Upload
saleemb
View
227
Download
0
Embed Size (px)
Citation preview
7/30/2019 EIA Guidelines
1/84
1
VERSION 2
STANDARDS / MANUALS / GUIDELINES FORSMALL HYDRO DEVELOPMENT
SPONSOR:MINISTRYOFNEWANDRENEWABLEENERGYGOVERNMENTOFINDIA
GUIDELINES FOR
ENVIRONMENTAL IMPACT ASSESSMENT FOR
SMALL HYDROPOWER PROJECTS
LEADORGANISATION:ALTERNATEHYDROENERGYCENTRE
INDIANINSTITUTEOFTECHNOLOGY,ROORKEE
7/30/2019 EIA Guidelines
2/84
i
CONTENTS
TITLE PAGE NO.
Section-1 Guidelines on Environmental Impacts and Need for Small
Hydropower Projects
1
1.1 Small Hydro-Potential and Projects 11.2 Environmental Impacts of Small Hydropower Projects 3
1.3 Positive Impacts 4
1.4 Meaning of EIA 5
1.5 Need of Guidelines for EIA of Small Hydropower Projects 6
Section-2 Environmental Acts and Procedures for Clearance of Hydropower
Projects in India
8
2.1 Environmental Acts 8
2.2 Procedure for Obtaining Environmental Clearance 10
Section-3 Baseline Data 16
3.1 Land Environment 16
3.2 Air and Water Environment 18
3.3 Biological Environment 20
3.4 Socioeconomic Environment 20
Section-4 Environmental Impact Assessment Methodology 22
4.1 Levels of EIA 22
4.2 EIA Procedure 22
4.3 Methods for Impact Identification and Assessment 26
4.4 Socio-economic Assessment 29
Section-5 Water Quality Monitoring Program 32
5.1 Effects on Water Quality 32
5.2 Purpose of water Quality Monitoring 34
5.3 Sampling Design 34
5.4 Regulatory Audit 38
5.5 Interpretation of Monitoring Results 39
Section-6 Stake Holders in EIA Process 42
6.1 Ways to Identify Stakeholders and Group Representatives 43
6.2 Involving Stakeholders 436.3 Public Consultation 45
Section-7 Principles and Procedures of an Environmental Management Plan 47
7.1 Environmental Monitoring 47
7.2 Environmental Auditing 49
7.3 Implementation of Environmental Management Plan 49
Section-8 Preparation of Terms of References 58
8.1 Basic Objectives and Purpose 58
8.2 Good practice Criteria for the Preparation of TOR 59
7/30/2019 EIA Guidelines
3/84
ii
TITLE PAGE NO.
Annexure I Useful References 64
Annexure II Definition of Terms Related to Soil, Air and Water Environment of a
Hydropower Project
66
Annexure III Environmental Standards prescribed by Central Pollution Control
Board
72
Annexure IV Format of Environmental Impact Assessment Document 75Annexure V Environmental Appraisal Questionnaire As Prescribed in Appendix I
Form of EIA Notification (MoEF, 2006)
77
7/30/2019 EIA Guidelines
4/84
1
SECTION 1
GUIDELINES ON ENVIRONMENTAL IMPACTS AND NEED FORSMALL HYDROPOWER PROJECTS
Developing countries need increased energy supplies in order to bring about
improvement in the quality of life of their people. Sustainable and environmentally sound
progress towards energy self reliance is probably best achieved through development of
renewable energy sources as these will eventually be the only sources available to sustain the
societies. Out of various renewable energy sources, small hydropower is the only source which
has sufficient potential to accommodate remote area needs. Although the adverse
environmental impacts of individual small hydropower project (SHP) may not be significant and
yet, the aggregate impact of several such projects in vicinity could be of a magnitude to cause
significant damage to the environment.
EIA study should provide information based on scientific analysis and adequate data
basis as such information is to be placed in public domain and is subject to critical review by
public. As a scientific analysis of the environmental constraints the EIA constitutes an important
part of pre-project study which helps in improving project standard.
EIA study is aimed at protecting the environment by integrating the environmental
issues in planning process.
1.1 SMALL HYDRO POTENTIAL AND PROSPECTS
Small hydro is a renewable, non-polluting and environmentally benign source of energy.
In India, depending on the capacities, small hydropower projects are categorized as Micro, Mini
and Small hydro projects as under.
Mini hydro - 10 kW to 99 KW
Micro hydro - 100 kW to 999 kW
Small hydro - 1,000 kW to 25,000 kW
Depending on the head, SHPs may be further classified as low head (below 3 meters),
medium head (from 30 75 meters) and high head (above 75 meters).
The estimated potential of small hydro power in India is about 15,000 MW. Thus far
about 4250 potential sites have been identified aggregating to a capacity of 10,000 MW.
However, so far 466 projects in 29 states aggregating to 1530 MW have been installed and
projects amounting to 610 MW are under implementation. This offers a tremendous potential of
small hydro power to be tapped in India. A very large number of villages have potential forsetting up mini, micro and small hydroelectric projects. It presents a huge business potential for
investors and equipment manufactures.
7/30/2019 EIA Guidelines
5/84
2
Potential available - 15,000 MW
Installed so far - 1530 MW; Projects under implementation - 610 MW
1.2 ENVIRONMENTAL IMPACTS OF SMALL HYDROPOWER PROJECTS
A hydropower scheme entails change in use of land and water. Magnitude of suchchange depends on the selected site configuration. An illustrative site configuration is shown
below. The environmental impacts of SHPs are positive (favourable) and negative (undesirable)
in nature.
Figure 1.1: Physical components of small hydropower project
The environmental impacts of small hydropower project may be summarized as follows:
Table 1.1: Environmental impacts of small hydropower projects
Activity Adverse Impact
Construction of road,
dam, surface powerhouse and switch
yard, diversion tunnel,
channel
1. Reservoir sedimentation and deterioration of water quality
2. Air and noise pollution and disturbance to flora and faunaby work force
3. Visual intrusion caused by construction activity
4. Disturbance of recreational spots (e.g. waterfalls) and
activities
5. Soil erosion due to removal of vegetation and excavation
of construction material
6. Alteration in ground water flow
Construction of
transmission line
1. Damaging flora due to right of way clearing
2. Endangering the lives of fauna
7/30/2019 EIA Guidelines
6/84
3
3. Visual intrusion
Stream diversion
through channel and
conduit
1. Loss of habitat of fish and other aquatic flora and fauna
2. Decrease in dilution capacity of stream
3. Depletion in ground water recharge where diversion is
taken off from effluent stream
4. Loss of waterfalls and other recreational activities
Ponding 1. Flow disruption
2. Channel degradation during generation or spilling and
flushing of silt from dam
3. Trapped nutrients and sediments, eutrophication
4. Changed water temperature
5. Changes in land uses: (a) submergence of agricultural and
forest land (b) submergence of human settlement and
displacement of population (c) submergence of
monuments/sites of historic importance (d) loss of
whitewater recreation
6. Change in aquatic plant life and fish species
7. High evaporation rate
8. Sedimentation adversely affects fish spawning areas by
burying them9. Provides increased habitat for mosquitoes and snails
which are vectors of diseases like malaria, yellow fever,
dengue, encephalitis and schistosomiasis
Operation of
hydropower station
1. Increase in pollution concentration in the downstream due
to release of pollutants from residential areas, hydropower
plant
2. Released water containing low dissolved oxygen
3. Fish mortality from turbine passage4. Sonic impact: noise level may increase
Peaking operation of
power station
1. Damage to fish spawning ground and nesting ground for
water fowls and other aquatic birds
2. Erosion of banks
3. Transport of nutrients from the shallow water to deeper
water in pond
4. Affects recreational facilities due to fluctuating water level
5. Exposure of drawdown zone creates visual intrusion
7/30/2019 EIA Guidelines
7/84
4
1.3 POSITIVE IMPACTS
Positive environmental impacts of hydropower projects are somehow ignored as a
routine probably due to the fact that these projects are conveniently considered as demanding
an environmental price. It is equally important to highlight and quantify (to the extent possible)
positive environmental impacts of SHPs.
Positive Socio-Economic Impacts
1. No transmission loss due to commercial availability of power at customers door step
2. Multiplier effect of electricity on economy of the area especially in remote areas such as
agro-industrial units
3. Improvement of agricultural produce through lift irrigation which requires energy
4. Project related infrastructure (roads, health facilities, education facilities will help the
local people as well as project affected people. There will be net improvement in
community health
5. Improvement in living standard of local people
6. Creation of reservoir will increase potential for fish and fisheries (catch and income)
7. Generation of employment opportunities locally. Direct employment during construction
and indirect employment in allied activities
8. Motivation of higher literacy
9. Check on migration from villages to towns, thereby checking urban concentration of
population
10. Increasing tourism potential water sports, boating, fishing etc.
11. It helps in checking deforestation which is taking place to meet food, fodder and fuel
demands in rural, remote areas.
12. It is significant for off-grid, rural, remote area applications in far flung isolated
communities having no chances of grid extension for years to come. It is operationally
flexible, suitable for peaking support to the local grid as well as for stand alone
applications in isolated remote areas.
13. Small hydro does not require much expertise to build and operate. Components of smallhydro projects are simple and fairly visible at site. They can become centre of education.
14. In specific cases SHPs are eligible for carbon credits through reduction in CO2 emission
and adding sink for CO2 via plantation schemes.
Positive Ecological/Environmental Impacts
1. Clean and renewable source of energy. SHPs result in saving of non-renewable fuel
resources such as coal, liquid fuels and gases.
2. It is benign source of power generation, harnessing only gravitational potential of water
to make it yield energy in a continuum
7/30/2019 EIA Guidelines
8/84
5
3. Decrease of pollution in the area (hydro replacing diesel generation, electricity replacing
polluting energy sources)
4. Increased water surface creates habitat for aquatic life in or near the reservoir.
Receiving waters create dry mudflats which provide feeding sites for migratory birds and
breeding habitat for resident species.
5. Improved ground water table enhancing greenery all around
6. Improvement towards vegetation and plantation associated with the project
(compensatory afforestation) and thus providing sink for CO2 emission
7. Improved habitat
8. Lake shore environment in otherwise dry areas
9. Modification of micro climate due to storage and regulation of water to a more or less
uniform pattern. This also leads to a somewhat stabilizing impact on local environment
influencing flora and fauna aquatic as well as terrestrial.
10. SHPs are environmentally more friendlier than conventional large hydro plants:
a. Non-involvement of setting up of large dams and thus not associated with
problems of deforestation, submergence or rehabilitation
b. Non-polluting and environmentally benign. It is one of the least CO2 emission
responsible power sources, even by considering full energy chain right from the
impact of production of plant equipment etc.
c. Least impact on flora and fauna (aquatic and terrestrial) and biodiversity due to
localised nature of activities
11. There may be overall improvement in biodiversity due to creation of habitats.
1.4 MEANING OF EIA
EIA is an activity designed to identify, predict and describe in appropriate terms the
primary and secondary changes due to a proposed action. Such actions may include policies,
plans, programmes and projects. EIA covers the biophysical environment, mans health, the
quality of life and social environment, and communicates results in a form which is
understandable by the community and decision makers. Thus, EIA is required not only for a
particular hydropower project but also for a set of projects (existing and proposed) under a plan
or a programme.
The EIA should contain descriptions of both the likely beneficial and adverse impacts
(short and long-term). The EIA approach should be inter-disciplinary, systematic,
comprehensive and capable of presenting results that are understandable to non-experts.
Assessments should indicate the possible need for pollution control measures, health care
programmes and environmental monitoring on the basis of an understanding of the affected
environment. The EIA process does not stop at the production of an Environmental Impact
7/30/2019 EIA Guidelines
9/84
6
Statement (EIS) or the granting of project authorisation, but continues throughout the life of a
project.
The potential advantages of EIA are more efficient use of resources and improved
quality of life. If the probable environmental, social and health consequences of proposed
development are known from an early stage, attempts can be made to minimise adverse
impacts and maximize beneficial impacts.
1.5 NEED OF GUIDELINES FOR EIA OF SMALL HYDROPOWER PROJECTS
A series of standards, guidelines and manuals have been brought out by various
agencies dealing with environmental impact assessment of large river valley/hydropower
projects. However, such literature for small hydropower projects is not available. There is an
urgent need to develop and adopt simplified guidelines for SHPs.
Guidelines have been issued by Ministry of Environment and Forests (MOEF) for
diversion of forest land for non-forest purposes and for EIA of river valley projects. These
guidelines are exhaustive covering wide range of environmental subjects. Small hydropower
projects may not require same type of scrutiny as that required by large projects. Further, in
depth study of some of environmental aspects may not be necessary.
Basic physical character of SHP and the local factors influencing the environment are to
some extent similar to those of large projects; the only difference is in terms of magnitude of
change in the use of land, water and other resources. Further there are certain positive impacts
(socio-economic and environmental) unique to small hydropower. Several of the positive socio-
economic impacts are intangible in nature (i.e. not quantifiable) and yet could be significant.
Intangibility does not imply insignificance.
There is an urgency to accelerate development of small hydro and remove regional
imbalances in economic development. Private sector has a big role to play in development of
SHPs. Standards and guidelines are required to help concerned agencies in carrying out EIA in
a systematic and scientific manner and thus avoiding delay in clearance of the projects.
Keeping the above in view, these guidelines have been prepared to address needs of
SHPs. The following aspects are covered in this manual:
various acts and decision making process as followed in India for obtaining
environmental clearance.
baseline data required as per environmental indicators
the EIA methodology
procedure for water quality monitoring and auditing
methods and procedures for engaging stake holders principles and procedures of environmental management plan
7/30/2019 EIA Guidelines
10/84
7
the preparation of terms of references and good practice criteria
some terms related to environment
standards of environmental parameters used in India
prescribed format of EIA document
Environmental Appraisal Questionnaire as prescribed in Appendix I Form I of EIA
notification (MOEF, 2006)
Useful references
7/30/2019 EIA Guidelines
11/84
8
SECTION 2
ENVIRONMENTAL ACTS AND PROCEDURES FOR CLEARANCE OFHYDROPOWER PROJECTS IN INDIA
2.1 ENVIRONMENTAL ACTS
Adequate provisions for protection of environment and forests are made in the
Constitution of India. Article 47 provides for protection and improvement of health. Article 48(A)
is directed towards protection and improvement of environment and protection of forest and
wildlife. Article 51(A) says it is the duty of every citizen to protect and improve natural
environment. Following the UN Conference on Human Environment (Stockholm, 1972), a
constitutional amendment (42, 1976) inserted relevant provisions for environment protection in
Constitution in Part IV Directive Principles and Part IVA Fundamental Duties.
In order to ensure sustainable development from water resources angle the Government
of India has enacted various Acts and Legislations. Prominent among these is the Environment
(Protection) Act, 1986 through which the Government has acquired wide powers for protecting
the environment. Some other acts related to Water and Environment are Water (Prevention and
Control of Pollution) (Cess) Act, 1977 (amended in 1991), Forest Conservation Act, 1980,
Environmental Impact Assessment (EIA) Notification of MOEF 2006 and the Ministry of
Environment and Forests Notification of January 1977 constituting the Central Ground Water
Authority (CGWA).
The Water (Prevention and Control of Pollution) Act, 1974 seeks to maintain or restore
wholeness of water and the Central and State Pollution Control Boards have been established
under this Act. According to the Water Cess Act, 1997, both Central and State Governments
have to provide funds to the Boards for implementing this Act. The Forest Conservation Act,
1980 provides for compensatory afforestation to make up for the diversion of forestland to non-
forest use. The Environment (Protection) Act, 1986 was enacted in 1986 for the protection and
improvement of human environment.
Recently, Government of India has constituted Water Quality Assessment Authority
(WQAA) vide MoEF/Nc. J-15011/8/2000-NRCD dated 29th May, 2001 under the chairmanship
of Secretary, MOEF, exercising the powers under the Environment (Protection) Act, 1986. This
authority exercises the powers and functions under the said Act for several functions. Some of
these relevant to hydropower projects are given below:
To direct various agencies to standardize methods for water quality monitoring
To ensure quality of data generation of utilization thereof
To make measures so as to ensure proper treatment of waste water with a view to restoringthe water quality of the river water bodies to meet the designated best uses
7/30/2019 EIA Guidelines
12/84
9
To maintain minimum discharge for sustenance of aquatic life forms in riverine system
To promote rain water harvesting
To utilize self assimilation capacities at the critical river stretches
To constitute/set up state level Water Quality Review Committees (WQRCs) to coordinate
the works to be assigned to such committees
To deal with any environmental issues concerning surface and ground water quality referred
to it by central Government or the State Government relating to the respective areas, for
maintaining and/or restoration of quality to sustain designated best-uses.
TABLE 2.1: KEY ENVIRONMENTAL LEGISLATIONS AND GUIDELINES
Name Scope and objective Key areasOperational
agencies/key
players
Water Prevention andControl of PollutionAct, 1974, 1988
To provide for theprevention andcontrolof water pollution andenhancing the qualityof water
Controls sewage andindustrial effluentdischarges
Central and StatePollution ControlBoards
Air Prevention andControl of PollutionAct 1981, 1987
To provide for theprevention andcontrol of air pollution
Controls emissions ofair pollutants
Central and StatePollution ControlBoards
Forest ConservationAct, 1980, 1988
To consolidateacquisition ofcommon propertysuch as forests; haltIndias rapiddeforestation andresultingEnvironmentaldegradation
Regulates access tonatural resources,state has a monopolyright over land;categorize forestsRestriction on de-reservation and usingforest for non-forestpurpose
State governmentAnd Centralgovernment
Wildlife ProtectionAct, 1980
To protect wildlife
Creates protectedareas (nationalparks/sanctuaries)categorize wildlife
which are protected
Wildlife advisoryboards; Central ZooAuthorities
EnvironmentProtection Act, 1986
To provide for theprotection andimprovement ofEnvironment
An umbrellalegislation;supplements pollutionlaws
Central governmentnodal agency MoEF;can delegate powersto state department ofEnvironment
EnvironmentalClearanceNotification, 2006 OFMoEF (GOI)
Environmental ImpactAssessment ofProjects; EnvironmentManagement Plans
EnvironmentalProtection
Project Developer,State and CentralGovernments.
National Policy onR&R, 2003 of Min. of
Rural Development,GOI
Resettlement andRehabilitation of
project affectedpeople
Social Issues State Government
7/30/2019 EIA Guidelines
13/84
10
2.2 PROCEDURE FOR OBTAINING ENVIRONMENTAL CLEARANCE
Before January, 1994, it was an administrative requirement for the mega projects to
obtain environmental clearance from the MOEF, Government of India. However, in order to
assess the impacts of the developmental projects/activities on the environment, MOEF issued a
gazette notification on the EIA on January 27, 1994 (as amended on May 04, 1994) and made
environmental clearance statutory for all the projects located in ecologically sensitive/fragile
areas as notified by the Government of India from time to time, besides various categories of
the projects as specified in the schedule of the notification. These also include water resource
development (WRD) project. MOEF has issued a revised gazette notification on 14th
September, 2006 suppressing the earlier notification of January 27, 1994. The new gazette
notification is based on National Environment Policy which was approved by Union Cabinet on
18th May, 2006. Flow chart depicting procedure of environmental clearance is given in Figure
2.1. Flow chart depicting appraisal procedure is shown in Figure 2.2.
2.2.1 Requirements for Environmental Clearance
The gazette notification dated 14th September, 2006 stipulates two regulatory authorities
to deal with environmental clearance for all new project and expansion/modernization of
existing projects.
Central Government in Ministry
of Environment and Forests
for Category A projects 50 MW
for category B projects if located wholly or partially
within 10 km from boundary of notified protected
area/critically polluted area/ecosensitive area
State Environmental
Assessment Authority (SEIAA)for category B projects 25 MW and
7/30/2019 EIA Guidelines
14/84
11
and whether they are listed in the schedule of the EIA notification or not. All the projects located
in/near wildlife sanctuaries, national parks, wetlands, mangroves, biosphere reserve also need
environmental clearance.
Therefore, even a small hydropower project (
7/30/2019 EIA Guidelines
15/84
12
categorization as B1 and B2. For categorization of projects into B1 or B2, the Ministry of
Environment and Forests shall issue appropriate guidelines from time to time.
Stage (II) Scoping
Scoping refers to the process by which the Expert Appraisal Committee in the case of
Category A projects or activities, and State level Expert Appraisal Committee in the case of
Category B1 projects or activities, including applications for expansion and/or modernization
and/or change in product mix of existing projects or activities, determine detailed and
comprehensive Terms Of Reference (TOR) addressing all relevant environmental concerns for
the preparation of an Environment Impact Assessment (EIA) Report in respect of the project or
activity for which prior environmental clearance is sought. The Expert Appraisal Committee or
State level Expert Appraisal Committee concerned shall determine the Terms of Reference on
the basis of the information furnished in the prescribed application form including Terns of
Reference proposed by the applicant, a site visit by a sub- group of Expert Appraisal
Committee or State level Expert Appraisal Committee concerned only if considered necessary
by the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned,
Terms of Reference suggested by the applicant if furnished and other information that may be
available with the Expert Appraisal Committee or State Level Expert Appraisal Committee
concerned. All projects and activities listed as Category B shall not require Scoping and will be
appraised on the basis of application form and the conceptual plan.
It is required for category A and B1 projects. Purpose is to determine detailed and
comprehensive terms of reference for preparation of EIA report.
For category A, hydroelectric project item 1(c) (i) of schedule of TOR shall be conveyed
along with clearance for preconstruction activities.
Stage (III) Public consultation
Public Consultation refers to the process by which the concerns of local affected
persons and others who have plausible stake in the environmental impacts of the project or
activity are ascertained with a view to taking into account all the material concerns in the project
or activity design as appropriate.
It is required for category A and B1 project with some exceptions e.g. modernization of
irrigation projects, expansion of roads and B2 type and projects, projects concerning national
defence and security. MOEF (2006) has specified procedure for conduct of public hearing.
Purpose is to take into account concerns of local affected persons and others who have
plausible stake in environmental impacts. Based on this, appropriate changes in the draft EIA
and EMP shall be made. Applicant may submit a supplementary report to draft EIA for
appraisal.
The detailed methodology for public consultation is explained in Chapter 6.
7/30/2019 EIA Guidelines
16/84
13
Stage (IV) Appraisal
Figure 2.2 depicts the procedure for project appraisal. Appraisal means the detailed
scrutiny by the Expert Appraisal Committee or State Level Expert Appraisal Committee of the
application and other documents like the Final EIA report, outcome of the public consultations
including public hearing proceedings, submitted by the applicant to the regulatory authority
concerned for grant of environmental clearance. This appraisal shall be made by Expert
Appraisal Committee or State Level Expert Appraisal Committee concerned in a transparent
manner in a proceeding to which the applicant shall be invited for furnishing necessary
clarifications in person or through an authorized representative. On conclusion of this
proceeding, the Expert Appraisal Committee or State Level Expert Appraisal Committee
concerned shall make categorical recommendations to the regulatory authority concerned
either for grant of prior environmental clearance on stipulated terms and conditions, or rejection
of the application for prior environmental clearance, together with reasons for the same.
7/30/2019 EIA Guidelines
17/84
14
Figure 2.1: Flow chart describing procedure of environmental clearance
7/30/2019 EIA Guidelines
18/84
15
APPRAISAL
Figure 2.2: Flow chart describing Appraisal procedure by Regulatory Authority (RA)
Documents: Final EIA or Draft EIA reports andsupplementary reports, video tape/CD of
public hearing, layout plan, projectfeasibility report and Form 1
Scrutiny by RA office with respect toTOR (30 days)
EAC/SEAC completes approval (60 days)
EAC/SEAC meetingApplicant makes presentation
Minutes displayed on website (5 days)
Clearance given, environmental safeguardsand conditions specified or reasons for
rejection are explicitly stated
7/30/2019 EIA Guidelines
19/84
16
SECTION 3
BASELINE DATA
Baseline data is required to describe environmental and socio-economic status of
project site and project impact area for pre-project condition. It consists of primary data (field
tests, surveys, measurements) and secondary data (published information, unpublished
information available with various agencies). Much of the required secondary
data/information is often available within the various government agencies. Major difficulty
with the unpublished information is determining which of it is important and then correctly
interpreting it while eliminating all the unimportant data.
The data is compiled for: Land Environment, Water Environment, Air Environment,
Noise Environment and Socio-economic Environment. Primary data related to the
environmental attributes like air, noise level, water quality and soil are collected from field
studies. A structured questionnaire is used for collection of primary information on socio-
economic aspects. Ecological information is collected from field studies as well as secondary
sources. A summary of environmental attributes related parameters and source of
information is given in Table 3.1.
3.1 LAND ENVIRONMENT
3.1.1 Land Use
Land use and land cover patterns are important in environmental impact assessment
study from the point of view that land use describes the present use such as agriculture,
settlement etc. and land cover describes the material on it such as forest, vegetation, rocks
or building etc. Land cover of the 10 km radius study area with reference to the site can be
derived using latest cloud free satellite imageries. The data is geo-referenced using SOI
1:50000 scale toposheets with the help of standard data preparation techniques in GIS
software such as ERDAS IMAGINE. Interpretation of the geo-referenced data is done using
standard enhancement techniques and ground truthing. The land use is explained in terms
of type and areal extent i.e. dense vegetation, medium vegetation and sparse vegetation
which refers to the crown cover density of >40%, 10-40% and
7/30/2019 EIA Guidelines
20/84
17
Table 3.1: Environmental attributes, parameters and source of information
S. No. Attribute Parameter Source
LAND ENVIRONMENT1 Land Use Land use pattern District Planning Map
2 Soil Soil Characteristics Soilerosivity in catchment area
Field studies, GIS basedinformation
3 Geology Geological Status Project Pre-Feasibility Report
4 Seismology Seismic Hazard Pre-Feasibility Report
WATER ENVIRONMENT5
Water ResourcesCatchment Area, Flow,Design
Project Pre-Feasibility Report
6 Water Quality Physical, Chemical andBiological parameters
Field studies
7 Hydrology Drainage area and pattern Project Pre-Feasibility Report
8 Ambient Air Quality SPM, RPM, SO2, NOx andCO
Field Studies
9 Meteorology Temperature and Relativehumidity
Field Studies
Temperature, Relativehumidity, Rainfall, WindSpeed and Wind Direction
India MeteorologicalDepartment
10 Noise Noise levels in dB (A) Field StudiesBIOLOGICAL ENVIRONMENT
11 Ecology Flora & Fauna Diversity Field Studies, Informationfrom Forest department and
Literature Study12 Aquatic Ecology Density & diversity of aquatic
speciesField studies, FisheriesDepartment, Literaturereview
SCIO-ECONOMIC13 Socio-economic
aspectsSocio-economic characteristicof the affected area
Field Studies, Literaturereview.
(d) Homestead land(e) Grazing land(f) Fallow
(g) Marshes(h) Water bodies(i) Road(j) Railway(k) Bridges(l) Airport
3.1.2 Drainage Pattern(a) Data regarding flash floods, frequency of occurrence(b) Ground water strata(c) Springs
7/30/2019 EIA Guidelines
21/84
18
3.1.3 Soils
The locations for collection of soil samples should be well distributed to represent the
spatial variation in project area. The soil samples are to be analysed for the following
parameters:
(a) Land capability classification (for agricultural land)(i) Physical properties of soil (soil texture, porosity, particle size distribution)(ii) Chemical properties of soil (pH, electrical conductivity, cations, anions)(iii) N, P, K content
3.1.4 Catchment Profile (Directly Draining)(a) Drainage pattern(b) Watershed characteristics
(i) Size(ii) Shape(iii) Relief
(iv) Slope(v) Drainage(vi) Pattern and density
(c) Ground water potential and runoff behaviour(d) Sediment/silt yield data(e) Existing cropping pattern(f) Migrant behaviour of human and livestock population
3.1.5 Geomorphology/Geology(a) Data with reference to the entire project area (rock type, slopes, strata, minerals
etc.)(b) Seismic zones/classification
(c) Data pertaining to occurrence of earthquakes
3.2 AIR AND WATER ENVIRONMENT
3.2.1 Water Quality Parameters
To generate baseline data for existing water quality in the project area, water
samples (composite) should be collected and analysed for examination of water and
wastewater as per the standard procedure such as given in Protocol for Water Quality
Monitoring (http://www.cwc.nic.in/main/HP/download/ProtocolforWaterQualityMonitoring.pdf)
or the relevant code of the Bureau of Indian Standards (BIS). The details for conducting
water quality assessment are given in Chapter 5. These water samples are to be assessed
for the following parameters:
(a) Physico-chemical pH, temperature, conductivity, dissolved oxygen, TDSand TSF, turbidity, total alkalinity, total hardness, chloride, iron, nitrate,phosphate, BOD, COD
(b) Bacteriological E coli, coliform(c) Depending upon the pollution source concerned heavy metals namely
mercury, arsenic etc. also to be analysed(d) Base line data:
(i) Pre-construction: Two season data i.e. high flow and lean flow
(ii) Post-construction: Water quality parameters upstream of the projectsite to be compared with the quality downstream of the project site
7/30/2019 EIA Guidelines
22/84
19
3.2.2 Hydrological Data(a) Monthly discharge data at dam site(b) Lean season flow (cumec)
(i) upstream of project site(ii) downstream of the project site
(c) Water required for (cumec)(i) power generation(ii) irrigation(iii) domestic/industrial use
(d) Ground water profile pre-monsoon/post-monsoon
3.2.3 Meteorology3.2.3.1 Seasonal-monitored data (monthly basis)
(i) Temperature (in 0C)(a) Maximum
(b) Minimum(c) Mean(ii) Mean rainfall (in mm)(iii) Wind speed (km/h)
(a) Maximum(b) Minimum(c) Mean
(iv) Windrose diagram for winter, summer, rainy season and annual(iv) Humidity (mean monthly)(v) Evaporation (observed class A pan evaporation or estimated using appropriate
method)
3.2.4 Air Quality(a) Season wire/air quality (SPM, NOX, SO2, CO)(b) Construction material required (Table 3.2)(c) Dust emissions
(i) Quarry sites(ii) Haulage roads(iii) Construction activity(iv) Stone crusher
Table 3.2: Construction material required (clause 3.2.4 b)List of construction
materials to be used at all
stages of construction
Quantity(tonnes/month)
Peak Average
Source of
material
Means of transportation(source to storage site)
with justificationCementStoneSteelSandOther
3.2.5 Noise(a) Major sources of noise in the project area (stationary and mobile)(b) Level at source (dB)(c) Level at project boundary (dB)
7/30/2019 EIA Guidelines
23/84
20
3.3 BIOLOGICAL ENVIRONMENT
3.3.1 Aquatic
Aquatic ecosystem to be studied over an area atleast between 2km upstream of the
project site and atleast 2 km downstream of the project site. The study should include the
following:
(a) Fish species of commercial value(b) Resident species(c) Migratory species, their spawning ground, fish morphology, anatomy, feeding
pattern, breeding pattern etc.
Aquatic ecological analysis may be made following the methods outlined in Wetzel
and Likens (1991) and APHA (1998). Periphyton, phytoplankton, macrobenthos and
zooplankton should be studied for frequency, density, abundance and diversity indices.
3.3.2 Terrestrial
An inventory of flora, listing of rare, endangered, economically important and
medicinal plant species should be prepared and their frequency, abundance and density
should be determined. Quadrate method is generally used for sampling.
3.3.2.1 Flora
(a) Major forest products and dependability of the local communities on these suchas fuel wood, edible species, construction material etc.
(b) Forest type(c) Trees, shrubs, herbs(d) Rare and endangered species(e) Endemic species(f) Economically important species
3.3.2.2 Fauna(a) Aerial distance of National Park/Sancturay/Biosphere Reserve etc., if any in the
vicinity, from the project site(b) Rare and endangered species(c) Endemic species(d) Species of special interest to local population and tourists
(e) Migratory route of animals, if any, in the project area
3.4 SOCIOECONOMIC ENVIRONMENT
3.4.1 Demographic Profile (gender based details of the population)(a) Rural/urban(b) Population density(c) SC/ST and others(d) Literacy(e) Employment and occupation(f) Economic status (land holding/house holding)
3.4.2 Details of Villages to be Affected(a) Total no. of villages
7/30/2019 EIA Guidelines
24/84
21
(b) Total no. of families(i) Tribal(ii) Others
(c) Total population(i) Tribal(ii) Others
3.4.3 Village wise Land Details(a) Name of village(b) Total land(c) Land coming under project area(d) Main occupation of villagers
(i) Agriculture(ii) Service(iii) Labourers(iv) Business
3.4.4 Details of Families to be Displaced
Name ofvillage
PopulationLand oustees only Homestead oustees only Land and homestead oustees
Tribal Others Tribal Others Tribal Others
3.4.5 Infra Structure Development(a) Education(b) Industrial development(c) Drinking water
(d) Communication(e) Roads(f) Electricity(g) Sanitation
3.4.6 Cultural Sites(a) Places of worship(b) Archeological sites/monuments(c) Anthropological sites
3.4.7 Health Profile(a) Existing health(b) Screening of the facilities urgent labour
(i) No. of persons to be employed for construction (average and during peakperiod)
(ii) No. of persons to be employed from the affected population(iii) Details of temporary labour colonies
(c) Disease surveillance(i) Endemic health problem(ii) Epidemic prevention and control(iii) Probability of the occurrence of malaria etc.
7/30/2019 EIA Guidelines
25/84
22
SECTION 4
ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY
This section aims at description of environmental impact assessment (EIA) methodology
with reference to water resource projects. As a scientific and technical analysis of the
environmental impacts, the EIA constitutes an important part of the project studies which
alongwith techno-economic studies contribute to improving the project standard.
4.1 LEVELS OF EIA
The potential scope of a comprehensive EIA system is considerable and can include
appraisal of policies, plans, programmes and projects. Even if policies were not environmental
in nature, they might still have severe environmental implications.
The top tier of EIA application would be a Policy EIA which attempts to assess the
environmental and health implications of national policies. For example, agricultural policies
may cause severe ecological impacts or energy policies will influence the demand for natural
resources and affect industrial development. At a lower level a Plan EIA would seek to identify
key environmental factors affecting land use such as agricultural land quality and resources
exploitation.
EIAs could assist in the identification of preferred areas where certain types of
development might be encouraged. A Programme EIA would be prepared for a series of like
projects, such as in a river basin development scheme in which different hydropower projects
including SHPs may be constructed at different times. A Project EIA would be undertaken when
local environmental issues are particularly important for individual projects. It should be
recognised that EIA is not a universal panacea, it may have restricted use in certain areas of
decision-making. Most EIA experience is related to projects (Project EIA); very few plan EIAs
have been undertaken.
4.2 EIA PROCEDURE
The key activities are screening, scoping and assessment which will be discussed in
detail in following sections. These steps require intensive interaction between the human
resources and information resources available for a proposed project.
Finally, an EIA has to be organized to address certain specific topics. Most EIAs cover
the following features:
Description of the proposed project,
Description of the proposed location or study area, including information about physicalresources, ecological resources, human and economic development and existing quality of
life
7/30/2019 EIA Guidelines
26/84
23
Alternatives considered (including no-action),
Potential impacts and benefits including evaluation of each alternative considered,
Mitigation of adverse effects,
Irreversible and irretrievable commitment of resources,
Identification of temporary, short-term and long-term effects,
Disposition of reviews comments,
Summary, conclusions and recommendations,
Monitoring,
Addition of other features or topics particular to the proposed project.
4.2.1 Screening
Screening is a procedure which aims to identify, as early as possible, those projects with
potentially significant impacts, that should therefore be subject to EIA. Projects can be
investigated and, if no significant impacts are anticipated, they can then be exempted from
further environmental analysis. According to MoEF guidelines, Category B projects or activities
(see Chapter 2) are subjected to scrutiny by concerned State Level Expert Appraisal
Committee for determining whether or not the project or activity requires an EIA. Those
requiring EIA are termed as B1 project and those not requiring EIA are termed as B2 project.
For categorization of projects into B1 or B2, the MoEF shall issue appropriate guidelines from
time to time. A number of approaches to screening can be identified. These are listed and
discussed below:
Project thresholds,
Locational criteria,
Positive and negative lists,
Initial Environmental Evaluations (IEEs),
4.2.1.1 Thresholds
Thresholds may be developed on the basis of size, cost or pollution levels. For example,
in India, a policy has been established (MoEF, 2006) that all hydropower projects with installed
capacity less than 25 MW would not be subject to prior environmental clearance by competent
authority. This approach, unfortunately, neglects the implications of several small hydropower
developments in vicinity, each below the threshold, but which in combination may cause
significant adverse impacts and thus should be subject to EIA.
4.2.1.2 Locational criteria
Locational criteria usually involve designation of sensitive areas, for example nature
preserves, national parks, historical/religious sites and biospheres. Thus any project or activity
7/30/2019 EIA Guidelines
27/84
24
in category B will be treated as category A if located in whole or part within 10 km from the
boundary of protected areas/critically polluted areas/notified ecosensitive areas etc.
4.2.1.3 Positive and negative lists
The approach is based upon a list of proposed projects for which an EIA is alwaysrequired (positive list) and a list for which no EIS is required (negative list). Initially, some work
is needed to justify the inclusion of one project and the exclusion of another.
Example: individual industries located in notified ecosensitive zone (positive list)/biotech parks
(negative list)
4.2.1.4 Initial environmental evaluation
An initial environmental evaluation (IEE) approach requires considerably more
understanding of a project and its environs than the approaches described previously. IEEsoperate on a project-by-project basis and consequently it is impossible to make generalizations
as to which project will be subject to an EIA. However, the RA is an essential precursor to an
IEE since it provides sufficient information on pollution loads and levels to allow decision to be
made on the need for an EIA.
An IEE-approach is presented in the UNEP guidelines (United Nations Environment
Programme, 1980) for the assessment and siting of industry. This approach requires a
systematic identification of possible interactions between the characteristics of the proposed
development, and those of the size and surroundings. Both an interactions matrix andscreening tests may be needed for this approach.
There are several general criteria that can be used when making a decision as to the
environmental effect of an activity. These criteria are not mutually exclusive but are very much
interrelated.
Magnitude : This is defined as the probable severity of each potential impact. Will the impact
be irreversible? If reversible, what will be the rate of recovery or adaptability of an impact area?
Will the activity preclude the use of the impact area for other purpose?
Prevalence : This is defined as the extent to which the impact may eventually extend as in the
cumulative effects of a number of stream crossings. Each one taken separately might represent
a localized impact of small importance and magnitude but a number of such crossing could
result in a widespread effect. Coupled with the determination of cumulative effective is the
remoteness of an effect from the activity causing it. The deterioration of fish production resulting
for access roads could affect sport fishing in an area many miles away and for months or years
after project completion.
7/30/2019 EIA Guidelines
28/84
25
Duration and Frequency : The significance of duration and 1frequency can be explained as
follows. Will the activity be long-term or short-term? If the activity is intermittent, will it allow for
recovery during inactive periods?
Risks : This is defined as the probability of serious environmental effects. The accuracy of
assessing risk is dependent upon the knowledge and understanding of the activities and the
potential impact areas.
Importance : This is defined as the value that is attached to a specific area in its present state.
For example, a local community may value a short stretch of beach for bathing or a small
marsh for hunting. Alternatively, the impact area may be of a regional, provincial or even
national importance.
Mitigation : Are solutions to problems available? Existing technology may provide a solution to a
silting problem expected during construction of an access road or bank erosion resulting form a
new stream configuration.
While single screening approaches may be applied, they may also be used in
conjunction with each other. Screening techniques can, therefore, vary in sophistication, but
there is considerable merit in keeping this activity as simple as possible. A simple approach
such as a positive and negative list approach, will allow both the development proponent and
the authorizing agency to clearly understand EIA requirements in advance. This approach may
need to be reinforced with an IEE approach in order to accommodate non-listed projects.
Alternatively, a simple questionnaire approach may be acceptable.
4.2.2 Scoping (Depth of Analysis)
Scoping is the procedure used to determine the "terms of reference" of an EIA and
concentrates on identifying those issues which require in-depth analysis. Scoping has the
following specific objectives:
To identify the major environmental issues that must be assessed in the EIA.
To determine the range of alternatives to the project which should be examined.
To determine the boundary for the study in a geographical context.
To establish a procedure for the preparation of an EIS and its format.
Scoping often involves contact between those proposing a development and the public,
and it is a procedure that allows interested persons to state their concerns before an EIA is
undertaken. Participation of the public in scoping is important because it may help identify
people who have useful knowledge about the proposed site. It also allows them to propose
alternatives and suggest the kind of study that should be undertaken. Scoping is the first stage
in creating public confidence in EIA and the decision-making process (US Council on
Environmental Quality, 1981). It is helpful in providing participants with a report from the
7/30/2019 EIA Guidelines
29/84
26
developer which contains the preliminary information. This may allow any serious issue
associated with a proposal to be identified early on.
4.3 METHODS FOR IMPACT IDENTIFICATION AND ASSESSMENT
Although there are many types of EIA methods, this section will only discuss checklists,matrices, network and overlays manuals. These represent the most widely used methods.
Before discussing these methods, it should be noted that evidence for their partial utility is often
limited. Whenever possible evidence relating to this important aspect of methods will be
considered.
4.3.1 Checklists
The checklists method lists local environmental factors, which are likely to be affected
where a development is planned. This list can contain broad categories of factors, for example,flora, fauna, hydrological regimes, surface water bodies and the atmosphere. Conversely, it can
be extensive and detailed. An example of checklist is given Table 4.
Another useful type of checklist is the "questionnaire", which presents a series of
questions relating to the impact of a project. Checklists are used to provide answers to specific
questions relating to the particular project being assessed. Once an initial question has been
answered in the affirmative, additional questions investigate the nature of particular impacts in
detail.
There have been many attempts to develop checklists by the use of weighing andscaling. Numerical weights are assigned to items of a checklist in accordance with the relative
importance of each item. Scaling is a procedure for reducing impacts on all items to a common
arbitrary scale. These methods have not been widely used because of their complexity, cost
and extensive data requirements. Also, they can be politically controversial due to the need to
assign weights for relative importance to environmental components.
4.3.2 Interaction matrices
A development of basic checklists is the interaction matrix. The most well known is theLeopold matrix development for the U.S. Geological Survey (Leopold et al, 1971). The matrix
consists of a horizontal list of development activities displayed against a vertical list of
environmental factors. The matrix is used to identify impacts by systematically checking each
development activity against each environmental parameter. If it were thought that a particular
development activity were to affect an environmental component, a mark is placed in the cell
which occurs at the intersection of the activity and the environmental component. It should be
noted that the matrix can be expanded to cover the construction and operational phases of
various components on horizontal scale or more than one alternative can be represented on thehorizontal scale. An illustrative example is shown in Table 4.1.
7/30/2019 EIA Guidelines
30/84
27
Table 4.1: Example: Checklist of impacts of a hydropower project
S.
NO
PROJECT PHASE /
ENVIRONMENTAL IMPACT
IMPACT NO
CHANGE
SHORT
TERM
LONG
TERM
POSITIVE NEGATIVE
A. Impacts due to Project Location
1 Displacement of People *2 Loss of Land / Change in Land
Use
* *
3 Encroachment into Forest Land /
Loss of Forest Produce
* *
4 Encroachment into Nature
Reserves & Wildlife
*
5 Loss of Historical/Cultural
Monuments
*
6 Loss of Infrastructure *
7 Erosion and Silt Risks * *
8Disruption of Hydrological
Balance*
B. Impacts due to ProjectConstruction
9 Soil Erosion at Construction Sites * *
Muck Generation * *
Transportation of muck and
construction material
* *
10 Deforestation * *
11 Human Health * *
12 Water Quality * *
13 Cultural Hazards * *
14 Air and Noise Pollution * *
C. Impacts due to Project Operation
15 Reservoir Evaporation Losses *
16 Deforestation * *
17 Effect on Wildlife *
18 Change in Water Quality & Risk of
Eutrophication
*
19 Increased Incidences of Water
Borne Diseases
*
20 Impact on Fish and Aquatic Life *
21 Public Health * *
22 Drainage *
D. Positive Impacts
23 Clean and renewable source of
energy
* *
24 Employment Opportunities * * *
25 Catchment Area Treatment * *
26 Recreation and Tourism Potential * *
27 Additional Habitat for Aquatic
Wildlife / Wetland Species
* *
28 Fisheries & Aquaculture potential * *
29 Benefits to Economy * *
30 Reduction in Air Pollution * *
31 Reduction in Greenhouse gas
Emissions
* *
32 Increased Infrastructure * *
7/30/2019 EIA Guidelines
31/84
28
After the initial identification of impacts, it is possible to use the same matrix to indicate
those impacts considered to be the most important. In the original Leopold matrix, scores from
a 1-10 scale can be assigned to describe the importance and magnitude of individual impacts.
Importance refers to the significance of an impact and magnitude to its scale and extent.
Leopold-type matrices are easy to use and perhaps the most widely employed and successful
of all EIA methods.
4.3.3 Network
This method, although widely discussed in the EIA literature, has not been used as
extensively as matrices and simple checklists. It was developed to explicitly consider the
secondary, tertiary and higher order impacts that can arise from an initial impact. Checklists
and matrices structure thinking towards impacts on single environmental entities. When using a
matrix the effects of vegetation clearance, for example, are considered in relation to all listed
environmental components. With this approach to impact identification, there is a danger that
linked impacts are omitted. In this case, vegetation clearance can have an initial or primary
impact on both soils and animal and bird life. However, the impact on soils can result in erosion
and this can increase the sediment load in rivers. This sediment load can, in turn, affect life of
reservoir and various forms of aquatic life. Should the river support a commercial or
recreational fishery, then any changes in aquatic structure might have economic repercussions.
4.3.4 Overlays
The overlays approach to impact assessment involves the use of a series of
transparencies. The study area is subdivided into convenient geographical units, based on
uniformly spaced grid points, topographic features or differing land uses. Within each unit, the
assessor collects information on environmental factors and human concerns, through various
sources/techniques. The concerns are assembled into a set of factors, each having a common
basis and regional maps (overlays) are drawn for each factor. The degree of impact or
importance of each factor is represented by varying the degree of shading with light shading
indicating low impact and heavy shading the highest impact. The overlays are then stacked one
on the other using the same reference points and the total degree of shading is visually
observed. Those areas on the maps with the highest shading are thus the most acceptable
alternatives. Because of the reduction in light transparency with each overlay, only about 10
maps or overlays can be used.
This method is easily adaptable for use with a computer which may be programmed to
perform the tasks of aggregating the predicted impacts for each geographical subdivision and
of searching for the area least affected. Automated procedure can be used for selecting
sequence of unit areas for routing highways, canal network, pipelines, and other corridors. The
7/30/2019 EIA Guidelines
32/84
29
computer method is more flexible, an advantage whenever the reviewer suggests that the
system of weights be changed.
The overlay approach can accommodate both qualitative and quantitative data. For
example, water is often shaded blue while land elevation can be shown by contour lines. There
are, however, limits to the number of different types of data that can be comprehended in one
display. A computerized version thus has greater flexibility. Although in this case, too, the
individual cartographic displays may be too complex to follow in sequence, the final maps
(optimum corridors for each alternative, and comparisons amongst alternative) are readily
prepared and understood.
When using overlays, the burden of ensuring comprehensiveness is largely on the
analyst. Also, the approach is selective because there is a limit to the number of transparencies
that can be viewed together. Finally, extreme impacts with small probabilities of occurrence are
not considered. A skilled assessor may indicate in a footnote or on a supplementary map,
however, those areas near proposed corridors where there is a possibility of landslides, floods,
or other unacceptable risks. Overlays do have some strong features too. For example, overlays
may be mutually exclusive provided that checklists of concerns, effects, and impacts are
prepared at the outset and a simplified matrix-type analysis is undertaken. Also, the objectivity
of the overlay method is very good with respect to the spatial positioning of effects and impacts
(e.g., area of land to be flooded), but is otherwise low. Overlays are not effective in estimating
or displaying uncertainty and interactions.
4.4 SOCIO-ECONOMIC ASSESSMENT
A hydropower project generally requires construction of the diversion barrage, headrace
tunnel, powerhouse etc. Construction of the project facilities would require acquisition of land,
out of which part may be the government/forest land and the remaining private land owned by
the individuals. Expropriation of private lands may cause social disruption and economic loss
for the project affected families/people. The workers, which will be migrating in the project area
during construction, would also cause certain demographic and social changes, since theproject is normally situated in remote area.
A survey should be undertaken to study and understand the socio economic conditions
of these project-affected households and to examine the impact of the proposed project
thereupon.
Socio-Economic Profile of Project Affected People (PAP):
It should cover analysis of the following:
Sex and Age
Educational Attainment:
Religion and Caste
7/30/2019 EIA Guidelines
33/84
30
Occupation\
Family Income
Marital Status
Family Pattern and Size
Enlistment
Family Assets and Acquisition
Infrastructure Facilities
Social Impact Analysis
It should cover analysis of the following:
Pressure on existing infrastructure/resources : Creation of the project infrastructure like
roads, electric supply would also be available for the project affected people.Incidence of water related diseases: The aggregation of labour, discharge of uncontrolled
wastewater and formation of stagnant water would result in occurrence/spread of diseases like
malaria, cholera etc.
Cultural conflicts: People in the project area have distinct habits of food and clothing along
with deep religious faiths celebrating their festivals with great enthusiasm. Hence, chances of
cultural conflicts may take place with that of migratory population.
Cost of living and inflation: Minor increase in cost of living and inflation may be experienced
in the project area as a result of increased commercial activities.
Resettlement, Rehabilitation and Social Response Program (SRP) of the Project
Ministry of Rural Development, Government of India have published the National Policy
on Resettlement and Rehabilitation for Project Affected Families (NPRR-2003) in February,
2004 which gives guidelines for resettlement and rehabilitation of project affected families.
Family to be displaced due to the project are to be identified. Only partial acquisition of
agricultural land from the only four families of Lumber village would be necessitated for the
project. If the number of affected families is much less than 250, then the NPRR-2003 is notcompulsorily applicable.
The affected families should be compensated for acquisition of their land in accordance
with the local norms applicable for such acquisition. It is also obvious that such compensation
would never render sufficient to compensate the indirect losses to the local people. The local
population of the project area deserves certain incentives towards their social upliftment, so that
they feel themselves an integral part of the overall development. With this principal objective in
view, the project proponent should prepare a Social Response Program (SRP) for the project.
The SRP should be carried out with active involvement of the affected people. It provides forlivelihood support, infrastructure development, education assistance, public health facility,
7/30/2019 EIA Guidelines
34/84
31
gender support, water conservation and harvesting and creation of employment opportunities.
A separate body comprising of representatives from project management & public
representatives should be formed for monitoring and concerted evaluation of the SRP.
7/30/2019 EIA Guidelines
35/84
32
SECTION 5
WATER QUALITY MONITORING PROGRAM
Assessment of potential impacts of a hydropower development to water quality firstrequires an effective plan to acquire sufficient baseline information to make the assessments.
At the time of construction activities begin, a modified monitoring program is necessary to
evaluate the effectiveness of measures to prevent adverse effects to water quality. Ultimately,
additional modifications to the monitoring plan are needed to evaluate the actual effects of the
project on water quality and to enable identification of unanticipated effects and/or ineffective
protection measures. The first monitoring plan, to develop a baseline of the information, should
be a component of the Terms of References (TOR) developed within the Environmental Impact
Assessment (EIA) process. The second and third modifications to the baseline monitoring
program are to be presented in the Environmental Management Plan (EMP) which is a part of
the EIA report.
5.1 EFFECTS ON WATER QUALITY
5.1.1 Water Quality Effects During Construction
Generally, effects of construction on water quality in a river system stem primarily from
the discharge of wastewater (both construction waste water and sanitary waste water from
workforce housing areas) to the adjacent river and runoff from quarries and construction areas.Discharge of wastewater from construction areas that may affect water quality include
discharge of water used to wash concrete mixing and hauling equipment, wash water used to
prepare concrete aggregate, and other minor on-site discharges of water to the river system.
Generally, the effect is an increase in suspended sediment loads and an increase in alkalinity of
the water due to discharge of calcium carbonate (CaCO3), a component of concrete. However,
dissolved solids may also increase significantly as a consequence of runoff from the
construction area. If excavated material is deposited in or adjacent to the river channel,
suspended solids concentrations and dissolved solids concentrations may increase further. Of
particular concern with deposition of spoil materials is the potential for increasing
concentrations of heavy metals such as iron, manganese, copper, lead, and other heavy
metals.
Deposition of suspended solids in the river channel downstream from the construction
area may cause changes in the river channel if significant amounts of sediment is contributed to
the river, and may cause problems with spawning areas of fish in the downstream reach of the
river.
Discharge of sanitary waste from work camps and other human sanitary facilities can
affect Biochemical Oxygen Demand (BOD) in the river as well as increasing fecal coliform
7/30/2019 EIA Guidelines
36/84
33
bacteria concentrations, an indicator of potential disease risk to to downstream users. Suitable
handling and treatment of sanitary wastes will significantly reduce the potential for adverse
effects to water quality from this source.
Runoff from construction areas constitutes a more problematic situation. Potential water
quality effects on runoff from construction sites include increases in sediment emanating from
erosion from disturbed areas (construction staging areas, excavated areas, quarries, access
road construction, spoil disposal areas), flushing of oils, greases and other hydrocarbon
lubricants from maintenance areas, and potential flushing of other hazardous materials used at
the project site for construction purposes. Containment of such materials and installation of
erosion barriers will significantly reduce the potential effects to water quality. Maintenance of
the erosion control measures and containment facilities must be accomplished throughout the
construction period.
5.1.2 Water Quality Effects During Operation
Most of the significant water quality effects are realized only after the project begins
operation. At this time the affected river has been partitioned into two major components:
Upstream of the project site and Downstream of the project site.
5.1.2.1 Water quality effects upstream of the project site
In general, a hydropower project can not and should not directly affect water quality
conditions upstream of the project site. Any realized changes in water quality are generallyattributable to changes in land use patterns, changes in population distributions and changes in
industrial or commercial installations in the upper river basin. Consequently, any changes in
water quality conditions upstream will be reflected in changes in water quality downstream.
Management of land use, population distribution and industrial development upstream is
basically the only option available to minimize these impacts.
5.1.2.2 Water quality effects downstream of the project site
The more significant effects of a hydropower development on water quality, at least fromthe perspective of ecological characteristics and human use, are generally realized in the river
downstream of the project site. The magnitude of the changes in water quality parameters
realized downstream from the project are attributable to the operating regime of the project
which defines the hydrologic regime. Aside from the alteration of the hydrologic regime, two of
the more common water quality parameters that are affected by a small hydropower
development in the downstream reach are water temperature and dissolved oxygen.
While the temperature regime in the river is not necessarily considered an adverse
condition, it is the changes in the biological community that are affected by those changes thatcan become significant. The temperature regime of a river may affect the types of organisms
7/30/2019 EIA Guidelines
37/84
34
that are able to survive in the affected reach, the biological productivity within the reach
(generally, biological production is positively correlated with temperature in aquatic systems),
and the reproductive cycles of aquatic organisms downstream from the project. It should be
noted that although some species may cue reproductive cycles on water temperature, other
species cue their cycles on changing hydrologic regimes that may or may not be correlated with
seasonal changes in water temperature. Therefore, the significance of predicted changes in
water temperature must be framed in reference to the biological requirements of the organisms
inhabiting the river downstream of the project.
5.2 PURPOSE OF WATER QUALITY MONITORING
Generally, the statement of purpose for a water quality monitoring program is fairly
straight forward. Though the development cycle, three basic monitoring programs will be
designed and implemented corresponding to the baseline description period (EIA), construction
period, and operation period.
The primary purpose of the baseline monitoring program are twofold: First, the baseline
monitoring program should provide sufficient information to enable accurate (justifiable)
predictions of potential effects of the hydropower project on water quality parameters; second,
the baseline data set will provide the standard against which project effects and/or mitigation
effectiveness can be determined. Obviously, it is necessary to determine the starting point
condition to determine if changes occur.
The purpose of the water quality monitoring program for the construction period,
likewise, can serve two purposes: First, the program should be designed to enable evaluation
of the effect of various construction activities and construction related facilities on water quality;
second, certain components of the program can provide further baseline information for
determining the effect of project operation on water quality.
The purpose of the final water quality monitoring program to be implemented during
operation also has two purposes: First, data collected during the operational period are
compared with the baseline data to determine if projections made in the EIA are accurate and
mitigation or avoidance measures are effective; second, the monitoring program can be used to
determine if changes occur during the operation period and might require attention and can be
used as a basis to determine the sources of any pollutants.
5.3 SAMPLING DESIGN
Design of the water quality monitoring program is key to obtaining a useful set of
information for describing baseline conditions and measuring the effects of construction and
operation on those conditions. Thus, the sampling design presented in the monitoring plans is
the most important part of the plan.
7/30/2019 EIA Guidelines
38/84
35
5.3.1 Duration
The duration of the water quality monitoring programs will vary according to the stage in
project development.
For baseline monitoring, the minimum length of time necessary for basic understanding
of cycles in water quality parameters is one year. The baseline monitoring program should
provide sufficient information on all parameters included in the monitoring program to
demonstrate annual cycles in concentrations or conditions. While the data set should provide at
least one full year of sampling, continuing monitoring for longer periods would facilitate
understanding of year-to-year variation in those parameters. Consequently, the baseline
monitoring program should be implemented for as long as possible given the schedule for
project construction and completion.
Determination of the duration of the construction period monitoring program should
correspond to the construction period, including preparatory period. In addition to monitoring
the effects of construction, continuation of monitoring parameters included in the baseline
program will provide additional foundation for measuring the effects of the project once it
becomes operational.
The duration of the monitoring program to be implemented during operation of the
project will depend upon specific conditions at the project. For some parameters, the monitoring
program could extend throughout the life of the project. For other parameters, sampling for a
period of up to 5 years will provide an adequate basis for evaluating the effect of the project.
5.3.2 Sampling frequency
As defined above, recommended parameters for inclusion in the baseline, construction
period, and operational period include two groups: Those for general monitoring and those for
assessment monitoring.
During the baseline period (EIA preparation), parameters included in general monitoring
should be measured on at least a biweekly basis, preferably on a weekly basis for one full year.
Parameters included for the assessment monitoring include some parameters that should be
measured on a monthly basis, with the remainder measured on a quarterly or seasonal basis
through the planning phase of the project.
The sampling frequency during the construction period, particularly for parameters that
may be affected by construction activities should be measured at least on a monthly basis
throughout the construction period. Parameters that are included in the general monitoring
program and contribute to the baseline descriptions should be measured at the same frequency
as determined for the planning (EIA) phase.
The sampling frequency of parameters during the operational phase may be divided into
two periods: Initial effects and long-term effects. The basic operational monitoring program
should include sampling of the various parameters on at least a monthly basis for a period of up
7/30/2019 EIA Guidelines
39/84
36
to 5 years after initial operation of the project. Once the initial period expires, the monitoring
program may be reduced to include the only a few basic, indicative parameters. If significant
changes in one or more of the basic monitoring parameters occur, expansion of the monitoring
program for a specified period of time may be necessary to identify the cause of those changes.
In general, during the long-term monitoring phase, the basic set of parameters should be
sampled on a monthly basis.
5.3.3 Sampling Locations
The number of sampling locations for water quality will depend on the particular project
configuration. For single projects (located on a single river), a minimum of three sampling
locations is needed for both baseline monitoring and construction and operation monitoring.
For construction monitoring, additional locations may be included to enable evaluation
of possible pollutants from various areas of the construction facilities. For example, an
additional location might be downstream from construction staging areas or downstream from
labour camps. If some of these facilities are located on the tributaries of the main river, the
samples should be collected upstream and downstream from those facilities.
5.3.4 Sample and Data Analysis
To the extent possible, parameters recommended for the monitoring program,
particularly those included in the general monitoring group, may be measured in the field with
appropriate instrumentation and/or field kits. The remaining parameters generally requiretransport of water samples to a laboratory for analysis. For parameters that require laboratory
analysis, sample bottles and containers with appropriate preservatives, if necessary, can
normally be obtained from the laboratory. A preliminary list of water quality laboratories (private,
governmental and non-governmental) is presented in Annexure 1. A list of possible field
equipments to conduct the monitoring program is included in Annexure 2. As with any field or
laboratory instrumentation, it is necessary to standardize the equipment according to
manufacturer specifications throughout the field effort.
All samples should be clearly labeled with an identifying number and all pertinent
information regarding the sample recorded on separate data sheets for each location and
sampling time. A sample data sheet for use in the field should be presented as part of the
proposed monitoring plan. In addition to the field data sheets, it is highly recommended that a
Chain of Custody form also be used to document delivery of the samples from the field to the
laboratory. Samples collected for analysis in the field should be taken to the laboratory as soon
as possible. The length of time a sample may be held prior to analysis can be determined in
consultation with the laboratory.
The water quality monitoring plans should include a section on the logistics of data
collection and sample handling. Information to be included in the water quality monitoring plans
7/30/2019 EIA Guidelines
40/84
37
should include the field and laboratory procedures that will be used to analyze the samples.
There are a number of Standard Methods for analysis of water quality. The particular methods
that are to be used should be cited in the monitoring plan.
Statistical analysis of the results of the water quality analysis will generally vary from
phase to phase and project to project. For baseline monitoring, particular attention should be
given to identifying seasonal cycles and longitudinal trends. The data may then be used to
estimate how the project will affect each parameter. In some cases, it will be appropriate to use
the data for calibration of one or more water quality simulation models. Relatively simple
models are available to determine the effect of a project on water temperature and dissolved
oxygen in the river.
The most important component of the data analysis during the construction and
operating periods is comparison of the pre-project condition or baseline condition with the
construction and operating conditions. Such analysis will determine if and by how much impacts
to water quality have occurred and are used as determinants of the effectiveness of any
mitigation measures that have been incorporated into the project configuration. As construction
and operating data are acquired over the duration of the monitoring program, additional
analysis of trends in water quality changes may be identified from the monitoring data. Such
trend analysis might include seasonal changes as well as changes that occur gradually through
the years.
5.3.5 Identification of Water Quality Laboratory
An important component of the water quality monitoring plans is the identification of the
institutions responsible for collecting the samples and for conducting the analysis of those
samples. Measurements of water quality parameters in the field and collection of the water
quality samples for analysis in the laboratory may be performed by trained field technicians
employed by the environmental consultant. Samples collected for laboratory analysis should be
conveyed to the laboratory according to the protocol furnished by the selected water quality
laboratory.
5.3.6 Quality Control
An issue that should be addressed in the water quality monitoring plans relates to
quality assurance that the data presented are accurate and reliable. An acceptable quality
assurance program will consist of both external and internal controls by the laboratory providing
the analytical evaluations of samples.
First, the developer and/or the environmental consultant should implement an external
quality control procedure. The procedure should at least include submittal of duplicate samples
from one or more locations on each sampling data. These samples should be blind samples
such that the water quality laboratory is unaware of which samples are duplicated. A second
7/30/2019 EIA Guidelines
41/84
38
possible component of an external quality control procedure could consist of periodic submittal
of duplicate samples to a second laboratory, one not responsible for the routine analysis
process.
Second, the quality control procedures adopted by the water quality laboratory should
be presented in the plans. An acceptable procedure should include duplication of samples by
the quality control officer of the laboratory after submittal of the sample to the laboratory but
prior to delivery to the laboratory technicians. The procedure should also include submittal of
blank samples and spiked samples (samples with known concentrations of a parameter) to
the laboratory technicians for analysis. Reports from the laboratory should include results of the
internal quality control procedure for review by the developer/environmental consultant and the
reviewing agencies.
5.3.7 Reporting
Reporting of water quality data will be dependent upon the phase of the water quality
monitoring program. Data and analysis of those data obtained during the pre-construction
phase are to be presented in the EIA. As appropriate raw water quality data should be
presented with the EIA to enable independent evaluation of results. A condition of the TOR may
include a requirement for submittal of the water quality data in a standardized format for
incorporation into a country wide data base. The water quality data should be submitted with
the EIA.
Reporting of results of the construction and operation monitoring program will also be
submitted to the concerned agencies for review. The schedule for reporting the data will be
negotiated as part of the approval of the EMP and will likely become conditions of the license to
construct and operate the project. An appropriate schedule for reporting of results from the
monitoring of construction activities would be on a quarterly basis. This will depend on the
monitoring program itself and the frequency with which samples are being collected.
Reporting of results of operation monitoring will likely be divided into two phases: an
initial phase for a period up to five years with reporting on a semiannual basis and a second
period following the initial period with reporting on an annual basis.
5.4 REGULATORY AUDIT
In developing the regulatory audit procedure for a given hydropower project, the
following areas should specified:
1. Purpose
The comprehensive audit will cover all aspects of engineering, environmental and social
considerations regarding the project. With respect to water quality, the regulatory audit will seek
to determine if projections of the EIA are accurate and whether or not measures to mitigate
7/30/2019 EIA Guidelines
42/84
39
anticipated adverse effects are effective. Thus, the objective of the regulatory audit of the water
quality monitoring program is to confirm the results of the monitoring program are accurate.
2. Acquisition of information and sampling design
The regulatory audit of water quality monitoring will consist of two components: first, the
audit will consist of a detailed review of data reported by the developer and construction
contractor, including a review of the water quality control procedures and results implemented
by the developer; second, the audit consist of an independent analysis of water quality
conditions at the project site. This will consist of acquisition of measurements and samples in
the same manner and location defined in the EMP. An independent laboratory, one not involved
in the continuing monitoring program, should be selected to analyze the samples. Selection of
the laboratory may consist either of using the governmental laboratory or another laboratory.
3. Analysis
Analysis of results of the regulatory audit will consist of two factors: first, the data will be
compared with available water quality standards established for hydropower projects; second,
the data will be compared with results of the monitoring program submitted by the developer.
4. Presentation and reporting
Results of the water quality component of the environmental audit are to be included in
the environmental audit report submitted to the government.
5.5 INTERPRE