Cantrell - Dillsboro Dam Removal

Embed Size (px)

Citation preview

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    1/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Dillsboro DamDillsboro Dam

    Removed from theRemoved from the

    Tuckasegee RiverTuckasegee River

    Mark A. CantrellMark A. Cantrell

    US Department of InteriorUS Department of Interior

    Fish and W ildlife ServiceFish and Wildlife Service

    Ashev ille Field OfficeAshev ille Field Office

    160 Zil l icoa Street160 Zil l icoa Street

    Ashevil le, North Carolina 28801Ashevil le, North Carolina 28801

    828/258828/258 --39393939

    [email protected][email protected]

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    2/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    FERC relicensing of Duke EnergysNantahala Area Projects

    Most expired at about the same timeMost expired at about the same time

    Dillsboro was the smallest 225 kWDillsboro was the smallest 225 kW

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    3/24

    U. S. Fish and W ildlife Serv ice

    Dillsboro Hydroelectric Project

    The Dillsboro Project was located in Jackson County,

    North Carolina, on the Tuckasegee River nearthe town of Dillsboro.

    Constructed in 1913 by C.J. Harris to provideelectricity for Blue Ridge Locust Pin Factory.1. The Project consists of a concrete masonry dam

    approximately 12-feet high and 310-feet long,2. a powerhouse containing two generating units with a

    total installed capacity of 0.225 MW, related electricpower production components and facilities, and

    3. a reservoir approximately 0.9 miles in length. TheProject had limited storage.

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    4/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Tuckasegee CooperativeStakeholders Agreement

    20052005 -- Many agreements for riverMany agreements for riverenhancementenhancement

    Proposed removal of Dillsboro DamProposed removal of Dillsboro Dam FERC approved and Ordered theFERC approved and Ordered thesurrender and demolitionsurrender and demolition

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    5/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Potential benefitsPotential benefits

    Restore 1 mile of habitatRestore 1 mile of habitat

    Reconnect 2 subpopulationsReconnect 2 subpopulations

    MusselsMussels

    Fish hostsFish hosts

    Increase genetic interchangeIncrease genetic interchange

    Larger, more stable populationLarger, more stable population

    Restore river continuum of allRestore river continuum of allspeciesspecies

    Improved river recreationImproved river recreation

    Why remove the dam?

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    6/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Fish Assemblages

    Total number of fish species collected at sampling stations on the Tuckasegee River, upstream ofBarkers Creek, during May 2001, July 2001, September 2001, and March 2002. Stations T-1, T-2, andT-3 were downstream of the Dillsboro Dam. Station DR was a sample site in the Dillsboro

    Reservoir. Stations T-4 and T-5 were on the Tuckasegee River, upstream of the Dillsboro Dam andReservoir (Duke Power 2002).

    Sample Site T-1 T-2 T-3 DR T-4 T-5

    Total Fish Species 32 28 38 11 24 24

    Introduced Species 4 3 5 3 5 3

    Total Native SpeciesTotal Native Species 2828 2727 3333 88 1919 2121

    Assemblage Resistance Ratio 0.88 0.9 0.87 0.73 0.79 0.88

    Assemblage Resilience Ratio 0.76 0.73 0.89 0.22 0.51 0.57

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    7/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Formal Removal Plans Developed

    1. Planning Mussel surveys Mussel Relocation

    Bat boxes

    2. Dredging in 2009

    3. Demolition in January 20104. Post-removal monitoring

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    8/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Paperwork

    FERC Order USFWS Biological Opinion

    Clean Water Act Section NC DWQ 401 Certificate

    U.S. Army Corps of Engineers 404

    permits

    NC DLQ Mining Permit

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    9/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Endangered Species

    USFWS issued a Biological OpinionProject demolition has the potential to result insedimentation in the Tuckasegee River. Tominimize the potential for sedimentation, Duke

    Power has developed specific erosion-controlmeasures, including a detailed constructionsequence, phased drawdown, turbiditymonitoring, and bank stabilization for theProject that are designed to protectenvironmentally sensitive areas. Sedimentinputs from demolition activities should be of

    relatively short duration.

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    10/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Mussel Relocation

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    11/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Monitoring Plans

    During demolition Turbidity

    Mussel

    Long-term Physical response

    Vegetation

    Fish

    Mussel

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    12/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Dillsboro Dam timeline2005 Settlement Agreement

    2007 FERC Order, then 7 court cases, appeals, etc

    2010

    Jan 11 15 Asbestos and hazardous materials removal from the powerhouse

    January 18-21 Powerhouse removal of superstructure

    January 25-29 Shoreline stabilization for sewer line and fiber optic cable January 25-29 Construction of access road for removal of dam debris

    Feb 3 Notching of Dillsboro Dam to begin dewatering

    February 16 Completion of dam demolition

    March 3 Completion of powerhouse removal May 11 Recycled spillway stone to remaining south dam abutment

    July 15, 2010 Demolition & Restoration Complete!

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    13/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Dillsboro Dam Gone!Currently

    Revegetation continues all native species River access area completed in February

    Fish, mussel, bat surveys and monitoring continue

    for 3 years

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    14/24

    U. S. Fish and W ildlife Serv ice

    MonitoringVisual/photographic

    Sediment

    before/after

    upstream/downstream

    Biological

    Fish Macroinvertebrates

    Mussels U.S. Fish & Wildlife Service

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    15/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Dillsboro Dam Gone!January 2010 July 2010

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    16/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Jan 2010

    Dec 2010

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    17/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Tuckasegee River Again!

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    18/24

    U. S. Fish and W ildlife Serv ice

    Bat removal Little brown bats readily accepted boxes

    U.S. Fish & Wildlife Service

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    19/24

    U. S. Fish and W ildlife Serv ice

    Example sediment particle sizeD80 from silt to sand/gravel

    U.S. Fish & Wildlife Service

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0.010.1110100

    PercentFiner(%)

    Grain Size (mm)

    Particle Size Distribution T-14

    Pre-Removal Max Pre-Removal Min 2nd Quarter 2010

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    20/24

    U. S. Fish and W ildlife Serv ice

    Of note

    Appalachian elktoes have alreadyrecolonized the former pond area

    Native fishes have recolonized

    River recreation has been booming

    Angling

    Boating

    Significant public acceptance

    U.S. Fish & Wildlife Service

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    21/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Sicklefin Redhorse

    Great expectations for extension of this Candidate to

    an additional 9.5 miles to base of Cullowhee Dam(n)

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    22/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service

    Summary FERC hydroelectric project surrender

    Detailed planning

    Swift removal

    Biological response has been swift

    Many detailed reports available Duke Energy Carolinas LLC and their

    contractors did a great job

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    23/24

    U. S. Fish and W ildlife Serv ice

    QUESTIONS?

    MANY DETAILED REPORTSAVAILABLE

    Contact: [email protected]

    U.S. Fish & Wildlife Service

  • 8/6/2019 Cantrell - Dillsboro Dam Removal

    24/24

    U. S. Fish and W ildlife Serv ice

    U.S. Fish & Wildlife Service