ANALISIS PENGURANGAN WASTE PADA PROSES
PERAWATAN MESIN CONSUMER PACKING DENGAN
PENDEKATAN LEAN DI PT. BFM
SKRIPSI
BERLIANA SIHOTANG
1610312008
UNIVERSITAS PEMBANGUNAN NASIONAL VETERAN JAKARTA
FAKULTAS TEKNIK
PROGRAM STUDI S1 TEKNIK INDUSTRI
2020
i
ANALISIS PENGURANGAN WASTE PADA PROSES
PERAWATAN MESIN CONSUMER PACKING DENGAN
PENDEKATAN LEAN DI PT. BFM
SKRIPSI
Diajukan Sebagai Salah Satu Syarat untuk Memperoleh Gelar
Sarjana Teknik
BERLIANA SIHOTANG
1610312008
UNIVERSITAS PEMBANGUNAN NASIONAL VETERAN JAKARTA
FAKULTAS TEKNIK
PROGRAM STUDI S1 TEKNIK INDUSTRI
2020
ii
iii
iv
v
vi
ANALISIS PENGURANGAN WASTE PADA PROSES
PERAWATAN MESIN CONSUMER PACKING DENGAN
PENDEKATAN LEAN DI PT. BFM
Berliana Sihotang
Abstrak
PT. BFM adalah pabrik penggiling gandum terkemuka di Indonesia serta sekaligus
menjadi produsenItepungIteriguIpertamaIdanIterbesarIdiIIndonesia. Pabrik ini sangat
mementingkan kualitas produknya maka pada bagian engineer memiliki tugas dalam
memberikan pelayanan jasa dengan cara merawat mesin agar dapat memenuhi permintaan
pelanggan dan menjaga kualitas produk dengan baik. Untuk tetap menjaga kepercayaan
pelanggan pada bagian Engineer tentu harus memperhatikan proses dalam perawatan mesin
itu sendiri, karena mesin yang digunakan pasti memiliki waste. Penelitian ini bertujuan untuk
mengidentifikasi waste dan memberikan solusi rekomendasi perbaikan yang bertujuan untuk
mengurangi waste yang terjadi. Dengan menggunakan pendekatan Lean Concept yang lebih
dominan ke arah Lean Manufacturing dan Six Sigma, sehingga pada penelitian ini dapat
mengkombinasikan antara pengurangan waste dengan pengendalian kualitas menggunakan
tahap DMAIC. Dengan begitu proses perawatan mesin dapat meningkatkan efisiensi dan
peningkatan kualitas. Penelitian ini dimulai dengan menggambarkan Big Picture Mapping
dan pembobotan nilai waste berdasarkan kuesioner menggunakan VALSAT. Waste juga
diidentifikasi menggunakan FMEA untuk dilakukan perhitungan nilai kritis waste kemudian
dilakukan rekomendasi perbaikan menggunakan 5W+1H. Hasil perhitungan dari pengolahan
data dari data yang telah terkumpul, didapatkan bahwa total waktu proses yang sebelumnya
76.895 detik menjadi 57.342,497 detik. Hasil presentase Value Added Activity sebesar
85,233%, Non-Necessary Value Adding sebesar 8,67% dan Non Value Added sebesar
6,10%. Hasil analisa FMEA didapat waste kritis yang perlu perbaikan adalah waste waiting
dengan skor sebesar 160.
Kata Kunci : Waste, Lean Concept, Six Sigma, DMAIC, Fishbone Diagram, FMEA,
5W+1H.
vii
ANALYSIS OF WASTE REDUCTION IN THE CONSUMER
PACKING MACHINE PROCESS WITH LEAN APPROACH IN PT.
BFM
Berliana Sihotang
Abstract
PT. BFM is a leading wheat mill in Indonesia and is also the largest producer of
flour and flour in Indonesia. This factory is very concerned about the quality of its products
so the engineer has a duty to provide services by maintaining the machine in order to meet
customer demand and maintain product quality well. To maintain customer confidence on the
part of the engineer certainly must pay attention to the process of maintaining the machine
itself, because the machine used must have waste. This study aims to identify waste and
provide recommendations for improvement that aim to reduce the waste that occurs. By using
Lean Concept approach which is more dominant towards Lean Manufacturing and Six
Sigma, so that this research can combine waste reduction with quality control using the
DMAIC stage. That way the machine maintenance process can improve efficiency and
improve quality. The study began by describing the Big Picture Mapping and weighting of
waste values based on a questionnaire using VALSAT. Waste was also identified using FMEA
to calculate the critical value of waste then a recommendation for improvement was carried
out using 5W + 1H. Calculation results from processing data from data that has been
collected, it was found that the total processing time which was previously 76,895 seconds to
57,342,497 seconds. The results of Value Added Activity are 85.233%, Non-Necessary Value
Adding is 8.67% and Non-Value Added is 6.10%. FMEA analysis results obtained that
critical waste that needs improvement is waste waiting with a score of 160.
Keywords: Waste, Lean Concept, Six Sigma, DMAIC, Fishbone Diagram, FMEA, 5W+1H.
viii
PRAKATA
Puji syukur penulis panjatkan Kehadirat Tuhan Yang Maha Esa karena atas
berkat, rahmat, dan karunia-Nya, sehingga penulis dapat menyelesaikan penulisan
Laporan Skripsi ini tepat pada waktunya dengan judul “Analisis Pengurangan
Waste Pada Proses Perawatan Mesin Consumer Packing Dengan Pendekatan
Lean Di PT. BFM” yang dilaksanakan dari tanggal 2 Maret 2020 s/d 31 Mei 2020.
Penulis sangat berharap bahwa skripsi ini dapat bermanfaat untuk menambah
pengetahuan dan wawasan pembaca. Skripsi ini disusun bertujuan memenuhi salah
satu syarat dalam memperoleh gelar S-1 Sarjana Teknik serta menyelesaikan program
studi S-1 Jurusan Teknik Industri Fakultas Teknik Universitas Pembangunan
Nasional Veteran Jakarta.
Pada kesempatan ini, penulis ingin mengucapkan terima kasih kepada beberapa
pihak yang telah membantu dalam penyusunan skripsi ini, sehingga skripsi ini dapat
terselesaikan dengan sebaik-baiknya. Ucapan terima kasih yang sebesar-besarnya
penulis berikan kepada:
1. Kedua orang tua serta keluarga tercinta yang banyak membantu, mendukung,
dan sekaligus mendoakan penulis.Terima kasih atas segalanya. Semoga
Tuhan Yang Maha Esa selalu memberikan kesehatan dan kebahagiaan, Amin.
2. Bapak Dr. Ir. Reda Rizal, M.Si., selaku Dekan Fakultas Teknik Universitas
Pembangunan Nasional Veteran Jakarta.
3. Bapak Muhammad As’adi, ST, MT, selaku Ketua Program Studi Teknik
Industri Universitas Pembangunan Nasional Veteran Jakarta. Serta selaku
membantu penulis dalam memberi solusi dari masalah yang ada dalam
penulisan skripsi ini.
4. Ibu Nurfajriah, ST, MT, selaku dosen pembimbing 1 yang telah memberikan
arahan dan dorongan kepada penulis dalam penulisan skripsi ini.
ix
5. Bapak Donny Montreano, ST, MT, IPM, selaku dosen pembimbing 2 yang
telah membimbing penulis dalam penyusunan skripsi ini sehingga menjadi
tugas akhir ini dapat terselesaikan dengan baik.
6. Bu Santika Sari, ST, MT, selaku dosen pembimbing yang telah
membimbing serta mengarahkan penulis dalam penyusunan skripsi ini dan
tidak henti-henti memberikan semangat kepada penulis selama penulisan
skripsi ini.
7. Bapak Akhmad Nidhomuz Zaman, ST, MT, selaku dosen mata kuliah Lean
Manufacturing yang telah mengajarkan mata kuliah yang bermanfaat sekali
dan memberikan ilmu yang bagus dalam pengajarannya.
8. Dosen penguji dan dosen mata kuliah Teknik Industri UPNVJ yang telah
memberikan banyak sekali ilmu yang sangat bermanfaat.
9. Bapak Thimoteus Dagomez, selaku Public Relations di PT. ISM Tbk. Divisi
Bogasari Flour Mills Jakarta, yang telah membantu penulis dalam
memberikan kesempatan dalam persetujuan dalam penelitian tugas akhir ini.
10. Bapak M. Zulkarnain selaku Manager bagian Maintenance/Engineer divisi
consumer packing di PT. ISM Tbk. Divisi Bogasari Flour Mills yang telah
sangat membantu penulis dalam memberikan kesempatan untuk penelitian
tugas akhir penulis. Beliau bersedia menyediakan waktu untuk memberikan
bimbingan serta pengajaran bagi penulis.
11. Bapak Didi Santoso, Bapak Hendra, Bapak Dimas, Bapak Randek, Bapak
Gustom, Bapak Risky, Bapak Ibnu, dan seluruh karyawan divisi Maintenance
yang tidak bisa disebutkan satu-satu, yang bekerja di PT. ISM Tbk. Divisi
Bogasari Flour Mills Jakarta yang telah membantu penulis saat berada di
lingkungan PT. ISM Tbk. Divisi Bogasari Flour Mills Jakarta.
12. M. Afi Fahmi, Agung Adi S., Taufan Kurnia F., Selaku teman-teman
seperjuangan selama periode praktik kerja lapangan dan periode skripsi ini
selesai dibuat menjadi berkesan. Terima kasih.
x
13. Widia Rizky L, Meriyanti, Aulia Djumantara, Purwati, Nadya Cahyani, Zelika
Hana P, Finka N, selaku support system penulis dalam memberi informasi
yang bermanfaat bagi penulis dalam menyelesaikan skripsi ini.
14. Seluruh rekan-rekan Teknik Industri Angkatan 2016 Universitas
Pembangunan Nasional Veteran Jakarta yang telah memberikan motivasi dan
semangat selama pelaksanaan dan penyusunan skripsi ini. Terima kasih atas
semua dukungannya.
15. Himpunan Mahasiswa Teknik Industri UPNVJ, karena telah membuat penulis
menjadi mengerti tentang organisasi dan mendapat ilmu yang bermanfaat
nantinya.
PenelitianIiniIdilakukanIpadaItanggal 02 maret 2020 - 31 mei 2020. Penelitian
pada rentang waktu tersebut sedang mengalami penyebarann wabah Covid 19 dan
ditetapkannya PSBB (Pembatasan Sosial Berskala Besar), sehingga diharuskan
mematuhi protokol kesehatan. Penulis menyadari bahwa di dalam penyusunan skripsi
ini masih jauh dari kesempurnaan dan tidak jauh dari kesalahan dan keterbatasan.
Oleh karena itu, penulis mengharapkan kritik dan saran yang bersifat membangun
bagi penulis. Akhir kata semoga skripsi ini dapat berguna dan bermanfaat, Amin.
Jakarta, Maret 2020
Penulis
xi
DAFTAR ISI
HALAMAN JUDUL .................................................................................................... i
HALAMAN PENGESAHAN PENGUJI .................................................................. ii
HALAMAN PENGESAHAN PEMBIMBING ........................................................ iii
PERNYATAAN ORISINALITAS ............................................................................ iv
HALAMAN PERSETUJUAN PUBLIKASI ............................................................ v
ABSTRAK .................................................................................................................. vi
ABSTRACT ................................................................................................................ vii
PRAKATA ................................................................................................................ viii
DAFTAR ISI ............................................................................................................... xi
DAFTAR GAMBAR ................................................................................................ xiv
DAFTAR TABEL .................................................................................................... xv
DAFTAR LAMPIRAN ........................................................................................... xvii
BAB I PENDAHULUAN
1.1 Latar Belakang Penelitian .......................................................................... 1
1.2 Perumusan Masalah ................................................................................... 5
1.3 Tujuan Penelitian ....................................................................................... 5
1.4 Batasan Masalah ....................................................................................... 6
1.5 Manfaat Penelitian .................................................................................... 7
1.6 Sistematika Penulisan ................................................................................ 7
BAB II TINJAUAN PUSTAKA
2.1 Penelitian Terdahulu .................................................................................. 9
2.2 Landasan Teori ........................................................................................ 17
2.2.1. Konsep Dasar Lean ........................................................................... 17
2.2.1.1 Implementasi Lean Thinking ......................................................... 19
2.2.2. Definisi Pemborosan (Waste) ............................................................ 19
2.2.3. Definisi Lean Manufacturing ............................................................ 21
2.2.4. Definisi Lean Service ........................................................................ 22
xii
2.2.5. Definisi Six Sigma ............................................................................. 25
2.2.5.1 DMAIC ......................................................................................... 25
2.2.5.2 Rumus Six Sigma .......................................................................... 28
2.2.6. Definisi Big Picture Mapping (BPM) .............................................. 29
2.2.7. Definisi Kuesioner 7 Waste .............................................................. 32
2.2.8. Definisi Value Stream Analysis Tools (VALSAT) .......................... 33
2.2.9. Definisi Fishbone Diagram............................................................... 39
2.2.10. Definisi Failuer Mode Effect Analysis (FMEA) ............................... 40
BAB III METODE PENELITIAN
3.1 Flowchart Penelitian ................................................................................ 44
3.2 Metode Penelitian ................................................................................... 45
3.3 Kerangka Pemikiran ................................................................................ 46
3.4 Tempat, Waktu, dan Objek Penelitian .................................................... 47
3.5 Teknik Pengumpulan Data ...................................................................... 47
3.6 Jenis dan Sumber Data ............................................................................ 48
3.7 Tahap Penelitian ...................................................................................... 49
BAB IV HASIL DAN PEMBAHASAN
4.1 Pengumpulan Data ................................................................................... 54
4.1.1 Aliran Proses Perawatan .................................................................... 54
4.1.2 Data Aliran Waktu Pengerjaan .......................................................... 58
4.2 Pengolahan dan Analisa Data .................................................................. 59
4.2.1 Fase Define ........................................................................................ 59
4.2.1.1 Current Big Picture Mapping (CBPM) ...................................... 59
4.2.1.2 Kuesioner .................................................................................... 60
4.2.2 Fase Measure ...................................................................................... 62
4.2.2.1 Skor dan Urutan Waste Tertinggi ................................................. 62
4.2.2.2 Pengolahan Kuesioner dengan VALSAT .................................... 64
4.2.2.3 Fase Perhitungan Process Activity Mapping (PAM) ................... 67
4.2.2.4 Perhitungan Six Sigma ................................................................. 73
xiii
4.2.3 Fase Analyze ...................................................................................... 77
4.2.3.1 Analisa VALSAT dengan Tool PAM ......................................... 77
4.2.3.2 Analisa Waste dengan Kuesioner................................................ 92
4.2.3.3 Analisa Fisbone Diagram ........................................................... 93
4.2.3.4 Analisa Failure Mode Effect and Analysis (FMEA) ................... 99
4.2.3.5 Analisa 5W+1H ........................................................................ 107
4.2.4 Fase Improve ................................................................................... 109
4.2.4.1 Usulan Tindakan Perbaikan ...................................................... 109
4.2.5 Fase Control ..................................................................................... 114
4.2.5.1 Future Big Picture Mapping (FBPM)....................................... 115
4.2.5.2 Peningkatan Sigma .................................................................... 116
BAB V SIMPULAN DAN SARAN
5.1 Simpulan ................................................................................................ 119
5.2 Saran ..................................................................................................... 120
DAFTAR PUSTAKA .............................................................................................. 121
DAFTAR RIWAYAT HIDUP ............................................................................... 124
LAMPIRAN
xiv
DAFTAR GAMBAR
Gambar 1.1 Grafik Persentase Kenaikan Kegiatan PM Tahun 2018 .......................... 3
Gambar 1.2 Grafik Persentase Kenaikan Kegiatan PM Tahun 2019 .......................... 4
Gambar 2.1 Siklus DMAIC ....................................................................................... 26
Gambar 2.2 SimbolIBigIPictureIMapping ............................................................... 32
Gambar 2.3 Fishbone Diagram ................................................................................. 40
GambarI3.1 FlowchartIPenelitian ............................................................................. 45
Gambar 3.2 Skema Kerangka Berfikir ...................................................................... 46
Gambar 4.1 Alur proses perawatan mesin consumer packing................................... 54
Gambar 4.2 Mesin Retail Packer BS 201, 202, dan 203 ........................................... 56
Gambar 4.3 Mesin Case Erector .............................................................................. 56
Gambar 4.4 Mesin Prodec ........................................................................................ 57
Gambar 4.5 Mesin Case Sealer ................................................................................ 57
Gambar 4.6 Current Big Picture Mapping (BPM) .................................................... 60
Gambar 4.7 Diagram Persentase Keseluruhan Aktivitas .......................................... 68
Gambar 4.8 Diagram persentase waktu keseluruhan aktivitas .................................. 70
Gambar 4.9 Diagram persentase Value Stream Activity ........................................... 72
Gambar 4.10 Diagram perbandingan persentase PAM Jumlah Aktivitas ................ 87
Gambar 4.11 Diagram perbandingan persentase PAM Waktu pengerjaan .............. 87
Gambar 4.12 Diagram perbandingan persentase jumlah aktivitas Value Stream ..... 90
Gambar 4.13 Diagram perbandingan persentase waktu aktivitas Value Stream ....... 90
Gambar 4.14 Fishbone Diagram Waiting ................................................................. 94
Gambar 4.15 Fishbone Diagram Unnecessary Motion ............................................. 95
Gambar 4.16 Fishbone Diagram Defect.................................................................... 96
Gambar 4.17 Fishbone Diagram Transportation ...................................................... 97
Gambar 4.18 Fishbone Diagram Unnecessary Inventories ...................................... 98
Gambar 4.19 Fishbone Diagram Inapropriate Processing ....................................... 99
Gambar 4.20 Future Big Picture Mapping .............................................................. 115
xv
DAFTAR TABEL
Tabel 1.1 Jadwal Perawatan Mesin pada divisi consumer packing tahun 2018 .......... 2
Tabel 1.2 Jadwal Perawatan Mesin pada divisi consumer packing tahun 2019 ........... 3
Tabel 2.1 PenelitianITerdahulu .................................................................................. 11
Tabel 2.2 PrinsipIdalam leanImanufacturingIdanIleanIservice ................................. 21
Tabel 2.3 Kelebihan dan Kekurangan Six Sigma (DMAIC) ...................................... 28
Tabel 2.4 TingkatIPencapaianISigma ........................................................................ 29
Tabel 2.5 Kuesioner 7 Waste ..................................................................................... 32
Tabel 2.6 Tools padaIVALSAT ................................................................................. 34
Tabel 2.7 Keuntungan dan Kekurangan Fishbone Diagram ...................................... 39
Tabel 2.8 Skala Severity ............................................................................................ 42
Tabel 2.9 Skala Occurance ........................................................................................ 43
Tabel 2.10 Skala Detection ........................................................................................ 43
Tabel 4.1 Data aliran waktu pengerjaan ..................................................................... 58
Tabel 4.2 Pilihan jawaban dari kuesioner................................................................... 61
Tabel 4.3 Hasil dari kuesioner .................................................................................... 62
Tabel 4.4 Rata-rata dan ranking waste ....................................................................... 64
Tabel 4.5 Nilai Korelasi Tools pada VALSAT .......................................................... 65
Tabel 4.6 Perhitungan VALSAT ................................................................................ 66
Tabel 4.7 Hasil rekapitulasi perhitungan VALSAT ................................................... 67
Tabel 4.8 Hasil rekapitulasi perhitungan presentase PAM ........................................ 68
Tabel 4.9 Pengelompokkan aktivitas kerja ................................................................. 70
Tabel 4.10 Presentase aktivitas pada value stream .................................................... 72
Tabel 4.11 Check sheet CTQ Komponen yang rusak ................................................. 74
Tabel 4.12 Hasil Pengukuran Nilai Sigma dan DPMO .............................................. 76
Tabel 4.13 Usulan perbaikan pada PAM .................................................................... 78
Tabel 4.14 Perbandingan PAM awal dan usulan berdasarkan aktivitas .................... 86
Tabel 4.15 Perbandingan PAM awal dan usulan berdasarkan Value Stream............. 89
xvi
Tabel 4.16 Hasil rekapitulasi kuesioner ..................................................................... 92
Tabel 4.17 Tabel list waste identifikasi resiko ......................................................... 100
Tabel 4.18 Usulan perbaikan dengan FMEA ........................................................... 105
Tabel 4.19 Improve mengatasi waste waiting .......................................................... 110
Tabel 4.20 Improve mengatasi waste unnecessary motion ..................................... 110
Tabel 4.21 Improve mengatasi waste defect ............................................................. 111
Tabel 4.22 Improve mengatasi waste transportation ............................................... 112
Tabel 4.23 Improve mengatasi waste unnecessary inventories ............................... 112
Tabel 4.24 Improve mengatasi waste overprocessing .............................................. 113
Tabel 4.25 Perbandingan CBPM dan FBPM ........................................................... 116
Tabel 4.26 Presentase komponen defect bulan Mei 2020 ........................................ 117
xvii
DAFTAR LAMPIRAN
Lampiran A Current Process Activity Mapping
Lampiran B Future Process Activity Mapping
Lampiran C CBPM Maintenance Consumer Packing PT. BFM
Lampiran D FBPM Maintenance Consumer Packing PT. BFM
Lampiran E Kuesioner
Lampiran F Hasil Kuesioner
Lampiran G Hasil Wawancara
Lampiran H Perhitungan Formulasi
Lampiran I Hasil PAM Usulan
Lampiran J Tabel Konversi DPMO