Upload
balan-palaniappan
View
215
Download
0
Embed Size (px)
Citation preview
7/28/2019 svv_refcase_757446_lrena.pdf
1/8
Power system and automation reerenceEnhanced power delivery reliabilitythrough network automation
Relion
7/28/2019 svv_refcase_757446_lrena.pdf
2/82 Power system and automation reerence | Enhanced power delivery reliability through network automation
Enhanced power delivery reliabilitythrough network automationSavon Voima Verkko Oy implementsABBs zone concept
Savon Voima Verkko Oy is a wholly-owned subsidiary
of Savon Voima Oyj. By the end of 2010 Savon Voimas
power distribution system had some 110 000 user
locations and some 2 600 customers were connected
to the district heating system. Within the investment
framework for enhancing the reliability of the power
delivery Savon Voima has systematically increased thelevel of automation in its power system. Protection zones
according to ABBs zone concept have been introduced
into the network and the substation protection equipment
has been renewed using IEC 61850 compliant 630 series
feeder management IEDs of the Relion product family.
The connection to ABBs MicroSCADA Pro and DMS 600
system has been secured using COM600 substation
automation devices.
The power d istribution system o Savon Voima covers an area
o 40 000 square kilometer, roughly the size o Denmark, with
a total line length o 25 000 km. The medium voltage network
is mainly composed o overhead line eeders, which count
or some 10% o the entire overhead line network in Finland.
The Savon Voimas network comprises thirty- ive 110/20 kV
and three 45/20 kV substations. Distribution management isextensively used in the power system o Savon Voima. The
entire substation base o the power system is connected to
the MicroSCADA Pro and DMS 600 system. Furthermore,
protection zones have been added to the network by installing
remote controlled reclosers on lengthy eeders. Adding
automation is a ast and cost-eective way o enhancing the
reliability o supply o the power system.
Flexible technological solutions
At the new Pellesmki substation REF630 eeder management
IEDs have been installed in ABBs Unigear switchgear. On thesubstation level an IEC 61850 substation automation bus has
been implemented. Besides the eeder management IEDs,
a SACO alarmsystem, the COM600 substation automation
The IEC 61850 substation automation bus solution and its connection to the ABBs MicroSCADA Pro and DMS 600 of the Pellesmki substation.
MicroSCADA Pro
DMS600
IEC 60870-5-104 IEC 60870-5-104
COM600
REF630 REF630 REF630 REF630 REF630 REF630 REF615RET 543
TCP/IP
IEC 61850
REF630 REF630 REF630 REA 101 SACO 16 REG-DPA
7/28/2019 svv_refcase_757446_lrena.pdf
3/8Enhanced power delivery reliability through network automation | Power system and automation reerence 3
device, all by ABB, and a Petersen-coil regulator by
A. Eber le GmbH & Co. KG have been connected to the bus.
The implementation o the IEC 61850 standard on the
substation level enables a smooth interconnection o
substation devices rom dierent suppliers. One o the
strengths o the standard is that it is not a proprietary
standard o a particular device manuacturer. The entiretranser o inormation at the Pellesmki substation is routed
through the IEC 61850 bus. In industrial automation data
transer buses have been used or years. It is exciting that
the development in network companies also is heading in
the same direction. The IEC 61850 standard is an important
milestone in this ongoing development, Matti Pirskanen,
substation engineer at Savon Voima, states. Savon Voimas
network currently comprises six substations based on the
IEC 61850 standard and in the uture all new and retroit
substations will be designed according to the standard.
ABBs 630 series eeder management IEDs are reelyconigurable devices that can be lexibly conigured to suite
the intended application. The reely conigurable eeder
terminals, on their part, support our companys long-term
investment program. The conigurability enables us to not
just adapt to the networks current state, but also to uture
changes in the power system, Matti Pirskanen states.
We know right now that the network will incorporate wind
power in the near uture, that isolated overhead lines will
become common and that the degree o cabling o the power
system will increase. In the realization o the Pellesmki pro-ject one aim was also to allow or these oreseeable changes,
Pirskanen continues. In the planning phase, or instance, the
REF630 eeder management IED confgurations were prepared
or directional overcurrent protection, phase discontinuity
protection and intermittent earth-ault protection.
Total control of the whole network
All o Savon Voimas substations and remote contro lled
reclosers are connected to ABBs MicroSCADA Pro and
DMS 600. Our network is geographically widespread.
Securing high delivery reliability in this type o a networkcalls or an extensive implementation o automation.
The DMS 600 distribution management system provides
immediate inormation about the current state o the network.
Matti Pirskanen and Sami Viiliinen of Savon Voima Verkko Oy.
7/28/2019 svv_refcase_757446_lrena.pdf
4/84 Power system and automation reerence | Enhanced power delivery reliability through network automation
Among other th ings, we use DMS 600 or ault locat ion
tasks and relevant reporting. Without automation the
interruption times caused by ault instances would be too
long, Matti Pirskanen describes. In the uture, Savon Voima
plans to also use data collected rom remotely readable
meters at the customers premises or ault location.
The solution oered by ABB, where MicroSCADA Pro andDMS 600 are integrated into one package, is an excellent
solution or us. I see it as an advantage that these systems
come rom one and the same supplier. The systems cooperate
seamlessly also ater updates have been perormed to just
one o the systems, Matti Pirskanen summarizes.
The use o automation and a rel iable data transer network
go hand in hand. Savon Voima relies on its own data transer
network. The network is a so-called radio link network with
ring topology. The data transer between the substations and
the SCADA/DMS uses the IEC 60870-5-104 protocol.
The most important eature o the data transer network isits availability. Thereore we have invested in redundant
solutions and an adequate data transer capacity. Despite
the high capacity it is not a realistic option to transer all
data rom the substation level to the MicroSCADA Pro and
DMS 600. On the substation level we use COM600 station
automation devices. Through this solution we can lexibly pick
those network data collected by the protection relay system
that are essential rom the SCADA/DMS point o view, such
as e.g. network ault location calculations rom the REF630
eeder management IED, Matti Pirskanen describes.
Improving delivery reliability through automation
The main principle o the zone concept is to con ine the im-
pact o a network ault to as limited an area as possible.
A ault in the d istr ibut ion network oten inter rupts distribution
along the entire eeder and to all the consumers connected to
it. Integrating protection and reclosing unctions deeper into
the network directs reclosing unctions and interruptions
selectively to the problematic parts o the network. Thus
distribution interruptions on other sections o the network are
avoided. To do this, the eeder is divided into sections, also
known as zones. Savon Voima is among the irst network
companies in Finland to systematically implement the zoneconcept on a large scale.
By inserting reclosers the size o the protection zones o the
network can be reduced and the eects o the disturbances
limited to aect just a smaller group o customers. In practice
this means a reduction in the number o interruptions and the
interruption times experienced by the customers, Sami Viil-
iinen, development engineer at Savon Voima, explains.
For the implementation o the zone concept throughout the
distribution network o Savon Voima the insertion points orrecloser stations investigated eeder by eeder or the whole
network. In this so-called potential study the insertion o one
or two reclosers was ound to be commercially justiiable in
about one third o the some 300 eeders o the utility.
By orming a more accurate technical reliability model or
individual line eeders the most proitable location points or
reclosers and the eects obtained by reclosers can be
analyzed more accurately than with more simple potentialcalculations. In the planning process, however, the total
eects o the solutions must be noticed also on the rest o
the examined network. By means o the overall zone concept
thinking, or instance, the power quality key igures are
improved and the number o aults is reduced and the
interruption times are shortened on the zones ormed on
the line eeder, Sami Viiliinen discloses.
In the Konnuslahti pilot object, ABBs remote controlled
recloser station was inserted on a 106 km long eeder having
a total mean load o 700 kW. In the supply direction the
insertion point splits the eeder into zones. The insertion pointwas urther chosen in such a way that 65% o the mean
power o the eeder was located upstream o the station
and thus out o reach o aults arising on the eeder section
downstream o the recloser station. The mean powers o the
- 5 000
0
5 000
10 000
15 000
20 000
25 000
30 000
35 000
The potential profitability of reclosers as per line feeder.
Interruptioncosts,netsavings(/year)
Line eeders
Konnuslahti
7/28/2019 svv_refcase_757446_lrena.pdf
5/8Enhanced power delivery reliability through network automation | Power system and automation reerence 5
line sections downstream o the reclosers amount to about
18% and about 17% o the mean power o the eeder.
The addition o recloser stat ion in the pilot object has a
substantial impact on the quality o the power distribution
as experienced by the customer. In the planning phase the
reduction o interruptions upstream o the recloser station
was as high as 60% and on both line sections downstream
o the station about 30% each, based on the reliability
calculation models that were used. The improvementexpected to be reached over the whole line eeder in energy
weighted interruption igures was about 50% and even
about 20% in ault interruption times.
The zone concept is also a cost-eic ient solution or
enhancing the delivery reliability o rural power distribution
networks. In the pilot network o Savon Voima the calculated
34% saving in interruption costs can be obtained with 13%
lower lie-cycle costs than in the initial state. The practical
experience o the recloser station set up a ew years ago has
been positive. This encourages us to continue on the chosen
path. Today there is an installed base o some 20 remotecontrolled pole-mounted reclosers and ive recloser stations.
In the coming years some 60 pole-mounted reclosers will
probably be installed and another 20 recloser stations,
Sami Viiliinen anticipates.
43 km
Recl. 1
Recl. 2
110/20 kV
30km
33km
Location of the Konnuslahti recloser station on the line feeder. One o the oreseeable zone concept investments will be
or the new Pellesmki substation. All along the 106 km
Pellesmki eeder standardized ABB recloser station will be
located. The unctionality o the station comprises protection
and control, also including e.g. auto-reclose unctions.
The station is provided with two remote controlled reclosers
and an arc ault resistant switchgear system with integratedisolation and earthing devices.
The insertion point o the recloser stat ion has been chosen
such that the ault prone line length downstream o the
recloser station will be considerably reduced. In the new
situation 23% o the total mean power o about 813 kW o
the eeder alls upstream o the recloser station and 27% or
50% alls on the eeder zones downstream o the reclosers.
O signiicance or the selection o the location point is that
now aults are produced on a just 66 km long section
(26 km + 40 km) downstream o the recloser instead o on
a length o 106 km in the beginning. The calculated paybackperiod o the investment is about our years.
Our goal is zero fatal accidents
The goal or the power system maintenance and
construction unctions o Savon Voima is zero severe
accidents. Personal saety and security have always been
put in ocus. Already in the 1990s we took a decision that
all new substations would be equipped with arc ault
protection. We also carried out an updating project o our
substations, during which we installed arc protection systems
also in all old substations. In the Pellesmki substationwe installed ABBs REA arc ault protection system,
Matti Pirskanen reveals. Electrical saety and saety at
work aspects are emphasized even more nowadays, as
maintenance jobs and construction work to a large extent
have been outsourced. The number o actors in the power
system ield is constantly growing. As a network owner we
must be able to assure saety at work and power system
security under all situations. Besides instructions and
guidance it is important that risks caused by human errors
also are taken into consideration in the protection system
o the substation. We have been spared rom serious
consequences because o the extremely ast operation othe arc protection system, Matti Pirskanen summarizes.
Parameter
Interruption time*
Number o interruptions*
Interruption costs (CIC)**
Lie-cycle total costs
The impact of the pilot object on the energy weighted key figures,
interruption costs (CIC) and the economical profitability of the investment.
* The interruption time and number o interruptions are energy weighted key fgures othe power quality.
** Reducing CIC-costs (customer interruption costs) means that the delivery reliability
improves correspondingly.
Impact
- 20%
- 50%
- 34%
- 13%
7/28/2019 svv_refcase_757446_lrena.pdf
6/86 Power system and automation reerence | Enhanced power delivery reliability through network automation
Network automation solution
Embedding the communication solutions deep in the
network structure and including all the central equipment
into ABBs MircoSCADA Pro and DMS 600 enable the
effective use of the entire network. Disturbance situations
can be resolved effectively with the help of accurate
fault locating and DMS functions. In case of a fault,
the reclosers with versatile protection capability
automatically perform fast, zone-discriminative fault
disconnection. In case of major disturbance, the zone
division significantly facilitates the use of the network.
The operative actions can be performed in a safe way,
and the use of earthing switches ensures secure and
reliable earthing in all network situations.
Wind power plant
Pellesmki
110/20 kV
Unigear switchgear, REF630 feeder management
IEDs and REA arc protection system
Station automation device COM600
110/20 kV
7/28/2019 svv_refcase_757446_lrena.pdf
7/8Enhanced power delivery reliability through network automation | Power system and automation reerence 7
MicroSCADA Pro
Hydro power plant
Network Control Center
Distribution Management System
DMS 600
Data communication
network IEC 104
Pole mounted recloser
Recloser station
7/28/2019 svv_refcase_757446_lrena.pdf
8/8
Contact us
1MRS757446
C
opyright2011ABB.
Allrightsreserved.
ABB Oy, Distribution Automation
P.O. Box 699
FI-65101 VAASA, Finland
Phone: +358 10 22 11
Fax: +358 10 22 41094
www.abb.com/substationautomation