Chapter4[1] Reji

Embed Size (px)

Citation preview

  • 8/6/2019 Chapter4[1] Reji

    1/55

    Chapter 4 Planning The Project Chapter 4 Planning The Project

  • 8/6/2019 Chapter4[1] Reji

    2/55

    MOST MANAGERS DO NOT LIKE PLANNING DUE TO THE FOLLOWING: MOST MANAGERS DO NOT LIKE PLANNING DUE TO THE FOLLOWING:

    * It takes time.* You have to think.* It involves paper work.* You are bound to systematic procedures.* You are committed to achieve a specific

    result within a specified time period.

    * It takes time.* You have to think.* It involves paper work.* You are bound to systematic procedures.* You are committed to achieve a specific

    result within a specified time period.

  • 8/6/2019 Chapter4[1] Reji

    3/55

    Effective Planning Effective Planning An effective plan will be:-

    * Explicit - stated in detail, leaving nothingmerely implied .

    * Intelligible - it must be understood and becomprehensible .

    * Flexible - capable of accepting change.* Controllable - capable of being monitored for

    control purposes.

  • 8/6/2019 Chapter4[1] Reji

    4/55

    Planning Fundamentals Planning Fundamentalsy If the task is well understood prior to

    being performed, much of the work can bepreplanned.

    y If the task is not understood, then duringthe actual task execution more knowledgeis gained that, in turn, leads to changes inresource allocations, schedules, andpriorities.

    y The more uncertain the task, the greater the amount of information that must beprocessed in order to ensure effectiveperformance.

    y If the task is well understood prior tobeing performed, much of the work can bepreplanned.

    y If the task is not understood, then duringthe actual task execution more knowledgeis gained that, in turn, leads to changes inresource allocations, schedules, andpriorities.

    y The more uncertain the task, the greater the amount of information that must beprocessed in order to ensure effectiveperformance.

  • 8/6/2019 Chapter4[1] Reji

    5/55

    Reasons for Planning Reasons for Planning y To eliminate or reduce uncertaintyy To improve efficiency of the operationy To obtain a better understanding of theobjectivesy To provide a basis for monitoring and

    controlling work

    y To eliminate or reduce uncertaintyy To improve efficiency of the operation

    y To obtain a better understanding of theobjectivesy To provide a basis for monitoring and

    controlling work

  • 8/6/2019 Chapter4[1] Reji

    6/55

    DEFINITION OF A PROJECT LIFE CYCLE DEFINITION OF A PROJECT LIFE CYCLE

    ResourcesUtilized

    RESOURCES

    TIME

    CONCEPTUALPHASE

    DETAILEDPLANNING PHASE

    FEASIBILITY ANDPRELIMINARY

    PLANNING PHASE

    IMPLEMENTATIONPHASE

    CONVERSIONOR TERMINATION

    PHASE

    PMO

    PMO *

  • 8/6/2019 Chapter4[1] Reji

    7/55

    The Line Manager(s) ?The Project Manager ?

    Both Parties ?

    *

    Who plans the project?* Who executes the project?* Who is responsible for monitoring work and

    controlling work?* Who is responsible for providing feedback regarding

    the planning and execution phases of a project?

    *

    Who plans the project?* Who executes the project?* Who is responsible for monitoring work and

    controlling work?* Who is responsible for providing feedback regarding

    the planning and execution phases of a project?

    PLANNING QUESTIONS OFTEN ASKED

  • 8/6/2019 Chapter4[1] Reji

    8/55

    Project Managers

    Responsibility

    Project Managers

    Responsibilityy Project Manager will define:

    Goals and objectives

    Major milestones Requirements Ground rules and assumptions Time, cost, and performance constraints Operating procedures Administrative policy Reporting requirements

    y Project Manager will define: Goals and objectives

    Major milestones Requirements Ground rules and assumptions Time, cost, and performance constraints Operating procedures Administrative policy Reporting requirements

  • 8/6/2019 Chapter4[1] Reji

    9/55

    Line Managers

    Responsibility

    Line Managers

    Responsibilityy Line manager will define:

    Detailed task descriptions to implement

    objectives, requirements, and milestones Detailed schedules and manpower allocationsto support budget and schedule

    Identification of areas of risk, uncertainty, and

    conflict

    y Line manager will define: Detailed task descriptions to implement

    objectives, requirements, and milestones Detailed schedules and manpower allocationsto support budget and schedule

    Identification of areas of risk, uncertainty, and

    conflict

  • 8/6/2019 Chapter4[1] Reji

    10/55

    Senior Managements

    Responsibility

    Senior Managements

    Responsibilityy Senior management (project sponsor)

    will:

    Act as the negotiator for disagreementsbetween project and line management

    Provide clarification of critical issues Provide communication link with customers

    senior management

    y Senior management (project sponsor)will:

    Act as the negotiator for disagreementsbetween project and line management Provide clarification of critical issues Provide communication link with customers

    senior management

  • 8/6/2019 Chapter4[1] Reji

    11/55

    THE SEVEN PHASES OF A PROJECT

    1. Wild enthusiasm2. Disillusionment3. Chaos4. Search for the guilty

    5. Punishment of the innocent6. Promotion of the non-participants7. Define the requirements

    THE SEVEN PHASES OF A PROJECT

    1. Wild enthusiasm2. Disillusionment3. Chaos4. Search for the guilty

    5. Punishment of the innocent6. Promotion of the non-participants

    7. Define the requirements

  • 8/6/2019 Chapter4[1] Reji

    12/55

    Planning/Scheduling Tools Planning/Scheduling Tools

  • 8/6/2019 Chapter4[1] Reji

    13/55

    Defining Requirements Defining Requirements

    y The statement of work (SOW)y The project specificationsy The milestone scheduley The work breakdown structure (WBS)

    y The statement of work (SOW)y The project specificationsy The milestone scheduley The work breakdown structure (WBS)

  • 8/6/2019 Chapter4[1] Reji

    14/55

    STATEMENT-OF-WORK (SOW)

    COMPLEXITY IS DETERMINED BY TOP

    MANAGEMENT, CUSTOMER AND/OR USERGROUP(S)

    FOR INTERNAL PROJECTS:SOW IS PREPARED BY THE PROJECT OFFICE

    AND/OR USER GROUP(S)

    STATEMENT-OF-WORK (SOW)

    COMPLEXITY IS DETERMINED BY TOP

    MANAGEMENT, CUSTOMER AND/OR USERGROUP(S)

    FOR INTERNAL PROJECTS:

    SOW IS PREPARED BY THE PROJECT OFFICEAND/OR USER GROUP(S)

  • 8/6/2019 Chapter4[1] Reji

    15/55

    POINTS TO ADDRESS WHEN

    DEVELOPING A STATEMENT-OF-WORK

    POINTS TO ADDRESS WHEN

    DEVELOPING A STATEMENT-OF-WORK y Purpose - objectivesy Exclusions - what should not be done

    y Quantities - how manyy Schedule - when the work will be

    started/completedy

    Deliverables (i.e... work done)y Acceptance criteria - what method will be used toaccept deliverables

    y Responsibility - department, office or personresponsible

    y Purpose - objectivesy Exclusions - what should not be done

    y Quantities - how manyy Schedule - when the work will be

    started/completedy Deliverables (i.e... work done)y Acceptance criteria - what method will be used to

    accept deliverablesy Responsibility - department, office or person

    responsible

  • 8/6/2019 Chapter4[1] Reji

    16/55

    Preparation of internal SOWsy Project office and/or user groups

    Preparation of external SOWsy Dependent on situation, & complexityy Project manager/ line managers and project

    sponsor y Client who may have the capabilitiesy

    Client may decide to contract out to an independentbodyy Client may contract your services

    PREPARATION OF A STATEMENT OF WORK REQUIRES TRAINING RATHER THAN LUCK.

    Preparation of internal SOWsy Project office and/or user groups

    Preparation of external SOWsy Dependent on situation, & complexityy Project manager/ line managers and project

    sponsor y Client who may have the capabilitiesy

    Client may decide to contract out to an independentbodyy Client may contract your services

    PREPARATION OF A STATEMENT OF WORK REQUIRES TRAINING RATHER THAN LUCK.

    WHO PREPARES THE STATEMENT-OF-WORK (SOW)WHO PREPARES THE

    STATEMENT-OF-WORK (SOW)

  • 8/6/2019 Chapter4[1] Reji

    17/55

    IF A STATEMENT OF WORK ISMISINTERPRETED, IS IT

    NORMALLY IN FAVOR OFTHE CLIENT OR

    CONTRACTOR ?

    IF A STATEMENT OF WORK ISMISINTERPRETED, IS IT

    NORMALLY IN FAVOR OFTHE CLIENT OR

    CONTRACTOR ?

    STATEMENT-OF-WORK RISKS STATEMENT-OF-WORK RISKS

  • 8/6/2019 Chapter4[1] Reji

    18/55

    Statement of Work Elements Statement of Work Elementsy General scope of the worky Objectives and related backgroundy Contractors tasksy Contractor end-item performance requirementsy Reference to related studies, documentation,

    and specificationsy Data items (documentation)y Support equipment for contract end-item

    y General scope of the worky Objectives and related backgroundy Contractors tasksy Contractor end-item performance requirementsy Reference to related studies, documentation,

    and specificationsy Data items (documentation)y Support equipment for contract end-item

  • 8/6/2019 Chapter4[1] Reji

    19/55

    Statement of Work Elements Statement of Work Elements

    y Customer-furnished property, facilities,

    equipment, and servicesy Customer-furnished documentationy Schedule of performancey Exhibits, attachments, and appendices

    y Customer-furnished property, facilities,

    equipment, and servicesy Customer-furnished documentationy Schedule of performancey Exhibits, attachments, and appendices

    (Continued)

  • 8/6/2019 Chapter4[1] Reji

    20/55

    The Cost Of Paperwork

  • 8/6/2019 Chapter4[1] Reji

    21/55

    Problem Areas Problem Areasy Project objectives/goals are not agreeable

    to all parties.y Project objectives are too rigid to

    accommodate changing prioritiesy Insufficient time exists to define

    objectives well.y Objectives are not adequately quantified.y Objectives are not documented wellenough.y Efforts of client and project personnel are

    not coordinated.y Personnel turnover is high.

    y Project objectives/goals are not agreeableto all parties.

    y Project objectives are too rigid toaccommodate changing priorities

    y Insufficient time exists to defineobjectives well.

    y Objectives are not adequately quantified.

    y Objectives are not documented wellenough.y Efforts of client and project personnel are

    not coordinated.y Personnel turnover is high.

  • 8/6/2019 Chapter4[1] Reji

    22/55

    Misinterpretation Areas Misinterpretation Areasy Mixing tasks, specifications, approvals,

    and special instructionsy Using imprecise language (nearly,

    optimum, approximately, etc.)y No pattern, structure, or chronological

    order y Wide variation in size of tasksy Wide variation in how to describe details

    of the worky

    Failing to get third-party review

    y Mixing tasks, specifications, approvals,and special instructions

    y Using imprecise language (nearly,optimum, approximately, etc.)

    y No pattern, structure, or chronologicalorder

    y Wide variation in size of tasksy Wide variation in how to describe details

    of the worky

    Failing to get third-party review

  • 8/6/2019 Chapter4[1] Reji

    23/55

  • 8/6/2019 Chapter4[1] Reji

    24/55

  • 8/6/2019 Chapter4[1] Reji

    25/55

    WORK BREAKDOWN STRUCTURE WORK BREAKDOWN STRUCTURE

    y Can be developed using a top-down or bottom-up approach

    y Can be hardware-related, function-related, or

    a combinationy Depth of WBS must balance out

    management effort against planningaccuracy (influences technical and cost

    control)y For accuracy purposes the WBS should be

    taken down several levelsy The WBS must be structured for objective

    control & evaluation

    y Can be developed using a top-down or bottom-up approach

    y Can be hardware-related, function-related, or

    a combinationy Depth of WBS must balance outmanagement effort against planningaccuracy (influences technical and cost

    control)y For accuracy purposes the WBS should be

    taken down several levelsy The WBS must be structured for objective

    control & evaluation

  • 8/6/2019 Chapter4[1] Reji

    26/55

    Work Breakdown

    Structure (WBS)

    Work Breakdown

    Structure (WBS)y The total program can be described as asummation of subdivided elements.

    y Planning can be performed.y Costs and budgets can be established.y Time, cost, and performance can be

    tracked.y Objectives can be linked to company

    resources in a logical manner.y Schedules and status-reporting

    procedures can be established.

    y The total program can be described as asummation of subdivided elements.

    y Planning can be performed.y Costs and budgets can be established.y Time, cost, and performance can be

    tracked.y Objectives can be linked to company

    resources in a logical manner.y Schedules and status-reporting

    procedures can be established.

  • 8/6/2019 Chapter4[1] Reji

    27/55

    Work Breakdown

    Structure (WBS) (Continued)

    Work Breakdown

    Structure (WBS) (Continued)y Network construction and control

    planning can be initiated.

    y The responsibility assignments for eachelement can be established.

    y Network construction and controlplanning can be initiated.

    y The responsibility assignments for eachelement can be established.

  • 8/6/2019 Chapter4[1] Reji

    28/55

    y Have clearly defined start datesy Have clearly defined end datesy Must be able to be used as a

    communicative tool in which you cancommunicate the expected results

    y Be estimated on a total time duration

    not when the individual activities start or endy Be structured so that a minimum of

    project office control and documentation(i.e. forms) are necessary

    y Have clearly defined start datesy Have clearly defined end datesy Must be able to be used as a

    communicative tool in which you cancommunicate the expected results

    y Be estimated on a total time duration

    not when the individual activities start or endy Be structured so that a minimum of

    project office control and documentation(i.e. forms) are necessary

    IN SETTING UP A WORK BREAKDOWN STRUCTURE THE ACTIVITIES MUST:

  • 8/6/2019 Chapter4[1] Reji

    29/55

    Most common type: Six-Level Indentured Structure

    LEVEL DESCRIPTION1 Total Program

    2 Project(s)3 Task(s)4 Subtask(s)

    5 Work Package(s)6 Level of Effort

    WORK BREAKDOWN

    STRUCTURE (WBS)

  • 8/6/2019 Chapter4[1] Reji

    30/55

    THE WBS BREAKS WORK DOWN INTO SMALLER ACTIVITIES THUS REDUCING THE RISK THAT ANY MAJOR OR MINOR ITEM WILL BE OMITTED

    THE WBS BREAKS WORK DOWN INTO SMALLER ACTIVITIES THUS REDUCING THE RISK THAT ANY MAJOR OR MINOR ITEM WILL BE OMITTED

    WBS: SIX-LEVEL STRUCTURE

    Usually specified by the client andmanaged the project manager.

    Generated by contractor for in-housecontrol and managed by thefunctional manager(s).

    Planning accuracy is dependent on the WBS levelselected. The lower the level the greater is the planningaccuracy but the higher the management cost .

    LEVELS RESPONSIBILITY

    123456

  • 8/6/2019 Chapter4[1] Reji

    31/55

    WBS TasksWBS Tasks

    y Have clearly defined start and end datesy Be usable as a communications tool in

    which results can be compared withexpectations

    y Be estimate on a total time duration, notwhen the task must start or end

    y Be structured so that a minimum of project office control and documentation(i.e., forms) is necessary

    y Have clearly defined start and end datesy Be usable as a communications tool in

    which results can be compared withexpectations

    y Be estimate on a total time duration, notwhen the task must start or end

    y Be structured so that a minimum of project office control and documentation(i.e., forms) is necessary

  • 8/6/2019 Chapter4[1] Reji

    32/55

    DEVELOPING A WORK BREAKDOWN STRUCTURE (WBS)

    DEVELOPING A WORK BREAKDOWN STRUCTURE (WBS)

    PROTOTYPEDEVELOPMENT

    (1.1.0)

    ADVANCEDDEVELOPMENT

    (1.2.0)

    PRE-PRODUCTION

    QUALIFICATION(1.3.0)

    FINALPRODUCTION

    (1.4.0)

    UTILITY CAR (1.00.00)

  • 8/6/2019 Chapter4[1] Reji

    33/55

    1.00.001.00.00

    1.1.01.1.0 1.2.01.2.0 1.3.01.3.0 1.4.01.4.0

    1.2.11.2.1 1.2.31.2.31.2.21.2.2

    1.2.2.11.2.2.1 1.2.2.21.2.2.2 1.2.2.31.2.2.3

    1.2.2.1.11.2.2.1.1 1.2.2.1.21.2.2.1.2 1.2.2.1.31.2.2.1.3 1.2.2.1.41.2.2.1.4

    WBS ExampleWBS LEVELS

    5

    4

    3

    2

    1 PROGRAM

    PROJECT

    TASK

    SUBTASK

    WORKPACKAGE

  • 8/6/2019 Chapter4[1] Reji

    34/55

    WBS ControlsWBS Controls

    WORK

    BREAKDOWN

    STRUCTURE

    WORK

    BREAKDOWN

    STRUCTURE

    MGT.

    COORDIN.

    MGT.

    COORDIN.

    ORGANIZ.

    CHARTS

    ORGANIZ.

    CHARTS

    COSTSCOSTSACCOUNT-

    ABILITY

    ACCOUNT-

    ABILITY

    DECISION

    TREES

    DECISION

    TREESSCHEDULESSCHEDULES

  • 8/6/2019 Chapter4[1] Reji

    35/55

    WBS Interfacing BenefitsWBS Interfacing Benefits

    y The responsibility assignment matrixy Network schedulingy Costingy Risk analysisy Organizational structure

    y Coordination of objectivesy Control (including contract

    administration)

    y The responsibility assignment matrixy Network schedulingy Costingy Risk analysisy Organizational structure

    y Coordination of objectivesy Control (including contract

    administration)

  • 8/6/2019 Chapter4[1] Reji

    36/55

    Work Package Control Point Work Package Control Point

    WORKPACKAGES

    WBS

    FUNCTIONALORGANIZATION

  • 8/6/2019 Chapter4[1] Reji

    37/55

    WBS Work PackagesWBS Work Packages

    y Represents units of work at the levelwhere the work is performed

    y Clearly distinguishes one work packagefrom all others assigned to a singlefunctional group

    y Contains clearly defined start and enddates that are representative of physicalaccomplishment

    y Target is 80 hours and about two weeks,

    but depends on size/nature of the project.

    y Represents units of work at the levelwhere the work is performed

    y

    Clearly distinguishes one work packagefrom all others assigned to a singlefunctional group

    y Contains clearly defined start and enddates that are representative of physicalaccomplishment

    y Target is 80 hours and about two weeks,

    but depends on size/nature of the project.

  • 8/6/2019 Chapter4[1] Reji

    38/55

    WBS Packages (Continued)WBS Packages (Continued)

    y Specifies a budget in terms of dollars,man-hours, or other measurable units

    y Limits the work to be performed torelatively short periods of time tominimize the work-in-process effort

    y Specifies a budget in terms of dollars,man-hours, or other measurable units

    y

    Limits the work to be performed torelatively short periods of time tominimize the work-in-process effort

  • 8/6/2019 Chapter4[1] Reji

    39/55

    The Project Kickoff Meeting The Project Kickoff Meeting

  • 8/6/2019 Chapter4[1] Reji

    40/55

    Knowing When To Pull The Plug Knowing When To Pull The Plug

  • 8/6/2019 Chapter4[1] Reji

    41/55

    REASONS WHY PLANS FAIL

    y Corporate goals not understood lower down in the organization/company

    y Plans encompass too much in too little timey Poor financial estimatesy Plans based upon insufficient datay

    Poor staff requirementsy Insufficient time allocated for project estimating

    REASONS WHY PLANS FAIL

    y Corporate goals not understood lower down in the organization/company

    y Plans encompass too much in too little timey Poor financial estimatesy Plans based upon insufficient datay

    Poor staff requirementsy Insufficient time allocated for project estimating

  • 8/6/2019 Chapter4[1] Reji

    42/55

    OTHER REASONS WHY PLANS FAIL

    y

    No attempt made to systemize the planning processy Planning was performed by a planning groupy No one knows the ultimate objectivesy No one knows the major milestone datesy Project estimates are best guesses and are not based

    on any standards, or historyy No one bothered to see if there would be personnel

    available with the necessary skillsy People not working towards the same specsy

    Constant shuffle of personnel in and out of theproject with little regard for the scheduley Change of management and their objectives.y Change(s) in the macro environment

    OTHER REASONS WHY PLANS FAIL

    y

    No attempt made to systemize the planning processy Planning was performed by a planning groupy No one knows the ultimate objectivesy No one knows the major milestone datesy Project estimates are best guesses and are not based

    on any standards, or historyy No one bothered to see if there would be personnel

    available with the necessary skillsy People not working towards the same specsy

    Constant shuffle of personnel in and out of theproject with little regard for the scheduley Change of management and their objectives.y Change(s) in the macro environment

  • 8/6/2019 Chapter4[1] Reji

    43/55

    Stopping Projects Stopping Projectsy Final achievement of the objectivesy Poor initial planning and market

    prognosisy A better alternative is foundy A change in the company interest and

    strategyy

    Allocated time is exceededy Key people leave the organizationy Personal whims of managementy Problem too complex for the resources

    available

    y Final achievement of the objectivesy Poor initial planning and market

    prognosisy A better alternative is foundy A change in the company interest and

    strategyy

    Allocated time is exceededy Key people leave the organizationy Personal whims of managementy Problem too complex for the resources

    available

  • 8/6/2019 Chapter4[1] Reji

    44/55

    Behavioral Stoppages Behavioral Stoppages

    y Poor moraley Poor human relationsy Poor labor productivityy No commitment by those involved in the

    project

    y Poor moraley Poor human relations

    y Poor labor productivityy No commitment by those involved in the

    project

  • 8/6/2019 Chapter4[1] Reji

    45/55

    Ways to TerminateWays to Terminatey Orderly planned terminationy The hatchet (withdrawal of funds and

    removal of personnel)y Reassignment of people to higher priority

    effortsy Redirection of efforts toward different

    objectivesy Burying it or letting it die on the vine (i.e.,

    not taking any official action)

    y Orderly planned terminationy The hatchet (withdrawal of funds and

    removal of personnel)y Reassignment of people to higher priority

    effortsy Redirection of efforts toward different

    objectivesy Burying it or letting it die on the vine (i.e.,

    not taking any official action)

  • 8/6/2019 Chapter4[1] Reji

    46/55

    Termination Problem

    Areas

    Termination Problem

    Areasy Worker moraley Reassignment of personnely Adequate documentation and wrap-up

    y Worker moraley Reassignment of personnel

    y Adequate documentation and wrap-up

  • 8/6/2019 Chapter4[1] Reji

    47/55

    Planning For Project Completion

  • 8/6/2019 Chapter4[1] Reji

    48/55

    Planned Closure Planned Closure

    y Transferring responsibilityy Completion of project records

    Historic reports Post project analysis

    y Documenting results to reflect as builtproduct or installation

    y Acceptance by sponsor/user y Satisfying contractual requirements

    y Transferring responsibilityy Completion of project records

    Historic reports Post project analysis

    y Documenting results to reflect as builtproduct or installation

    y Acceptance by sponsor/user y Satisfying contractual requirements

  • 8/6/2019 Chapter4[1] Reji

    49/55

    Planned Closure (Continued) Planned Closure (Continued)

    y Releasing resources Reassignment of project office team members

    Disposition of functional personnel Disposition of materialsy Closing out work orders (financial

    closeout)y Preparing for financial payments

    y Releasing resources Reassignment of project office team members

    Disposition of functional personnel Disposition of materialsy Closing out work orders (financial

    closeout)y Preparing for financial payments

  • 8/6/2019 Chapter4[1] Reji

    50/55

    Updating The Project Diary

  • 8/6/2019 Chapter4[1] Reji

    51/55

    Managing Scope Changes Managing Scope Changes

  • 8/6/2019 Chapter4[1] Reji

    52/55

    Change Management Change Management y YOU CANNOT MANAGE YOUR CUSTOMER

    WITHOUT MANAGEMENT OF YOUR PROJECTMANAGEMENT PROCESS.

    y WHEN YOUR CUSTOMER INITIATES A CHANGEREQUEST, YOU MUST BE ABLE TO PREDICTIMMEDIATELY THE IMPACT ON SCHEDULE ,COST AND TECHNICAL PERFORMANCE.

    y YOU CANNOT MANAGE YOUR CUSTOMERWITHOUT MANAGEMENT OF YOUR PROJECTMANAGEMENT PROCESS.

    y WHEN YOUR CUSTOMER INITIATES A CHANGEREQUEST, YOU MUST BE ABLE TO PREDICTIMMEDIATELY THE IMPACT ON SCHEDULE ,

    COST AND TECHNICAL PERFORMANCE.

  • 8/6/2019 Chapter4[1] Reji

    53/55

    Unmanaged vs. Managed ChangesUnmanaged vs. Managed Changes

    UnmanagedChangeUnmanagedChange

    Where TIMEis invested

    Where TIMEis invested

    HowENERGYis invested

    HowENERGYis invested

    WhichRESOURCES

    are used

    WhichRESOURCES

    are used

    ManagedChangeManagedChange

    Back-end Back-end

    Front-end

    Front-end

    Rework Enforcement Compliance Supervision

    Rework Enforcement Compliance Supervision

    Education Communication Planning Improvements Value-Added

    Education Communication Planning Improvements Value-Added

    Senior Managementand key

    players only

    Senior Managementand key

    players only

    Stakeholders(internal) Suppliers Customers

    Stakeholders(internal) Suppliers Customers

  • 8/6/2019 Chapter4[1] Reji

    54/55

    DefinitionDefinition

    Cost of CorrectionsCost of Corrections

    $1$1

    PreliminaryPlanning

    PreliminaryPlanning

    $5$5 $25$25 $100$100 $1000$1000

    DetailedPlanningDetailedPlanning ExecutionExecution

    Implementation/Conversion

    Implementation/Conversion

  • 8/6/2019 Chapter4[1] Reji

    55/55

    Integrated Processes for The 21st Century

    Integrated Processes for The 21st Century

    Project ManagementProject Management

    ConcurrentEngineeringConcurrentEngineering Total QualityManagementTotal QualityManagement

    Risk Management

    Risk Management

    ChangeManagement

    ChangeManagement