Upload
nitin-p-kumare
View
221
Download
0
Embed Size (px)
Citation preview
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 1/11
H5/202 E
The second 265 t RH DEGASSERThe second 265 t RH DEGASSER
at the Beeckerwerth steelplant
of ThyssenKrupp Stahl AGMETALLURGICAL PLANTS and ROLLING MILLS
SECONDARY METALLURGY
Reprint of a paper presented at
ASSOCIATION TECHNIQUE de la SIDERURGIE FRANCAISE,
Paris, December 11-12, 2002.
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 2/11
The second 265 t RH-TOP degasser at ThyssenKrupp Stahl AG in operation.
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 3/11
3
Introduction
Today, secondary metallurgical units represent the versatile
usable connection between melting and casting plants insteelworks.
Future process-improving measures must consequently be
developed and applied to ensure that the secondary metall-
urgical facilities achieve their full extent of availability and
thus a high level of productivity at low operative costs. Fur-
thermore, metallurgical processes must be optimised to
ensure that steel grades to be produced fulfil the continual-
ly increasing demands with regard to steel purity, precision
of chemical composition and low contents of undesired
tramp elements. RH and RH TOP vacuum units use the prin-
ciple of the vacuum circulation process, and are in particu-
lar applied in flat-product steelplants to enable mass pro-duction of deep drawing grades with very low contents of
Carbon under economically favourable conditions. Additio-
nally, RH and RH TOP
vacuum units are also used
for the removal of hydro-
gen, for deoxidation and for
the precise adjustment of
the chemical analysis and
temperature of the molten
steel.
TKS Beeckerwerth works
Oxygensteelworks 2 of ThyssenKrupp Stahl AG was ori-
ginally built and put into operation in 1962. The annualproduction of crude steel at Beeckerwerth steelworks was
5.3 million tons in 2001.
The steelworks is equipped with the following production
facilities: two pig iron desulphurisation units, three conver-
ters and two continuous casters, unit 2 of which was revam-
ped to a vertical bending continuous slab casting machine in
the summer of 2001.
The second 265 t RH degasserat the Beeckerwerth steelplant of
ThyssenKrupp Stahl AG
Heinz Liebig, ThyssenKrupp Stahl AG, Duisburg, Germany
Rainer Dittrich and Dieter Tembergen, SMS Mevac GmbH, Essen, Germany
Fig. 1. 2nd 265 t RH-TOP atThyssenKrupp Stahl AG
Heinz Liebig, ThyssenKrupp Stahl AG, Duisburg,Rainer Dittrich, Managing Director, SMS Mevac GmbH, Essen,Dieter Tembergen, SMS Mevac GmbH, Essen
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 4/11
4
A majority of the product is supplied to the automotive indu-
stry. The continuously rising market demand for ultra-low
carbon steel grades could not be met by the existing RH faci-
lity no. 1. Additionally production of vacuum treated steel
was lost after the closure of the Dortmund works, however
the increase in market demand meant that production had to
be increased. The logical consequence was the construction
of a second RH facility.
Project aim
In recent years, the client demands for ultra-low carboncontent lead to a situation that the portion of steel melts that
have to undergo vacuum treatment increased by more than
47%.
The main task of the new RH unit is to decarburise liquid
steel down to carbon contents of less than 0.0020 % for hot
rolled strip. These steels have the highest mechanical requi-
rements, specifically excellent ductile properties. Further-
more, the vacuum facility is required to produce steels with
a hydrogen content below 1.5 ppm for the production of
heavy plates and high carbon steels. The annual production
was planned to be around 2.4 million tonnes of molten steel.Cycle times of less than 26 minutes at the continuous casting
plants had to be taken into account for planning the vacuum
unit, figure 2.
Basic concept and main components
The plant is designed as a RH fast-vessel-exchange plant,
figure 2. Each RH vessel is placed on a transfer car which
moves between the treatment position and the respective
stand-by position.
In the treatment position the vessel is connected to the gas
cooler, the suction line and the vacuum pump system by
means of a hydraulically operated compensator. The alloy
agent supply and the vacuum-tight lance passage are also
connected to the vessel via pneumatically operated com-
pensators. The TOP lance is lowered into the vessel in thetreatment position. In this position there is also a wire-fee-
ding machine and a lance system for taking samples and
temperature / E.M.F. measurements by means of a sleeve
manipulator.
Below the vessel two ladle transfer cars (one for getting
the ladle from the BOF and one for taking it to the conti-
nuous caster) travel on a rail track. These cars move the
steel casting ladle into the treatment position below the RH
vessel. The ladle is lifted out of the ladle transfer car by
means of a mechanical lifting device until the snorkels are
immersed into the steel. When the treatment is completedthe ladle is lowered into the ladle transfer car, serving the
continuous caster.
At each of the stand-by positions, burner lances are instal-
led which can be retracted into the stand-by vessel and
serve to heat-up or keep the vessel hot. Snorkel maintenan-
ce can also be performed simultaneously in these positi-
ons.
A vessel lining and heating system serves to dry and bring
the new vessels to temperature.
A separate repair station is provided for the wrecking, reli-
ning and heating of used vessels.
Fig. 2. Main components.
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 5/11
5
Ladle lifting system
Lifting and lowering of the ladle is done by a mechanical lif-
ting system driven by a cable winch, figure 3. The laminated
hook can be swivelled hydraulically for picking up the lad-
les. The lifting system is equipped with two parallel opera-
ting drives. If one drive fails, the lifting system can be ope-
rated solely by the second drive.
The stroke is determined by means of two angle encoders.
The measured values of both angle encoders are constantly
compared to each other. If the values differ by more than 20
mm an alarm is triggered and the lifting and lowering pro-
cess is stopped.
After the ladle transfer car is positioned in the treatment
position, the automatic ladle pick-up and lifting process is
started while the beams are lowered by means of the lifting
gear with the laminated hooks in the retracted position.
The laminated hooks are then swivelled into the release posi-
tion and located below the ladle trunnions. The hook positi-
ons are monitored by limit switches on both the hydraulic
cylinder and the beam. The operator can check the hook posi-
tion by means of two cameras. Once the laminated hooks have
been driven into the bails of the ladle suspension system, the
lifting process is initiated. The correct load pick-up is moni-tored by a device which checks the load difference – separa-
te load recognition on the left and right crane hooks – and the
correct lifting position of the load. In automatic mode the lif-
ting and lowering sequence is started by the operator.
Vacuum system
The vacuum pump has four stages and consists of two low-
vacuum steam ejectors (stages 1 and 2), condenser 1, two
parallel operating medium-vacuum steam ejectors (stages 3a
and 3b), condenser 2 and parallel operating water ring
pumps as the atmospheric stage. The sucked off waste gas –
a high content of CO has to be taken into account during
decarburisation – is conveyed by the water ring pumps
through the flare stack to the CO postcombustion unit (flare
stack burner) where the remaining CO is burned and the
waste gas is expelled into the atmosphere, figure 4a.
In order to save steam at lower cooling water temperatures
and to control the vacuum in the range of 300 to approx. 60
mbar, steam ejectors 3a and 3b are equipped with injector
needles. For vacuum control in the range of 60 to approx. 6mbar, steam ejector 2 is also fitted with an injector needle.
The position of the needle in the tuyere is adjusted by means
of a pneumatic actuator, figure 4b.
The injector needles are driven into a certain position depen-
ding on the pressure in condenser 2. This control process is
superimposed by a vacuum control system which is active
for ejectors 3a and 3b until ejector 2 is switched on. After
ejector 2 is switched on, the vacuum control system takes
effect on the injector needle of ejector 2. The generated pres-
sure measurement is the reference input for this. When ejec-
tor 1 is switched on, the injector needle of ejector 2 is driven
to a defined position. Thus this arrangement ensures the best
preconditions to adapt the pressure reduction in the vessel to
suit the relevant metallurgical requirements, whilst also
taking into account the cost savings derived from reduced
steam consumption, figure 5.
Fig. 3. Mechanical ladle lifting system Fig. 4a and b. Vacuum system and ejector needle.
1 mbar 10 mbar 100 mbar
S t e a m [ t / h
]
20
15
10
5
0
25°C30°C34°C
Fig. 5. Suction capacity of vacuum system and steam consumptionaspects.
a b
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 6/11
6
Vacuum alloying system
The purpose of the vacuum lock system is to allow the addi-
tion of alloys to the melt during the vacuum treatment. The
alloying materials are added via a side chute connected to
the vacuum vessel.
The vacuum alloying system consists of four vacuum weig-hing bins with a vacuum vibratory feeder arranged below
them and a vacuum shut-off gate as well as two vacuum
locks each with two feeding hoppers and each with a con-
veying chute arranged below.
The vacuum weighing bins (VB) are generally filled with
the following alloying materials:
- VB 01 Scrap 2 m3
- VB 02 Aluminium 2 m3
- VB 03 Titanium 2 m3
- VB 04 Iron silicon 10 m3
The two vacuum locks each consist of the following com-ponents:
- Large feeding lock 3 m3
- Small feeding lock 0.5 m3
- Vacuum lock 3 m3
- Vibratory feeder 3 m3
The alloys are added to the vessel via a vibratory feeder.
The conveying capacity of each can be adjusted via the
motor speed and is switched on according to the material. To
optimise the time, the pure filling process of the feeding
locks can be started by the operator irrespective of the addi-
tion into the vessel.
Located above these components is a rotary chute whichdistributes the material coming from the day bin system to
the corresponding vacuum weighing bin or feeding hoppers
of the respective vacuum locks. The pipe, which can be rota-
ted 360°, has eight discharge positions for filling and a fur-
ther ninth emergency discharge position in case of wrong
weights or for emptying components, e.g. conveying belts of
the superposed day bin system.
The very short cycle periods of the continuous casting plants
at the Beeckerwerth works dictated the design of this com-
plex vacuum alloy system, figure 6. The system design allo-
ws the realisation of very short alloy addition periods. Bypre-filling the feeding hoppers the treatment process can be
optimally controlled and the alloying materials can be added
at very short intervals.
Fig. 6. Vacuum alloying system
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 7/11
7
Vessel exchange system
In order to ensure a high level of availability of the plant,
two vacuum vessels are provided.
Each vessel is installed on its own transfer car so that it can
be driven either into the stand-by position or the treatment
position, figure 7.
In the stand-by positions the suction pipe is closed by a
pneumatically operated refractory lined pan. Through the
TOP lance port the stand-by burner can be driven into the
vessel to a distance of 5,000 mm to the vessel bottom. The
purpose of the burner lance is to heat up vessels in the stand-
by position or to keep them hot.
In the treatment position the suction pipe, alloy pipe and
TOP lance are connected via hydraulically or pneumatically
operated compensators.
Change-over of the vessel from the treatment position to therelevant stand-by position is executed by the operator in
automatic mode. The entire process can be performed during
a sequence between two heats within a period of 4 minutes.
Fig. 7. Vessel exchange plant views
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 8/11
8
Process operation of ULC steel grades
Amongst the requirements of the RH process, the foremost
is production of steel grades with very low carbon levels –
interstitial free (IF) steel stabilised by titanium or niobium
and high silicon electric steel, down to 20 ppm carbon.
To conduct the decarburisation process in the RH plant in the
best possible way, the starting conditions regarding the rela-tion of carbon and oxygen content have to be controlled.
The required carbon and oxygen content can be adjusted
easily and consistently by TBM (Thyssen Blowing Metall-
urgy, BOF converter) steelmaking. During tapping Ferro-
manganese is added. After tapping and homogenising by
means of lance argon stirring, the heat is transferred to the
RH unit, where the treatment is immediately started on arri-
val of the ladle. It is common practice to treat up to 7 heats
consecutively, which are sequence cast in one of the two
slab casting machines.
A typical RH treatment pattern is shown in table 1. Shortly
after starting of the RH vacuum treatment the steel begins torecirculate and the decarburisation reaction starts.
The decarburisation reaction is controlled by means of a
computerised pump down program and automatically plot-
ting of set points for lift gas flow rate. The heats have to be
decarburised within 15 minutes and the total RH treatment
time should not exceed 26 minutes.
Use of RH degasser No. 2
The secondary metallurgical treatment in the RH facilityNo.2 is used at ThyssenKrupp Stahl Beeckerwerth for the
following purpose:
■ Production of ULC-IF steel grades with minimum carbon
content
■ Production of heavy plates with minimum hydrogen con-
tent
■ Increase of alloying output of oxygen-affine elements
(e.g. Ti)
■ Production of high carbon steel grades
■ Homogenisation and control of small ranges of analysis,
even in case of large alloying quantities (e.g. for the pro-
duction of electrical grades)
The product mix of RH degasser No. 2 during the first 12
months after hot commissioning is shown in figure 8.
Fig. 8. Product mix of RH No. 2
Alloyed+Micro-alloyed steels
6.3 %High strength steels
5.3 %
Low-carbon steel6.9 %
IF-steel(Ti+Nb-alloyed)
8.9 %
High carbonsteels2.9 %
Cold rolledsteels3.0 % Tin plate
14.3 %
IF-steels (Ti-alloyed)52.5 %
Table 1: Total RH cycle time
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 9/11
9
200000
160000
120000
80000
40000
0
P r o d u c t i o n [ t ]
Nov2001
Jan2002
Mar2002
May2002
July2002
Sept2002
Nov2002
69,144
87,086
104,564
118,174
139,129
150,513
140,617
174,187
183,542
181,440171,518
191,553
205,682
planned
achieved
C a r b o n [ p p m ]
50
40
30
20
10
0
Decarburisation time [min]
0 5 10 15 20 25 30
k c - v a l u e [ 1 / m i n ]
0.30
0.25
0.20
0.15
0.10
0.05
0.00
RH facility No. 2 (new)
RH facility No. 1
Carbon content (C1 + C2)/2 [ppm]0 10 20 30 40 50
C2 = C1 e-kt
Production of RH degasser No. 2
The 13 months following hot commissioning have shown
a continuous increase of vacuum capacity of RH degasserNo. 2. Within the first month of being put into operation, the
plant achieved a production rate of over 60,000 tonnes.
After eight months, more than 150,000 tonnes of crude steel
per month were vacuum treated in the RH degasser No. 2.
After 13 months a monthly production of over 200,000 ton-
nes was achieved, figure 9.
First metallurgical results
Decarburisation
After a decarburisation time of 15 minutes, Carbon is redu-
ced to approximately 15 ppm, figure 10. An increase of the
decarburisation time to 22 minutes permits the attainment of
Carbon contents between 10 to 12 ppm.
The relationship between the decarburisation constant (kC-
value) and the Carbon concentration obtained in the RHfacility No. 2 (new plant) compared to the RH facility No.1
is shown in figure 11.
The following points are important in case of the excellent
decarburisation results in the RH facility No.2 (new plant):
■ Degree of vacuum necessary in order to achieve internal
decarburisation by the high suction capacity
■ Carbon concentration of the steel in the vessel is made
close to that of the steel in the ladle by the high circulati-
on rate (snorkel and vessel geometry, lift gas flow rate)
■ Effective reaction area of the surface reaction by use of
strong agitation
■ Minimised Carbon contamination from the skull on the
vessel’s inner wall by improved operation of TOP lance
Fig. 9. Production of RH No. 2 duringthe first 12 months.
Fig. 10. Decarburisation results RH No.2 Fig. 11. Relationship between carbon content and decarburisationrate constant (kc)
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 10/11
10
Hydrogen removal
The course of Hydrogen contents during RH vacuum treat-
ment for the production of high Carbon steel grades is
shown in figure 12. The Hydrogen content was determined
with the HYDRIS-system.
Removal of Hydrogen at the RH is quite effective due to its
high diffusion coefficient. The achievable hydrogen contentduring vacuum treatment depends on the low-vacuum tre-
atment time. Initial hydrogen contents have a negligible
influence on the achievable final content. A low-vacuum tre-
atment of 15 minutes makes it possible to achieve hydrogen
contents of less than 1.4 ppm.
Summary
In November 2001, ThyssenKrupp Stahl AG started up at
Beeckerwerth work, a new RH vacuum degassing equip-
ment. The RH degasser, supplied by SMS Mevac GmbH,
has been designed to produce 2.4 Mt/year. The main task of
this unit is to decarburise liquid steel down to 20 ppm for the
production of Ultra Low Carbon steel grades. Other capabi-lities include the reduction of Hydrogen, the decrease in
aluminium consumption and production of Ultra Low Carb-
on-high Si electric grades.
This plant has been designed to meet the targets in short tre-
atment times matching those of sequence casting at the exi-
sting casting machines. After a description of the main RH
degasser components and characteristics, the metallurgical
results achieved after the first 13 months operation were pre-
sented. Within this time the metallurgical targets with res-
pect to decarburisation and hydrogen removal have been
successfully achieved.
H y d r o g e n [ p p m
]
Vacuum treatment time (p < 2 mbar) [min]
3
2
1
000 5 10 15 20 25
Fig. 12. Hydrogen removal.
7/30/2019 H5_202_TKS_engl
http://slidepdf.com/reader/full/h5202tksengl 11/11
SMS Mevac GmbH
Secondary Metallurgy
Bamler Strasse 3 a · 45141 Essen · Germany
Phone: +49 201 6323-0Telefax: +49 201 6323-200
E-Mail: [email protected]
Internet: www.sms-mevac.com 1 0 0 0 / 0 3 / 2 0 0 3 k y
· P r i n t e d i n G e r m a n y