Upload
raji-murugan
View
5
Download
0
Embed Size (px)
DESCRIPTION
dfs
Citation preview
5/24/2018 06021756
1/4
2011 International Conference on Electrical Engineering and Informatics
17-19 July 2011, Bandung, Indonesia
In-Service Early Indication of 500 kV Circuit
Breaker Function Loss Operated in PLN P3B
Jawa Bali IndonesiaY. Wibisana,R.Setyo Wibowo,H. Maryono
PT. PLN (Persero) P3B Jawa Bali- Jakarta
PT. PLN (Persero) P3B Jawa Bali RJBR, Jl. M TOHA Km 04 Bandung, [email protected]
[email protected]@pln-jawa-bali.co.id
Abstract Since year of 2004 PLN P3B Jawa Bali has beenchanging its maintenance strategy from time based to the
combinations of time-based and condition-based maintenance.
Currently, as part of the new strategy PLN P3B Jawa Bali has
been implementing a visual inspection and early indication of
equipment function loss by using visual inspection, in-service
monitoring and on-line measurement.
. This early indication uses critical failure modes of visual
inspection item and thermovision as its input. The critical failure
modes are identified by using FMEA /FMECA which were
developed based on statistical data and engineering senses. The
output of the early indication are either 1,6 or9 in which 1
represents bad, 6 fair and 9 good conditions. By using this in-
service early indication of function loss, we will able to obtain
symptoms to equipment failure earlier.Keywords circuit breaker, in-service early indication of function
loss, fmea/fmeca
I. INTRODUCTIONIn order to improve the quality of maintenance, availability
and reliability of electrical energy supply and reduce the
maintenance costs, PT PLN (PERSERO) Jawa Bali has
changed its maintenance strategy for both primary and
secondary equipment. Among others, condition-based
maintenance (CBM) strategy of circuit breaker (CB) has been
introduced to reduce time-based maintenance (TBM) scheme.
Figure.1 Maintenance concept
The goal of Maintenance improvement in P3B Jawa Bali is
for minimize Time Base Maintenanceand, corrective
maintenance and then to maximize the job function ofsubstation operator, this time the operator have a bigger
portions operational function its like recorded current,voltages
and load. In future we want to changed the paradigm and
mindset of substation operator for maximized maintenance
function . Maintenance function are covered visual inspection
and reporting the anomally by the CBM application that we
developed beside still recorded the currents, voltages and
load,.
In the past years, TBM was proven to be ineffectively
reduce system faults. In TBM the circuit breaker was
measured and maintained once a year . In 2008 the period was
extended to 2 years. Unfortunately in some occasions some
faults occurred after the maintenance have been done. Besidethat we must spend for TBM cost every year.
According to P3B Jawa Balis equipment database in,
32.52 % of CB total population has technical lifetime of 16-
20 years. 500 kV CB is one of the most crucial because 500
kV transmission system is the backbone of electrical energy
supply. Based on these reasons, we will focus on in-service
early indication of 500 kV CB, in particularly the
implementation on inspection level 1 (visual inspection).
Figure. 2 Technical lifetime distribution of 500 kV CB.
Years
E14 - 7
978-1-4577-0752-0/11/$26.00 2011 IEEE
5/24/2018 06021756
2/4
II. FMEAA large number of CB types are installed in PLN P3B Jawa
Bali. In order to simplify the analysis we classified the CB
based on its operating voltages. For further development CB
will be classified based on its type.
In analysing the failure mode and effects, CB is defined as
one system. Furthermore, it is divided into five subsystems
based on its function, namely primary, secondary, dielectric,
driving mechanisms and supporting part subsystems. For each
subsystem we define its failure modes and the root cause(s) of
each possible and occurred failure modes. The failure modes
of each CB subsystem are used as a reference in developing
and optimizing the maintenance programs because the
program not only focuses on the most critical subsystem, but
also the most critical failure mode.
The symptoms of possible failures of each subsystem are:
Primary - Damage due to excessive cumulative interrupting
duty, overheated contact, overheated clamp, objects attached
on clamp (kite), floating contacts, capacitor and resistor
breakdown.
Secondary Loss of power supply, moisture in control box ,
shorted circuit coils, abnormally fan heating, short circuit of
control cable, or open circuit from termination failure,
corrosion termination.
Dielectric Broken insulator chamber, contaminated oil, oil
leakage, low pressure of SF6and low pressure of air blast
Driving mechanism - Mechanical issues such as faultylinkages, faulty latches, ageing seal, pipe leakage and
malfunctions of spring, pneumatic or hydraulic system. These
problems may either gradually degradation, or rapid
development from a component failure.
Supporting part Sloping foundation, broken support
insulator, broken steel/concrete structure and grounding
problems.
III.FMECAAfter performing FMEA and finding the root causes of
failures, we continue to conduct FMECA. A failure mode is
considered to be critical if its risk level is high enough,according to the utility. We need to calculate the probability
and effects of each failure mode to determine the most critical
failure mode of a circuit breaker. The failure probability are
obtained from statistical failure information which were
collected from a brainstorm sessions of engineers, corrective
maintenance data and failure record. PLN P3B Jawa Bali hasbeen developing an application that record all failures
occurred in the transmission system, namely FOIS (Forced
Outage Information System). In this analysis we use failure
record data from 2008 until 2010.
In calculating the effect of each failure modes, we use four
four criteria which is described hereafter.The score of each effect is defined based on the result of
the brainstorm sessions and discussion within switchgear
working group.
FREQUENCY
Score Frequency1 Rarely (30%)
SAFETY
Score Frequency
1 No life threatening
7 Life threatening
ENVIRONMENT
Score Frequency
1 No impact
3 Easy to clean / treat
5 Need work to restore
SYSTEM
Score System outage
1 No system impact
2 8 hours
3 > 8 h dan 32 h
4 > 32 h dan 7 days
5 Total out of operation
CORRECTIVE COST
1 Minor (300 MRp)
A. Scores of FMECAThe scores in FMECA is obtained by multiplying the
probability to the effects, as shown in the following formula.
Risk = Probability x Effects (safety + environment + system +
corrective cost)
The accuracy of this calculation is verified by mapping the
calculated risk on a risk matrices as shown on figure below.
Ideally, the calculated risk should be spread evenly .
Otherwise, the score of each criteria should be adjusted .
5/24/2018 06021756
3/4
Figure.3 Risk metrics
The list of critical failure modes and components are hence
used to create a checklist items of In-Service Early Indication
and inspection period. We classified the inspection period into
daily, weekly, monthly and annually, depend on how critical
is the failure modes and the components are.
The inspection period of In-Service Early Indication on CB
are:
annually or monthly if the risk is low risk monthly, if the risk is average weekly or daily, if the risk is high
IV.IN-SERVICEEARLYINDICATIONOF FUNCTIONLOSSCB
The In-Service Early Indication is intended to conduct the
inspection level 1 (visual inspection). It is conducted by
optimizing 5 (five) human sense and completed with some
simple monitoring tool, for example the binocular. In-Service
Early Indication of CB are including the visual inspection and
thermovision camera. Other critical components that are
impossible to be inspected through visual inspection has to be
measured through offline measurement.
The result of visual inspection of each component condition is
categorized into. normal condition and anomaly condition.
Then we scores these conditions by using the following
number: 1, 6 and 9. These number represents the following
conditions:
1 : bad condition 6 : fair condition 9 : good condition
The purpose of In-Service Early Indication 500 kV Function
Loss is to record anomalies of each component and initiated
maintenance recommendation.
In order to describe how the system works, we take the
inspection on driving mechanism subsystem as the example.
In visual inspection we monitor the spring condition. The
condition of spring is categorized into
9 ( good ): full charged: 1 ( bad ): not charged :
Note: there is no fair condition.
Another example is monitoring a grounding cable condition
of supporting part subsystem. we categorized the grounding
cable condition into:
9: normal, 6: corotion 1: loose,broken
In the following figure below showed the daily visual
inspection applications in 500 kV circuit breaker for SF6 and
spring mechanism type. We monitored pressure of SF6 and
spring condition.
Figure.4 Dailly visual inspection application
5/24/2018 06021756
4/4
After notifying the anomalies of the circuit breaker, we
determine:
Maintenance recomendationMaintenance recomendation is determined based on
bad or fair condition of a component
Time interval of maintenanceTime interval of maintenance is determined based on
ageing process knowledge and maintenance
experience
Maintenance recomendations are including :
o Simple maintenance which conducted by operator orSupervisor assistant of a substation
o Complex maintenance which conducted by amaintenance team
o On line minitoring that we called inspection level-2o Advanced inspection/measurement that we called
inspection level-3 . This inspection/measurement can
be either on-line or shutdown measurement
o Shutdown investigationIn-Service Early Indication of Function Loss in circuit breaker
that we called inspection level 1 (visual inspection) has been
implemented in PLN P3B Jawa Bali using an applications that
have been developed by PLN P3B Jawa Bali.
V. SUMMARIESAND CONCLUSIONS1. PT. PLN (Persero) P3B JB is in a way to change the
maintenance method by applying the CBM method .
2. The process of FMEA/FMECA will be evaluatedcontinuously and it still needs further knowledge todeveloping this complete CBM CONCEPT, BECAUSE this
paper only focusing on implementation on In-Service
Early Indication of Function Loss in circuit breaker.
3. Nowadays, In-Service Early Indication of 500 kV CircuitBreaker Function Loss has been implemented in PLN P3BJawa Bali and still needs improvement to developed the
application.
REFERENCES
[1] John Moubray, Reliabilty-centered maintenance, Secondedition ,May 2000.
[2] PLN P3B, Equipment assessment tools, October 2010[3] Frank de Vries, Frans de Rijke, Theo van Rijn, Review CBM
approach PLN General, KSANDR, February 2010.[4] Edwin R.S. GROOT, Edward GULSKI, Abe van DAM, Frank J.
WESTER Successful implemented condition based maintenanceconcept for switchgear, CIRED session, May 2003 ,paper no-14