Upload
lyhuong
View
218
Download
0
Embed Size (px)
Citation preview
CROSS-BORDER ENERGY TRADE IN SOUTH ASIA
MANJU GUPTA POWER GRID CORPORATION OF INDIA LTD.
INDIA
1
USAID/SARI-E SOUTH ASIA REGIONAL WORKSHOP ON TRANSMISSION OPERATIONS FOR CROSS BORDER ENERGY TRADE
THIMPHU, BHUTAN AUGUST 28-30, 2012
Common Features of South Asia Countries
• Abundant reserves of Natural resources
• Low per capita electricity consumption
• Fast Growth in Demand & deficit of Power in most of the countries
• Common frequency of operation
• Similar voltage class
2
• Improving Reliability and pooling reserves
• Improving load factor and increasing load diversity
• Economies of scale in new construction
• Diversity of generation mix and supply security
• Economic exchange
• Thermal resources – cheaper to transport in electricity form; Hydro
resources – can only be transported in electricity form
• Exporting countries benefitted economically, Importing countries
benefited by deferring investment towards setting up power plants
• Evolving Open Electricity market
• Countries with limited resources would be benefited
3
Benefits of Interconnection
6
Interconnection between India & Bangladesh Grids
• Purpose : –Exchange of Power between
India and Bangladesh
• Interconnection : – Baharampur(India)-
Bheramara(Bangladesh) 400kV D/c
line
–500MW HVDC B/b stn at
Bheramara(Bangladesh)
• Type of connection : –Asynchronous(HVDC)
• Transfer Capacity : – 500MW (upgradable to
1000MW)
GOALPARA33.2 MVA
KHULNADOMJUR
LILUAH
HOWRAH(WB)
JOKA
BUDGEBUDGE
SOUTHERN
BARIPADA
HALDIATAMLUK
FALTA
KOLAGHAT
KRG'PUR(D)
ULUBERIA
KOLAGHAT(D) HWH(D)
HM
LEGEND
BHOLAGALLAMARI
LAKSHMIKANTOPUR
SUBHASGRAM
BASIRHATSONARPUR
KASBA
MANGLA13.3 MVA
SOUTH
SATKHIRA
BHANDARIA13.3 MVA
26.6 MVABAGERHAT
KAWKHALI
PATUAKHALI40 MVA
BARISAL82 MVA
230/220kV
EXISTING
132kV
FUTURE
BANDARBAN
20 MVA
COX'S BAZAR
RAUJAN
JULDAH
SHAHMIRPUR
126 MVA
Bay of Bengal
HALISHAHAR167 MVA
BURHANUDDIN
63 MVA
82 MVA
HATHAZARI
BAROAULIA
KULSISIKALBAHA
80 MVA
41 MVA
DOHAZARI
CHANDROGHONA26.6 MVAMADANHAT
82 MVA
KAPTAI
LUNGSEN
TENGA
NBU
LDTEESTA
RAIGANJ
GANGARAMPUR
DALKHOLA(WBSEB)
CH. NAWABGANJ40 MVA
SAGARDIGHI
RAGHUNATHGANJ
DEBAGRAM
KRNAGAR
RANAGHAT
TITAGARH
DPL
ARAMBAG
ARAMBAGBURDWAN
RISHRA
BELMURI
KHANYAN
BTPS
DURGAPUR
NAGARBIDHAN
MANKAR
BOLPUR
SATGACHIA
KATWA
DHULIAN
RAMPURHAT
BAKRESHWARSAITHIA
GOKARNA
FARRAKA
KHEJURIA
PURNEA
KAHALGAON
MALDA
SAMSI
DALKHOLA
KATIHAR
PURNEA(BSEB)(WBSEB)DALKHOLA
LEBONG
RAMMAM
JOYDEVPUR
GHORASAL
ASHUGANJ
MEGHNAGHATMAGURA
40 MVA
KHULNA CENTRAL192 MVA
NOAPARA
BONGAON
JEERAT
ASHOKNAGAR
DHRMPR
BARASAT
KALYANI JESSORE80 MVA
CHUADANGA
JHENAIDA40 MVA
BOTTAIL82 MVA
MADARIPUR26.6 MVA
GOPALGANJCHANDPUR
40 MVA
AMINBAZAR
FARIDPUR40 MVA
MANIKGANJ41 MVA
HASNABAD
MIRPUR
KALYANPUR
TONGI
ULLON
BASUNDHARA
BOGRA82 MVA
40 MVA
SHAHJAD
SIRAJGANJ
PUR40 MVA
BHERAMARA16.6 MVA
ISHURDIBEHRAMPUR
BEHRAMPUR
53 MVARAJSHAHI
82 MVAPABNA
NATORE40MVA
NIAMATPUR NAOGAON82 MVA
BOGRASOUTH
SRIPUR(MODHUPUR)
TANGAIL82 MVA
BAGHABARI
KABIRPUR82 MVA
68 MVA
JAMALPUR82 MVA
82 MVAMYMENSINGH
JIRIBAMKOLASIB100 MVAKHOWAI
TRIPURA
CHOWMOHANI
82 MVA
COMILLA
82 MVASOUTH
FENI40 MVA
40 MVA
COMILLANORTH
AGARTALAHARIPUR
SIDDHIRGANJ
RAMPURAGPP
AGARTALA
AMBASSA
W.PHAILENG
RANGAMATI
KHAGRACHARI
LUNGLEI
MARPARA
SERCHIP
(ZEMABAWK)
MIZORAM
AIZWAL
AIZWAL
EASTKANCHANBARI
KISHORGANJ
20 MVASHAHJIBAZAR
50 MVA
B. BARIA
B BARIA
40 MVA
KAMALPUR
SREEMONGAL
40 MVA
NETROKONA40 MVA
SYLHET
DULLABCHERA
KAILASHAHAR
KUMARGHAT
DHARMNAGAR
BADARPUR
PANCHGRAM
FENCHUGANJ
33 MVA
SYLHET40 MVA
JIRIBAM
PILAPOOL
BONGAIGAON
ASSAM
BORNAGAR
40 MVA
LALMONIRHAT
PALASHBARI
JOYPURHAT
BALURGHAT40 MVA
82 MVASAIDPUR
33.4 MVA
BOROPUKURIA
PURBASADIPUR
(2x41+1x20) MVATHAKURGAON
RANGPUR82 MVA
TURA
ALIPURDUAR
SILIGURI
MOINAGURI
PANCHAGARH
BIRPARA
MELLI
BIRPARA(WB)
GOSAIGAON
DHALIGAON
AGIA
SALAKATI
SINGIGAON
CHUKHA
GUWAHATI
NEHU
KYRDEMKULAIUMIAM-4
MEGHALAYANANGAL
BIBRA
40 MVACHATTAK
CHERRAPUNJI
SHILLONG
LONGPI
UMTRU
UMIAM
CHANDRAPUR
KHLIEHRIAT
KHLIEHRIAT
KHANDONG
HAFLONG
KOPILI
BYRNIHAT
JAGIROAD
UMRANGSO
NECHIPHU
RANGIA
AMINGAON
ROWTA TEJPUR
SAMAGURI
MARIANI
BALIPARA GOHPUR
POWER MAP OF BANGLADESH AND INDIA
GANGTOK
RANJIT
TEESTA-VTALA
LHAO
KAMENGKHUPI
SURYAMANINAGAR
SILCHAR
400kV at 132kV
PALLATANA
AZARA
7
India & Bangladesh Interconnection
• MOM signed between Indian Delegation and BPDB & PGCB officials, Bangladesh on November 24, 2009 at Dhaka.
• Executing Agency :
– Indian portion : POWERGRID, India
– Bangladesh portion : PGCB (Power Grid Company of Bangladesh Ltd.), Bangladesh.
• Cost Estimate :
– India Portion : Rs. 169.86 Crore (USD 37.75 million)
– Bangladesh Portion : Rs. 736.84 Crore (USD 163.75 million)
• Commissioning Schedule : July, 2013
8
BOGRASOUTH
BHERAMARA
NAOGAON
NIAMATPUR
FARRAKA
SUBHASGRAM
KATWA
GOKARNA
JEERAT
KHULNA(SOUTH)
BOTTAIL
BAHARAMPUR
CH. NAWABGANJ
RAGHUNATHGANJ
KA
HA
LG
AO
N
SAGARDIGHI
RAJSHAHI
BAHARAMPUR
ISHURDI
NATORE
KHEJURIA
FARIDPUR
BAGHABARI
GHORASAL
MA
DH
OP
UR
SHAHJAD
PABNAPUR
SIRAJGANJ
BOGRA
INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS
400 kV230 kV132 kV
THE PROJECT
LEGEND
BAKRESHWAR
KOLAGHAT
BANGLADESH
INDIA
400kV D/c
(400 KV)
MALDA
DHULIAN
DURGAPUR
Existing
Under Constr. / Future
JAYPURHAT BARAPUKURIA
9
India & Bangladesh Future Interconnection
• In the 4th Joint Steering Committee Meeting held in Delhi on 28th
February 2012, possibility of import of power from Tripura and
interconnection between the eastern and western sides of
Bangladesh was discussed.
• It was agreed that a Joint Technical Team (JTT) may be set up to look
into the feasibility of power exchange through eastern side of
Bangladesh border.
• The following TOR for the JTT was agreed:
To explore the opportunity of power exchange between eastern
side of Bangladesh and India.
To recommend associated transmission system on both sides of
the border and its integration required for facilitating such power
exchange.
India - Bhutan : Existing Interconnections
For import of power from following Projects • Chukha HEP (4x84 = 336 MW)
– Chukha – Birpara 220kV 3 ckts
• Kurichu HEP (4x15 = 60 MW)
– Kuruchu - Geylegphug(Bhutan) – Salakati(NER) 132 kV S/c
• Tala HEP (6x170 MW = 1020 MW)
– Tala – Siliguri 400kV 2x D/c line
11
India - Bhutan : On Going Trans. System
Tr. System for Punatsangchu-I (1200 MW)
• Interconnection (Bhutan Portion) : Punatsangchu-I HEP – Lhamoizingkha
(Bhutan Border) 400 kV 2xD/c line with twin moose Conductor.
• Interconnection (Indian Portion) : Lhamoizingkha (Bhutan Border) –
Alipurduar 400kV D/c (Quad)
• Other Major Transmission System in India
– New + 800kV, 3000MW HVDC pooling station at Alipurduar.
– Extn. of + 800kV, 3000MW HVDC station at Agra
– LILO of Bishwanath Chariali – Agra 800kV, 6000MW HVDC line at Alipurduar
– LILO of Bongaigaon – Siliguri 400kV D/c line(quad) at Alipurduar
– LILO of Tala-Siliguri 400kV D/c line at Alipurduar.
Estimated Cost (Indian Part) : Rs. 4400Cr. (USD 978 million) 12
India - Bhutan : Future Scenario • Identified Hydro Potential : About 24000 MW
• Major Hydro power addition – By 2020 : 10300 MW (from 14 HEP)
– By 2030 : 22280 MW (from 71 HEPs)
• Major Projects by 2020
13
Sl No Project Capacity Commissioning
1 Punatsangchu-I 1200 2015
2 Punatsangchu-II 1020 2017
3 Sunkosh 2500 2020
4 Wangchu 570 2019
5 Bunakha 180 2020
6 Amochhu 540 2018
7 Dagachhu 126 2015
8 Mangdechhu 720 2017
9 Nikachhu 210 2020
10 ChamKharchu-I 770 2018
11 Kuri-Gongri 1800 2020
12 Kholongchu 600 2018
India – Bhutan : Transmission system from future Projects
• Major portion of power from the future generation projects in
Bhutan is envisaged to be imported into Indian grid.
• 4 no of high capacity 6000MW HVDC corridors to various regions of
India required
• The 1st of the 3000MW HVDC terminal being established at
Alipurduar along with 6000MW NER-NR/WR interconnector) – Would take care of evacuation from projects like Punatsangchu-I(1200MW),
Punatsangchu-II(1020 MW) & Mangdechu(720MW)
– To be commissioned in 2014-15.
14
India - Nepal : Present Interconnection
Power Scenario in Nepal
Installed Capacity : 617MW (Hydro – 91%)
Demand : 600 MW
Peak Deficit : 100 MW (250MW likely by 2014-15)
Interconnection : 22 links at 132/33/11 kV
About 50 MW of power being exchanged in radial mode which has recently gone up to about 100MW (increase in power exchange with Bihar) after some short term strengthening work carried out by POWERGRID.
Supply of 70MU/annum from Tanakpur HEP(India) to Nepal (as per the Mahakali Agreement)
Net export to Nepal (about 10% of demand of Nepal met from India)
17
India – Nepal : On–Going Trans. System • Transmission Line
– 400kV inter-connection (initially op. at 220kV level) between Muzaffarpur(India) and Dhalkebar(Nepal) : 125 km
• Indian Portion :
– Line length : 86.43km; Estimated cost : Rs. 131.75 Crs. (USD 29.28million)
– To be implemented by Cross Border Power Transmission Company Pvt. Ltd. (CPTC)
[Proposed equity shares of JV partners : IL&FS(38%), POWERGRID (26%), SJVNL
(26%) and NEA (10% )]
• Nepalese Portion :
– Line length : 39km ; Estimated cost : Rs. 127.54 Crs. (USD 28.34million)
– To be implemented by Power Transmission Company Nepal Ltd. (PTCN)
[Proposed equity shares of JV partners : NEA(50%), POWERGRID (26%), Financial
Institutions of Nepal (14%), IL&FS (10%)] 19
India – Nepal : On–Going Trans. System
• Status of Implementation
20
Milestone Status
Transmission License Granted for both portions
PSA (Power Sale Agreement) Signed on 12th December,2011 between NEA and PTC for 150 MW
ITSA between JVs & NEA Signed on 13-Dec-2011 between CPTC & NEA and PTC & NEA
Shareholder Agreement (SHA) SHAs for both the JVs signed on 9-Jul- 2012.
India – Nepal : Future • Hydro Potential : about 83,000 MW • Future Hydro Projects :
–Karnali - 10,800 MW (Upper Karnali - 900MW)
–Tamakoshi III - 880 MW
–U. Marsyangdi – 2 - 600 MW
–Pancheshwar HEP - 5,600 MW
–Sapta Koshi - 3,300 MW
–Arun HEP - 1,100 MW
–West Seti HEP - 750 MW
–Lower Marsyangdih - 300 MW
• High capacity transmission interconnection between Nepal and India need
to planned for evacuation and transfer of power from future hydel projects
in Nepal.
21
22
India - Nepal : Future Plan
East-West High capacity transmission Corridor need to be planned in Nepal
This corridor may be connected with hydro projects in Nepal and Load centres in
India
Development may be carried out through SPV
• Installed Capacity : 2684 MW
(Hydro – 45%, Thermal-55% )
• Maximum Demand : 2200MW
• Demand Growth : 8 %
• Hydro potential : 2000 MW
out of which 1200 MW already
harnessed
EMBILIPITIYA
MATARA
GALLE
DENIYAYA
SAMANALAWEWA
BALANGODA
MATUGAMA
PANADURA
RANTEMBE
RANDENIGALA
VICTORIA
INGINIYAGALA
AMPARA
BOWATENNA
UKUWELA
KIRIBATHKUMBURA
KOTMALE
WIMALASURENDRA
BADULLA
N'ELIYA
MADAMPE
BOLAWATTA
THULHIRIYA
KURUNEGALA
VEYANGODA
BIYAGAMA
ORUWALA
KOLONNAWA
KOTUGODA
RATMALANA PANNIPITIYA
TRINCOMALEE
ANURADHAPURA
PUTTALAM HABARANA
RATMALANA
PANNIPITIYA
ORUWALA
BIYAGAMA
FORT
KOLLUPITIYA
KELANITISSA
KOLONNAWA
S'KANDA
132kV : Underground Cable
132kV Line
220kV Line
POLPITIYA
NEWLAXAPANA
CANYON
KELANIYA
KOTUGODA
SAPUGASKANDA
KELANITISSA
KHD
KOSGAMA
VAVUNIA
POLONNARUWA
HAMBANTOTA
LAKDANAWI
LAXAPANA
SITHAWAKA
220/132 kV Sub Station
132kV GS
Hydro Power Station
Thermal Power Station
NEW ANURADHAPURA
Sri Lanka Transmission System
BARGE PS
CHUNNAKAM
KILINOCHCHI
VALACHCHANAI
132kV Line (not in operation)
24
Sri Lanka : Present Power Scenario
India – Sri Lanka interconnection
25
MoU Signed between GoI & GoSL for feasibility study to be carried out by
POWERGRID and CEB
Executing Agency : POWERGRID (India) & CEB (Sri Lanka)
Proposed Interconnection :
India(Madurai) – Sri Lanka(Anuradhapura) HVDC bipole line : 360 km
(Stage-I : 500MW; Stage-II : 1000MW)
Indian Territory : (Scope :POWERGRID) : 130 km
Sea Route : (Scope : POWERGRID) : 120km
Sri Lankan Territory : (Scope : CEB) : 110 km
Tentative cost : Rs. 5000 Cr. (USD 867 Million)
Rs. 3300 Cr. (USD 645 Million) (Stage-I)
Rs. 1700 Cr. (USD 222 Million) (Stage-II)
Feasibility Study Report : Technical Portion Completed, Other issues
like the economic and financial analysis, funding and recovery of the
investment, legal and Institutional aspects including modalities for
implementation etc. under discussion.
130 Kms
120 Kms
110 Kms
Proposed Route for Interconnection
Madurai-New
Panaikulam
New Anuradhapura
Taliamannar
Thirukketiswaram *
48 Kms
Madurai
India – Sri Lanka Interconnection
Madurai
Panaikulam
New Anuradhapura
Thirukketiswaram
Proposed Route for India – Sri Lanka Interconnection
India – Pakistan interconnection
29
• There is a proposal for trade of electricity between Pakistan and India which
is at preliminary stage.
• In pursuance of decision taken in the fifth round of talks on commercial and
economic co-operation between India and Pakistan held at Secretary level
on 27-28 April, 2011 in Islamabad, first meeting of the group of Experts was
held on October 20, 2011 in New Delhi.
• The second meeting of the group of Experts was held at Islamabad on
August 02, 2012 to further discuss and deliberate on the possibility of a
cross-border interconnection between India and Pakistan to facilitate
exchange and trade in electricity.
• It was deliberated that Pakistan may procure upto 500 MW power from
Indian power market on commercial terms.
• The next meeting of the Expert group will be held in India in October, 2012.
Before that, an interim technical level meeting shall be held in India in
September, 2012.
• Institutional Arrangement
• Techno-economical analysis and Preparation of Feasibility Study Report
• Commercial Arrangements
• Financial Arrangements
• Operation of the Interconnection
• Operation of the Grid
• Legal Issues
Road Map for Cross-Border Interconnection
• Trading of Electricity between the participating countries –
Prevalent restrictions
• Agreements/ MOUs between the participating countries need to be signed at various levels (Government, Planning, Operation and Regulatory) between the participating countries in order to study, finalise, implement, operate and maintain the interconnection between the electrical grids of the countries.
• Identification of Nodal Agencies • For Planning and preparation of feasibility study report
• For Operation and Maintenance of the transmission system
• For operation of the grid
• For Sale/Purchase of Power
Institutional Arrangement
• Identification of Joint Coordination Groups
– Technical Coordination Group : responsible for planning of the
interconnection link based on techno-economical study, preparation of feasibility report incorporating designing of equipments, bill of quantities, cost estimates etc.
– Operation & Maintenance Coordination Group : O&M of the interconnection system between the participating countries incl. maintenance of associated communication facilities, coordination of protective devices, maintenance coordination etc.
– Grid Operation and Protection Coordination Group: members from the System Operators of the participating countries to look into various aspects associated with the operation of the cross border links, including any
protection coordination issues.
– Commercial Coordination Group: members from the System Operators of participating countries to look into all commercial aspects related to the operation of the cross border links.
Institutional Arrangement
– Planning of Grid Interconnection
• Formation of Joint Study Team
• Purpose of Interconnection -generation linked scheme (like between Bhutan and India) or strengthening scheme (between India and Bangladesh)
• Identification of Power Exchange - quantum of power to be exchanged between the participating countries and its source need to be identified. The quantum of power and its duration in a day, month and year and thus the total energy to be transferred in either direction also need to identified.
• Type of Interconnection - Joint study need to be carried out to identify the mode of interconnection viz. Radial, Synchronous, Asynchronous based on the power system of the interconnecting countries.
Techno-economic Analysis and Preparation of
Feasibility Study Report
– Design Studies and Equipment parameter finalization
• includes tower configurations, foundation design, conductor and insulator finalization etc.
– Survey, Soil Investigation, Environment Impact Assessment and land identification
– Preparation of Bill of Quantity and Cost estimates
– Economic & Financial Analysis
Techno-economic Analysis and Preparation of
Feasibility Study Report
• Long term secured agreements
• Pricing of power and tariff mechanism
• Security Mechanism including payment (through Government Guarantee from respective governments)
• Terms for Indemnification for disruption of Transmission service
Commercial Arrangements
• Funding arrangement like multilateral, private etc
• Recovery of Investment
• In either case following aspects are to be considered:
• Sale/ Purchase of Power on a sustained/ long term basis
• Security of Payment / Signing of Covenant
• Immunity to Political Changes and changes in Law
Financial Arrangements
• For reliable and secure operation of the combined grid, operational and maintenance procedures of the interconnected system between the participating countries would have to be similar, so as to minimize the outages and breakdown of transmission system and ensure satisfactory performance of costly components of the transmission systems for their entire life, thus avoiding premature replacements.
Operation of the Interconnection
• Operating Code
– Operating Philosophy : Both countries would agree to abide by a common grid code for reliable, secure and stable operation of the cross border interconnection.
– System Security Aspects : The system security aspects incorporating isolation/tripping of interconnection link from the grid of respective countries under various conditions and its restoration under supervision by respective System Operator, in co-ordination with System Operator of the other country etc would be specified.
– Protection Coordination : Provision of protections and relay settings shall be coordinated periodically by the System Operators of the respective countries.
Operation of the Grid
• Scheduling and Despatch Procedure •
• Congestion Management
• Metering, Accounting, Deviations from Schedule and Settlement
• Real Time SCADA Data, Communication Facilities, Cyber Security
• Data Recording Instruments such as Data Acquisition System/Disturbance Recorder/Event Logging Facilities/Fault Locator (including time synchronization equipment) shall be provided and shall always be kept in working condition at both ends of the cross border interconnection for recording of dynamic performance of the system.
Operation of the Grid
• Firming up of procedures for dispute settlement and Arbitration
– Agreements on liability for power line failure or damage, and other issues of legal liability concerning grid operation
– Institutional arrangements for governing grid interconnection
– Agreements on operation of power line
– Agreements on power line security
Applicability of Laws of Respective countries/ International Laws should be specified
Legal Issues
• Engineering Consultancy Services (end to end) – Turnkey Execution of transmission projects
– Transmission System Master Plan
– Feasibility Reports/Detailed Project Reports
– Pre-Award Engineering activities
– Post-Award Engineering activities
– Project Management & Construction Supervision
– Quality assurance and Inspection
– Testing and Commissioning
– Telecom
– Establishment of National Load Dispatch Centers
– Tariff determination and regulatory requirements
– Capacity Building
Areas of co-operation