RENDIMIENTOS DE TRANSPORTE A PAGARSE EN M3/KM OBRA: TRANSPORTE AGREGADO MATERIAL ELIMINACION DE ELIMINACION DE TRANSPORTE TRANSPORTE BASES DE CALCULO UND AGUA/OBRA PARA PIEDRA GRANDE MATERIAL EXCED. MATERIAL EXCED. MATERIAL MATERIAL (CONCR/BASE/RE) CONCRETO Y MEDIANA BOTADERO BOTADERO P/AFIRMADO P/AFIRMADO < A 1 KM > A 1 KM < A 1 KM > A 1 KM DISTANCIA MEDIA PONDERADA Km. 18.00 15.00 14.00 1.00 1.00 1.00 1.00 VELOCIDAD CARGADO Km/Hr. 15.00 15.00 15.00 15.00 15.00 15.00 15.00 VELOCIDAD DESCARGADO Km/Hr. 20.00 20.00 20.00 20.00 20.00 20.00 20.00 TIEMPO CARGA Y DESCARGA Min. 15.00 6.80 10.50 6.80 0.00 6.80 0.00 TIEMPO RECORRIDO CARGADO Form. 60 d /15 60 d /15 60 d /15 60 d /15 60 d /15 60 d /15 60 d /15 TIEMPO RECORRIDO DESCARGADO Form. 60 d /20 60 d /20 60 d /20 60 d /20 60 d /20 60 d /20 60 d /20 TIEMPO RECORRIDO Min. 7.00 7.00 7.00 7.00 7.00 7.00 7.00 CICLO Form. 15.00 + 7.00d 6.80 + 7.00d 10.50 + 7.00d 6.80 + 7.00d 0.00 + 7.00d 6.80 + 7.00d 0.00 + 7.00d CICLO Min. 141.00 111.80 108.50 13.80 7.00 13.80 7.00 TIEMPO TRABAJADO POR DIA Min. 480.00 480.00 480.00 480.00 480.00 480.00 480.00 EFICIENCIA % 95.00% 95.00% 95.00% 95.00% 95.00% 95.00% 95.00% TIEMPO UTIL TRABAJADO Min. 456 456 456 456 456 456 456 VOLUMEN DEL VOLQUETE M3. 7.57 12.00 12.00 12.00 12.00 12.00 12.00 VOLUMEN DE CISTERNA M3. 2000.00 NUMERO DE VIAJES AL DIA Un. 3.23 4.08 4.20 33.04 65.14 33.04 65.14 VOLUMEN TRANSPORTADO M3. 24.48 48.94 50.43 396.52 781.71 396.52 781.71 ESPONJAMIENTO 1.00 1.20 1.25 1.25 1.20 1.20 RENDIMIENTO m3/dia 24 49 42 317 625 330 651

rendimient_transporte

Embed Size (px)

DESCRIPTION

hojas excel para el calculo de rendimientos de transporte

Citation preview

Page 1: rendimient_transporte

RENDIMIENTOS DE TRANSPORTE A PAGARSE EN M3/KM

OBRA:

TRANSPORTE AGREGADO MATERIAL ELIMINACION DE ELIMINACION DE TRANSPORTE TRANSPORTE

BASES DE CALCULO UND AGUA/OBRA PARA PIEDRA GRANDE MATERIAL EXCED. MATERIAL EXCED. MATERIAL MATERIAL

(CONCR/BASE/RE) CONCRETO Y MEDIANA BOTADERO BOTADERO P/AFIRMADO P/AFIRMADO

< A 1 KM > A 1 KM < A 1 KM > A 1 KM

DISTANCIA MEDIA PONDERADA Km. 18.00 15.00 14.00 1.00 1.00 1.00 1.00

VELOCIDAD CARGADO Km/Hr. 15.00 15.00 15.00 15.00 15.00 15.00 15.00

VELOCIDAD DESCARGADO Km/Hr. 20.00 20.00 20.00 20.00 20.00 20.00 20.00

TIEMPO CARGA Y DESCARGA Min. 15.00 6.80 10.50 6.80 0.00 6.80 0.00

TIEMPO RECORRIDO CARGADO Form. 60 d /15 60 d /15 60 d /15 60 d /15 60 d /15 60 d /15 60 d /15

TIEMPO RECORRIDO DESCARGADO Form. 60 d /20 60 d /20 60 d /20 60 d /20 60 d /20 60 d /20 60 d /20

TIEMPO RECORRIDO Min. 7.00 7.00 7.00 7.00 7.00 7.00 7.00

CICLO Form. 15.00 + 7.00d 6.80 + 7.00d 10.50 + 7.00d 6.80 + 7.00d 0.00 + 7.00d 6.80 + 7.00d 0.00 + 7.00d

CICLO Min. 141.00 111.80 108.50 13.80 7.00 13.80 7.00

TIEMPO TRABAJADO POR DIA Min. 480.00 480.00 480.00 480.00 480.00 480.00 480.00

EFICIENCIA % 95.00% 95.00% 95.00% 95.00% 95.00% 95.00% 95.00%

TIEMPO UTIL TRABAJADO Min. 456 456 456 456 456 456 456

VOLUMEN DEL VOLQUETE M3. 7.57 12.00 12.00 12.00 12.00 12.00 12.00

VOLUMEN DE CISTERNA M3. 2000.00

NUMERO DE VIAJES AL DIA Un. 3.23 4.08 4.20 33.04 65.14 33.04 65.14

VOLUMEN TRANSPORTADO M3. 24.48 48.94 50.43 396.52 781.71 396.52 781.71

ESPONJAMIENTO 1.00 1.20 1.25 1.25 1.20 1.20

RENDIMIENTO m3/dia 24 49 42 317 625 330 651