    NATIONAL SOLIDARITY PROGRAMME

    MINISTRY OF RURAL REHABILITATION AND DEVELOPMENT

    ISLAMIC REPUBLIC OF AFGHANISTAN

    WORLD BANK

    IMPLEMENTATION SUPPORT MISSION

    OPERATIONAL UPDATE

    May 2011

  • 8/3/2019 20110514 - DoO's PPT

    2/18

    Key Achievements

    Key Performance Indicators NSP I&II NSP IIIA Total NSP I&II NSP IIIA Total NSP I&II NSP IIIA Total

    Communities Mobilized 22,371 175 22,546 77 4,484 4,561 22,448 4,659 27,107

    Communities Elected 22,371 196 22,567 77 4,109 4,186 22,448 4,305 26,753

    CDPs Completed 22,290 76 22,366 96 3,882 3,978 22,386 3,958 26,344

    Communities with SPP

    Submission21,950 13 21,963 235 3,931 4,166 22,185 3,944 26,129

    CDCs Financed 21,767 10 21,777 325 3,715 4,040 22,092 3,725 25,817

    CDCs with 100% BGE

    Utilization16,691 1 16,692 2,037 3 2,040 18,728 4 18,732

    Total Block Grant

    Entitlement to CDCs749$ 13$ 762$ 4$ 187$ 192$ 753$ 201$ 954$

    Total Commitment to SPs 722$ 0$ 722$ 12$ 155$ 167$ 733$ 156$ 889$

    Total Disbursed to CDCs 710$ 0$ 711$ 15$ 133$ 148$ 725$ 133$ 858$

    Total Expenditure 584$ 0$ 584$ 58$ 0$ 58$ 643$ 0$ 643$

    Subprojects Submitted 50,271 29 50,300 773 6,144 6,917 51,044 6,173 57,217

    Subprojects Approved 50,236 13 50,249 797 6,055 6,852 51,033 6,068 57,101

    Subprojects Financed 49,791 13 49,804 1,006 5,881 6,887 50,797 5,894 56,691

    Subprojects Financed 43,234 - 43,234 3,105 9 3,114 46,339 9 46,348

    As of 22 August 2010 Cumulative as of 20th April 201123rd August 2010 - 20th April 2011

  • 8/3/2019 20110514 - DoO's PPT

    3/18

    General

    y Focus on budget execution for 2nd semester of 1389

    y Intense procurement activity with regard to NSP III A FP

    procurement

    y Departmental and field office ToRs revised to suit changing

    face of the programme

    y Departmental and field office work plans and budgetsprepared for SY 1390

    y Need to revise NSPIIIA and IIIB community numbers and

    extend NSP III period

    y Exposure trips

    oED to Canada for Capacity Building Workshop

    oDoO to Australia for Public Sector Management

    Workshop

    oGHU & select field staff to India on Grievance Handling

    oHQ and FP select staff to Indonesia to visit PNPM

  • 8/3/2019 20110514 - DoO's PPT

    4/18

    Work Progress & Plans for NSP I&II

    Communities: End 1389

    Total 23,180 communities

    Category A: 18,557 (80%) all work completed

    Category B: 1,496: Another 967 will be completed

    by Sept11: Reminder 529 Category C: 2,027: Another 1,025 will be completed

    by Sept 11: Reminder 1,002

    C

    ategory D: 1,100: None will be completed by Sept11: Reminder 1,100

    Total communities not finishing work by Sept 11 =2,631

    Decision needed on this

  • 8/3/2019 20110514 - DoO's PPT

    5/18

    Work Plan for 1390: Overview

    NSP I&II: 1,992 communities in Categories B & C to be completed

    in 1st semesterNSP I&II to be transferred to NSP III: 2,631 communities

    1,531 of these expected to be completedby end of 1390

    1,100of these expected to be continued into 1391

    NSP IIIA:

    3,700 (1389) communities to complete 1 SP each andreceive 2ndBG tranche

    7,500 new communities expected to be mobilized of which

    4,000will receive 1stBG tranche

    NSP IIIB:

    6,000communities planned for 1strollout

    2,500of above to receive 1stBG tranche

    Summary:

    First semester: 15,823 active communities

    Second semester: 19,831 active communities

    Key Assumptions: Security, simple & quick FP procurement,

    sufficient funds in float accounts, simplifications in procurement

  • 8/3/2019 20110514 - DoO's PPT

    6/18

    Operational Manual Version Six (OMVI):

    Key changes from OM V proposed

    Revised CDC structural options Key subphases with clear timelines for mobilization:

    minimum requirements Annex on modus operandi in communities for 2nd

    round of block grants Annex on Gender Mainstreaming Annex on Linkages Increased ceilings for various procurement methods Increased training packages

    Gender segregated data Women CDC office bearer signatories on all forms FPs as CDC bank signatories Physical-cum-financial progress in subproject

    monitoring/reporting forms

  • 8/3/2019 20110514 - DoO's PPT

    7/18

    Cross-Cutting Issues 1/2:

    ESMF and Gender

    ESMF to be moved from Engg Dept to OD as a stand-aloneunit ToRs and trainings provided to focal points identified for ESMF New manual to be included in the OM Planning to consider wider aspects of ESMF in NSP

    Gender also to be considered one component of the ESMF International IC as NSP Gender Mainstreaming Advisor Consultancy firm being procured for Gender Mainstreaming

    Operationalizing and Training Packages MRRD GWG: NSP Participation: Draft MRRD Gender Policy

    NSP GWG: Areas being considered HRAS, CCDC NSP GOC: Set up in Dec 2010. Key Decisions: CDC form revisions, CDC structure, Staffing

    ratios, FP contracts for 2nd BG communities with incentive (partof FBS linked to female SOs), ranking of FPs to include

    indicator of female staff ratios and womens inclusion incommunities

  • 8/3/2019 20110514 - DoO's PPT

    8/18

    Cross-Cutting Issues 2/2: Capacity

    Building International IC TA being procured

    Draft concept for new Capacity Development Department within NSP Capacity development for NSP CDCs divided into soft and hard

    components Soft components: Community assessment, CDP preparation, saving box/

    self-help schemes, linkages Hard components: 12 defined and standardized packages

    Skills development at community level to be considered Consultancy firm to be procured for preparing standardized packages Cascade-down training approach to be further decentralized

    NSP to train FPs NSP Provincial staff and District managers atprovincial level

    Departments proposed functions:

    Core group of trainers for some packagesManage outsourced training package preparation and implementationMonitor and report on training inputs for FP field staff and

    CDC/community membersEvaluate impact of trainings based on small samples

    Database module and forms developed to include gender-segregated FP/

    CDC training inputs

  • 8/3/2019 20110514 - DoO's PPT

    9/18

    CCDC- JSDF Pilot

    Working group (including donor, NSP &FPs) established and functioning

    Work ongoing in 10 CCDCs in Rodat

    district in Nangarhar

    Womens inclusion and community

    procurement ceilings

    Procurement of external evaluation to beinitiated

  • 8/3/2019 20110514 - DoO's PPT

    10/18

    Key Decisions Needed

    Transfer of unfinished work of NSP I&IICommunities to NSP III: Implications,mechanisms

    NSP III to be expanded from 5 to 7 years: FA tobe amended at MTR

    Second round of block grants: CDCs/ CCDCs:

    Implications, mechanisms

    Simplifications in procurement: Especially FPproc for 2nd BG communities

  • 8/3/2019 20110514 - DoO's PPT

    11/18

    Financial Management

    FMRs prepared and submitted for 3rd and 4th QRs of1389

    FMA key staff replacement in February 2011 Revised draft MoU with DaB Float Account reconciliations

    Liaison with WB, MRRD Finance and MoF 160 FP payments processed through MoF worth US$

    26.3 million ____ BG installment requests processed worth US$

    160.1 million ____ operational payments processed worth US$ 19.1million

    32 Community financial management monitoring tripsundertaken covering 462 communities in 107 districts in

    24 provinces

  • 8/3/2019 20110514 - DoO's PPT

    12/18

    Procurement

    Procurement plan revisions taking into account widerchanges in the programme

    17 FP Contract amendments worth US$ 32.9 million forNSP III A Category 1 communities

    1 FP Contract amendments worth US$ 551,224 for NSP III A

    Category 2 communities Procurement underway for FP contracts worth US$ 2.5million for NSP III A Category 3 communities

    5 New National IC Contracts/ Amendments prepared worthUS$ 449,968.

    3 New International IC Contracts/ Amendments preparedworth US$ 493,404.

    ____ New Consultancy-firm procurements underway withestimated worth US$ 98,552.

    31 Contracts processed for goods, works, non-consultancy

    services worth US$ _____

  • 8/3/2019 20110514 - DoO's PPT

    13/18

    FP Management

    FP input monitoring forms prepared, reportingforms revised NSP I&II communities work progress by FP and

    district analyzed on monthly basis Analysis completed on NSP I&II communities to be

    transferred to NSP III 71 monthly NSP-FP Coordination Meetings held 1 to 13 rounds of bilateral FP review meetings held 29 monthly FP ranking sheets as per contractual

    milestone achievements released 319 FP invoices valued at US$ 19.8 million verified

    and processed

  • 8/3/2019 20110514 - DoO's PPT

    14/18

    M&E & MIS

    Support provided in procurement for mobile phonemonitoring consultancy firm

    Support provided in procurement for consultancy firm asthird-party monitor for high risk areas

    3 combined IM Reports produced covering 3537

    communities & 2,308 subprojects in 150 districts in 34provinces

    2 combined PIM Reports produced covering 858communities & 1898 subprojects in 93 districts in 31provinces

    2 combined CPM Reports produced covering 707communities & ____ subprojects in 132 districts in 21provinces

    3 NSP quarterly reports produced

    New modules of _______ and __________ prepared

  • 8/3/2019 20110514 - DoO's PPT

    15/18

    Engineering

    Regular FP-NSP Engineering Coordinationmeetings initiated

    HoD Recruitment underway

    468 Complex subproject proposals reviewed

    20 requests channeled to central line ministries

    for subproject approval

    38 field visits conducted covering 228subprojects in 198 communities in 37 districts in

    15 provinces

  • 8/3/2019 20110514 - DoO's PPT

    16/18

    Human Resources / Administration

    New MRRD Personnel Policy Manual for NSPEmployees finalized

    New HRAI Unit and vacancies in M&ED filled

    Staffing plans being prepared for considerableexpansion of field offices given increasedwork load with regard to community numbers

    780 New contracts prepared for existing staff

    105 Vacancies filled with new recruitments

  • 8/3/2019 20110514 - DoO's PPT

    17/18

    Public Communication

    Video:

    4 documentary films produced and broadcast 6 TV spots produced and broadcast 20 TV and Radio interviews facilitated for ED and OD

    Radio: 7886 minutes of radio programs have been produced

    and broadcasted

    Print/Website:

    258 news bulletins, articles, success stories and pressreleases, 12000 info kits and 8000 newsletters havebeen produced and distributed

    Additionally, 10 documentary films and 8 TV and radio

    spots have been produced for MRRD media department.

  • 8/3/2019 20110514 - DoO's PPT

    18/18

    Thank You !