February 10, 2010
Construction Milestone Schedule
February 10, 2010
• Preparation for Structural Steel
• Close Arlington Street
Capture Site
Set up Crane for Structural Steel
• Open Arlington Street
Project Milestones – Surgery Vertical Expansion:Target Start – 2/22/10
Target Start – 4/12/10
Target Start - 12/31/10
February 10, 2010
Site Phasing Diagram – Surgery Vertical Expansion
Construction Zone for Crane, Material Deliveries, etc.
Ambulance Access to be Maintained at All Times
February 10, 2010
• Wound Care Renovations• CEP Equipment Removal• Construct Temporary Waldemere Garage Entrance• After Garage Entrance is complete construct Interim
Main Entrance• Old Central Energy Plant Structure Demolition• Construct Temporary ECC Canopy & Drop off• Open Temporary Canopy & Drop Off / Close
Hawthorne in Front of ECC / Construct New ECC Drop Off
• Install New & Relocate Site Utilities / Construct New Loop Road
• Open New Loop Road / New Drop Offs / Close Hawthorne / Capture Site for Bed Tower Demolition / Construct Stair & Elevator Tower & Bridge Connector
• New Bed Tower Construction
Project Milestones – New Bed Tower:Target Completion - 7/1/10
Target Start - 3/8/10
Target Start - 3/29/10
Target Start - 5/17/10
Target Start - 3/29/10
Target Start - 5/3/10
Target - 6/7/10
Target Start - 5/3/10
Target Start - 9/20/10
Target Start - 12/28/10
February 10, 2010
Site Phasing Diagram - 1
Demolish Old CEP
Interim Moves for Surgery Support & Pathology
Remove Equipment from CEP
Create Temporary Garage Entry/Exit onto Waldemere St
February 10, 2010
Site Phasing Diagram - 2
Create Temporary ECC Entry Drop-Off
Temporary ECC Entry Canopy
February 10, 2010
Site Phasing Diagram - 3
Open Temporary ECC Entry Canopy & Drop-off
Build Temp Main Entrance Canopy, Drop-off & Vestibule
Close Hawthorne Street
Construct New Loop Road and Associated Utilities
Temporary Route to ECC
Construct New ECC Vestibule, Canopy & Drop-off
Open New Entry/Exit at Waldemere Garage
February 10, 2010
Site Phasing Diagram - 4
Open Temporary Main Entry Canopy & Drop-off
Demolish Existing Main Entry Canopy
Open ECC Vestibule, Canopy & Drop-off
Open New Loop Road
Demolish Northeast Tower
Demolish Portion of Critical Care Tower for New Bridge
February 10, 2010
Site Phasing Diagram - 5
Construct New Bed Tower and Bridge