GREENING MAGGIE’S FLOWER SHOP PRESENTED BY THE NINJA PROS. May 22, 2010 Tom Fisher, Jacqueline Clarke, Karen Lynn, Adhiti Naik, Maggie Leung and AJin Lim. Table of Contents. P roject Charter…………………………………………………………………. S cope………………………………………………………………………………… - PowerPoint PPT Presentation
Citation preview
GREENING MAGGIE’S FLOWER SHOPPRESENTED BY THE NINJA PROS
May 22, 2010Tom Fisher, Jacqueline Clarke, Karen Lynn, Adhiti Naik, Maggie Leung and AJin Lim
NINJA PROs 2
Table of Contents
Project Charter………………………………………………………………….Scope…………………………………………………………………………………Project Lifecycle…………………………………………………………………Stakeholder Analysis………………………………………………………….Communication Plan………………………………………………………….Responsibility Assignment Matrix………………………………………WBS…………………………………………………………………………………. Schedule, Cost Baseline and Investment S Curve………………. Risk Management Plan………………………………………………………Quality Management Plan…………………………………………………Closure & “Green” Opening……………………………………………….Addendum………………………………………………………………………..
NINJA PROs 3
Project Charter Project Greening of Maggie’s FlowersCreated By Ninja Pros Date May 20, 2010
Convert existing flower shop to be certified by Bay Area Green Program Standards
Roles & Responsibilities
Sponsor: Kimi Project Manager: Tom Fisher Project Stakeholders: Maggie Leung/Owner, Customers, Bay Area Green Business & Other green businesses , Employees, Suppliers, Project teamCore team members : Maggie Leung, Jacqueline Clarke, Tom Fisher, A Jin Lim, Adhiti Niak, Karen Lynn
Description Background info: Maggie purchased an existing flower shop. She wants to convert her business into a green certified business. Project team will act as consultants to create an energy efficiency plan. Have her certified as a Bay Area Green Business in the Bay Area Green Business Program.Project Objectives:Create complete project plan for Maggie within 5 weeks.In Scope:Get flower shop Bay Area Green Business certified.Follow Bay Area Green ProgramOut of scope:No structural changesChanges that are outside of the Bay Area Green Program qualificationsBudget:$100,000
NINJA PROs 4
Project Charter
Information
Deliverable: Project Plan that fits the certification requirements. Structure project so it provides: basic = required needs; additional items on check list = nice to have & if budget permits.Assumptions: Increase customer base, save energy costs and consumption.
Constraints: Determine if phase in construction; or business will cease during renovations. Run out of budget. Weather and unforeseen construction/equipment problems.Dependencies with other projects: NoneRisks or Opportunities: Does not get approved by Bay Area Green Program. Unforeseen infrastructure problems/old building have to replace equipment and parts. Sponsor pulls out of project or lose funding.
Milestones:
NINJA PROs
Supporting information
May have to change store hours; phases or sections at a time; or limit number of employees. Acceptance criteria: get certification, meets checklist of Bay Area Green Program and Maggie accepts project plan.Some requirements include: Window/insulationCompostingUpgrade lightingRefrigerationRecyclingLow-flow water consumptionGuidelines for energy efficiencyFurther recommendations: Solar power, vendors, etc. can be suggested.
5
Project Charter
NINJA PROs 6
Scope
Business Need• Long-term costs savings through increasing operations efficiencies and
reduction in energy use• Use Green Certification as a way to advertise and market business
Project DescriptionMaggie purchased an existing flower shop. She wants to convert her business
into a green certified business. Project team will act as consultants to create an energy efficiency plan. Create a proposal for Maggie’s Flowers to be certified as a Bay Area Green Business according to standards set by Bay Area Green Business Program.
Vision StatementTo prepare Maggie to convert her existing flower shop to be green certified by Bay Area Green Business Program standards.
NINJA PROs 7
Scope
Is Is NotCreate a clear plan to meet Bay Area Green
Program requirements No structural changes.
Give cost estimates for each phase of project. Team will not act as a general contractor.
Recommend programs that provide monetary or other incentives to cover cost of each upgrade.
No permits required.
Provide vendor selection criteria. Suggest Bay Area Green Program preferred vendors that give rebates.
Not do anything that is outside of the requirements set by the Bay Area Green Program.
Define requirements that shop owner can do on his/her own or require contractor or maintenance person.
Cannot guarantee that the proposal ensures green certification.
Provide oversight, if Addendum suggested contract signed.
Provide oversight, if Addendum suggested contract not signed.
NINJA PROs 8
Scope
Objective Criteria for Evaluation
Determine the specific requirements that the shop owner wants based on the Bay Area Green Program checklist.
Meets checklist and owner approval (Yes, No)
Meet shop owner’s budget and needs. Project comes in on budget ($90K +/- 10%) Verify that meet minimum number of requirements in
each category (Jacqueline)
Proposal signed off by shop owner. Yes/No
Proposal signed off by sponsor Yes/No
Create a budget for entire project that meets shop owner’s needs.
Meets requirements on checklist. Vendor/program cost estimates
Create a project timeline to find contractors, accept bids, equipment, coordination, and completion of project.
Weeks needed to complete 30 days to contact and get people from program to visit
shop 90 days for work to be completed 30 days for unforeseen risks 30 days for certification
Identify preferred vendors, materials, and programs Meets vendor acceptance criteria and Green Checklist
Create plan phases to accommodate keeping the business open during project.
Matches timeline milestones and hours of operation for Maggie’s Flowers.
NINJA PROs 9
Scope
Assumptions •Maggie owns a flower shop that is not green certified.•Greening will give a marketing advantage.•Delivering a plan as a consultant, not a contractor.•No major construction, permits or structures altered.•Stakeholders agree to each stage of the project.•Progress in a linear process starting at the execution project plan.•Shop owner does not terminate the process during the project.
Constraints •Determine if phase in construction; or business will cease during renovations. •Pre-determined budget of $100,000 for making any modifications to shop and greening•5 weeks to finish plan. •No unforeseen equipment problems, material or schedule delays.
NINJA PROs 10
Assumptions
Maggie’s Flower Shop Before Upgrades
•Single stand-alone structure• No landscaping outside• Five-car parking lot in the front for deliveries• Store Space is 20ft x 20ft• Twelve 2ft x 4ft fluorescent fixtures lighting the main part of the flower shop• Bathroom contains incandescent light • “Exit” signs are incandescent• Single bathroom with one toilet/sink with no window - fan for ventilation• Single work sink in the back for working with flowers•Three refrigerators, one display refrigerator in the front area with and one walk in refrigerator in the back •Both refrigerators have power outlets feeding them with enough wattage to be legal. The third refrigerator is a small one for food. It is old i.e. not energy star certified
NINJA PROs 11
Project Life Cycle
NINJA PROs 12
Project Life Cycle
Iterative Planning
NINJA PROs 13
Stakeholder Analysis
Name Needs or Expectations
Sponsor and Owner
• Project within budget, time and specifications• Successful certification of the project and opening• Long-term cost savings• More Customers and increased foot traffic
Shop Employees• Functional facility• Knowledgeable operating a green business
Subcontractors• Specifications are on target with the Bay Area Green Business
requirements• Ensure within budget and timeline
Team Members/Consultants
• Project on time and budget• Successful certification of the project and opening• Deliverables on time• Both Sponsor and Owner satisfied with end results
Bay Area Green Businesses• Word of mouth marketing from one green business to another• Increase green business awareness
Customers • Flowers at a good price and quality
NINJA PROs 14
Communication Plan
Sponsor Owner Project Manager
Team Members
Sub-Contractors Frequency Communication
MethodDelivery Format
Project Charter R R, I O O - Once Phone, email,
meetingMS Word
Doc
Project Scope S S O O - Once Phone, email,
meetingMS Word
Doc
WBS S I, S O, I, R O, I, R Once Phone, email, meeting MS PP Chart
Project Schedule S I, S I, R I, R I Ongoing Phone, email,
meeting MS Project
Cost Baseline S I, S I, R I, R - Milestone
BasedPhone, email,
meeting MS Excel
Risk Mgt. Plan R R I, R O - Ongoing Phone, email,
meeting MS Word
Status Report R R I, R O I Weekly Email, meeting MS Excel
QA Report R R O O S Milestone Based Email, meeting MS Word
O=Owner I=Input R=Reviewer S=Sign-off
NINJA PROs 15
Sponsor Owner Project Manager
Team Members
Sub-Contractors Frequency Communication
MethodDelivery Format
Procurement Plan R R O I - Milestone
Based Email, Meeting MS Word Doc
Responsibility Matrix - - O R R Ongoing Email, Meeting MS Excel
Communication Plan - - O I - Once Phone, Email,
Meeting MS Word
Lessons Learned I I O R I Ongoing Phone, Email,
Meeting MS Word
Project Plan Review S S O, R I - Once Phone, Email,
Meeting MS Word
Final Sign-off S S O I - Once Meeting MS Word
Communication Plancontinue
O=Owner I=Input R=Reviewer S=Sign-off
NINJA PROs 16
Responsibility Assignment Matrix
NINJA PROs
17
Greening of Maggie’s Flowers
Team Charter
Project Charter
WBS
Vendor Selection Criteria
Project Schedule
Cost Analysis
Responsibility Assignment Matrix
Program Enrollment
“Do It Yourself”/ Handy-Person
Monitoring & Controlling
Vendors
Schedule Green Business Audits
Sign-off by Auditors per Checklist Areas
Risk Analysis
Communications Plan
Sponsor Approval
Stakeholder Analysis
Work Breakdown Structure
Project Life-cycle
Quality Management
Planning Execution Approval & Closure
Closure
Initiation
NINJA PROs 18
Schedule & Cost Baseline
NINJA PROs 19
Investment by Phase (S curve)
NINJA PROs 20
Risk Management Plan
Facility Fails Certification M H H
• Requirements are not met
• PM not up-to-date on checklist req(s)
• PM overlooks req(s)
• Auditor ‘s inspection
• Auditor, Owner notices oversight(s)
• Identify issue and fix it• PM performs QA checks the req(s) • PM confirms req(s) in plan & up-to-date at the end of each phase
• Alternative checklist req(s) to substitute
• Consultants advise during construction
• Include in T&Cs for addtl. consultancy
Funding Cut L H M
• Sponsor backs out• Work interrupts
business too much• Owner changes
business priorities
• Neighborhood Complains
• Sales decrease• Owner gives notification
• Check-in with Sponsor on project status regularly
• Notify neighbors, ensure that work matches Owner’s hours
• Check-in/update priorities based on Owner ‘s needs
• Loan, program rebates or grants
• Work non-peak business hours
• Include in contract 30-day notification required
Stakeholders Not in Agreement
L H M
• Disagreement over budget/scope /time• Disagreement over changes during project planning/ control/ implementation• Stakeholders performs outside of scope
• Owner not available to advise on decisions when issues arises
• Owner not available upon contact
• Owner provides advanced notice about absence and communicate during absence
• Delegate PM as a back-up • Develop a communication
plan• Owner provides schedule
• Have Owner delegate alternate decision maker
• Designate on-site back-up for Owner
• Inquire Owner’s schedule
Pro
bab
ilit
y
Imp
act
Pri
ori
ty Probable Root Cause Triggers Mitigating Strategy ContingencyRisk
NINJA PROs 21
Risk Management Plancontinue
Owner N/A for Decisions L H M
• Personal emergency• Communication plan
not clearly defined at start of project
• PM does not check availability of Owner
• Not there to make decisions
• Issues arises• Cannot contact Owner
• Owner gives as much advanced notice as possible
• Have PM as a back-up contact and make communication plan
• Include this as a task in Communication Plan
• Owner delegates alternate decision maker
• Designate on-site back-up Owner
• Ask at daily meeting
Subcos Does Not Deliver M H H
• Unclear specifications for product/service
• Material out of stock, back-ordered
• Increase in cost between planning and execution
• Missed negotiation during discussions
• Material N/A upon delivery
• $ increase
• Review contract and fix• Plan out procurement and delivery dates
• Get bids with enough lead time
• Make a contingency into contract
• Search for an alternate Vendors
Equipment Malfunctions or Material Delays
M M M
• Not enough lead time/availability of material
• Equipment is not in working order
• Material /equipment does not match
• Materials not onsite
• Equipment breaks down
•Material does not fit existing
order
• Include lead time/check for material status
• Check-in regularly with contractors on status
• Know which substitute materials are available
• Have alternate vendors on back-up
• Negotiate in contract counter - any fee reductions applied due to time delays
• Get materials from alternate vendor
Pro
bab
ilit
y
Imp
act
Pri
ori
ty Probable Root Cause Triggers Mitigating Strategy ContingencyRisk
NINJA PROs 22
Quality Management Plan
Project Benefits Cost Savings Increased Edge over the Competition Improved Employee Morale &
Workplace Health Recognition before the County Board
of Supervisors
Responsibility Matrix Project Manager Project Reviewer Green Business Program Auditors
Quality Standards During Planning Phase, each Project
Task is reviewed before finalizing Project Presentation is delivered in a
clear and concise manner Oversight is performed during Project
Execution Phase
NINJA PROs 23
Closure & “Green” Opening
Closure• Project deliverables approved• Passed audits• Project approved• Lessons Learned
• Good: • Bad: • Improve:
Recommendations • Ninja Pros Project Management• Walk-in Energy Efficient Refrigerators
Opening a Green Certified Maggie’s Flowers
NINJA PROs 24
Addendum
NINJA PROs 25
Team CharterTeam: Ninja Pros Team Duration: 5 weeks (24 Apr to 22 May 2010)Member Name Role Phone E-mailMaggie Leung Sponsor 917-723-4795 [email protected] Fisher Project Manager 415-516-5492 [email protected] Clarke Stakeholder 925-525-5442 [email protected] Jin Lim Stakeholder 510-926-5190 [email protected] Adhiti Naik Stakeholder 408-431-4810 [email protected] Lynn Stakeholder 408-887-4574 [email protected]/goals (include project assignment goals, group process goals, and quality level goals):
Convert existing flower shop to Bay Area Green Program standards and green certified.
Values (include strengths/weaknesses/areas members want to develop):
Hold each person equally accountable.
Be honest up front.
Open communication and group consensus.
Team work.
Administrative guidelines
Make all 5 classes.
Communicate documents via email or the Wiki
Meet after class to check-in 15 minutes after class to prep for the week; Skype on Tues. @ 8-9pm. Be on time.
Everyone presents at one point. Common team workbook.
PROJECT TEAM CHARTER TEMPLATE
NINJA PROs 26
Team Chartercontinue
Ground Rules (include meeting schedule, attendance expectations, agenda, communication methods):
If sick, notify the rest of the group.
Communicate if have to shift workload.
Decision guidelines:
Group consensus: use voting Agree, Live with it, Disagree. Have a 2/3 consensus.
Devil’s advocate = Project Manager. Ask “Why” to get to root cause.
Meeting guidelines
Check in to determine if additional time is needed
Have project manager act as time keeper during meeting.
Project Manager tracks/updates project timeline.
Modify documents: figure the Wiki tools and use to track revisions. Email as needed.
NINJA PROs 27
Bay Area Green Business Program Detailed Checklist
General Standards - Establish a "green team" of employees by implementing check listo Adopt a written environmentally friendly purchasing policyo Provide 3-on-going incentives or training to employees to participate in the Green Business programo Write and post green work tasks to perform according to Green Business checklist in offi ceo Train all employees on taskso Discuss tasks at staff meetings
General Standards - Inform customers and other businesses about being, and them becoming, greeno Inform customers about environmental effortso Use one of the listed signs, communications or ways on checklisto Assist at least one other business in learning about becoming a Green Buisnesso Identify business to partner with
Solid Waste Reduction - Replace disposable utensuls, bottles, etc and write guidelines for thiso Eliminate individual bottles of water for employees and guests o Eliminate use of polystyrene in beverages and food service ware o Provide disposable paper bags instead of plastic; use plastic only when necessary o In the lunch/breakroom, replace disposables with permanent items (ie, mugs, dishes, utensils, coffee filters, etc)
NINJA PROs 28
Bay Area Green Business Program Detailed Checklist
Continued
Solid Waste Reduction - Set up additional reduction and re-use of paper and plastic productso Provide disposable paper bags instead of plastic; use plastic only when necessary o Enable duplex printing for copier and printero Discourage the printing of emails and documents o Subscribe to journals online rather than receiving hard copies
oPrint on the back side of previously printed on paper. Either use of second tray of the printer for such paper, or keep it stacked next to the printer for hand loading.
o Reuse offi ce paper as scratch paper o Have toner cartridges refilled instead of purchasing a new one. o Reuse paper or plastic packaging materials
Solid Waste Reduction - Set up recycling for paper, plastic, metals, and green wasteo Recycle cardboard o Provide recycling containers at convenient and appropriate locations (ie, kitchen, next to garbage containers, desks) o Recycle glass bottles and jars o Recycle metal cans, containers, aluminium foil o Recycle plastic bottles and containers o Recycle Landscape trimmings (green waste)
Solid Waste Reduction - Buy items with recycled contento Buy copier/printer paper with at least 30% post-consumer waste o Buy paper towels with 35% post-consumer waste o Buy business cards with recycled content o Buy boxes or bags for retail use or shipping with recycled content
NINJA PROs 29
Go Green!