PENJADWALAN PRODUKSI TI-2408 PERENCANAAN & PENGENDALIAN PRODUKSI Penjadwalan Tenaga Kerja

TI 2408 Penjadwalan Tenaga Kerja.ppt

Embed Size (px)

DESCRIPTION

penjadwalan

Citation preview

Page 1: TI 2408 Penjadwalan Tenaga Kerja.ppt

PENJADWALAN PRODUKSI

TI-2408 PERENCANAAN & PENGENDALIAN PRODUKSIPenjadwalan Tenaga Kerja

Page 2: TI 2408 Penjadwalan Tenaga Kerja.ppt

SISTEM PERENCANAAN PRODUKSIAggregate Planning

Master Production Schedule

Material Requirements Planning

Planned Order Release

Production Scheduling Staffing Facility with People

Page 3: TI 2408 Penjadwalan Tenaga Kerja.ppt

KARAKTERISTIK PERENCANAAN TENAGA KERJA Characteristics:

Demand tends to fluctuate widely in the short term and to occur seven days a week

Human effort cannot be inventoried Customer convenience is critical

Steps to solve the problem: Identify the services to be provided Determine the average time required for each service Forecast the demand for each service over the seven day period

and for the staffs Smooth out the staffing needs

Page 4: TI 2408 Penjadwalan Tenaga Kerja.ppt

TERMINOLOGI Demand: the number of people needed during some periods to

provide a predefined level of service. A weekly demand forecast is the number of people to be employed during each day of the week

Shift: (1) the time of a day when a person begins work and takes a rest and breaks

during the day. Example: Shift 5 starts at 08:00 with 15 minutes off at 10:00 and 14:00, and lunch from 12:15 to 12:45

(2) the set of days during a given week when a person will be expected at work. Example: Shift 5 is Monday through Friday, with Saturday and Sunday off

Schedule: the set of shifts that satisfies the demand criteria at minimum labor cost

Page 5: TI 2408 Penjadwalan Tenaga Kerja.ppt

SHIFT SCHEDULING - EXAMPLE Kondisi Sistem :

Dibutuhkan tenaga kerja sebanyak 28 orang untuk memenuhi kebutuhan tenaga kerja satu minggu.

Setiap pekerja individu diinginkan bekerja selama 5 hari dalam satu minggu, dengan begitu dibutuhkan 6 shift (6 individu) untuk memenuhi kebutuhan 28 tenaga kerja (28/5).

Gambar 1 menunjukkan contoh forecast kebutuhan tenaga kerja sederhana dan solusi jadwal shift yang dapat diterapkan.

Setiap pekerja di set bekerja 5 hari seminggu dan masing-masing memiliki 2 hari libur berurutan dalam 1 minggu

Solusi ini mengandung overstaffing pada Tuesday dan Friday, akan tetapi sudah merupakan solusi optimal karena melibatkan 6 orang pekerja yang merupakan jumlah minimum yang masih feasible.

Page 6: TI 2408 Penjadwalan Tenaga Kerja.ppt

                                                                                                         

  Sun Mon Tue Wed

Thu Fri Sat      Shift #1           Shift #2       Shift #3                           Shift #4                           Shift #5                     Shift #6                        Sum

Staff 2 4 5 5 5 5 4 30Demand 2 4 4 5 5 4 4 28Overstaff 0 0 1 0 0 1 0 2

Gambar 1

Page 7: TI 2408 Penjadwalan Tenaga Kerja.ppt

ALGORITMA SHIFT SCHEDULING Algoritma Tibrewala, Philippe, and Browne

(TPB) Algoritma Monroe

Page 8: TI 2408 Penjadwalan Tenaga Kerja.ppt

Contoh Soal Diketahui hasil peramalan kebutuhan tenaga kerja dalam

satu minggu adalah sebagai berikut :

Sun Mon Tue Wed Thu Fri Sat  

4 8 7 7 7 7 6 Demand Forecast

Diinginkan sebuah jadwal yang melibatkan jumlah tenaga kerja yang optimal dengan syarat sebagai berikut : Setiap pekerja hanya bekerja 5 hari per minggu Setiap pekerja diusahakan mendapat dua hari libur berurutan

dalam satu minggu.

Page 9: TI 2408 Penjadwalan Tenaga Kerja.ppt

ALGORITMA TPB Step 1: Working from the largest manpower-need day to

the second largest and so forth, do the following. Place all days with the same manpower need on the schedule until a unique two-consecutive-days off period appears. If a tie exists, go to Step 2.

Step 2: If two identical two-days-off periods occur, select the pair with the smallest requirements on adjacent days. If the tie cannot be broken, go to Step 3.

Step 3: Select the most reasonable pair; for example, the one that has a Saturday/Sunday off or the first pair in the week

Page 10: TI 2408 Penjadwalan Tenaga Kerja.ppt

PENYELESAIAN DGN ALGORITMATPB (1)

Step 1: Mulai dari hari yang membutuhkan jumlah tenaga kerja terbesar, kedua terbesar, dan selanjutnya lakukan hal berikut : Place all days with the same manpower need on the schedule until a unique

two-consecutive-days off period appears. If a tie exists, go to Step 2.

Sun Mon Tue Wed Thu Fri Sat  

4 8 7 7 7 7 6 Demand Forecast

0 -1 -1 -1 -1 -1 0 Shift 1

4 7 6 6 6 6 6  

  -1 ? ? ? ? ?  a tie exist

Step 2: If two identical two-days-off periods occur, select the pair with the smallest requirements on adjacent days. If the tie cannot be broken, go to Step 3.

Page 11: TI 2408 Penjadwalan Tenaga Kerja.ppt

PENYELESAIAN DGN ALGORITMATPB (2)

Step 3: Select the most reasonable two-days-off pair; for example, the one that has a Saturday/Sunday off or the first pair in the week.

Sun Mon Tue Wed Thu Fri Sat  

4 8 7 7 7 7 6 Demand Forecast

0 -1 -1 -1 -1 -1 0 Shift 1

4 7 6 6 6 6 6  

0 -1 -1 -1 -1 -1 0 Shift 2

4 6 5 5 5 5 6  

  -1 ? ? ? ? -1  a tie exist

Page 12: TI 2408 Penjadwalan Tenaga Kerja.ppt

PENYELESAIAN DGN ALGORITMATPB (3)

Sun Mon Tue Wed Thu Fri Sat  

4 8 7 7 7 7 6 Demand Forecast

0 -1 -1 -1 -1 -1 0 Shift 1

4 7 6 6 6 6 6  

0 -1 -1 -1 -1 -1 0 Shift 2

4 6 5 5 5 5 6  

-1 -1 0 0 -1 -1 -1 Shift 3

3 5 5 5 4 4 5  

  -1 -1 -1 ? ? -1 a tie exist

Step 3: Select the most reasonable two-days-off pair, in this case Thu/Fri

Page 13: TI 2408 Penjadwalan Tenaga Kerja.ppt

PENYELESAIAN DGN ALGORITMATPB (4)

Sun Mon Tue Wed Thu Fri Sat  

4 8 7 7 7 7 6 Demand Forecast

0 -1 -1 -1 -1 -1 0 Shift 1

4 7 6 6 6 6 6  

0 -1 -1 -1 -1 -1 0 Shift 2

4 6 5 5 5 5 6  

-1 -1 0 0 -1 -1 -1 Shift 3

3 5 5 5 4 4 5  

-1 -1 -1 -1 0 0 -1 Shift 4

2 4 4 4 4 4 4  

  ? ? ? ? ? ?  a tie exist

Step 3: Select the most reasonable two-days-off pair, in this case Sat/Sun

Page 14: TI 2408 Penjadwalan Tenaga Kerja.ppt

Sun Mon Tue Wed Thu Fri Sat  

3 5 5 5 4 4 5  

-1 -1 -1 -1 0 0 -1 Shift 4

2 4 4 4 4 4 4  

0 -1 -1 -1 -1 -1 0 Shift 5

2 3 3 3 3 3 4  

0 0 -1 -1 -1 -1 -1 Shift 6

2 3 2 2 2 2 3  

-1 -1 0 0 -1 -1 -1 Shift 7

1 2 2 2 1 1 2  

-1 -1 -1 -1 0 0 -1 Shift 8

0 1 1 1 1 1 1  

0 -1 -1 -1 -1 -1 0 Shift 9

0 0 0 0 0 0 1  

0 0 -1 -1 -1 -1 -1 Shift 10

0 0 -1 -1 -1 -1 0  

ALGORITMATPB (5)

Page 15: TI 2408 Penjadwalan Tenaga Kerja.ppt

Demand Total 46      

Individual Requirement 46/5 = 9,2 Individu = 10

Solusi :  

4 Shift dengan SAT/SUN OFF  

2 Shift dengan SUN/MON OFF  

2 Shift dengan TUE/WED OFF  

2 Shift dengan THUR/FRI OFF        

PENYELESAIAN DGN ALGORITMA TPB (6)

SOLUSI

Page 16: TI 2408 Penjadwalan Tenaga Kerja.ppt

LATIHAN Sebuah perusahaan Call Center ingin menyusun jadwal

shift para pegawainya dalam seminggu. Hasil peramalan terhadap permintaan jasa menghasilkan estimasi kebutuhan jumlah tenaga kerja setiap harinya sbb :

Hari Senin Selasa Rabu Kamis Jumat Sabtu Minggu

Kebutuhan 8 6 7 8 4 6 5

Susun jadwal shift pekerja jika perusahaan ingin agar setiap pegawainya bekerja 5 hari dan memiliki libur 2 hari berurutan dalam seminggu.