Mod3 Funda Proj Network PERT

Embed Size (px)

Citation preview

  • 8/18/2019 Mod3 Funda Proj Network PERT

    1/23

    Program Evaluation Review

     Technique (PERT)Prof.G.Purandaran

    M.Tech (I.I.T-Madras)

    PGDM (I.I.M-Bangalore)

  • 8/18/2019 Mod3 Funda Proj Network PERT

    2/23

    Objective of theresentation

    •  To understand the formula , the useand the benets of Program ,Evaluation ,and Review Technic(PERT) analysis .

  • 8/18/2019 Mod3 Funda Proj Network PERT

    3/23

    Program (Proect) Evaluation and Review Technique (PERT)! is a "roect management toolused to schedule, organi#e, and coordinate tas$swithin a "roect. %t is basically a method to analysethe tas$s involved in com"leting a given "roect,es"ecially the time needed to com"lete each tas$,and to identify the minimum time needed tocom"lete the total "roect.

    !hat is the P"#T $

  • 8/18/2019 Mod3 Funda Proj Network PERT

    4/23

    !hen %e use P"#T $

    P"#T is used when activit& ti'es are uncertain. – &etermine the duration of the "roect .

     –  &ecision ma$ing under ris$ ('P for "robabilistic)

  • 8/18/2019 Mod3 Funda Proj Network PERT

    5/23

    Deter'ine the duration ofthe roject

    • OPTIMITI TIM"! Best time if everything goes

    "erfectly• RE*%+T% T%-E! Most li$ely time

    • PE++%-%+T% T%-E!  worstcase situation

      B / 0M  / P

    E1"ected Time 2   3

  • 8/18/2019 Mod3 Funda Proj Network PERT

    6/23

    Deter'ine the duration ofthe roject

    • "*a'le+,or e*cavation activit& let +

    B / da&s

    M 0 da&s

    P 12

    !hat is the e*ected ti'e for this activit&$

    ol +

      / / 0(0)  / 12

    E1"ected Time 2   3

      2 40 days

  • 8/18/2019 Mod3 Funda Proj Network PERT

    7/23

    Deter'ine the duration ofthe roject

  • 8/18/2019 Mod3 Funda Proj Network PERT

    8/23

    Deter'ine the duration ofthe roject

    +tart

    5

    6E

    &

    7

    5inish

  • 8/18/2019 Mod3 Funda Proj Network PERT

    9/23

    Deter'ine the duration ofthe roject

    +tartE+!8E5!8

    5&!0.9

    E+!:8.;;E5!:0..:=

    6&!9.:=

    E+!:0.;0E5!:>.9:

    E&!9.:=E+!>.:=E5!:0.;0

    &&!3.;;

    E+!0E5!:8.;;

    7&!9.;;E+!8

    E5!9.;;

    &!0E+!8E5!0

    5inish&!8

    E+!:>.9:

    E5!:>.9:

  • 8/18/2019 Mod3 Funda Proj Network PERT

    10/23

    Deter'ine the duration ofthe roject

    tartD+2"+2",+23+2

    3,+2

    ,D+4.5

    "+2.66

    ",+4.063+5.23,+7.5

    D+5.8"+4

    ",+7.83+4

    3,+7.8

    GD+5.8

    "+4.64",+7.53+4.64

    3,+7.5

    "D+5.8"+7.8",+4.643+7.8

    3,+4.64

    DD+1.66"+4

    ",+2.663+0.103,+5.2

    BD+5.66"+2

    ",+5.663+6.04

    3,+7.8

    9D+4"+2",+43+2

    3,+4

    ,inishD+2

    "+7.5",+7.5

    3+7.53,+7.5

  • 8/18/2019 Mod3 Funda Proj Network PERT

    11/23

    Deter'ine the duration ofthe roject

    ritical Path

    ritical Path! E6

    • Path &5 2 :0.

  • 8/18/2019 Mod3 Funda Proj Network PERT

    12/23

    Deter'ine the duration ofthe roject

    ritical Path

  • 8/18/2019 Mod3 Funda Proj Network PERT

    13/23

    9ssessing #is:s

    • #is:  is a measure of the "robability(and consequences) of not com"letinga "roect on time.

    maor res"onsibility of the "roectmanager at the start of a "roect is todevelo" a ris$management "lan.

    • #is:-Manage'ent Plan identies

    the $ey ris$s to a "roect?s success and"rescribes ways to circumvent them.

  • 8/18/2019 Mod3 Funda Proj Network PERT

    14/23

    • @ith PERT?s three timeestimates, we get amean (average) time and a variance for 

    each activity  and each path.

     –

    @e also get a  project  mean timeand variance.

    • %n order to com"ute "robabilities (assuming a

    normal distribution) we need the activity

    means and variances.

     – -ost com"uter "ac$ages calculate this for you.

    9ssessing #is:s

  • 8/18/2019 Mod3 Funda Proj Network PERT

    15/23

    3

    :8

    6

    ;9

     B

    0

    C

    08

    7

    >

    &

    :8

    E

    40

    %

    :9

    5inish+tart

    :4

    5

    :8

    8 >

    > ;;

    > :> :> 9>

    44 9=:4 44

    9> 3;

    :4 4=

    :4 44 3; 3>8 :4

    0< 3;

    9; 3;

    9> 3;

    40 9>

    :> 9>

    ;9 9>

    :0 40

    > :>

    4 :0

    8 >

    *atestnishtime

    3; 3>

    *ateststarttime

    Path Time

    (w$s)

    %A ;;;;

    5A 4<4<

    6BA 3=7&CBA 3>7EBA 0;

    9ssessing #is:s

  • 8/18/2019 Mod3 Funda Proj Network PERT

    16/23

    •@hat is the "robability that our sam"le"roect will nish in 3> wee$s as scheduledD

    :88 (@hyD)

     –7ecause we used P-F• (This means we were certain of all of our activity

    times.)

     – %f we weren?t certain, we should have used PERT

    • Gou can?t do ris$ analysis if you use P-

    9ssessing #is:s

  • 8/18/2019 Mod3 Funda Proj Network PERT

    17/23

    • alculate standard deviation  – +tandard deviation average deviation from the

    estimated time• +&2(TPT8)H3

     – higher the +& is the greater amount of uncertainty

    e1ists

    • alculate variance – reIects the s"read of a value over a normal

    distribution• J2+&4

     – a large variance indicates great uncertainty, asmall variance indicates a more accurate estimate

    9ssessing #is:s

  • 8/18/2019 Mod3 Funda Proj Network PERT

    18/23

      (variances of activities along critical ath); T <

      σ

    /

    .80 = .80 = /.80 = 5.44 = 2. .07

    ; 8/ < 17

      .07

    !hat is the Probabilit& of it ta:ing 8/%ee:s$ritical Path B - D - > - ? < @ 17 %ee:s

    T 8/ %ee:s 17 %ee:s

    *oo$ u" K value in normal distribution tableP# 2 .

  • 8/18/2019 Mod3 Funda Proj Network PERT

    19/23

    *oo$ u" the K value (8.

  • 8/18/2019 Mod3 Funda Proj Network PERT

    20/23

    Proect duration (wee$s)

    3> =4

     Probability ofta$ing =4 wee$sis 8.

  • 8/18/2019 Mod3 Funda Proj Network PERT

    21/23

    • ssume a PERT "roect critical "ath ta$es 42 da&s, and that

    the variance of this "ath is 4.:0= –  Gou wish to $now the "robability of the "roect going over 04 days.

    • om"ute the standard deviation of the critical "ath. (Ta$e the

    square root of the variance of 4.:0=) +td. &ev. 2 :.039

     – POM/QM software gives you the variance of the critical path.

    • om"ute the A value! K 2 (absolute time diOerence) H +td.&ev.

     %n this e1am"le, K 2 (04 days 08 days) H :.039 2 .615

    • *oo$ u" the K value of .615 in a Mormal &istribution table to

    get the "robability of the "roect ta$ing 04 days.

    • +ubtract it from :88 to get the "robability of going over 04.

    9ssessing #is:s

  • 8/18/2019 Mod3 Funda Proj Network PERT

    22/23

    *oo$ u" the K value (:.;39) in the table of normal

    distribution.

    (%n this case you need to inter"olate between the K values of .>;:; and .

    >:0=)

    .>:;> or >:.;> is the "robability of the "roect ta$ing u" to

    04 days.

    9ssessing #is:s

  • 8/18/2019 Mod3 Funda Proj Network PERT

    23/23

    Than: &ou for attention

    9n& Cuestions $$$$