Upload
daniel-bell
View
216
Download
0
Embed Size (px)
Citation preview
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 11
מבנה חברהמבנה חברה
((לא מחייבלא מחייב))
מנכ"ל
חשב מזכירה
רכש אבטחת איכות ייצור הנדסה פיתוח
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 22
מרכיב חשוב במערכת אבטחת האיכות.
מסמך כתוב המתאר כל שינוי של:חומר גלםמוצרמכשור/ ציוד תהליכיסביבת/מיקום התהליךשיטות ייצור/ בחינה ובדיקהכל הגורמים המשפיעים על התהליך
Master Validation Plan
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 33
All changes should be formally requested, documented and accepted by representatives of:
Production, QC/QA, R&D, Engineering and Regulatory Affairs as appropriate.
The likely impact (risk assessment) of the change on the product should be evaluated and the need for, and the extent of
Re-validation
Master Validation Plan
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 44
Master Validation Plan
כל השינויים המתבקשים חייבים להיות מתועדים במסמך
ומאושרים על ידי נציגי מחלקות: אבטחת איכות מחקר ופיתוח
הנדסה תקינה
נדרש תהליך של ניהול סיכונים לבדיקת תוצאות IQ,OQ, PQ(השינוי המבוקש וכן רה ולידציה (
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 55
Master Validation PlanMaster Validation PlanChange Control בקרת שינוי
Change control is an important element in any Quality Assurance system. Written procedures should be in place to describe the actions to be taken if a change is proposed to a:
product, component, process equipment, process environment (or site), method of production or testing or any other change that may affect
product quality or support system operation.
.
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 66
Master Validation PlanChange Control (Cont’)
The change control system should ensure that all notified or requested changes are satisfactorily investigated, documented and authorised.
Products made by processes subjected to changes should not be released for sale without full awareness and consideration of the change by responsible staff, including (where appropriate) the Qualified Person.
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 77
Master Validation PlanChange Control (cont’)
Changes that are likely to require Re-validation are as follows:
(a) Changes of raw materials (physical properties: e.g. density, viscosity, particle size distribution may affect the process or product
(b) Change of starting material manufacturer(c) Changes of packaging material (e.g. substituting plastic for glass)(d) Changes in the process (e.g. mixing times, drying temperatures)(e) Changes in the equipment (e.g. addition of automatic detection systems) Changes of equipment which involve the replacement of equipment on a 'like for like' basis would not normally require a Revalidation(f) Production area and support system changes (e.g. rearrangement of areas, new water treatment method)(g) Transfer of processes to another site(h) Unexpected changes (e.g. those observed during self-inspection or
during routine analysis of process trend data)
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 88
Master Validation Plan
PERSONNEL – כח אדם
Operators who perform routinely should be trained in the application of validated procedures.
Training records should be available for all training carried out.
It is difficult to validate a manual, i.e. an inherently variable procedure.Therefore, operators carrying out manual procedures should besupervised at regular intervals.
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 99
Responsibility for Qualification and Validationאחריות וסמכויות
The responsibility for qualification and validation in pharmaceutical manufacture is a multi-disciplinary one. GMP Guide states that the heads of the Production and Quality Control departments generally have the responsibility:
"To ensure that the appropriate validations are done.“
While the GMP Guide specifically identifies the responsibility of the Production and Quality Control departments, in practice, other departments, like Engineering and R& D as well as
Contractors are usually involved in the program.
Master Validation Plan
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 1010
Master Validation PlanResponsibility for Qualification and Validation
It is the responsibility of the pharmaceutical company to define the respective responsibilities of its personnel and of external contractors in the qualification and validation programme.
This should form part of the Validation Master Plan.
However, the Quality Assurance function of a company should normally have a critical role in overseeing the whole qualification and validation process.
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 1111
Master Validation Plan
Costs and Time - עלויות ולוחות זמנים
Costs: - מחיר Validation studies are costly as they require time of highly specialized personnel and expensive technology
Multidisciplinary approach: - גישה רב תחומיתA specific characteristic of validation work is that it requires the collaboration of experts of various
disciplines such as: pharmacists, technologists, metrologists, chemical analysts, microbiologists, engineers, experts on Q.A. validation etc.
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 1212
Costs and Time (cont’)
Time constraints: - לוחות זמנים
Generally validation work is submitted to rigorous time schedules.
These studies are always the last stage prior to taking
new processes, facilities into routine operation.
The above factors require a well organized and structured approach that should be adequately described in a Validation Master Plan.
Master Validation Plan
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 1313
Revalidation
• Modifications• Problems• Equipment Relocation / Replaced• Critical Equipment or process are routinely revalidated
at appropriate intervals to demonstrate that the process
in control
Master Validation Plan
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 1414
Operational Qualification
Summary Master Validation Plan
Design Specification/Qualification(DQ)
Installation Qualification
INTERRELATIONSHIP BETWEEN QUALIFICATION AND VALIDATION
Process Validation /Performance Qualification
Change Control
Lect. No 4-2009-10Lect. No 4-2009-10 Eli Solomon M.Sc,Eli Solomon M.Sc, 1515
httphttp://www.whowww.who
http://www.fda.gov/cdrh/qsr/04valid.html
Guideline on General Principles of Process Guideline on General Principles of Process Validation, May 1987, FDA, CDRH/CDER Validation, May 1987, FDA, CDRH/CDER
ReferencesReferences