8/19/2019 NDTbkpngENG
1/8
PNG Drilling Company: New Drilling Technologies
8/19/2019 NDTbkpngENG
2/8
PNG Drilling Company: New Drilling Technologies
New Drilling Technologies Reducing Risks of Wellbore Integrity Loss: MPD & CCS
Introduction
One of the important aspects of oil & gas well drilling is early prevention of troubles related to kicks
or losses during bore hole drilling.
Such troubles are caused by undesirable depressions (or repressions) arising in the course of
drilling as result of mud bore hole column pressure excess or reduction against reservoir pore
pressure.
Such situation may take place in the following cases:
• bore hole mud column height drops as a result of catastrophic mud losses;
• loss of borehole fluid column weight resulting from gas kicks onto the well;
• mud flowing pressure decrease (during tripping operations, forced downtime caused by
drilling equipment failure etc.);
• over-balanced or under-balanced well completion;
• mistakes in forecasting (calculating) formation (pore) pressures, loss and fracture
pressures (drilling conditions compatibility zone identification) etc.
Today, to prevent the above complications traditional methods are used: mud weight (density)change using chemical additives, running intermediate casing strings for incompatible formation
isolation etc. However, such conventional methods require, on the one hand, considerable non-
refundable tangible costs, on the other hand, those methods lack operational flexibility as, e.g.,
mud weighting up or weight reduction require time and considerable labor input. Moreover, it is not
always possible to overcome complications arising in the course of drilling solely by means of mud
control, sometimes this is not sufficient.
PNG Drilling Company offers efficient additional technologies and tools of the said problem
solution based on best international practices and know-how of complicated well drilling including
but not limiting to offshore drilling.
The key point of the offered technologies is the use of dedicated non-conventional wellhead
equipment set, complex design manifolds, special drill pipe subs and software. It should be noted
that PNG DC technologies do not replace but rather complement operator or contractor outfit with
new highly efficient means for complicated well drilling.
PNG Drilling Company offers 2 (two) new techniques that may be used both jointly and separately
from each other:
• Managed pressure or underbalanced drilling (hereinafter – "MPD")
8/19/2019 NDTbkpngENG
3/8
PNG Drilling Company: New Drilling Technologies
• Mud continuous circulation system (hereinafter – "CCS").
The offered techniques have been developed by PNG DC jointly with European equipment
manufacturers and have foreign analogues (NOV, Aker Solutions, ENI, Halliburton, Schlumberger,
Weatherford, MPO Companies), the said analogues being mainly applied in offshore drilling (Gulf
of Mexico and Persian Gulf, Caspian, North and Mediterranean Seas).
Application of the offered technologies enables to essentially mitigate risks of well control loss in
the course of drilling and the related therewith secondary risks. At the same time, the said
technologies are cheaper than traditional solutions and techniques applied in Russia.
Fig. 1 below presents schematically our MPD and CC systems' allocation on drill site. The blue
lines represent high pressure (HP) delivery line from mud metering tank to vertical manifold andtop drive (mud circulation great circle). Green lines show HP delivery line branch from complex
design manifold to CCS hydraulic power arm, see Fig. 4 below (mud circulation minor circle). Black
lines show return line from rotating BOP to Circulation System through mud gas separator (optional
- on request).
MPD and CCS functioning logic is presented herein below.
Schematic presentation of well inlet and outlet lines, choke controllers, other monitoring systems
including MPD and CCS control panels are shown in the diagram (see Fig. 3 below).
Fig. 1. Drilling rig simplified schematic with new system and techniques' elements
8/19/2019 NDTbkpngENG
4/8
PNG Drilling Company: New Drilling Technologies
Brief Technology Description
1. Managed Pressure & Underbalanced Drilling (MPD)
This technique application is recommended for drilling in the so-called narrow window zones when
gradient curves of formation (pore) pressure (Ppore), mud pressures (Рmud) and fracture pressures
(Рfr.) are close to each other (see Fig. 2 below).
Fig. 2. Evseevsky Field (Pre-Caucasian region) Geological & Technical Conditions and Exploration
Well Design
In such conditions, insignificant variations of mud density may cause either mud loss (Рmud > Рfr.) or
oil/gas/water kicks (Рpore > Рmud).
8/19/2019 NDTbkpngENG
5/8
PNG Drilling Company: New Drilling Technologies
This refers also to situations when it is difficult to forecast the presence and/or characteristics of
narrow drilling window zones because of insufficient geological data of drilling concession area.
Traditionally in such situations the first thing to do is to try to change mud weight/density (reducing
weight or weighting up) in order to balance pore pressure and well column mud pressure.
However, this requires additional time and, as experience has proven, sometimes it is too late to
take such measures. Then you have to stop drilling and deal with complications. There is high risk
of serious accidents.
The offered by PNG DC MPD technique uses dedicated sensors enabling every single moment to
monitor mud (a) density, (b) temperature and (c) flow rate in and out and to provide contractor with
corresponding information in on-line mode (Fig. 3 below).
Fig. 3. Diagram of wellhead equipment when using MPD technique
Contractor is informed of loss or kicks in well within less than one minute from the corresponding
event occurrence.
Dedicated electronic adjustable wellhead choke (located downstream of rotating BOP) enables
drilling contractor to adjust outlet well choke (from 0 to 100% opening).
8/19/2019 NDTbkpngENG
6/8
PNG Drilling Company: New Drilling Technologies
In this way, drilling contractor has the possibility to change immediately bottom hole pressure by
means of (i) fully opened inlet valve (delivery line manifold), on the one hand, and (ii) partly closedby choke regulator outlet valve, on the other hand. The difference between mud flow rate in and
out creates fluid column adjustable hydrodynamic pressure onto open bore hole and onto bottom
hole.
2. Mud Continuous Circulation System (CCS)
Even short interruption of mud circulation may cause potential geological complications in the
course of drilling.
In drilling practice, forced interruption of mud circulation, as a rule, takes place during tripping
operation performance. Even when drilling using top drive, in the course of making up or breakingin connection, circulation may stop for up to 10 minutes and more. In case of top drive breakdown,
swivel failure, circulation may stop for a longer time.
Requirements to bottomhole cleaning process and mud circulation are even much more stringent
in offshore drilling. A wellbore left without mud circulation for 10 minutes and more, is subjected to
serious risk of caving-in, borehole wall collapse, tool sticking and even well control loss.
In current Russian drilling practice there are no industrially tested methods ensuring continuous
mud circulation.
Continuous circulation technique enables drilling contractor to provide uninterrupted mud
circulation without stopping to make up connections or to perform tripping operations.
CCS comprises:
• complex design manifold with control station and control panel,
• hydraulic power arm mounted on a pedestal on drilling floor with a dedicated jaws to catch
DP and mud insulation packer (see Fig. 4),
• Dedicated subs with valves screwed on every DP or DP stand (see Fig. 4 below).
Depending on the type of operation being performed (well drilling or tripping), CCS directs mud
flow via complex design manifold from mud pumps along (A) great circle (see Fig. 1 – blue color)
or along (B) minor circle (see Fig. 1 – green color).
(A) great circle circulation (blue lines in Fig.1) is effected during well deepening via complex design
manifold to the top drive (swivel).
(B) minor circle circulation (green lines in Fig.1) is effected during drill string connections or other
tripping operations. In this case, the same complex design manifold directs mud flow via hydraulic
power arm to a dedicated sub screwed onto DP the latter being at that time off-loaded on rotor
slips.
8/19/2019 NDTbkpngENG
7/8
PNG Drilling Company: New Drilling Technologies
Further on, upon connection completion and special drill pipe torqueing, operator retracts the
hydraulic power arm away from the dedicated sub and the complex design manifold directs mudflow along the great circle. The sub with a back pressure valve system is run with every DP (or DP
stand) into bore hole.
In this way, mud circulation through borehole doesn't stop even for a minute, which fact essentially
mitigates the risk of wellbore integrity loss.
Fig. 4. Hydraulic power arm with a packer and dedicated DP sub
8/19/2019 NDTbkpngENG
8/8
PNG Drilling Company: New Drilling Technologies
Conclusion
PNG Drilling Company in cooperation with European manufacturers of drilling equipment has
developed efficient techniques of risk mitigation in oil and gas well drilling, the said techniques
being new for the Russian market.
PNG DC technologies ensure continuous mud circulation irrespective of operations' type as well as
managed pressure drilling achieved by means of in-process monitoring and regulation of
backpressure in wellbore while drilling through narrow drilling window zones.
PNG DC offers application of new technologies as an individual service at moderate day rates
comparable with top drive rental rates.
PNG DC technologies provide operators and contractors with additional toolkit for emergency
situation prevention in complicated oil and gas well construction.
Recommended