    SEI CMMI Quick Assessment Process

    This process can be used to quickly assess the SEI CMMI Maturity Level (Staged

    Representation) of an Organization. A typical meeting with Project Managers and Their

    Managers to answer the Level 2 Questions would take between 2 to 4 hours depending on

    the amount of discussion between the Managers in determining the "score" for each

    Activity.

    The Rating Guide uses a combination of the Common Features translated into a scoring

    method that enables the selection of a score of 0 to 10 for each Specific Practice (Activity)

    within each Process Area of the CMMI. The Method for scoring is designed to be simple

    to understand for Managers trained or not trained in the CMMI. The moderator/scorer

    must have knowledge of the CMMI.

    The specific practices within the CMMI describe the activities expected to result in

    achievement of the specific goals of a process area. The Rating Guide, combined with

    the Process Area Specific Practices Questions in each Sheet of this Workbook can be

    used to produce a quick "score" showing organizational process maturity.

    During a typical meeting with several project managers, there is a lot of discussion on

    how to score the first few questions. Once the scoring is understood by the managers

    the pace quickens and it usually takes less than 3 hours to complete the Level 2

    Questions.

    The process is applicable to each level of the CMMI, although its value is greatest in the

    CMM Level 2 and Level 3 Project Management KPAs.

    Each spreadsheet is filled out with an example of the answers from a group of Managers.

    The results spreadsheet shows the summary and gives a visual picture (radar chart) ofthe results. The visual provides an overall "gap" view and the each process area sheet

    contains a specific roadmap to specific practices that comprise the gap.

    A score of 8 for all specific practices in a process area would indicate that the process

    area would be likely to pass an assessment. An overall level score 1.8 for the level 2

    252586688.xls.ms_office 1 11/23/2014 10:23 PM

  • 8/10/2019 cmmiquick

    2/12

    SEI CMMI Level 2 Quick AssessmentScoring Guide Date:

    Key Activitity Evaluation Guideline

    Score APPROACH DEPLOYMENT RESULTS

    No management No part of the organization Ineffective.

    recognition of need. uses practice.

    POOR No organizational ability. No part of the organization

    0 No organizational shows interest.commitment.

    The practice is not evident.

    Management has begun to Fragmented use. Spotty results.

    recognize the need. Inconsistent use. Inconsistent results.

    WEAK Support items for the practice Deployed in some parts of Some evidence of effective-

    2 start to be created. the organization. effectiveness for some parts

    A few parts of the organization Limited monitoring/verification of the organization.

    are able to implement the of use.

    practice.

    Wide but not complete Less fragmented use. Consistent and positivecommitment by management. Some consistency in use. results for several parts of

    FAIR Roadmap for practice Deployed in some major parts the organization.

    4 implementation defined. of the organization. Inconsistent results for other

    Several supporting items for Monitoring/verification of use parts of the organization.

    the practice in place. for many parts of the

    organization.

    Strong management commit- Deployed in almost all parts Positive measurable results

    ment; some management of the organization. in most parts of the

    MARGINALLY becomes proactive. Mostly consistent use across organization.

    QUALIFIED Practice implementation well many parts of the organization. Consistently positive results

    6 under way across parts of Monitoring/verification of use over time across many parts

    the organization. for almost all parts of the of the organization.Supporting items in place. organization.

    Total management commitment. Deployed in almost all parts Positive measurable results

    Majority of management is of the organization. in almost all parts of the

    QUALIFIED proactive. Consistent use across almost organization.

    8 Practice established as an all parts of the organization. Consistently positive results

    integral part of the process. Monitoring/verification of use over time across almost all

    Supporting items encourage and for almost all parts of the parts of the organization.

    facilitate the use of the practice. organization.

    Management provides zealous Pervasive and consistent Requirements exceeded.

    leadership and commitment. deployment across all parts Consistently world class

    WORLD Organizational excellence of the of the organization. results.

    STANDARD practice is recognized even Consistent use over time Counsel sought by others.

    10 outside of the company. across all parts of the

    organization.

    Monitoring/verification for all

    parts of the organization.

    252586688.xls.ms_office Page 2 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    3/12

    SEI CMMI Level 2 Quick AssessmentRequirements Management Process Area Date: 09/13/04

    SG1

    List of Specifice Practices 0 1 2 3 4 5 6 7 8 9 10SP 1.1 Obtain an Understanding of Requirements x

    SP 1.2 Obtain Commitment to Requirements x

    SP 1.3 Manage Requirements Changes x

    SP 1.4 Maintain Bidirectional Traceability of Requirements x

    SP 1.5 Identify Inconsistencies between Project Work and

    Requirementsx

    0 0 4 0 12 0 0 0 0 0 0

    Requirements Management (REQM) Process

    Manage Requirements

    Score

    252586688.xls.ms_office Page 3 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    4/12

    SEI CMMI Level 2 Quick Assessment Date: 09/13/04

    SG1

    SG 2 Develop a Project Plan

    SG 3 Obtain Commitment to the Plan

    List of Specifice Practices 0 1 2 3 4 5 6 7 8 9 1SP 1.1 Estimate the Scope of the Project x

    SP 1.2 Establish Estimates of Work Product and Task Attributes x

    SP 1.3 Define Project Life Cycle x

    SP 1.4 Determine Estimates of Effort and Cost x

    SP 2.1 Establish the Budget and Schedule x

    SP 2.2 Identify Project Risks x

    SP 2.3 Plan for Data Management x

    SP 2.4 Plan for Project Resources x

    SP 2.5 Plan for Needed Knowledge and Skills x

    SP 2.6 Plan Stakeholder Involvement x

    SP 2.7 Establish the Project Plan xSP 3.1 Review Plans that Affect the Project x

    SP 3.2 Reconcile Work and Resource Levels x

    SP 3.3 Obtain Plan Commitment x

    0 0 12 0 28 0 6 0 0 0

    Project Planning (PP) ProcessEstablish Estimates

    Score

    252586688.xls.ms_office Page 4 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    5/12

    SEI CMMI Level 2 Quick Assessment Date: 09/13/04

    SG1

    SG 2 Manage Corrective Action to Closure

    List of Specifice Practices 0 1 2 3 4 5 6 7 8 9 10SP 1.1 Monitor Project Planning Parameters x

    SP 1.2 Monitor Commitments x

    SP 1.3 Monitor Project Risks x

    SP 1.4 Monitor Data Management x

    SP 1.5 Monitor Stakeholder Involvement x

    SP 1.6 Conduct Progress Reviews x

    SP 1.7 Conduct Milestone Reviews x

    SP 2.1 Analyze Issues x

    SP 2.2 Take Corrective Action x

    SP 2.3 Manage Corrective Action x

    0 0 6 0 28 0 0 0 0 0 0Score

    Project Monitoring & Control (PMC) ProcessMonitor Project Against Plan

    252586688.xls.ms_office Page 5 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    6/12

    SEI CMMI Level 2 Quick Assessment Date: 09/13/04

    SG1

    SG 2 Satisfy Supplier Agreements

    List of Specifice Practices 0 1 2 3 4 5 6 7 8 9 10SP 1.1 Determine Acquisition Type x

    SP 1.2 Select Suppliers x

    SP 1.3 Establish Supplier Agreements x

    SP 2.1 Review COTS Products x

    SP 2.2 Execute the Supplier Agreement x

    SP 2.3 Accept the Acquired Product x

    SP 2.4 Transition Products x

    0 0 8 0 12 0 0 0 0 0 0Score

    Supplier Agreement Management (SAM) ProcessEstablish Supplier Agreements

    252586688.xls.ms_office Page 6 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    7/12

    SEI CMMI Level 2 Quick Assessment Date: 09/13/04

    SG1

    SG 2 Provide Measurement Results

    List of Specifice Practices 0 1 2 3 4 5 6 7 8 9 10SP 1.1 Establish Measurement Objectives x

    SP 1.2 Specify Measures x

    SP 1.3 Specify Data Collection and Storage Procedures x

    SP 1.4 Specify Analysis Procedures x

    SP 2.1 Collect Measurement Data x

    SP 2.2 Analyze Measurement Data x

    SP 2.3 Store Data and Results x

    SP 2.4 Communicate Results x

    0 0 8 0 16 0 0 0 0 0 0Score

    Measurement & Analysis (M&A) ProcessAlign Measurement and Analysis

    252586688.xls.ms_office Page 7 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    8/12

    SEI CMMI Level 2 Quick Assessment Date: 09/13/04

    SG1

    SG 2 Provide Objective Insight

    List of Specifice Practices 0 1 2 3 4 5 6 7 8SP 1.1 Objectively Evaluate Processes x

    SP 1.2 Objectively Evaluate Work Products and Services x

    SP 2.1 Communicate and Ensure Resolution of Noncompliance Issues x

    SP 2.2 Establish Records x

    0 0 8 0 0 0 0 0 0Score

    Measurement & Analysis (M&A) ProcessObjectively Evaluate Processes and Work Products

    252586688.xls.ms_office Page 8 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    9/12

    SEI CMMI Level 2 Quick Assessment Date: 09/13/04

    10

    0

    252586688.xls.ms_office Page 9 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    10/12

    SEI CMMI Level 2 Quick Assessment Date: 09/13/04

    SG1

    SG 2 Track and Control Changes

    SG 3 Establish Integrity

    List of Specifice Practices 0 1 2 3 4 5 6 7 8 9 1SP 1.1 Identify Configuration Items x

    SP 1.2 Establish a Configuration Management System x

    SP 1.3 Create or Release Baselines x

    SP 2.1 Track Change Requests x

    SP 2.2 Control Configuration Items x

    SP 3.1 Establish Configuration Management Records x

    SP 3.2 Perform Configuration Audits x

    0 0 0 0 24 0 6 0 0 0 0Score

    Process & Product Quality Assurance (PPQA) ProcessEstablish Baselines

    252586688.xls.ms_office Page 10 11/23/201410:23 PM

  • 8/10/2019 cmmiquick

    11/12

    SEI CMMI Level 2 Quick Assessment Results and Radar Chart Date: 0

    World Standard Certification Score Level Score vs

    Requirements Management 10 8.0 4.0 1.50

    Project Planning 10 8.0 4.1 1.51

    Project Monitoring & Control 10 8.0 4.3 1.53

    Supplier Agreement Management 10 8.0 3.6 1.45

    Measurement & Analysis 10 8.0 3.8 1.47

    Process & Product QA 10 8.0 2.5 1.31

    Configuration Management 10 8.0 5.4 1.67

    Total Points and Level Rating 440 352 150 1.43

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    Requirements Management

    Project Planning

    Project Monitoring & Control

    Supplier AgreementManagement

    Measurement & Analysis

    Process & Product QA

    Configuration Management

    World Standard

    Certification

    Score

    252586688.xls.ms_office Page 11 11/23/2014

  • 8/10/2019 cmmiquick

    12/12

    SEI CMMI Level 2 Quick Assessment Date: 09/13/04

    Process Area TotalsProcess Area KPA

    Score

    Total

    Questions

    Total

    Score

    Certification

    Score

    Level World

    Standa

    ScoreRequirements Management 4.00 5 16 40 1.40 50

    Project Planning 4.11 14 46 112 1.41 140Project Monitoring & Control 4.25 10 34 80 1.43 100

    Supplier Agreement Management 3.57 7 20 56 1.36 70

    Measurement & Analysis 3.75 8 24 64 1.38 80

    Process & Product QA 2.50 4 8 32 1.25 40

    Configuration Management 5.36 7 30 56 1.54 70

    Total 4.05 55 178 440 1.40 550