3_danh Gia Lua Chon Du An

  • Upload
    184load

  • View
    224

  • Download
    0

Embed Size (px)

Citation preview

  • 8/11/2019 3_danh Gia Lua Chon Du An

    1/45

    Le Thi Kim Oanh Project Selection 1

    Lecture 2PROJECT EVALUATIONAND SELECTION

    Le Thi Kim Oanh, Ph.D.Vice Rector

    Danang University of Technology

  • 8/11/2019 3_danh Gia Lua Chon Du An

    2/45

    Le Thi Kim Oanh Project Selection 2

    1. Criteria for project selection models

    Project evaluation and selection is the process of evaluating individual projects orgroups of projects, and then choosing to implement some set of them so thatthe objectives of the parent organization will be achieved.

    When a firm chooses a project selection model, the following criteria are most

    important:

    Realisim

    Capability

    Flexibility Ease of use

    Cost

  • 8/11/2019 3_danh Gia Lua Chon Du An

    3/45

    Le Thi Kim Oanh Project Selection 3

    2. Numeric Models2.1. Profitprofitability Models

    2.2. Scoring Models

  • 8/11/2019 3_danh Gia Lua Chon Du An

    4/45

    Le Thi Kim Oanh Project Selection 4

  • 8/11/2019 3_danh Gia Lua Chon Du An

    5/45

    Le Thi Kim Oanh Project Selection 5

  • 8/11/2019 3_danh Gia Lua Chon Du An

    6/45

    Le Thi Kim Oanh Project Selection 6

  • 8/11/2019 3_danh Gia Lua Chon Du An

    7/45

    Le Thi Kim Oanh Project Selection 7

  • 8/11/2019 3_danh Gia Lua Chon Du An

    8/45

  • 8/11/2019 3_danh Gia Lua Chon Du An

    9/45

    Le Thi Kim Oanh Project Selection 9

  • 8/11/2019 3_danh Gia Lua Chon Du An

    10/45

    Le Thi Kim Oanh Project Selection 10

  • 8/11/2019 3_danh Gia Lua Chon Du An

    11/45

    Le Thi Kim Oanh Project Selection 11

  • 8/11/2019 3_danh Gia Lua Chon Du An

    12/45

    Le Thi Kim Oanh Project Selection 12

  • 8/11/2019 3_danh Gia Lua Chon Du An

    13/45

    Le Thi Kim Oanh Project Selection 13

  • 8/11/2019 3_danh Gia Lua Chon Du An

    14/45

    Le Thi Kim Oanh Project Selection 14

  • 8/11/2019 3_danh Gia Lua Chon Du An

    15/45

    Le Thi Kim Oanh Project Selection 15

  • 8/11/2019 3_danh Gia Lua Chon Du An

    16/45

    Le Thi Kim Oanh Project Selection 16

    2.1. Profit profitability Models

    Payback Period

    Average Rate of Return

    Net Present Value (discounted cashflow)

    Internal Rate of Return

  • 8/11/2019 3_danh Gia Lua Chon Du An

    17/45

    Le Thi Kim Oanh Project Selection 17

    2.1. Profit profitability Models

    Average Rate of Return

    R = average annual profit/investmentcosts

  • 8/11/2019 3_danh Gia Lua Chon Du An

    18/45

    Le Thi Kim Oanh Project Selection 18

  • 8/11/2019 3_danh Gia Lua Chon Du An

    19/45

    Le Thi Kim Oanh Project Selection 19

  • 8/11/2019 3_danh Gia Lua Chon Du An

    20/45

    Le Thi Kim Oanh Project Selection 20

  • 8/11/2019 3_danh Gia Lua Chon Du An

    21/45

    Le Thi Kim Oanh Project Selection 21

  • 8/11/2019 3_danh Gia Lua Chon Du An

    22/45

    Le Thi Kim Oanh Project Selection 22

  • 8/11/2019 3_danh Gia Lua Chon Du An

    23/45

    Le Thi Kim Oanh Project Selection 23

  • 8/11/2019 3_danh Gia Lua Chon Du An

    24/45

    Le Thi Kim Oanh Project Selection 24

  • 8/11/2019 3_danh Gia Lua Chon Du An

    25/45

    Le Thi Kim Oanh Project Selection 25

  • 8/11/2019 3_danh Gia Lua Chon Du An

    26/45

    Le Thi Kim Oanh Project Selection 26

    omments on the profit profitability models

    Advantages:

    1. The undiscounted models are simple to use andunderstand

    2. All use readily available accounting data todetermine the cash flows

    3. Model output is interns familiar to business decisionmaker

    4. With a few exceptions, model output is on anabsolute profit profitability scale and allowsabsolute go/no-go decisions

    5. Some profit models account for project risk

  • 8/11/2019 3_danh Gia Lua Chon Du An

    27/45

    Le Thi Kim Oanh Project Selection 27

    omments on the profit profitability models

    Disadvantages:1. These models ignore all nonmonetary factor except risk.2. Models that do not include discounting ignore the timing of cash

    flows and the time value of money.3. Model that reduce cash flows to their present value are strongly

    bias toward the short run.4. Payback-type models ignore cash flows beyond the payback

    period.5. All are sensitive to errors in the input data for the early years.6.

    All discounting models are nonlinear, and the effects of changes(or errors) in the variable or parameters are generally not obviousto most decision makers.

    7. All these models depend for input on a determination of cashflows, but it is not clear exactly how the concept of cash flow isproperly defined for the purpose of evaluating projects.

  • 8/11/2019 3_danh Gia Lua Chon Du An

    28/45

    Le Thi Kim Oanh Project Selection 28

    2.1. Scoring Models

    In an attempt to overcome some of thedisadvantages of profitability models,

    particularly their focus on a single criterion, anumber of evaluation and selection modelsthat use multiple criteria to evaluate a projecthave been developed.

    Such models vary widely in their complexityand information requirements.

  • 8/11/2019 3_danh Gia Lua Chon Du An

    29/45

    Le Thi Kim Oanh Project Selection 29

    2.1. Scoring Models

    Unweighted 0-1 factor model

    Unweighted Factor Scoring model

    Weighted Factor Scoring model

  • 8/11/2019 3_danh Gia Lua Chon Du An

    30/45

    Le Thi Kim Oanh Project Selection 30

    2.1.1. Unweighted 0 - 1 Factor Model

    A set of relevant factors is selected List these factors in a preprinted form, and

    one or more raters score the project on each

    factor depending on whether or not itqualified for that individual criterion

    The raters are chosen by seniormanagement, for most part from the rolls of

    senior management The criteria for choice are understanding of

    organizational goals and a good knowledge ofthe firms potential project porfolio.

  • 8/11/2019 3_danh Gia Lua Chon Du An

    31/45

    Le Thi Kim Oanh Project Selection 31

    Example of the project rating sheet evaluation

    form) for Unweighted 0 - 1 Factor Model

    Project:

    Rater: Date:

    Factors Qualifies Does not qualify

    No increase in energy requirement

    Potential Market size, in dollars

    Potential market share, percent

    No new facility required

    No new technical expertise required

    No decrease in quality of final product

    Ability to manage project with current personnel

    No requirement for reorganization

    Impact on workforce safety

    Impact on environment standardsProfitability: Rate of return >15% after tax

    Estimated annual profit more than $100,000

    Time to break-even less than 3 years

    Need for external consultants

    Consistency with current lines of business

    Impact on company image: With costumers

    With our industry

    X

    X

    X

    X

    X

    X

    X

    XX

    X

    X

    X

    X

    X

    X

    X

    X

    Totals 12 5

  • 8/11/2019 3_danh Gia Lua Chon Du An

    32/45

    Le Thi Kim Oanh Project Selection 32

    2.1.1. Unweighted 0 - 1 Factor Model

    Advantage of the model:

    It uses several criteria in the decision process

    Disadvantages:

    It assumes all criteria are of equal importance

    It allows no gradation of the degree to whicha specific project meets the various criteria

  • 8/11/2019 3_danh Gia Lua Chon Du An

    33/45

    Le Thi Kim Oanh Project Selection 33

    2.1.2. Unweighted Factor Scoring model

    Constructing a simple linear measure of the degreeto which the project being evaluated meets each ofthe listed criteria

    Using a point scale (3,5,7 or ten-point scales arecommon)Example: 5 very good, 4 good, 3 fair, 2 poor, 1 very poor

    The column of score is summed and the project witha total score exceeding some critical value are

    selected (or the highest scoring project is selecteduntil the estimated costs of the selected projectequaled the resource limit

  • 8/11/2019 3_danh Gia Lua Chon Du An

    34/45

    Le Thi Kim Oanh Project Selection 34

    Example of constructing scale for rating

    For the criterion estimated annualprofit in dollars

    For the criterion the quality of finalproduct

    This scale is scoring cells that represent opinionrather than subjective fact, as was the case inthe profit scale

    Score Performance Level

    5

    4

    3

    2

    1

    Above $1,100,000

    $750,000 to $1,100,000

    $500,000 to $750,000

    $200,000 to $500,000

    Less than $200,000

    Score Performance Level

    5

    4

    3

    2

    1

    Significant and visibly improved

    Significant improved but not visible

    Not significantly changed

    Significantly lowered but not visible

    Significantly and visibly lowered

  • 8/11/2019 3_danh Gia Lua Chon Du An

    35/45

    Le Thi Kim Oanh Project Selection 35

    2.1.3. Weighted Factor Scoring model

    When numeric weights reflecting the relative importanceof each individual factor are added, we have a weightedfactor scoring model

    In general, it takes the formSi = sijwj j = 1,2,3,.,n

    whereSi= the total score of the ith projectSij= the score of the ith project on the jth criterion

    Wj= the weight of the jth criterion When numeric weights have been generated, it is helpful

    to scale the weights so that0 wj 1 j = 1,2,3, ,nw

    j= 1

  • 8/11/2019 3_danh Gia Lua Chon Du An

    36/45

    Le Thi Kim Oanh Project Selection 36

    omments on the scoring models

    Advantages:

    1. These modes allow multiple criteria to be

    used for evaluation and decision. They caninclude profit-profitability models and bothtangible and intangible criteria

    2. They are structurally simple and therefore

    easy to understand and use3. They are a direct reflection of managerial

    policy

  • 8/11/2019 3_danh Gia Lua Chon Du An

    37/45

    Le Thi Kim Oanh Project Selection 37

    omments on the scoring models

    Advantages:4. They are easily altered to accommodate

    changes in the environment or managerial

    policy5. Weighted scoring models allow for the fact

    that some criteria are more important thanothers

    6. These models allow easy sensitivityanalysis. The trade-offs between the criteriaare readily observable

  • 8/11/2019 3_danh Gia Lua Chon Du An

    38/45

    Le Thi Kim Oanh Project Selection 38

    omments on the scoring models

    Disadvantages:1. The output of a scoring model is strictly a relative

    measure. Project scores do not represent the valueor utility associate with a project and thus do notindicate whether or not the project should besupported.

    2. In general, scoring models are linear in form and theelements of such model assumed to be independent

    3. The ease of use of these models is conducive to theinclusion of a large number criteria, most of whichhave such small weights that they have little impacton the total project score

  • 8/11/2019 3_danh Gia Lua Chon Du An

    39/45

    Le Thi Kim Oanh Project Selection 39

    omments on the scoring models

    Disadvantages:

    4. Unweighted scoring models assume all

    criteria are of equal importance, which isalmost certainly contrary to fact

    5. To the extent that profit-profitability isincluded as an element in the scoring model,

    this element has the advantages anddisadvantages noted earlier for profitabilitymodel themselves.

  • 8/11/2019 3_danh Gia Lua Chon Du An

    40/45

    Le Thi Kim Oanh Project Selection 40

    1. Criteria for project selection models

    Two critical important facts:1. Models do not make decisions, people do. The

    manager, not the model, bears responsibility for

    the decision. The manager may delegate the taskof making decision to a model , but theresponsibility cannot be abdicated

    2. All models, however sophisticated, are only partialrepresentations of the reality they are meant toreflect. Reality is far too complex for us to capturemore than a small fraction of it in any model.Therefore no model can yield an optimal decisionexcept within its own, possibly inadequate,framework.

  • 8/11/2019 3_danh Gia Lua Chon Du An

    41/45

    Le Thi Kim Oanh Project Selection 41

    3. The information base forevaluation and selection

    Accounting Data

    Measurements

    Subjective versus objective

    Quantitative versus qualitative

    Reliable versus unreliable

    Valid versus invalid

    Technological Shock

  • 8/11/2019 3_danh Gia Lua Chon Du An

    42/45

    Le Thi Kim Oanh Project Selection 42

    4. Project Proposals

    The set of documents submitted forevaluation called the project proposal,

    whether it is brief (a page or two) orextensive, and regardless of theformality with which it is presented

  • 8/11/2019 3_danh Gia Lua Chon Du An

    43/45

    Le Thi Kim Oanh Project Selection 43

    4. Project Proposals

    Several issues face firms preparingproposals, particularly firms in the

    construction and consulting industries.- Which projects should be bid on?

    - How much should be spent onpreparing proposals for bids?

    - How should the bid prices be set?What is biding strategy

  • 8/11/2019 3_danh Gia Lua Chon Du An

    44/45

    Le Thi Kim Oanh Project Selection 44

    4. Project Proposals

    There are four distinct issues should be covered byany proposal:

    1. The nature of the technical problem and how it is

    to be approached2. The plan for implementing project once it has been

    accepted

    3. The plan for logistic support and administration

    4. A description of the group to proposing to do thework, plus its past experience in similar work.

  • 8/11/2019 3_danh Gia Lua Chon Du An

    45/45

    Project team assignment

    The project team is to develop a projectproposal, as described in the chapter. Pro

    forma documents should be included, as wellas a justification of the project

    The team should endeavor to apply as manyof the project selection-justification methods

    as may be applicable. Both profitability andscoring models should certainly be included.