10
Libya, Benghazi The “CONTRACT AREA 108” project (Terra Rossa problem) This document is dedicated to the foreign workers in construction sites all over the world because they are the essential stream which transfers and distributes knowledge through countries.

Libya & TERRA ROSSA

Embed Size (px)

Citation preview

Page 1: Libya & TERRA ROSSA

Libya, Benghazi

The “CONTRACT AREA 108” project(Terra Rossa problem)

This document is dedicated to the foreign workersin construction sites all over the world because they arethe essential stream which transfers and distributesknowledge through countries.

Page 2: Libya & TERRA ROSSA

A Google-earth snapshot showing the in brief the contract sites that Company XEKTESA , was constructing in 1980’s in Benghazi, Libya .

Page 3: Libya & TERRA ROSSA

The Contractor Company XECTE SA (Benghazi branch) was considered to be a middlesized contractor in Benghazi during the decade 1980-1990. At that time, the 2nd Ring Road ofBenghazi, the “Shari Al Andalus” highway, some drainage networks around the city, and thedevelopment of Urban Area 108A, were some of the projects that this company was constructing.

As a Contractor this Company had about one hundred workers, all foreigners, most of themfrom Philippines, some from Pakistan and India, a few from Palestine, Syria, Egypt and othercountries as well. The leading personnel, Engineer Manager, Supervising Engineers, Surveyors,Foremen, Operators of construction machines etc were all from Greece.

The Company operated a concrete pre-casting unit manufacturing cement tiles forsidewalks, kerbs and concrete drainage pipes, one asphalt drum mix plant and a warehouseproviding maintenance for the fleet of heavy construction machines (excavators, trucks, graders etc)that was in full operation. A mine for aggregates was occasionally operated in “El Abiar” providingmaterials for the road construction.

The above mentioned projects, that were running that time, were also the main operationalconcern of the Engineer Manager but as a Contractor the company was a provider of generaltechnical services to the Municipality of Benghazi such as repairs of public roads and substructures.The general outline of the main projects was:

1. The 2nd Ring Road of Benghazi project was a 5.5km road connecting Algeria street whichis close to harbor with “Assudan” Street in the area of “Northen Fwayhat”. The 2nd RingRoad was a two-way traffic, 12,0m / 15,0m wide with two lanes on each side. Six majorjunctions, planting, drainage, traffic signs and street lighting were the complete design andconstruction scheme of the contract.

2. The “Shari Al Andalus” project was the 3.4km city's section of a 9.9km highway leadingfrom the center of the city to the south suburbs.

3. The development of Urban Area 108A (contract 108A) concerned a complete and ready touse network of local roads and consisted of the construction of Public Utilities such as watersupply network and house connections, sanitary sewerage (foul and gray waters) networks,storm (surface) water drainage networks (manholes, inlets/gullies and drainage pipes), kerbsand sidewalks, street lighting, base and sub base aggregate courses and two layers of asphaltpavements. This contract imposed very strict specifications for road construction. Due to theflat landscape, the design of the roads required a small gradient of no more than 0,1%longitudinal slopes in favor of a sufficient drainage network. The accepted difference inelevations between design and construction should have been less than 1,5 millimeters / km.The outflows from sewers and storm water pipes were conveyed to the pumping stations.

Specifications that were applied to the works were for example AASHO T99-700, AASHOT193-63, AASHO T 27-70 and BS 1377, BS 1881, BS 812 etc.

All the above projects were constructed under the same main articles of works as theyapproved by the Municipality. However the applied specifications were causing technical orcompatibility problems having impact to the cost of works. For example the use of sulfur resistingcement for the concrete sewers appurtenant structures and the gutters-kerbs as well, as thespecifications predicted instead of Pozzolanic cement, was a failure since this concrete was crackingat the following the construction stages. Another example is the design of box culverts in somelocations were the circular shape was more appropriate. Further more the handling of dust on theroad’s surface during desert winds was a seasonal problem related to maintenance procedures.

Page 4: Libya & TERRA ROSSA

During the time that I was assigned as a Deputy Engineer to the project of Urban Area 108A(contract 108A), a problem appeared and was initially considered relative to the false compaction ofthe backfills of the sanitary sewer trenches. The deformation (settlement) of sub grade surface inroads, where sanitary sewers existed, was a sign that the upcoming works of base and sub baseaggregate courses would be affected as well.

The Office of Resident Engineers (Ove Arup & Partners) stated that «this was a constructionof sewers error since the specification defined that backfills should be compacted to (at least) 95%of standard Proctor Test». If the compaction rate of 95% of Proctors Test was achieved thensettlement of backfill would be zero.

On this statement, the Contractors argument was that it was a problem of the approvedbackfill material. In this case «approved material» was the originally excavated material for whichinitially the Contractor had claims rejecting it as unsuitable.

The following investigation lead to these conclusions: The existing material was a type ofclay known as «Terra Rossa» in the Mediterranean area, which is a stiff when dry and very reddishsoil, its color due to iron oxides originating from weathering of initial rock formations. This TerraRossa has a part of Montmorillonite (mineral) crystals, a rather long and flat molecule formingcornflake-like particles, which expands when it absorbs water. So when the laboratory executed theStandard Proctor Test under different moisture contents it was unavoidable that the volume ofcompacted material would be inflated. On site this meant to be the problem. When the compactedmaterial dried under the extreme heat of Africa, the volume shrunk and the backfill settled.

A new statement coming from the RE's led to additional and extensive investigation. Theystated that «if the California Bearing Ratio (CBR) value of material for fill was according tospecifications (ie over 10%) then the problem would be avoided». Since this test measures the load-bearing capacity of soils used for building roads, the Contractor (XEKTE SA) suggested that theevaluation of the results should be contacted on site. A program of site tests was agreed with RE's sothat from the results to decide if CBR value was the necessary and efficient parameter to approvethe material. This program included

· Excavating the trenches again to a suitable depth,· Backfilling with the excavated material in layers of 10cm,· Compacting to 95% of Proctor Value,· Measuring the levels on a predefined grid and· Flooding the trenches with water and wait to dry· When the trenches dried the surveyor should again measure the levels and· Finally the laboratory should test the CBR value on site.

Depending on the results the RE would decide if the settlement of the backfills was a matterof compaction or suitability of used material.

This was the procedure which finally led to the total rejection of the excavated material asunsuitable for backfilling. After all these years of Engineering experience, today I can state that anecessary test to determine the acceptable clay-like materials is based on the amount of Methyleneblue dye absorbed by the sample. If a soil fails this test then it should be rejected from use inconstruction.

Page 5: Libya & TERRA ROSSA

(1) Excavating the trenchesagain to a suitable depth,

(2) Backfilling with theexcavated material in layers of10cm,

(3a) Compacting to 95% ofProctor Value (aroundmanholes)

Page 6: Libya & TERRA ROSSA

(3b) Compacting to 95% of Proctor Value (overthe pipes) I recall with admiration an employee fromSyria, hard working under the summer sun andheat, hours and hours compacting, the backfillmaterial. The result was always a wellcompacted layer stiff as a stone.

(3c) Compacting to 95% of Proctor Value (Fieldlaboratory tests)

(3d) Compacting to 95% of Proctor Value (Field laboratory tests)

Page 7: Libya & TERRA ROSSA

(5a) Flooding the trenches with water andwait to dry

(5b) Flooding the trenches with water andwait to dry (monitoring the drying procedure)

(5c) Flooding the trenches with water and wait to dry (monitoring the drying procedure)

Page 8: Libya & TERRA ROSSA

Paving asphalt wearing course on the “Shari Al Andalus” highway

Page 9: Libya & TERRA ROSSA
Page 10: Libya & TERRA ROSSA