EIA Guidelines

  • Upload
    saleemb

  • View
    227

  • Download
    0

Embed Size (px)

Citation preview

  • 7/30/2019 EIA Guidelines

    1/84

    1

    VERSION 2

    STANDARDS / MANUALS / GUIDELINES FORSMALL HYDRO DEVELOPMENT

    SPONSOR:MINISTRYOFNEWANDRENEWABLEENERGYGOVERNMENTOFINDIA

    GUIDELINES FOR

    ENVIRONMENTAL IMPACT ASSESSMENT FOR

    SMALL HYDROPOWER PROJECTS

    LEADORGANISATION:ALTERNATEHYDROENERGYCENTRE

    INDIANINSTITUTEOFTECHNOLOGY,ROORKEE

  • 7/30/2019 EIA Guidelines

    2/84

    i

    CONTENTS

    TITLE PAGE NO.

    Section-1 Guidelines on Environmental Impacts and Need for Small

    Hydropower Projects

    1

    1.1 Small Hydro-Potential and Projects 11.2 Environmental Impacts of Small Hydropower Projects 3

    1.3 Positive Impacts 4

    1.4 Meaning of EIA 5

    1.5 Need of Guidelines for EIA of Small Hydropower Projects 6

    Section-2 Environmental Acts and Procedures for Clearance of Hydropower

    Projects in India

    8

    2.1 Environmental Acts 8

    2.2 Procedure for Obtaining Environmental Clearance 10

    Section-3 Baseline Data 16

    3.1 Land Environment 16

    3.2 Air and Water Environment 18

    3.3 Biological Environment 20

    3.4 Socioeconomic Environment 20

    Section-4 Environmental Impact Assessment Methodology 22

    4.1 Levels of EIA 22

    4.2 EIA Procedure 22

    4.3 Methods for Impact Identification and Assessment 26

    4.4 Socio-economic Assessment 29

    Section-5 Water Quality Monitoring Program 32

    5.1 Effects on Water Quality 32

    5.2 Purpose of water Quality Monitoring 34

    5.3 Sampling Design 34

    5.4 Regulatory Audit 38

    5.5 Interpretation of Monitoring Results 39

    Section-6 Stake Holders in EIA Process 42

    6.1 Ways to Identify Stakeholders and Group Representatives 43

    6.2 Involving Stakeholders 436.3 Public Consultation 45

    Section-7 Principles and Procedures of an Environmental Management Plan 47

    7.1 Environmental Monitoring 47

    7.2 Environmental Auditing 49

    7.3 Implementation of Environmental Management Plan 49

    Section-8 Preparation of Terms of References 58

    8.1 Basic Objectives and Purpose 58

    8.2 Good practice Criteria for the Preparation of TOR 59

  • 7/30/2019 EIA Guidelines

    3/84

    ii

    TITLE PAGE NO.

    Annexure I Useful References 64

    Annexure II Definition of Terms Related to Soil, Air and Water Environment of a

    Hydropower Project

    66

    Annexure III Environmental Standards prescribed by Central Pollution Control

    Board

    72

    Annexure IV Format of Environmental Impact Assessment Document 75Annexure V Environmental Appraisal Questionnaire As Prescribed in Appendix I

    Form of EIA Notification (MoEF, 2006)

    77

  • 7/30/2019 EIA Guidelines

    4/84

    1

    SECTION 1

    GUIDELINES ON ENVIRONMENTAL IMPACTS AND NEED FORSMALL HYDROPOWER PROJECTS

    Developing countries need increased energy supplies in order to bring about

    improvement in the quality of life of their people. Sustainable and environmentally sound

    progress towards energy self reliance is probably best achieved through development of

    renewable energy sources as these will eventually be the only sources available to sustain the

    societies. Out of various renewable energy sources, small hydropower is the only source which

    has sufficient potential to accommodate remote area needs. Although the adverse

    environmental impacts of individual small hydropower project (SHP) may not be significant and

    yet, the aggregate impact of several such projects in vicinity could be of a magnitude to cause

    significant damage to the environment.

    EIA study should provide information based on scientific analysis and adequate data

    basis as such information is to be placed in public domain and is subject to critical review by

    public. As a scientific analysis of the environmental constraints the EIA constitutes an important

    part of pre-project study which helps in improving project standard.

    EIA study is aimed at protecting the environment by integrating the environmental

    issues in planning process.

    1.1 SMALL HYDRO POTENTIAL AND PROSPECTS

    Small hydro is a renewable, non-polluting and environmentally benign source of energy.

    In India, depending on the capacities, small hydropower projects are categorized as Micro, Mini

    and Small hydro projects as under.

    Mini hydro - 10 kW to 99 KW

    Micro hydro - 100 kW to 999 kW

    Small hydro - 1,000 kW to 25,000 kW

    Depending on the head, SHPs may be further classified as low head (below 3 meters),

    medium head (from 30 75 meters) and high head (above 75 meters).

    The estimated potential of small hydro power in India is about 15,000 MW. Thus far

    about 4250 potential sites have been identified aggregating to a capacity of 10,000 MW.

    However, so far 466 projects in 29 states aggregating to 1530 MW have been installed and

    projects amounting to 610 MW are under implementation. This offers a tremendous potential of

    small hydro power to be tapped in India. A very large number of villages have potential forsetting up mini, micro and small hydroelectric projects. It presents a huge business potential for

    investors and equipment manufactures.

  • 7/30/2019 EIA Guidelines

    5/84

    2

    Potential available - 15,000 MW

    Installed so far - 1530 MW; Projects under implementation - 610 MW

    1.2 ENVIRONMENTAL IMPACTS OF SMALL HYDROPOWER PROJECTS

    A hydropower scheme entails change in use of land and water. Magnitude of suchchange depends on the selected site configuration. An illustrative site configuration is shown

    below. The environmental impacts of SHPs are positive (favourable) and negative (undesirable)

    in nature.

    Figure 1.1: Physical components of small hydropower project

    The environmental impacts of small hydropower project may be summarized as follows:

    Table 1.1: Environmental impacts of small hydropower projects

    Activity Adverse Impact

    Construction of road,

    dam, surface powerhouse and switch

    yard, diversion tunnel,

    channel

    1. Reservoir sedimentation and deterioration of water quality

    2. Air and noise pollution and disturbance to flora and faunaby work force

    3. Visual intrusion caused by construction activity

    4. Disturbance of recreational spots (e.g. waterfalls) and

    activities

    5. Soil erosion due to removal of vegetation and excavation

    of construction material

    6. Alteration in ground water flow

    Construction of

    transmission line

    1. Damaging flora due to right of way clearing

    2. Endangering the lives of fauna

  • 7/30/2019 EIA Guidelines

    6/84

    3

    3. Visual intrusion

    Stream diversion

    through channel and

    conduit

    1. Loss of habitat of fish and other aquatic flora and fauna

    2. Decrease in dilution capacity of stream

    3. Depletion in ground water recharge where diversion is

    taken off from effluent stream

    4. Loss of waterfalls and other recreational activities

    Ponding 1. Flow disruption

    2. Channel degradation during generation or spilling and

    flushing of silt from dam

    3. Trapped nutrients and sediments, eutrophication

    4. Changed water temperature

    5. Changes in land uses: (a) submergence of agricultural and

    forest land (b) submergence of human settlement and

    displacement of population (c) submergence of

    monuments/sites of historic importance (d) loss of

    whitewater recreation

    6. Change in aquatic plant life and fish species

    7. High evaporation rate

    8. Sedimentation adversely affects fish spawning areas by

    burying them9. Provides increased habitat for mosquitoes and snails

    which are vectors of diseases like malaria, yellow fever,

    dengue, encephalitis and schistosomiasis

    Operation of

    hydropower station

    1. Increase in pollution concentration in the downstream due

    to release of pollutants from residential areas, hydropower

    plant

    2. Released water containing low dissolved oxygen

    3. Fish mortality from turbine passage4. Sonic impact: noise level may increase

    Peaking operation of

    power station

    1. Damage to fish spawning ground and nesting ground for

    water fowls and other aquatic birds

    2. Erosion of banks

    3. Transport of nutrients from the shallow water to deeper

    water in pond

    4. Affects recreational facilities due to fluctuating water level

    5. Exposure of drawdown zone creates visual intrusion

  • 7/30/2019 EIA Guidelines

    7/84

    4

    1.3 POSITIVE IMPACTS

    Positive environmental impacts of hydropower projects are somehow ignored as a

    routine probably due to the fact that these projects are conveniently considered as demanding

    an environmental price. It is equally important to highlight and quantify (to the extent possible)

    positive environmental impacts of SHPs.

    Positive Socio-Economic Impacts

    1. No transmission loss due to commercial availability of power at customers door step

    2. Multiplier effect of electricity on economy of the area especially in remote areas such as

    agro-industrial units

    3. Improvement of agricultural produce through lift irrigation which requires energy

    4. Project related infrastructure (roads, health facilities, education facilities will help the

    local people as well as project affected people. There will be net improvement in

    community health

    5. Improvement in living standard of local people

    6. Creation of reservoir will increase potential for fish and fisheries (catch and income)

    7. Generation of employment opportunities locally. Direct employment during construction

    and indirect employment in allied activities

    8. Motivation of higher literacy

    9. Check on migration from villages to towns, thereby checking urban concentration of

    population

    10. Increasing tourism potential water sports, boating, fishing etc.

    11. It helps in checking deforestation which is taking place to meet food, fodder and fuel

    demands in rural, remote areas.

    12. It is significant for off-grid, rural, remote area applications in far flung isolated

    communities having no chances of grid extension for years to come. It is operationally

    flexible, suitable for peaking support to the local grid as well as for stand alone

    applications in isolated remote areas.

    13. Small hydro does not require much expertise to build and operate. Components of smallhydro projects are simple and fairly visible at site. They can become centre of education.

    14. In specific cases SHPs are eligible for carbon credits through reduction in CO2 emission

    and adding sink for CO2 via plantation schemes.

    Positive Ecological/Environmental Impacts

    1. Clean and renewable source of energy. SHPs result in saving of non-renewable fuel

    resources such as coal, liquid fuels and gases.

    2. It is benign source of power generation, harnessing only gravitational potential of water

    to make it yield energy in a continuum

  • 7/30/2019 EIA Guidelines

    8/84

    5

    3. Decrease of pollution in the area (hydro replacing diesel generation, electricity replacing

    polluting energy sources)

    4. Increased water surface creates habitat for aquatic life in or near the reservoir.

    Receiving waters create dry mudflats which provide feeding sites for migratory birds and

    breeding habitat for resident species.

    5. Improved ground water table enhancing greenery all around

    6. Improvement towards vegetation and plantation associated with the project

    (compensatory afforestation) and thus providing sink for CO2 emission

    7. Improved habitat

    8. Lake shore environment in otherwise dry areas

    9. Modification of micro climate due to storage and regulation of water to a more or less

    uniform pattern. This also leads to a somewhat stabilizing impact on local environment

    influencing flora and fauna aquatic as well as terrestrial.

    10. SHPs are environmentally more friendlier than conventional large hydro plants:

    a. Non-involvement of setting up of large dams and thus not associated with

    problems of deforestation, submergence or rehabilitation

    b. Non-polluting and environmentally benign. It is one of the least CO2 emission

    responsible power sources, even by considering full energy chain right from the

    impact of production of plant equipment etc.

    c. Least impact on flora and fauna (aquatic and terrestrial) and biodiversity due to

    localised nature of activities

    11. There may be overall improvement in biodiversity due to creation of habitats.

    1.4 MEANING OF EIA

    EIA is an activity designed to identify, predict and describe in appropriate terms the

    primary and secondary changes due to a proposed action. Such actions may include policies,

    plans, programmes and projects. EIA covers the biophysical environment, mans health, the

    quality of life and social environment, and communicates results in a form which is

    understandable by the community and decision makers. Thus, EIA is required not only for a

    particular hydropower project but also for a set of projects (existing and proposed) under a plan

    or a programme.

    The EIA should contain descriptions of both the likely beneficial and adverse impacts

    (short and long-term). The EIA approach should be inter-disciplinary, systematic,

    comprehensive and capable of presenting results that are understandable to non-experts.

    Assessments should indicate the possible need for pollution control measures, health care

    programmes and environmental monitoring on the basis of an understanding of the affected

    environment. The EIA process does not stop at the production of an Environmental Impact

  • 7/30/2019 EIA Guidelines

    9/84

    6

    Statement (EIS) or the granting of project authorisation, but continues throughout the life of a

    project.

    The potential advantages of EIA are more efficient use of resources and improved

    quality of life. If the probable environmental, social and health consequences of proposed

    development are known from an early stage, attempts can be made to minimise adverse

    impacts and maximize beneficial impacts.

    1.5 NEED OF GUIDELINES FOR EIA OF SMALL HYDROPOWER PROJECTS

    A series of standards, guidelines and manuals have been brought out by various

    agencies dealing with environmental impact assessment of large river valley/hydropower

    projects. However, such literature for small hydropower projects is not available. There is an

    urgent need to develop and adopt simplified guidelines for SHPs.

    Guidelines have been issued by Ministry of Environment and Forests (MOEF) for

    diversion of forest land for non-forest purposes and for EIA of river valley projects. These

    guidelines are exhaustive covering wide range of environmental subjects. Small hydropower

    projects may not require same type of scrutiny as that required by large projects. Further, in

    depth study of some of environmental aspects may not be necessary.

    Basic physical character of SHP and the local factors influencing the environment are to

    some extent similar to those of large projects; the only difference is in terms of magnitude of

    change in the use of land, water and other resources. Further there are certain positive impacts

    (socio-economic and environmental) unique to small hydropower. Several of the positive socio-

    economic impacts are intangible in nature (i.e. not quantifiable) and yet could be significant.

    Intangibility does not imply insignificance.

    There is an urgency to accelerate development of small hydro and remove regional

    imbalances in economic development. Private sector has a big role to play in development of

    SHPs. Standards and guidelines are required to help concerned agencies in carrying out EIA in

    a systematic and scientific manner and thus avoiding delay in clearance of the projects.

    Keeping the above in view, these guidelines have been prepared to address needs of

    SHPs. The following aspects are covered in this manual:

    various acts and decision making process as followed in India for obtaining

    environmental clearance.

    baseline data required as per environmental indicators

    the EIA methodology

    procedure for water quality monitoring and auditing

    methods and procedures for engaging stake holders principles and procedures of environmental management plan

  • 7/30/2019 EIA Guidelines

    10/84

    7

    the preparation of terms of references and good practice criteria

    some terms related to environment

    standards of environmental parameters used in India

    prescribed format of EIA document

    Environmental Appraisal Questionnaire as prescribed in Appendix I Form I of EIA

    notification (MOEF, 2006)

    Useful references

  • 7/30/2019 EIA Guidelines

    11/84

    8

    SECTION 2

    ENVIRONMENTAL ACTS AND PROCEDURES FOR CLEARANCE OFHYDROPOWER PROJECTS IN INDIA

    2.1 ENVIRONMENTAL ACTS

    Adequate provisions for protection of environment and forests are made in the

    Constitution of India. Article 47 provides for protection and improvement of health. Article 48(A)

    is directed towards protection and improvement of environment and protection of forest and

    wildlife. Article 51(A) says it is the duty of every citizen to protect and improve natural

    environment. Following the UN Conference on Human Environment (Stockholm, 1972), a

    constitutional amendment (42, 1976) inserted relevant provisions for environment protection in

    Constitution in Part IV Directive Principles and Part IVA Fundamental Duties.

    In order to ensure sustainable development from water resources angle the Government

    of India has enacted various Acts and Legislations. Prominent among these is the Environment

    (Protection) Act, 1986 through which the Government has acquired wide powers for protecting

    the environment. Some other acts related to Water and Environment are Water (Prevention and

    Control of Pollution) (Cess) Act, 1977 (amended in 1991), Forest Conservation Act, 1980,

    Environmental Impact Assessment (EIA) Notification of MOEF 2006 and the Ministry of

    Environment and Forests Notification of January 1977 constituting the Central Ground Water

    Authority (CGWA).

    The Water (Prevention and Control of Pollution) Act, 1974 seeks to maintain or restore

    wholeness of water and the Central and State Pollution Control Boards have been established

    under this Act. According to the Water Cess Act, 1997, both Central and State Governments

    have to provide funds to the Boards for implementing this Act. The Forest Conservation Act,

    1980 provides for compensatory afforestation to make up for the diversion of forestland to non-

    forest use. The Environment (Protection) Act, 1986 was enacted in 1986 for the protection and

    improvement of human environment.

    Recently, Government of India has constituted Water Quality Assessment Authority

    (WQAA) vide MoEF/Nc. J-15011/8/2000-NRCD dated 29th May, 2001 under the chairmanship

    of Secretary, MOEF, exercising the powers under the Environment (Protection) Act, 1986. This

    authority exercises the powers and functions under the said Act for several functions. Some of

    these relevant to hydropower projects are given below:

    To direct various agencies to standardize methods for water quality monitoring

    To ensure quality of data generation of utilization thereof

    To make measures so as to ensure proper treatment of waste water with a view to restoringthe water quality of the river water bodies to meet the designated best uses

  • 7/30/2019 EIA Guidelines

    12/84

    9

    To maintain minimum discharge for sustenance of aquatic life forms in riverine system

    To promote rain water harvesting

    To utilize self assimilation capacities at the critical river stretches

    To constitute/set up state level Water Quality Review Committees (WQRCs) to coordinate

    the works to be assigned to such committees

    To deal with any environmental issues concerning surface and ground water quality referred

    to it by central Government or the State Government relating to the respective areas, for

    maintaining and/or restoration of quality to sustain designated best-uses.

    TABLE 2.1: KEY ENVIRONMENTAL LEGISLATIONS AND GUIDELINES

    Name Scope and objective Key areasOperational

    agencies/key

    players

    Water Prevention andControl of PollutionAct, 1974, 1988

    To provide for theprevention andcontrolof water pollution andenhancing the qualityof water

    Controls sewage andindustrial effluentdischarges

    Central and StatePollution ControlBoards

    Air Prevention andControl of PollutionAct 1981, 1987

    To provide for theprevention andcontrol of air pollution

    Controls emissions ofair pollutants

    Central and StatePollution ControlBoards

    Forest ConservationAct, 1980, 1988

    To consolidateacquisition ofcommon propertysuch as forests; haltIndias rapiddeforestation andresultingEnvironmentaldegradation

    Regulates access tonatural resources,state has a monopolyright over land;categorize forestsRestriction on de-reservation and usingforest for non-forestpurpose

    State governmentAnd Centralgovernment

    Wildlife ProtectionAct, 1980

    To protect wildlife

    Creates protectedareas (nationalparks/sanctuaries)categorize wildlife

    which are protected

    Wildlife advisoryboards; Central ZooAuthorities

    EnvironmentProtection Act, 1986

    To provide for theprotection andimprovement ofEnvironment

    An umbrellalegislation;supplements pollutionlaws

    Central governmentnodal agency MoEF;can delegate powersto state department ofEnvironment

    EnvironmentalClearanceNotification, 2006 OFMoEF (GOI)

    Environmental ImpactAssessment ofProjects; EnvironmentManagement Plans

    EnvironmentalProtection

    Project Developer,State and CentralGovernments.

    National Policy onR&R, 2003 of Min. of

    Rural Development,GOI

    Resettlement andRehabilitation of

    project affectedpeople

    Social Issues State Government

  • 7/30/2019 EIA Guidelines

    13/84

    10

    2.2 PROCEDURE FOR OBTAINING ENVIRONMENTAL CLEARANCE

    Before January, 1994, it was an administrative requirement for the mega projects to

    obtain environmental clearance from the MOEF, Government of India. However, in order to

    assess the impacts of the developmental projects/activities on the environment, MOEF issued a

    gazette notification on the EIA on January 27, 1994 (as amended on May 04, 1994) and made

    environmental clearance statutory for all the projects located in ecologically sensitive/fragile

    areas as notified by the Government of India from time to time, besides various categories of

    the projects as specified in the schedule of the notification. These also include water resource

    development (WRD) project. MOEF has issued a revised gazette notification on 14th

    September, 2006 suppressing the earlier notification of January 27, 1994. The new gazette

    notification is based on National Environment Policy which was approved by Union Cabinet on

    18th May, 2006. Flow chart depicting procedure of environmental clearance is given in Figure

    2.1. Flow chart depicting appraisal procedure is shown in Figure 2.2.

    2.2.1 Requirements for Environmental Clearance

    The gazette notification dated 14th September, 2006 stipulates two regulatory authorities

    to deal with environmental clearance for all new project and expansion/modernization of

    existing projects.

    Central Government in Ministry

    of Environment and Forests

    for Category A projects 50 MW

    for category B projects if located wholly or partially

    within 10 km from boundary of notified protected

    area/critically polluted area/ecosensitive area

    State Environmental

    Assessment Authority (SEIAA)for category B projects 25 MW and

  • 7/30/2019 EIA Guidelines

    14/84

    11

    and whether they are listed in the schedule of the EIA notification or not. All the projects located

    in/near wildlife sanctuaries, national parks, wetlands, mangroves, biosphere reserve also need

    environmental clearance.

    Therefore, even a small hydropower project (

  • 7/30/2019 EIA Guidelines

    15/84

    12

    categorization as B1 and B2. For categorization of projects into B1 or B2, the Ministry of

    Environment and Forests shall issue appropriate guidelines from time to time.

    Stage (II) Scoping

    Scoping refers to the process by which the Expert Appraisal Committee in the case of

    Category A projects or activities, and State level Expert Appraisal Committee in the case of

    Category B1 projects or activities, including applications for expansion and/or modernization

    and/or change in product mix of existing projects or activities, determine detailed and

    comprehensive Terms Of Reference (TOR) addressing all relevant environmental concerns for

    the preparation of an Environment Impact Assessment (EIA) Report in respect of the project or

    activity for which prior environmental clearance is sought. The Expert Appraisal Committee or

    State level Expert Appraisal Committee concerned shall determine the Terms of Reference on

    the basis of the information furnished in the prescribed application form including Terns of

    Reference proposed by the applicant, a site visit by a sub- group of Expert Appraisal

    Committee or State level Expert Appraisal Committee concerned only if considered necessary

    by the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned,

    Terms of Reference suggested by the applicant if furnished and other information that may be

    available with the Expert Appraisal Committee or State Level Expert Appraisal Committee

    concerned. All projects and activities listed as Category B shall not require Scoping and will be

    appraised on the basis of application form and the conceptual plan.

    It is required for category A and B1 projects. Purpose is to determine detailed and

    comprehensive terms of reference for preparation of EIA report.

    For category A, hydroelectric project item 1(c) (i) of schedule of TOR shall be conveyed

    along with clearance for preconstruction activities.

    Stage (III) Public consultation

    Public Consultation refers to the process by which the concerns of local affected

    persons and others who have plausible stake in the environmental impacts of the project or

    activity are ascertained with a view to taking into account all the material concerns in the project

    or activity design as appropriate.

    It is required for category A and B1 project with some exceptions e.g. modernization of

    irrigation projects, expansion of roads and B2 type and projects, projects concerning national

    defence and security. MOEF (2006) has specified procedure for conduct of public hearing.

    Purpose is to take into account concerns of local affected persons and others who have

    plausible stake in environmental impacts. Based on this, appropriate changes in the draft EIA

    and EMP shall be made. Applicant may submit a supplementary report to draft EIA for

    appraisal.

    The detailed methodology for public consultation is explained in Chapter 6.

  • 7/30/2019 EIA Guidelines

    16/84

    13

    Stage (IV) Appraisal

    Figure 2.2 depicts the procedure for project appraisal. Appraisal means the detailed

    scrutiny by the Expert Appraisal Committee or State Level Expert Appraisal Committee of the

    application and other documents like the Final EIA report, outcome of the public consultations

    including public hearing proceedings, submitted by the applicant to the regulatory authority

    concerned for grant of environmental clearance. This appraisal shall be made by Expert

    Appraisal Committee or State Level Expert Appraisal Committee concerned in a transparent

    manner in a proceeding to which the applicant shall be invited for furnishing necessary

    clarifications in person or through an authorized representative. On conclusion of this

    proceeding, the Expert Appraisal Committee or State Level Expert Appraisal Committee

    concerned shall make categorical recommendations to the regulatory authority concerned

    either for grant of prior environmental clearance on stipulated terms and conditions, or rejection

    of the application for prior environmental clearance, together with reasons for the same.

  • 7/30/2019 EIA Guidelines

    17/84

    14

    Figure 2.1: Flow chart describing procedure of environmental clearance

  • 7/30/2019 EIA Guidelines

    18/84

    15

    APPRAISAL

    Figure 2.2: Flow chart describing Appraisal procedure by Regulatory Authority (RA)

    Documents: Final EIA or Draft EIA reports andsupplementary reports, video tape/CD of

    public hearing, layout plan, projectfeasibility report and Form 1

    Scrutiny by RA office with respect toTOR (30 days)

    EAC/SEAC completes approval (60 days)

    EAC/SEAC meetingApplicant makes presentation

    Minutes displayed on website (5 days)

    Clearance given, environmental safeguardsand conditions specified or reasons for

    rejection are explicitly stated

  • 7/30/2019 EIA Guidelines

    19/84

    16

    SECTION 3

    BASELINE DATA

    Baseline data is required to describe environmental and socio-economic status of

    project site and project impact area for pre-project condition. It consists of primary data (field

    tests, surveys, measurements) and secondary data (published information, unpublished

    information available with various agencies). Much of the required secondary

    data/information is often available within the various government agencies. Major difficulty

    with the unpublished information is determining which of it is important and then correctly

    interpreting it while eliminating all the unimportant data.

    The data is compiled for: Land Environment, Water Environment, Air Environment,

    Noise Environment and Socio-economic Environment. Primary data related to the

    environmental attributes like air, noise level, water quality and soil are collected from field

    studies. A structured questionnaire is used for collection of primary information on socio-

    economic aspects. Ecological information is collected from field studies as well as secondary

    sources. A summary of environmental attributes related parameters and source of

    information is given in Table 3.1.

    3.1 LAND ENVIRONMENT

    3.1.1 Land Use

    Land use and land cover patterns are important in environmental impact assessment

    study from the point of view that land use describes the present use such as agriculture,

    settlement etc. and land cover describes the material on it such as forest, vegetation, rocks

    or building etc. Land cover of the 10 km radius study area with reference to the site can be

    derived using latest cloud free satellite imageries. The data is geo-referenced using SOI

    1:50000 scale toposheets with the help of standard data preparation techniques in GIS

    software such as ERDAS IMAGINE. Interpretation of the geo-referenced data is done using

    standard enhancement techniques and ground truthing. The land use is explained in terms

    of type and areal extent i.e. dense vegetation, medium vegetation and sparse vegetation

    which refers to the crown cover density of >40%, 10-40% and

  • 7/30/2019 EIA Guidelines

    20/84

    17

    Table 3.1: Environmental attributes, parameters and source of information

    S. No. Attribute Parameter Source

    LAND ENVIRONMENT1 Land Use Land use pattern District Planning Map

    2 Soil Soil Characteristics Soilerosivity in catchment area

    Field studies, GIS basedinformation

    3 Geology Geological Status Project Pre-Feasibility Report

    4 Seismology Seismic Hazard Pre-Feasibility Report

    WATER ENVIRONMENT5

    Water ResourcesCatchment Area, Flow,Design

    Project Pre-Feasibility Report

    6 Water Quality Physical, Chemical andBiological parameters

    Field studies

    7 Hydrology Drainage area and pattern Project Pre-Feasibility Report

    8 Ambient Air Quality SPM, RPM, SO2, NOx andCO

    Field Studies

    9 Meteorology Temperature and Relativehumidity

    Field Studies

    Temperature, Relativehumidity, Rainfall, WindSpeed and Wind Direction

    India MeteorologicalDepartment

    10 Noise Noise levels in dB (A) Field StudiesBIOLOGICAL ENVIRONMENT

    11 Ecology Flora & Fauna Diversity Field Studies, Informationfrom Forest department and

    Literature Study12 Aquatic Ecology Density & diversity of aquatic

    speciesField studies, FisheriesDepartment, Literaturereview

    SCIO-ECONOMIC13 Socio-economic

    aspectsSocio-economic characteristicof the affected area

    Field Studies, Literaturereview.

    (d) Homestead land(e) Grazing land(f) Fallow

    (g) Marshes(h) Water bodies(i) Road(j) Railway(k) Bridges(l) Airport

    3.1.2 Drainage Pattern(a) Data regarding flash floods, frequency of occurrence(b) Ground water strata(c) Springs

  • 7/30/2019 EIA Guidelines

    21/84

    18

    3.1.3 Soils

    The locations for collection of soil samples should be well distributed to represent the

    spatial variation in project area. The soil samples are to be analysed for the following

    parameters:

    (a) Land capability classification (for agricultural land)(i) Physical properties of soil (soil texture, porosity, particle size distribution)(ii) Chemical properties of soil (pH, electrical conductivity, cations, anions)(iii) N, P, K content

    3.1.4 Catchment Profile (Directly Draining)(a) Drainage pattern(b) Watershed characteristics

    (i) Size(ii) Shape(iii) Relief

    (iv) Slope(v) Drainage(vi) Pattern and density

    (c) Ground water potential and runoff behaviour(d) Sediment/silt yield data(e) Existing cropping pattern(f) Migrant behaviour of human and livestock population

    3.1.5 Geomorphology/Geology(a) Data with reference to the entire project area (rock type, slopes, strata, minerals

    etc.)(b) Seismic zones/classification

    (c) Data pertaining to occurrence of earthquakes

    3.2 AIR AND WATER ENVIRONMENT

    3.2.1 Water Quality Parameters

    To generate baseline data for existing water quality in the project area, water

    samples (composite) should be collected and analysed for examination of water and

    wastewater as per the standard procedure such as given in Protocol for Water Quality

    Monitoring (http://www.cwc.nic.in/main/HP/download/ProtocolforWaterQualityMonitoring.pdf)

    or the relevant code of the Bureau of Indian Standards (BIS). The details for conducting

    water quality assessment are given in Chapter 5. These water samples are to be assessed

    for the following parameters:

    (a) Physico-chemical pH, temperature, conductivity, dissolved oxygen, TDSand TSF, turbidity, total alkalinity, total hardness, chloride, iron, nitrate,phosphate, BOD, COD

    (b) Bacteriological E coli, coliform(c) Depending upon the pollution source concerned heavy metals namely

    mercury, arsenic etc. also to be analysed(d) Base line data:

    (i) Pre-construction: Two season data i.e. high flow and lean flow

    (ii) Post-construction: Water quality parameters upstream of the projectsite to be compared with the quality downstream of the project site

  • 7/30/2019 EIA Guidelines

    22/84

    19

    3.2.2 Hydrological Data(a) Monthly discharge data at dam site(b) Lean season flow (cumec)

    (i) upstream of project site(ii) downstream of the project site

    (c) Water required for (cumec)(i) power generation(ii) irrigation(iii) domestic/industrial use

    (d) Ground water profile pre-monsoon/post-monsoon

    3.2.3 Meteorology3.2.3.1 Seasonal-monitored data (monthly basis)

    (i) Temperature (in 0C)(a) Maximum

    (b) Minimum(c) Mean(ii) Mean rainfall (in mm)(iii) Wind speed (km/h)

    (a) Maximum(b) Minimum(c) Mean

    (iv) Windrose diagram for winter, summer, rainy season and annual(iv) Humidity (mean monthly)(v) Evaporation (observed class A pan evaporation or estimated using appropriate

    method)

    3.2.4 Air Quality(a) Season wire/air quality (SPM, NOX, SO2, CO)(b) Construction material required (Table 3.2)(c) Dust emissions

    (i) Quarry sites(ii) Haulage roads(iii) Construction activity(iv) Stone crusher

    Table 3.2: Construction material required (clause 3.2.4 b)List of construction

    materials to be used at all

    stages of construction

    Quantity(tonnes/month)

    Peak Average

    Source of

    material

    Means of transportation(source to storage site)

    with justificationCementStoneSteelSandOther

    3.2.5 Noise(a) Major sources of noise in the project area (stationary and mobile)(b) Level at source (dB)(c) Level at project boundary (dB)

  • 7/30/2019 EIA Guidelines

    23/84

    20

    3.3 BIOLOGICAL ENVIRONMENT

    3.3.1 Aquatic

    Aquatic ecosystem to be studied over an area atleast between 2km upstream of the

    project site and atleast 2 km downstream of the project site. The study should include the

    following:

    (a) Fish species of commercial value(b) Resident species(c) Migratory species, their spawning ground, fish morphology, anatomy, feeding

    pattern, breeding pattern etc.

    Aquatic ecological analysis may be made following the methods outlined in Wetzel

    and Likens (1991) and APHA (1998). Periphyton, phytoplankton, macrobenthos and

    zooplankton should be studied for frequency, density, abundance and diversity indices.

    3.3.2 Terrestrial

    An inventory of flora, listing of rare, endangered, economically important and

    medicinal plant species should be prepared and their frequency, abundance and density

    should be determined. Quadrate method is generally used for sampling.

    3.3.2.1 Flora

    (a) Major forest products and dependability of the local communities on these suchas fuel wood, edible species, construction material etc.

    (b) Forest type(c) Trees, shrubs, herbs(d) Rare and endangered species(e) Endemic species(f) Economically important species

    3.3.2.2 Fauna(a) Aerial distance of National Park/Sancturay/Biosphere Reserve etc., if any in the

    vicinity, from the project site(b) Rare and endangered species(c) Endemic species(d) Species of special interest to local population and tourists

    (e) Migratory route of animals, if any, in the project area

    3.4 SOCIOECONOMIC ENVIRONMENT

    3.4.1 Demographic Profile (gender based details of the population)(a) Rural/urban(b) Population density(c) SC/ST and others(d) Literacy(e) Employment and occupation(f) Economic status (land holding/house holding)

    3.4.2 Details of Villages to be Affected(a) Total no. of villages

  • 7/30/2019 EIA Guidelines

    24/84

    21

    (b) Total no. of families(i) Tribal(ii) Others

    (c) Total population(i) Tribal(ii) Others

    3.4.3 Village wise Land Details(a) Name of village(b) Total land(c) Land coming under project area(d) Main occupation of villagers

    (i) Agriculture(ii) Service(iii) Labourers(iv) Business

    3.4.4 Details of Families to be Displaced

    Name ofvillage

    PopulationLand oustees only Homestead oustees only Land and homestead oustees

    Tribal Others Tribal Others Tribal Others

    3.4.5 Infra Structure Development(a) Education(b) Industrial development(c) Drinking water

    (d) Communication(e) Roads(f) Electricity(g) Sanitation

    3.4.6 Cultural Sites(a) Places of worship(b) Archeological sites/monuments(c) Anthropological sites

    3.4.7 Health Profile(a) Existing health(b) Screening of the facilities urgent labour

    (i) No. of persons to be employed for construction (average and during peakperiod)

    (ii) No. of persons to be employed from the affected population(iii) Details of temporary labour colonies

    (c) Disease surveillance(i) Endemic health problem(ii) Epidemic prevention and control(iii) Probability of the occurrence of malaria etc.

  • 7/30/2019 EIA Guidelines

    25/84

    22

    SECTION 4

    ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY

    This section aims at description of environmental impact assessment (EIA) methodology

    with reference to water resource projects. As a scientific and technical analysis of the

    environmental impacts, the EIA constitutes an important part of the project studies which

    alongwith techno-economic studies contribute to improving the project standard.

    4.1 LEVELS OF EIA

    The potential scope of a comprehensive EIA system is considerable and can include

    appraisal of policies, plans, programmes and projects. Even if policies were not environmental

    in nature, they might still have severe environmental implications.

    The top tier of EIA application would be a Policy EIA which attempts to assess the

    environmental and health implications of national policies. For example, agricultural policies

    may cause severe ecological impacts or energy policies will influence the demand for natural

    resources and affect industrial development. At a lower level a Plan EIA would seek to identify

    key environmental factors affecting land use such as agricultural land quality and resources

    exploitation.

    EIAs could assist in the identification of preferred areas where certain types of

    development might be encouraged. A Programme EIA would be prepared for a series of like

    projects, such as in a river basin development scheme in which different hydropower projects

    including SHPs may be constructed at different times. A Project EIA would be undertaken when

    local environmental issues are particularly important for individual projects. It should be

    recognised that EIA is not a universal panacea, it may have restricted use in certain areas of

    decision-making. Most EIA experience is related to projects (Project EIA); very few plan EIAs

    have been undertaken.

    4.2 EIA PROCEDURE

    The key activities are screening, scoping and assessment which will be discussed in

    detail in following sections. These steps require intensive interaction between the human

    resources and information resources available for a proposed project.

    Finally, an EIA has to be organized to address certain specific topics. Most EIAs cover

    the following features:

    Description of the proposed project,

    Description of the proposed location or study area, including information about physicalresources, ecological resources, human and economic development and existing quality of

    life

  • 7/30/2019 EIA Guidelines

    26/84

    23

    Alternatives considered (including no-action),

    Potential impacts and benefits including evaluation of each alternative considered,

    Mitigation of adverse effects,

    Irreversible and irretrievable commitment of resources,

    Identification of temporary, short-term and long-term effects,

    Disposition of reviews comments,

    Summary, conclusions and recommendations,

    Monitoring,

    Addition of other features or topics particular to the proposed project.

    4.2.1 Screening

    Screening is a procedure which aims to identify, as early as possible, those projects with

    potentially significant impacts, that should therefore be subject to EIA. Projects can be

    investigated and, if no significant impacts are anticipated, they can then be exempted from

    further environmental analysis. According to MoEF guidelines, Category B projects or activities

    (see Chapter 2) are subjected to scrutiny by concerned State Level Expert Appraisal

    Committee for determining whether or not the project or activity requires an EIA. Those

    requiring EIA are termed as B1 project and those not requiring EIA are termed as B2 project.

    For categorization of projects into B1 or B2, the MoEF shall issue appropriate guidelines from

    time to time. A number of approaches to screening can be identified. These are listed and

    discussed below:

    Project thresholds,

    Locational criteria,

    Positive and negative lists,

    Initial Environmental Evaluations (IEEs),

    4.2.1.1 Thresholds

    Thresholds may be developed on the basis of size, cost or pollution levels. For example,

    in India, a policy has been established (MoEF, 2006) that all hydropower projects with installed

    capacity less than 25 MW would not be subject to prior environmental clearance by competent

    authority. This approach, unfortunately, neglects the implications of several small hydropower

    developments in vicinity, each below the threshold, but which in combination may cause

    significant adverse impacts and thus should be subject to EIA.

    4.2.1.2 Locational criteria

    Locational criteria usually involve designation of sensitive areas, for example nature

    preserves, national parks, historical/religious sites and biospheres. Thus any project or activity

  • 7/30/2019 EIA Guidelines

    27/84

    24

    in category B will be treated as category A if located in whole or part within 10 km from the

    boundary of protected areas/critically polluted areas/notified ecosensitive areas etc.

    4.2.1.3 Positive and negative lists

    The approach is based upon a list of proposed projects for which an EIA is alwaysrequired (positive list) and a list for which no EIS is required (negative list). Initially, some work

    is needed to justify the inclusion of one project and the exclusion of another.

    Example: individual industries located in notified ecosensitive zone (positive list)/biotech parks

    (negative list)

    4.2.1.4 Initial environmental evaluation

    An initial environmental evaluation (IEE) approach requires considerably more

    understanding of a project and its environs than the approaches described previously. IEEsoperate on a project-by-project basis and consequently it is impossible to make generalizations

    as to which project will be subject to an EIA. However, the RA is an essential precursor to an

    IEE since it provides sufficient information on pollution loads and levels to allow decision to be

    made on the need for an EIA.

    An IEE-approach is presented in the UNEP guidelines (United Nations Environment

    Programme, 1980) for the assessment and siting of industry. This approach requires a

    systematic identification of possible interactions between the characteristics of the proposed

    development, and those of the size and surroundings. Both an interactions matrix andscreening tests may be needed for this approach.

    There are several general criteria that can be used when making a decision as to the

    environmental effect of an activity. These criteria are not mutually exclusive but are very much

    interrelated.

    Magnitude : This is defined as the probable severity of each potential impact. Will the impact

    be irreversible? If reversible, what will be the rate of recovery or adaptability of an impact area?

    Will the activity preclude the use of the impact area for other purpose?

    Prevalence : This is defined as the extent to which the impact may eventually extend as in the

    cumulative effects of a number of stream crossings. Each one taken separately might represent

    a localized impact of small importance and magnitude but a number of such crossing could

    result in a widespread effect. Coupled with the determination of cumulative effective is the

    remoteness of an effect from the activity causing it. The deterioration of fish production resulting

    for access roads could affect sport fishing in an area many miles away and for months or years

    after project completion.

  • 7/30/2019 EIA Guidelines

    28/84

    25

    Duration and Frequency : The significance of duration and 1frequency can be explained as

    follows. Will the activity be long-term or short-term? If the activity is intermittent, will it allow for

    recovery during inactive periods?

    Risks : This is defined as the probability of serious environmental effects. The accuracy of

    assessing risk is dependent upon the knowledge and understanding of the activities and the

    potential impact areas.

    Importance : This is defined as the value that is attached to a specific area in its present state.

    For example, a local community may value a short stretch of beach for bathing or a small

    marsh for hunting. Alternatively, the impact area may be of a regional, provincial or even

    national importance.

    Mitigation : Are solutions to problems available? Existing technology may provide a solution to a

    silting problem expected during construction of an access road or bank erosion resulting form a

    new stream configuration.

    While single screening approaches may be applied, they may also be used in

    conjunction with each other. Screening techniques can, therefore, vary in sophistication, but

    there is considerable merit in keeping this activity as simple as possible. A simple approach

    such as a positive and negative list approach, will allow both the development proponent and

    the authorizing agency to clearly understand EIA requirements in advance. This approach may

    need to be reinforced with an IEE approach in order to accommodate non-listed projects.

    Alternatively, a simple questionnaire approach may be acceptable.

    4.2.2 Scoping (Depth of Analysis)

    Scoping is the procedure used to determine the "terms of reference" of an EIA and

    concentrates on identifying those issues which require in-depth analysis. Scoping has the

    following specific objectives:

    To identify the major environmental issues that must be assessed in the EIA.

    To determine the range of alternatives to the project which should be examined.

    To determine the boundary for the study in a geographical context.

    To establish a procedure for the preparation of an EIS and its format.

    Scoping often involves contact between those proposing a development and the public,

    and it is a procedure that allows interested persons to state their concerns before an EIA is

    undertaken. Participation of the public in scoping is important because it may help identify

    people who have useful knowledge about the proposed site. It also allows them to propose

    alternatives and suggest the kind of study that should be undertaken. Scoping is the first stage

    in creating public confidence in EIA and the decision-making process (US Council on

    Environmental Quality, 1981). It is helpful in providing participants with a report from the

  • 7/30/2019 EIA Guidelines

    29/84

    26

    developer which contains the preliminary information. This may allow any serious issue

    associated with a proposal to be identified early on.

    4.3 METHODS FOR IMPACT IDENTIFICATION AND ASSESSMENT

    Although there are many types of EIA methods, this section will only discuss checklists,matrices, network and overlays manuals. These represent the most widely used methods.

    Before discussing these methods, it should be noted that evidence for their partial utility is often

    limited. Whenever possible evidence relating to this important aspect of methods will be

    considered.

    4.3.1 Checklists

    The checklists method lists local environmental factors, which are likely to be affected

    where a development is planned. This list can contain broad categories of factors, for example,flora, fauna, hydrological regimes, surface water bodies and the atmosphere. Conversely, it can

    be extensive and detailed. An example of checklist is given Table 4.

    Another useful type of checklist is the "questionnaire", which presents a series of

    questions relating to the impact of a project. Checklists are used to provide answers to specific

    questions relating to the particular project being assessed. Once an initial question has been

    answered in the affirmative, additional questions investigate the nature of particular impacts in

    detail.

    There have been many attempts to develop checklists by the use of weighing andscaling. Numerical weights are assigned to items of a checklist in accordance with the relative

    importance of each item. Scaling is a procedure for reducing impacts on all items to a common

    arbitrary scale. These methods have not been widely used because of their complexity, cost

    and extensive data requirements. Also, they can be politically controversial due to the need to

    assign weights for relative importance to environmental components.

    4.3.2 Interaction matrices

    A development of basic checklists is the interaction matrix. The most well known is theLeopold matrix development for the U.S. Geological Survey (Leopold et al, 1971). The matrix

    consists of a horizontal list of development activities displayed against a vertical list of

    environmental factors. The matrix is used to identify impacts by systematically checking each

    development activity against each environmental parameter. If it were thought that a particular

    development activity were to affect an environmental component, a mark is placed in the cell

    which occurs at the intersection of the activity and the environmental component. It should be

    noted that the matrix can be expanded to cover the construction and operational phases of

    various components on horizontal scale or more than one alternative can be represented on thehorizontal scale. An illustrative example is shown in Table 4.1.

  • 7/30/2019 EIA Guidelines

    30/84

    27

    Table 4.1: Example: Checklist of impacts of a hydropower project

    S.

    NO

    PROJECT PHASE /

    ENVIRONMENTAL IMPACT

    IMPACT NO

    CHANGE

    SHORT

    TERM

    LONG

    TERM

    POSITIVE NEGATIVE

    A. Impacts due to Project Location

    1 Displacement of People *2 Loss of Land / Change in Land

    Use

    * *

    3 Encroachment into Forest Land /

    Loss of Forest Produce

    * *

    4 Encroachment into Nature

    Reserves & Wildlife

    *

    5 Loss of Historical/Cultural

    Monuments

    *

    6 Loss of Infrastructure *

    7 Erosion and Silt Risks * *

    8Disruption of Hydrological

    Balance*

    B. Impacts due to ProjectConstruction

    9 Soil Erosion at Construction Sites * *

    Muck Generation * *

    Transportation of muck and

    construction material

    * *

    10 Deforestation * *

    11 Human Health * *

    12 Water Quality * *

    13 Cultural Hazards * *

    14 Air and Noise Pollution * *

    C. Impacts due to Project Operation

    15 Reservoir Evaporation Losses *

    16 Deforestation * *

    17 Effect on Wildlife *

    18 Change in Water Quality & Risk of

    Eutrophication

    *

    19 Increased Incidences of Water

    Borne Diseases

    *

    20 Impact on Fish and Aquatic Life *

    21 Public Health * *

    22 Drainage *

    D. Positive Impacts

    23 Clean and renewable source of

    energy

    * *

    24 Employment Opportunities * * *

    25 Catchment Area Treatment * *

    26 Recreation and Tourism Potential * *

    27 Additional Habitat for Aquatic

    Wildlife / Wetland Species

    * *

    28 Fisheries & Aquaculture potential * *

    29 Benefits to Economy * *

    30 Reduction in Air Pollution * *

    31 Reduction in Greenhouse gas

    Emissions

    * *

    32 Increased Infrastructure * *

  • 7/30/2019 EIA Guidelines

    31/84

    28

    After the initial identification of impacts, it is possible to use the same matrix to indicate

    those impacts considered to be the most important. In the original Leopold matrix, scores from

    a 1-10 scale can be assigned to describe the importance and magnitude of individual impacts.

    Importance refers to the significance of an impact and magnitude to its scale and extent.

    Leopold-type matrices are easy to use and perhaps the most widely employed and successful

    of all EIA methods.

    4.3.3 Network

    This method, although widely discussed in the EIA literature, has not been used as

    extensively as matrices and simple checklists. It was developed to explicitly consider the

    secondary, tertiary and higher order impacts that can arise from an initial impact. Checklists

    and matrices structure thinking towards impacts on single environmental entities. When using a

    matrix the effects of vegetation clearance, for example, are considered in relation to all listed

    environmental components. With this approach to impact identification, there is a danger that

    linked impacts are omitted. In this case, vegetation clearance can have an initial or primary

    impact on both soils and animal and bird life. However, the impact on soils can result in erosion

    and this can increase the sediment load in rivers. This sediment load can, in turn, affect life of

    reservoir and various forms of aquatic life. Should the river support a commercial or

    recreational fishery, then any changes in aquatic structure might have economic repercussions.

    4.3.4 Overlays

    The overlays approach to impact assessment involves the use of a series of

    transparencies. The study area is subdivided into convenient geographical units, based on

    uniformly spaced grid points, topographic features or differing land uses. Within each unit, the

    assessor collects information on environmental factors and human concerns, through various

    sources/techniques. The concerns are assembled into a set of factors, each having a common

    basis and regional maps (overlays) are drawn for each factor. The degree of impact or

    importance of each factor is represented by varying the degree of shading with light shading

    indicating low impact and heavy shading the highest impact. The overlays are then stacked one

    on the other using the same reference points and the total degree of shading is visually

    observed. Those areas on the maps with the highest shading are thus the most acceptable

    alternatives. Because of the reduction in light transparency with each overlay, only about 10

    maps or overlays can be used.

    This method is easily adaptable for use with a computer which may be programmed to

    perform the tasks of aggregating the predicted impacts for each geographical subdivision and

    of searching for the area least affected. Automated procedure can be used for selecting

    sequence of unit areas for routing highways, canal network, pipelines, and other corridors. The

  • 7/30/2019 EIA Guidelines

    32/84

    29

    computer method is more flexible, an advantage whenever the reviewer suggests that the

    system of weights be changed.

    The overlay approach can accommodate both qualitative and quantitative data. For

    example, water is often shaded blue while land elevation can be shown by contour lines. There

    are, however, limits to the number of different types of data that can be comprehended in one

    display. A computerized version thus has greater flexibility. Although in this case, too, the

    individual cartographic displays may be too complex to follow in sequence, the final maps

    (optimum corridors for each alternative, and comparisons amongst alternative) are readily

    prepared and understood.

    When using overlays, the burden of ensuring comprehensiveness is largely on the

    analyst. Also, the approach is selective because there is a limit to the number of transparencies

    that can be viewed together. Finally, extreme impacts with small probabilities of occurrence are

    not considered. A skilled assessor may indicate in a footnote or on a supplementary map,

    however, those areas near proposed corridors where there is a possibility of landslides, floods,

    or other unacceptable risks. Overlays do have some strong features too. For example, overlays

    may be mutually exclusive provided that checklists of concerns, effects, and impacts are

    prepared at the outset and a simplified matrix-type analysis is undertaken. Also, the objectivity

    of the overlay method is very good with respect to the spatial positioning of effects and impacts

    (e.g., area of land to be flooded), but is otherwise low. Overlays are not effective in estimating

    or displaying uncertainty and interactions.

    4.4 SOCIO-ECONOMIC ASSESSMENT

    A hydropower project generally requires construction of the diversion barrage, headrace

    tunnel, powerhouse etc. Construction of the project facilities would require acquisition of land,

    out of which part may be the government/forest land and the remaining private land owned by

    the individuals. Expropriation of private lands may cause social disruption and economic loss

    for the project affected families/people. The workers, which will be migrating in the project area

    during construction, would also cause certain demographic and social changes, since theproject is normally situated in remote area.

    A survey should be undertaken to study and understand the socio economic conditions

    of these project-affected households and to examine the impact of the proposed project

    thereupon.

    Socio-Economic Profile of Project Affected People (PAP):

    It should cover analysis of the following:

    Sex and Age

    Educational Attainment:

    Religion and Caste

  • 7/30/2019 EIA Guidelines

    33/84

    30

    Occupation\

    Family Income

    Marital Status

    Family Pattern and Size

    Enlistment

    Family Assets and Acquisition

    Infrastructure Facilities

    Social Impact Analysis

    It should cover analysis of the following:

    Pressure on existing infrastructure/resources : Creation of the project infrastructure like

    roads, electric supply would also be available for the project affected people.Incidence of water related diseases: The aggregation of labour, discharge of uncontrolled

    wastewater and formation of stagnant water would result in occurrence/spread of diseases like

    malaria, cholera etc.

    Cultural conflicts: People in the project area have distinct habits of food and clothing along

    with deep religious faiths celebrating their festivals with great enthusiasm. Hence, chances of

    cultural conflicts may take place with that of migratory population.

    Cost of living and inflation: Minor increase in cost of living and inflation may be experienced

    in the project area as a result of increased commercial activities.

    Resettlement, Rehabilitation and Social Response Program (SRP) of the Project

    Ministry of Rural Development, Government of India have published the National Policy

    on Resettlement and Rehabilitation for Project Affected Families (NPRR-2003) in February,

    2004 which gives guidelines for resettlement and rehabilitation of project affected families.

    Family to be displaced due to the project are to be identified. Only partial acquisition of

    agricultural land from the only four families of Lumber village would be necessitated for the

    project. If the number of affected families is much less than 250, then the NPRR-2003 is notcompulsorily applicable.

    The affected families should be compensated for acquisition of their land in accordance

    with the local norms applicable for such acquisition. It is also obvious that such compensation

    would never render sufficient to compensate the indirect losses to the local people. The local

    population of the project area deserves certain incentives towards their social upliftment, so that

    they feel themselves an integral part of the overall development. With this principal objective in

    view, the project proponent should prepare a Social Response Program (SRP) for the project.

    The SRP should be carried out with active involvement of the affected people. It provides forlivelihood support, infrastructure development, education assistance, public health facility,

  • 7/30/2019 EIA Guidelines

    34/84

    31

    gender support, water conservation and harvesting and creation of employment opportunities.

    A separate body comprising of representatives from project management & public

    representatives should be formed for monitoring and concerted evaluation of the SRP.

  • 7/30/2019 EIA Guidelines

    35/84

    32

    SECTION 5

    WATER QUALITY MONITORING PROGRAM

    Assessment of potential impacts of a hydropower development to water quality firstrequires an effective plan to acquire sufficient baseline information to make the assessments.

    At the time of construction activities begin, a modified monitoring program is necessary to

    evaluate the effectiveness of measures to prevent adverse effects to water quality. Ultimately,

    additional modifications to the monitoring plan are needed to evaluate the actual effects of the

    project on water quality and to enable identification of unanticipated effects and/or ineffective

    protection measures. The first monitoring plan, to develop a baseline of the information, should

    be a component of the Terms of References (TOR) developed within the Environmental Impact

    Assessment (EIA) process. The second and third modifications to the baseline monitoring

    program are to be presented in the Environmental Management Plan (EMP) which is a part of

    the EIA report.

    5.1 EFFECTS ON WATER QUALITY

    5.1.1 Water Quality Effects During Construction

    Generally, effects of construction on water quality in a river system stem primarily from

    the discharge of wastewater (both construction waste water and sanitary waste water from

    workforce housing areas) to the adjacent river and runoff from quarries and construction areas.Discharge of wastewater from construction areas that may affect water quality include

    discharge of water used to wash concrete mixing and hauling equipment, wash water used to

    prepare concrete aggregate, and other minor on-site discharges of water to the river system.

    Generally, the effect is an increase in suspended sediment loads and an increase in alkalinity of

    the water due to discharge of calcium carbonate (CaCO3), a component of concrete. However,

    dissolved solids may also increase significantly as a consequence of runoff from the

    construction area. If excavated material is deposited in or adjacent to the river channel,

    suspended solids concentrations and dissolved solids concentrations may increase further. Of

    particular concern with deposition of spoil materials is the potential for increasing

    concentrations of heavy metals such as iron, manganese, copper, lead, and other heavy

    metals.

    Deposition of suspended solids in the river channel downstream from the construction

    area may cause changes in the river channel if significant amounts of sediment is contributed to

    the river, and may cause problems with spawning areas of fish in the downstream reach of the

    river.

    Discharge of sanitary waste from work camps and other human sanitary facilities can

    affect Biochemical Oxygen Demand (BOD) in the river as well as increasing fecal coliform

  • 7/30/2019 EIA Guidelines

    36/84

    33

    bacteria concentrations, an indicator of potential disease risk to to downstream users. Suitable

    handling and treatment of sanitary wastes will significantly reduce the potential for adverse

    effects to water quality from this source.

    Runoff from construction areas constitutes a more problematic situation. Potential water

    quality effects on runoff from construction sites include increases in sediment emanating from

    erosion from disturbed areas (construction staging areas, excavated areas, quarries, access

    road construction, spoil disposal areas), flushing of oils, greases and other hydrocarbon

    lubricants from maintenance areas, and potential flushing of other hazardous materials used at

    the project site for construction purposes. Containment of such materials and installation of

    erosion barriers will significantly reduce the potential effects to water quality. Maintenance of

    the erosion control measures and containment facilities must be accomplished throughout the

    construction period.

    5.1.2 Water Quality Effects During Operation

    Most of the significant water quality effects are realized only after the project begins

    operation. At this time the affected river has been partitioned into two major components:

    Upstream of the project site and Downstream of the project site.

    5.1.2.1 Water quality effects upstream of the project site

    In general, a hydropower project can not and should not directly affect water quality

    conditions upstream of the project site. Any realized changes in water quality are generallyattributable to changes in land use patterns, changes in population distributions and changes in

    industrial or commercial installations in the upper river basin. Consequently, any changes in

    water quality conditions upstream will be reflected in changes in water quality downstream.

    Management of land use, population distribution and industrial development upstream is

    basically the only option available to minimize these impacts.

    5.1.2.2 Water quality effects downstream of the project site

    The more significant effects of a hydropower development on water quality, at least fromthe perspective of ecological characteristics and human use, are generally realized in the river

    downstream of the project site. The magnitude of the changes in water quality parameters

    realized downstream from the project are attributable to the operating regime of the project

    which defines the hydrologic regime. Aside from the alteration of the hydrologic regime, two of

    the more common water quality parameters that are affected by a small hydropower

    development in the downstream reach are water temperature and dissolved oxygen.

    While the temperature regime in the river is not necessarily considered an adverse

    condition, it is the changes in the biological community that are affected by those changes thatcan become significant. The temperature regime of a river may affect the types of organisms

  • 7/30/2019 EIA Guidelines

    37/84

    34

    that are able to survive in the affected reach, the biological productivity within the reach

    (generally, biological production is positively correlated with temperature in aquatic systems),

    and the reproductive cycles of aquatic organisms downstream from the project. It should be

    noted that although some species may cue reproductive cycles on water temperature, other

    species cue their cycles on changing hydrologic regimes that may or may not be correlated with

    seasonal changes in water temperature. Therefore, the significance of predicted changes in

    water temperature must be framed in reference to the biological requirements of the organisms

    inhabiting the river downstream of the project.

    5.2 PURPOSE OF WATER QUALITY MONITORING

    Generally, the statement of purpose for a water quality monitoring program is fairly

    straight forward. Though the development cycle, three basic monitoring programs will be

    designed and implemented corresponding to the baseline description period (EIA), construction

    period, and operation period.

    The primary purpose of the baseline monitoring program are twofold: First, the baseline

    monitoring program should provide sufficient information to enable accurate (justifiable)

    predictions of potential effects of the hydropower project on water quality parameters; second,

    the baseline data set will provide the standard against which project effects and/or mitigation

    effectiveness can be determined. Obviously, it is necessary to determine the starting point

    condition to determine if changes occur.

    The purpose of the water quality monitoring program for the construction period,

    likewise, can serve two purposes: First, the program should be designed to enable evaluation

    of the effect of various construction activities and construction related facilities on water quality;

    second, certain components of the program can provide further baseline information for

    determining the effect of project operation on water quality.

    The purpose of the final water quality monitoring program to be implemented during

    operation also has two purposes: First, data collected during the operational period are

    compared with the baseline data to determine if projections made in the EIA are accurate and

    mitigation or avoidance measures are effective; second, the monitoring program can be used to

    determine if changes occur during the operation period and might require attention and can be

    used as a basis to determine the sources of any pollutants.

    5.3 SAMPLING DESIGN

    Design of the water quality monitoring program is key to obtaining a useful set of

    information for describing baseline conditions and measuring the effects of construction and

    operation on those conditions. Thus, the sampling design presented in the monitoring plans is

    the most important part of the plan.

  • 7/30/2019 EIA Guidelines

    38/84

    35

    5.3.1 Duration

    The duration of the water quality monitoring programs will vary according to the stage in

    project development.

    For baseline monitoring, the minimum length of time necessary for basic understanding

    of cycles in water quality parameters is one year. The baseline monitoring program should

    provide sufficient information on all parameters included in the monitoring program to

    demonstrate annual cycles in concentrations or conditions. While the data set should provide at

    least one full year of sampling, continuing monitoring for longer periods would facilitate

    understanding of year-to-year variation in those parameters. Consequently, the baseline

    monitoring program should be implemented for as long as possible given the schedule for

    project construction and completion.

    Determination of the duration of the construction period monitoring program should

    correspond to the construction period, including preparatory period. In addition to monitoring

    the effects of construction, continuation of monitoring parameters included in the baseline

    program will provide additional foundation for measuring the effects of the project once it

    becomes operational.

    The duration of the monitoring program to be implemented during operation of the

    project will depend upon specific conditions at the project. For some parameters, the monitoring

    program could extend throughout the life of the project. For other parameters, sampling for a

    period of up to 5 years will provide an adequate basis for evaluating the effect of the project.

    5.3.2 Sampling frequency

    As defined above, recommended parameters for inclusion in the baseline, construction

    period, and operational period include two groups: Those for general monitoring and those for

    assessment monitoring.

    During the baseline period (EIA preparation), parameters included in general monitoring

    should be measured on at least a biweekly basis, preferably on a weekly basis for one full year.

    Parameters included for the assessment monitoring include some parameters that should be

    measured on a monthly basis, with the remainder measured on a quarterly or seasonal basis

    through the planning phase of the project.

    The sampling frequency during the construction period, particularly for parameters that

    may be affected by construction activities should be measured at least on a monthly basis

    throughout the construction period. Parameters that are included in the general monitoring

    program and contribute to the baseline descriptions should be measured at the same frequency

    as determined for the planning (EIA) phase.

    The sampling frequency of parameters during the operational phase may be divided into

    two periods: Initial effects and long-term effects. The basic operational monitoring program

    should include sampling of the various parameters on at least a monthly basis for a period of up

  • 7/30/2019 EIA Guidelines

    39/84

    36

    to 5 years after initial operation of the project. Once the initial period expires, the monitoring

    program may be reduced to include the only a few basic, indicative parameters. If significant

    changes in one or more of the basic monitoring parameters occur, expansion of the monitoring

    program for a specified period of time may be necessary to identify the cause of those changes.

    In general, during the long-term monitoring phase, the basic set of parameters should be

    sampled on a monthly basis.

    5.3.3 Sampling Locations

    The number of sampling locations for water quality will depend on the particular project

    configuration. For single projects (located on a single river), a minimum of three sampling

    locations is needed for both baseline monitoring and construction and operation monitoring.

    For construction monitoring, additional locations may be included to enable evaluation

    of possible pollutants from various areas of the construction facilities. For example, an

    additional location might be downstream from construction staging areas or downstream from

    labour camps. If some of these facilities are located on the tributaries of the main river, the

    samples should be collected upstream and downstream from those facilities.

    5.3.4 Sample and Data Analysis

    To the extent possible, parameters recommended for the monitoring program,

    particularly those included in the general monitoring group, may be measured in the field with

    appropriate instrumentation and/or field kits. The remaining parameters generally requiretransport of water samples to a laboratory for analysis. For parameters that require laboratory

    analysis, sample bottles and containers with appropriate preservatives, if necessary, can

    normally be obtained from the laboratory. A preliminary list of water quality laboratories (private,

    governmental and non-governmental) is presented in Annexure 1. A list of possible field

    equipments to conduct the monitoring program is included in Annexure 2. As with any field or

    laboratory instrumentation, it is necessary to standardize the equipment according to

    manufacturer specifications throughout the field effort.

    All samples should be clearly labeled with an identifying number and all pertinent

    information regarding the sample recorded on separate data sheets for each location and

    sampling time. A sample data sheet for use in the field should be presented as part of the

    proposed monitoring plan. In addition to the field data sheets, it is highly recommended that a

    Chain of Custody form also be used to document delivery of the samples from the field to the

    laboratory. Samples collected for analysis in the field should be taken to the laboratory as soon

    as possible. The length of time a sample may be held prior to analysis can be determined in

    consultation with the laboratory.

    The water quality monitoring plans should include a section on the logistics of data

    collection and sample handling. Information to be included in the water quality monitoring plans

  • 7/30/2019 EIA Guidelines

    40/84

    37

    should include the field and laboratory procedures that will be used to analyze the samples.

    There are a number of Standard Methods for analysis of water quality. The particular methods

    that are to be used should be cited in the monitoring plan.

    Statistical analysis of the results of the water quality analysis will generally vary from

    phase to phase and project to project. For baseline monitoring, particular attention should be

    given to identifying seasonal cycles and longitudinal trends. The data may then be used to

    estimate how the project will affect each parameter. In some cases, it will be appropriate to use

    the data for calibration of one or more water quality simulation models. Relatively simple

    models are available to determine the effect of a project on water temperature and dissolved

    oxygen in the river.

    The most important component of the data analysis during the construction and

    operating periods is comparison of the pre-project condition or baseline condition with the

    construction and operating conditions. Such analysis will determine if and by how much impacts

    to water quality have occurred and are used as determinants of the effectiveness of any

    mitigation measures that have been incorporated into the project configuration. As construction

    and operating data are acquired over the duration of the monitoring program, additional

    analysis of trends in water quality changes may be identified from the monitoring data. Such

    trend analysis might include seasonal changes as well as changes that occur gradually through

    the years.

    5.3.5 Identification of Water Quality Laboratory

    An important component of the water quality monitoring plans is the identification of the

    institutions responsible for collecting the samples and for conducting the analysis of those

    samples. Measurements of water quality parameters in the field and collection of the water

    quality samples for analysis in the laboratory may be performed by trained field technicians

    employed by the environmental consultant. Samples collected for laboratory analysis should be

    conveyed to the laboratory according to the protocol furnished by the selected water quality

    laboratory.

    5.3.6 Quality Control

    An issue that should be addressed in the water quality monitoring plans relates to

    quality assurance that the data presented are accurate and reliable. An acceptable quality

    assurance program will consist of both external and internal controls by the laboratory providing

    the analytical evaluations of samples.

    First, the developer and/or the environmental consultant should implement an external

    quality control procedure. The procedure should at least include submittal of duplicate samples

    from one or more locations on each sampling data. These samples should be blind samples

    such that the water quality laboratory is unaware of which samples are duplicated. A second

  • 7/30/2019 EIA Guidelines

    41/84

    38

    possible component of an external quality control procedure could consist of periodic submittal

    of duplicate samples to a second laboratory, one not responsible for the routine analysis

    process.

    Second, the quality control procedures adopted by the water quality laboratory should

    be presented in the plans. An acceptable procedure should include duplication of samples by

    the quality control officer of the laboratory after submittal of the sample to the laboratory but

    prior to delivery to the laboratory technicians. The procedure should also include submittal of

    blank samples and spiked samples (samples with known concentrations of a parameter) to

    the laboratory technicians for analysis. Reports from the laboratory should include results of the

    internal quality control procedure for review by the developer/environmental consultant and the

    reviewing agencies.

    5.3.7 Reporting

    Reporting of water quality data will be dependent upon the phase of the water quality

    monitoring program. Data and analysis of those data obtained during the pre-construction

    phase are to be presented in the EIA. As appropriate raw water quality data should be

    presented with the EIA to enable independent evaluation of results. A condition of the TOR may

    include a requirement for submittal of the water quality data in a standardized format for

    incorporation into a country wide data base. The water quality data should be submitted with

    the EIA.

    Reporting of results of the construction and operation monitoring program will also be

    submitted to the concerned agencies for review. The schedule for reporting the data will be

    negotiated as part of the approval of the EMP and will likely become conditions of the license to

    construct and operate the project. An appropriate schedule for reporting of results from the

    monitoring of construction activities would be on a quarterly basis. This will depend on the

    monitoring program itself and the frequency with which samples are being collected.

    Reporting of results of operation monitoring will likely be divided into two phases: an

    initial phase for a period up to five years with reporting on a semiannual basis and a second

    period following the initial period with reporting on an annual basis.

    5.4 REGULATORY AUDIT

    In developing the regulatory audit procedure for a given hydropower project, the

    following areas should specified:

    1. Purpose

    The comprehensive audit will cover all aspects of engineering, environmental and social

    considerations regarding the project. With respect to water quality, the regulatory audit will seek

    to determine if projections of the EIA are accurate and whether or not measures to mitigate

  • 7/30/2019 EIA Guidelines

    42/84

    39

    anticipated adverse effects are effective. Thus, the objective of the regulatory audit of the water

    quality monitoring program is to confirm the results of the monitoring program are accurate.

    2. Acquisition of information and sampling design

    The regulatory audit of water quality monitoring will consist of two components: first, the

    audit will consist of a detailed review of data reported by the developer and construction

    contractor, including a review of the water quality control procedures and results implemented

    by the developer; second, the audit consist of an independent analysis of water quality

    conditions at the project site. This will consist of acquisition of measurements and samples in

    the same manner and location defined in the EMP. An independent laboratory, one not involved

    in the continuing monitoring program, should be selected to analyze the samples. Selection of

    the laboratory may consist either of using the governmental laboratory or another laboratory.

    3. Analysis

    Analysis of results of the regulatory audit will consist of two factors: first, the data will be

    compared with available water quality standards established for hydropower projects; second,

    the data will be compared with results of the monitoring program submitted by the developer.

    4. Presentation and reporting

    Results of the water quality component of the environmental audit are to be included in

    the environmental audit report submitted to the government.

    5.5 INTERPRE