of
permanent houses was started.
Last stage: development of physical and social
infrastructure was undertaken.
Enormous effort to support recovery of livelihood with
microfinance, technical assistance and capacity building
program. These would ensure the long-term
sustainability of any program activities.
13
Fig. Recovery Process: Livelihood Improvement and Development of Social Capital
“Build back better” in tsunami-affected community
Immediately after the disaster, donors provided emergency
support. They prepared houses, and shifted to physical and
social infrastructure. While decreasing involvement,
people and society increase self-dependence.
(Source) Author illustrated by referring to Rehabilitation and Reconstruction Agency (BRR, 2005),.
2010
Self-dependency
Donor support
14
Final goal of people in affected society
Restoration of livelihood and its sustainability
Means of production such as fishing boats and
gears were provided and/or reinvested by
themselves. Fisheries facilities and processing plants
were also repaired and rebuilt.
Guarantee of permanent houses and stable
community
This could not be overemphasized, although the
location became a problem in connection with a zoning
policy, etc.
15
Confusion and Conflict in Restoration and Reconstruction
Confusion and conflict the process of restoration
and reconstruction originated from peculiar
characteristics of fishers’ livelihood, social
classes, and fisheries industry.
Research and study on fisheries industry and
fishing community are much less, in comparison
with agricultural sector and rural society.
A plan for restoration and reconstruction, made
with adoption of top-down approach, always
became a controversial issue. 16
Declaration on conservation and zoning by LGU: in Phannga, Thailand17
Ex. Zoning coastal area, relocation of communities, etc.
A zoning policy on coastal areas affected by
tsunami was the most severe conflict.
Many countries took enforcement measures on
removing any structures including temporary
houses and plants, outside a certain fixed
distance from the seashore.
Illegally building houses and plants were
regarded as a social right and custom.
Introduction of the coastal zone management
and enforcement of laws caused conflicts.
18
Right: All houses were cleaned up.
Fishers are not allowed to resettle.
Left:New settlement for fishers
from the beach (below).
Fishers have to move to the
higher elevated area.
(Thailand)
20
Ground zero in Aceh: Ulele was completely destroyed by tsunami.
New houses were constructed close to the sea. Evacuation center
Was constructed with JICA’s support.
Reconstruction Plan
(National level)
Communitycommunity
Community
Province/ State
(Regional level)
Support &
coordination
NGOs
(abroad)
NGOs
Figure Plan for Support
conflict
Conflict
A community-based and community-driven approach to rebuild society
Supporting and donor agencies would avoid to adopt
top-down approach which might not fit in with local
reality. Communities and people would reduce over-
dependence on the donor agencies.
Not many communities could have worked effectively in
the rebuilding of society, where leaders were dead and
missing.
Local government units (LGUs) did not work effectively,
although they were expected to play an important role in
emergency and recovery activities.
22
Comprehensive approach to reconstruction of fisheries industry
Comprehensive approach is required for the recovery of
fishery industry. Donor agency and tsunami-affected
society focused more on the rehabilitation of fishing and
aquaculture, than infrastructure, processing and
marketing.
Fishers and families were target, while processers and
traders were often neglected. Small-scale fishers were
mainly supported with provision of small-scale fishing
boat, gear, and equipment.
Support to processing and marketing would have given
more impact the rehabilitation of fisheries sector, and
accelerate its reconstruction.
23
How to avoid dependency syndrome (for supporting agency and society)
A “dependency syndrome” is a wide spread phenomena
throughout the tsunami-affected areas.
Society, culture and even sprit of people have been
affected by this syndrome. Changed structure of society
and influenced people’s behaviors, after the 2004
disaster.
Local government and community heavily depended on
budget allocation and personal from central, and donors.
24
Rely on Community-based Organizations (CBOs) and People’s Organization (Pos)
Government and donor agencies encouraged people to
organize community-based organizations (CBOs) and
people’s organizations (POs), whatever the type.
Cohesion among people directly reflects the success and
failure of rehabilitation, reconstruction with self-reliance.
In Indonesia, traditional fisheries management groups act as
a representative of affected local society and people,
instead of local administrative unit (LGU).
25
Social capital works as before?
Marketing network becomes fragile. This is an obstacle
to recovery of market-oriented livelihood, such as
fisheries and aquaculture.
Technology and local knowledge are not much available
as before. People feel loss of social identity.
People had developed various forms of social networks
facilitating co-operation and mutual help. Without them,
they would be vulnerable vis-à-vis social disorders and
insecurity.
26
People’s organization and social capital
Development of social capital facilitate community-based
groups and associations.
People’s participation in the recovery process of social
network and trust among community members.
Leaders and their leadership skills are essential to create
strong community networks.
In a new settlement, fishers and people make effort to
establish people’s organization and strengthen social
capital. This is an appropriate measure to evaluate level of
restoration and reconstruction.
27
Symposium
Focus on Recovery of Livelihood and Participatory Approach to
Reconstruct Community
28
Goal of Symposium
This symposium is to identify an effective way how
affected people and coastal society could restore
livelihood and reconstruct community.
Community-based and community-driven approaches
are focused, referring to development of social capital,
strength of social networks and level of cooperation
among re-settlers in tsunami-affected coastal
communities (and in new settlements).
Lessons and experiences will be included into
suggestions and recommendations for the recovery of
fisheries industry and coastal communities affected by
Great East Japan Disaster in March 11, 2011.
Indonesia
Thailand
Phannga province (Klongkien, Ban Nam Ken)Issues: Social capital, donor dependency, struggles of
new communities, overuse of resources, impacts of
social zoning , local governance, etc.
Kurabi province (Khaotong, Ao Luk Noi))
Issues: Social capital, microfinance for livelihood,
institutional arrangement of sustainable resource
utilization, overuse of resources, recovery of
coastal environment , etc.
Banda Ache (Krungraya Bay)Issues: Social capital, donor dependency,
traditional community-based network, cultural
changes , struggles of new communities, etc.
Topics today (Thailand and Indonesia)
30
Program Symposium consists of four sessions.
1) Indonesian session
2) Thai session
3) Discussion
4) Special session for making suggestions and
recommendations.
Special sessions will be held on December 10. With
guest speakers, an executive summary with
suggestions and recommendations will be described.
December 9
Thank you for your attention.