    SDLC Project

    Examples

  • 7/27/2019 Sdl c Examples

    2/53

    Planning Phase

    Example 1

  • 7/27/2019 Sdl c Examples

    3/53

    Project Plan

    The system we are developing for our business is awebsite that we will use to update our customersabout our next location as a social network as well assell our products and merchandise.

    As a business we need to be able to manage ourwebsite effectively, update our information quicklyand clearly communicate our information to ourcustomers.

    Our website will allow customers to become

    members of our business, login into our site,browse products and information and contact thefounders of Forensic Fountain.

    Plan

    System Requirements

    Critical Success Factors

    Feasibility Studies

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

  • 7/27/2019 Sdl c Examples

    4/53

    Project Plan

    Our critical success factors include:

    A data-driven website

    Easy to navigate home, order, and other pages

    of the site

    Clear flow of the website

    Effective communication to the founders

    Used to analyze customer feedback and makechanges

    Plan

    System Requirements

    Critical Success Factors

    Feasibility Studies

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

  • 7/27/2019 Sdl c Examples

    5/53

    Project Plan

    For Forensic Fountains system we decided to

    conduct the following feasibility studies:

    o Cost-Benefit Analysis This study will allow ourcompany to determine if the benefits of running the

    click part of our click and mortar business outweighthe costs of running an online operation and will tellus whether to keep that part of our business or not

    o Schedule Study This feasibility study will help ourbusiness because we have a lot of dates and events tokeep track of due to the fact that we are a travellingbusiness. A schedule study will help us determine ifwe can meet all of our obligations as a company.

    Plan

    System Requirements

    Critical Success Factors

    Feasibility Studies

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

  • 7/27/2019 Sdl c Examples

    6/53

    Project Timeline/Milestones

    November 2, 2011 Business requirements and project plandrawn up and completed

    November 5, 2011 Sent database model to programmingcompany

    November 10, 2011 First basic prototype completed and

    under revision November 12, 2011 Second prototype completed

    November 13, 2011 Database received from programmingcompany

    November 13, 2011 Website completed and ready for

    system testing November 16, 2011 Final product approved for launch

    November 20, 2011 User documentation due

    November 21, 2011 Website opened to the public, databasefully functional

    Plan

    System Requirements

    Critical Success Factors

    Feasibility Studies

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

  • 7/27/2019 Sdl c Examples

    7/53

    Planning Phase

    Example 2

  • 7/27/2019 Sdl c Examples

    8/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    CheckPoint Rush is based around women dirtbiking. Our

    company wants to start a website that will familiarize our

    current and potential clients with what we do, what kind of

    products and services we offer, and what our location is. Our

    customers will be able to purchase products online through our

    website, and download special training videos.

    We will keep our customers up to date with all the latest

    information regarding our products and special offers and

    discounts.

    Customers will also be able to ask questions, and expect

    answers within 24 hours.

    Project Plan

  • 7/27/2019 Sdl c Examples

    9/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Project Plan

    Our company will focus on the following critical

    success factors:

    a website which is easy to navigate

    customers will be able to contact us in case

    they are having problems with placing orders

    all required information will be in place

    easy download option for training videos.

  • 7/27/2019 Sdl c Examples

    10/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Project TimelineNovember 12, 2012 Project plan completed and business

    requirements identified

    November 15, 2012 Database model is finished and sent to the

    programmers

    November 17, 2012 Website design completed and training

    videos due

    November 19, 2012 Premier prototype is completed and under

    review

    November 20, 2012 Page for custom orders designed and

    competed

    November 26, 2012 Final product completed and user

    documentation due

    December 1, 2012 Website is launched and available to the public

  • 7/27/2019 Sdl c Examples

    11/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Feasibility Studies

    Our company will conduct the following feasibility studies:

    Economic feasibility study will allow us to compare costs

    related with creating a website with forecasted benefits.

    By doing this analysis, we will be able to determine what

    parts of website should or should not be excluded from

    original design.

    We will perform operational feasibility study in order to

    see if the website will accomplish all objectives. It will

    help us find out on what parts of the project we need to

    focus more, and how to optimize them.

  • 7/27/2019 Sdl c Examples

    12/53

    Analysis Phase

    Example 1

  • 7/27/2019 Sdl c Examples

    13/53

    Project Analysis Business

    Requirements

    Our online system will:

    1. Be easy to navigate from login to checkout

    2. Have an online ordering and payment system

    3. Present information in a clear andunderstandable way to customers

    4. Allow employees to use customer information toanalyze business performance

    5. Allow the generation of reports regardingdifferent aspects of the business

    6. Allow customers to contact the business withcomments or concerns

    Plan

    Analyze

    Business Requirements

    Process Diagrams

    Buy vs. Build

    Design

    Develop

    Test

    Implement

    Maintain

  • 7/27/2019 Sdl c Examples

    14/53

    Project Analysis

    The two processes we chose to diagram are a customerorder and contact us.

    Due to the fact that our website will be a large part ofour sales, showing the customer order process will help

    you understand how a customer will go through oursystem and also help us identify where potentialproblems might arise.

    In addition, because we are a travelling business we donot have a concrete location where customers can

    come and share their concerns with us. Therefore, thecontact us process of our business will be crucial to oursuccess (or failure) as a business. A social networkingfunction would also help cohesion.

    Plan

    Analyze

    Business Requirements

    Process Diagrams

    Buy vs. Build

    Design

    Develop

    Test

    Implement

    Maintain

  • 7/27/2019 Sdl c Examples

    15/53

    Customer Order Process

    When our customers first visitour site they will see our homepage. In order to place anorder, they will need to sign in

    as members of our site.Customers will be promptedfor their User ID and Password.If they are new to our system,they can create a profile (freeof charge) by setting up a UserID, password, and some briefinformation. Once they havedone that, the system will

    either verify their information,or will reject it as an invalidlogin and request they entertheir information again. Oncethey have been accepted, theyare free to browse through allof our products and selectwhichever fits their fancy.Once a product has been

    selected and a customer isdone shopping, they willproceed to checkout wherethey will enter their paymentinformation, confirm theirorder and their method ofreception, and send in theirorder for packing.

    Verify user

    Enter User ID and

    Password

    Invalid

    Login

    Add User ID,

    Password and

    Confirm

    New User

    Product

    Selection

    Customer order

    and payment

    Products

    Existing User

    Order review and

    Payment

    Information/Type

    Shipping or Pick-up

    Order

    Confirmation/

    Package

    Destination

    Customer ComputerSta

  • 7/27/2019 Sdl c Examples

    16/53

    Buy vs Build Analysis

    Our business relies mainly on the building

    side of a buy v. build scenario. We plan on

    hiring someone to build our website in-house but do not plan on using a canned

    website development system. We will be

    able to have more options as far as being

    able to modify and update our website if

    we did this.

    Plan

    Analyze

    Business Requirements

    Process Diagrams

    Buy vs. Build

    Design

    Develop

    Test

    Implement

    Maintain

  • 7/27/2019 Sdl c Examples

    17/53

    Analysis Phase

    Example 2

  • 7/27/2019 Sdl c Examples

    18/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    We chose to diagram customer login process and the

    enrollment process.

    Our customer database is going to be a big part of our

    website because it keeps track of all of the different

    accounts as well as the information in each account

    including:

    Purchases

    Class enrollments

    User history

    User interests

    Project Analysis

  • 7/27/2019 Sdl c Examples

    19/53

  • 7/27/2019 Sdl c Examples

    20/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Buy VS Build Analysis

    Our company has performed buy vs. buildanalysis, compared costs and benefits related to both

    options, and come up with a conclusion that its in our

    best interest to build our own website.

    Our company has already hired employees who are

    experts in technology and design. Therefore, we are

    confident that the final product will live up to our highest

    expectations.

    By building our own website we will be able to make any

    necessary changes and alterations as they come up.

  • 7/27/2019 Sdl c Examples

    21/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Process Diagram: Enrollment Process

    During the enrollment process,

    customers will be prompted to login

    or create a user name. Then they will

    be presented with the available

    courses. From there they will have the

    option to browse our instructor

    profiles and select the instructor and

    the course that they like the best.

    After they have selected their course

    they will be required to make a down-

    payment to hold their seat in the

    class. They will pay the remainder of

    the cost when they arrive for the

    class.

  • 7/27/2019 Sdl c Examples

    22/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Process Diagram: Login Process

    The login process will enable our customers to create

    their own accounts, through which they

    will be able to place orders for standardized or customized

    products, ask questions, apply for

    training lessons, and download training videos.

    Current users will be able to access their accounts by

    inputting their user names and passwords.

    New clients will be able to sign up by inputting their

    personal information, like name, address

    and contact information, and choosing a unique user

    name and password to access their

    accounts.

    Our company will run a database of all users information,

    and it will guarantee confidentiality.

    By maintaining a database, we can learn about customers

    preference and inform them about

    specific discounts and offers regarding those products.

  • 7/27/2019 Sdl c Examples

    23/53

    Design Phase

    Example 1

  • 7/27/2019 Sdl c Examples

    24/53

    Plan

    Analyze

    Design

    System Model

    ER Diagram

    Navigation

    Develop

    Test

    Implement

    Maintain

    System Model - Website

    Log InFind Us

    Catalogue

    Contact Us

    Fan Pictures

    Home

    Comments

    Logo BUSINESS NAME

    Body

  • 7/27/2019 Sdl c Examples

    25/53

    Plan

    Analyze

    Design

    System Model

    ER Diagram

    Navigation

    Develop

    Test

    Implement

    Maintain

    CUSTOMER

    ORDER

    CUSTOMERORDER

    Payment

    Destination

  • 7/27/2019 Sdl c Examples

    26/53

    Plan

    Analyze

    Design

    System Model

    ER Diagram

    Navigation

    Develop

    Test

    Implement

    Maintain

    ShoppingCart

    HOME

    Log In

    Checkout

    Continue

    shopping

    Abandoncart

    Web Site Navigation

    Catalogue A Product

    Yes

    Add to cart?

    No

    Find Us

    Fan Photos

    Contact Us

  • 7/27/2019 Sdl c Examples

    27/53

  • 7/27/2019 Sdl c Examples

    28/53

    CheckPoint Rush [Logo] : Slogan

    Login

    Products

    Training Facilities

    FAQs

    About Us

    Our Riders

    Videos

    Photo Gallery

    Upcoming Events

    Blog

    Join Our Team -- Policies -- Contact Us

    Picture

    Slide Show

    (Body)

    System ModelPlan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

  • 7/27/2019 Sdl c Examples

    29/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    CUSTOMER

    PAYMENT

    CLASS

    REGISTRATION

    ORDERS

    PRODUCTS

    CheckPoint Rush Company Database

    VENDORS

  • 7/27/2019 Sdl c Examples

    30/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    CheckPoint Rush Website Navigation

    Login

    Products

    Training

    Facilities

    FAQs

    About Us

    Our Riders

    Videos

    Photo Gallery

    Upcoming Events

    Blog

    Follow us on Twitter

    HomePage

    Customer Account Account History

    Create New Account

    Shopping Cart

    Products

    Continue Shopping Check Out

    Training FacilitiesInfo

    Riders Bios

    Indoor

    Outdoor

    Our Bios

    Company Info

    Media Page

    SlideBomb

    News

    Posterous Spaces

    Twitter

  • 7/27/2019 Sdl c Examples

    31/53

    Development Phase

    Example 1

  • 7/27/2019 Sdl c Examples

    32/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Website Prototype

    We chose this prototype because it is

    easy for the customer to navigate. We

    also included fan photos because we

    wanted our customers to be recognizedfor their contributions to our business

    success.

  • 7/27/2019 Sdl c Examples

    33/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Website Prototype

  • 7/27/2019 Sdl c Examples

    34/53

    Development Phase

    Example 2

  • 7/27/2019 Sdl c Examples

    35/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Our company is satisfied with how the initial prototype looks

    like. The website is streamline and very

    easy to navigate. Our customers will not have any trouble

    finding the information that they need, which

    is one of our main requirements. The design of the website is

    very appealing. The combination of colors,

    pictures and text makes it look very professional and fun at

    the same time. It shows off the adventurous

    spirit, and excitement related to dirt biking.

    Prototype

  • 7/27/2019 Sdl c Examples

    36/53

  • 7/27/2019 Sdl c Examples

    37/53

    Testing Phase

    Example 1

  • 7/27/2019 Sdl c Examples

    38/53

    Plan

    Analyze

    Design

    Develop

    Test

    Website Test

    Implement

    Maintain

    Screen / Form Tested

    Date Tested

    Home page

    November 17, 2011

    Tester Name of Tester

    Test Condition Expected Results Actual Results (Circle one)

    Pass Fail

    Pass Fail

    Pass Fail

    Pass Fail

    Log In to the

    System

    A Customer/fan is able to

    log in with a username and

    password and access the

    system in a personalized

    matter.

    The system was able

    to match my user

    name and password

    Fan Photo

    Additions

    The fan photo addition

    uploads external photos to

    the system.

    The photo database

    wouldnt fully add

    photos to the

    appropriate folder

    Cart Memory

    Limits

    The customer database

    should be able to keep a

    cart in memory for two

    weeks.

    The cart was able to be

    accessed during random

    instances over the

    lengths of two weeks.

    Check Out Customers receive aconfirmation email with a

    receipt and conformation of

    their method of reception.

    The system generated

    an email that was sent

    to the customer inbox.

  • 7/27/2019 Sdl c Examples

    39/53

    Testing Phase

    Example 2

  • 7/27/2019 Sdl c Examples

    40/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Screen / Form Tested

    Date Tested

    Check Point Rush Shopping Cart Operations

    11/14/2012Tester Mary Smith

    Test Condition Expected Results Actual Results (Circle one)

    Payment Methods The system will take the

    Information of the payment

    (i.e. credit card, gift card)

    and process it correctly

    The system was able to

    Take the payment

    Information to process and

    Complete the transaction

    Pass Fail

    System Log in Customers are able to enter

    Their log-in info and system

    Will recognize it and bring

    them to the correct account

    System was not able to

    Match username and

    Password to the information

    Stored in the database

    Pass Fail

    Shopping Cart

    Performance

    Shopping cart will keep track

    Of all items and will navigate

    Through website while

    Shopping cart is open

    The shopping cart kept track of

    all items and navigated through

    The Website without losing the

    Items in the cart

    Pass Fail

    Check out Once customer is done

    Shopping the system will

    Navigate them to correct pages

    To complete transactions

    The system completed the

    Check out process after

    The payment cleared

    Pass Fail

    Testing

  • 7/27/2019 Sdl c Examples

    41/53

    Implementation Phase

    Example 1

  • 7/27/2019 Sdl c Examples

    42/53

    Implementation - Training

    Forensic Fountain is a travelling company and as such the amount of employees will be fairlysmall, thus our main training method is mainly based on a one-on-one interaction with atrainer. The company will not hire large groups of individuals, so group training will not berequired. Online training would also be beneficial because the training information would bearchived, thus making it available to employees as needed. For one-on-one training, eachemployee will spend a day of training with a founder or high level employee learning thesystem.

    USER DOCUMENTATION: Training manuals will be developed and available to employees asneeded. In addition, we will incorporate a train-the-trainer program people new to oursystem after the initial training. There will also be a FAQ area for employees to access asneeded.

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    System Training Implementation

    Method

    Maintain

  • 7/27/2019 Sdl c Examples

    43/53

    Implementation

    Our business will be implementing a plunge

    conversion method. We do not have a

    current website, so plunge makes the most

    sense for our business.

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    System Training Implementation

    Method

    Maintain

  • 7/27/2019 Sdl c Examples

    44/53

    Implementation

    Example 2

  • 7/27/2019 Sdl c Examples

    45/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    We will implement this system through a semi continuous training program.

    This means that a group of employees will attend meetings on a bimonthlybasis to learn what is changing within the system so they can train the rest of

    the employees. This will help keep the management and usage of the system

    the same.

    Parallel conversion will be used so we can have a system to fall back on just

    in case a problem does arise with the new system. This will ensure that wewill not be completely out of a system if something does end up failing. We

    will keep the system up through production and maintenance by using the

    training program stated above.

    User documentation will include a user manual. This manual will give

    detailed records on how everything within the system works. Any systemuser will be able to look in this manual if they have any question and they will

    be able to find exactly what they need to do in order for the system to run

    properly.

    Implementation

  • 7/27/2019 Sdl c Examples

    46/53

    Maintenance Phase

    Example 1

  • 7/27/2019 Sdl c Examples

    47/53

    Maintaining Forensic Fountain

    The founders of the company along with acouple two IT specialists will be in chargeof performing changes to the system as

    problems arise. We will have a help desk tofield both customer and employeequestions. The founders will also be incharge of changing the system format to

    customize the experience based oncustomer and employee feedback.

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Performing Changes

    System Maintenance

    Maintenance Schedule

  • 7/27/2019 Sdl c Examples

    48/53

    Maintenance Cont. Our adaptive maintenance will be handled by the owners of Forensic

    Fountain and will mostly entail them managing the layout and flow of thewebsite in order to better accommodate customers and employees and thegrowing needs of the business.

    Our corrective maintenance responsibilities will be handed over to the few ITspecialists the company has hired to make sure that the system runssmoothly and any defects are eradicated quickly and without problems.

    The perfective maintenance aspect of our company will be based heavily onthe feedback from our customers and employees. Once we have sufficientdata to warrant a change, those changes will fall under the adaptivemaintenance process and be handled by the same personnel.

    Our preventive maintenance will be monitored by our IT specialists, as is ourcorrective maintenance and will be based on trends produced by our

    maintenance schedule and commonly reported problems from within andoutside of the company. This maintenance will also be based on metrics

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Performing Changes

    System Maintenance

    Maintenance Schedule

  • 7/27/2019 Sdl c Examples

    49/53

    Maintenance ContPlan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Performing Changes

    System Maintenance

    Maintenance Schedule

    During the first 3 months of operation:

    Daily scans to check for any problems with the navigation, design, and other major areasof the site

    Routine weekly system testing to make sure system and databases are running smoothly

    Customer simulation by employees to test ease of system

    Effective April 1: Monthly scans of the system to ensure everything is still functioning highly (test links,

    documents, product database, etc)

    Periodic customer simulation to asses the quality of the website

    Quarterly updates to the system

    Bi-annual Deep checks/scans of databases perform data cleansing activities

    Monthly metrics will be ran to determine efficiency and effectiveness of site

    Company reports at the end of every quarter to assess performance and website quality

    Customer feedback, questions and complaints will be read and dealt with as soon as they occur.

  • 7/27/2019 Sdl c Examples

    50/53

    Maintenance Phase

    Example 2

  • 7/27/2019 Sdl c Examples

    51/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    In order to maintain the website and the system, weekly,

    monthly, and quarterly scans will be ran. These scans will

    certify that all the data in the system is up to date and

    accurate. If an issue is flagged, the operators and specialists

    that work on the system will fix it. If any updates need to be

    done, they will take care of that as well. Examples of itemsthat need to be updated include coupons/promotions, current

    company information, videos, our social media accounts, our

    blog, and any other information within our system that needs

    to be continually updated to keep our customers informed

    about what is going on with our company. Along side keeping

    our informed, we will respond to any customer questions or

    concerns as they come up.

    Maintenance

  • 7/27/2019 Sdl c Examples

    52/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    For adaptive, our technical team will keep tabs on new

    technologies and update our system correspondingly.

    For corrective, we will correct any imperfections that

    present themselves within the data in our database or any

    out dated information that comes up on our website.

    For perfective, we will have our team continuously try to

    make our site more efficient and effective for our

    customers by improving our site navigation.

    For preventive, our team will also be constantly be

    monitoring for issues with our software and upgrading any

    problems they may find to help our system stay healthy.

    Maintenance

  • 7/27/2019 Sdl c Examples

    53/53

    Plan

    Analyze

    Design

    Develop

    Test

    Implement

    Maintain

    Our technology team will work on a regular maintenance

    schedule.

    Daily:

    Check basic site functions

    Check links

    Check system stability

    Check database functioning

    Weekly:

    Run cleansing software on database information

    Check site traffic to help maintain the right level of

    functioning

    Monthly: Check system server stability

    Check system for bugs

    Maintenance