Upload
puramalli
View
213
Download
0
Embed Size (px)
Citation preview
8/18/2019 Mod3 Funda Proj Network PERT
1/23
Program Evaluation Review
Technique (PERT)Prof.G.Purandaran
M.Tech (I.I.T-Madras)
PGDM (I.I.M-Bangalore)
8/18/2019 Mod3 Funda Proj Network PERT
2/23
Objective of theresentation
• To understand the formula , the useand the benets of Program ,Evaluation ,and Review Technic(PERT) analysis .
8/18/2019 Mod3 Funda Proj Network PERT
3/23
Program (Proect) Evaluation and Review Technique (PERT)! is a "roect management toolused to schedule, organi#e, and coordinate tas$swithin a "roect. %t is basically a method to analysethe tas$s involved in com"leting a given "roect,es"ecially the time needed to com"lete each tas$,and to identify the minimum time needed tocom"lete the total "roect.
!hat is the P"#T $
8/18/2019 Mod3 Funda Proj Network PERT
4/23
!hen %e use P"#T $
•
P"#T is used when activit& ti'es are uncertain. – &etermine the duration of the "roect .
– &ecision ma$ing under ris$ ('P for "robabilistic)
8/18/2019 Mod3 Funda Proj Network PERT
5/23
Deter'ine the duration ofthe roject
• OPTIMITI TIM"! Best time if everything goes
"erfectly• RE*%+T% T%-E! Most li$ely time
• PE++%-%+T% T%-E! worstcase situation
B / 0M / P
E1"ected Time 2 3
8/18/2019 Mod3 Funda Proj Network PERT
6/23
Deter'ine the duration ofthe roject
• "*a'le+,or e*cavation activit& let +
B / da&s
M 0 da&s
P 12
!hat is the e*ected ti'e for this activit&$
ol +
/ / 0(0) / 12
E1"ected Time 2 3
2 40 days
8/18/2019 Mod3 Funda Proj Network PERT
7/23
Deter'ine the duration ofthe roject
8/18/2019 Mod3 Funda Proj Network PERT
8/23
Deter'ine the duration ofthe roject
+tart
5
6E
&
7
5inish
8/18/2019 Mod3 Funda Proj Network PERT
9/23
Deter'ine the duration ofthe roject
+tartE+!8E5!8
5&!0.9
E+!:8.;;E5!:0..:=
6&!9.:=
E+!:0.;0E5!:>.9:
E&!9.:=E+!>.:=E5!:0.;0
&&!3.;;
E+!0E5!:8.;;
7&!9.;;E+!8
E5!9.;;
&!0E+!8E5!0
5inish&!8
E+!:>.9:
E5!:>.9:
8/18/2019 Mod3 Funda Proj Network PERT
10/23
Deter'ine the duration ofthe roject
tartD+2"+2",+23+2
3,+2
,D+4.5
"+2.66
",+4.063+5.23,+7.5
D+5.8"+4
",+7.83+4
3,+7.8
GD+5.8
"+4.64",+7.53+4.64
3,+7.5
"D+5.8"+7.8",+4.643+7.8
3,+4.64
DD+1.66"+4
",+2.663+0.103,+5.2
BD+5.66"+2
",+5.663+6.04
3,+7.8
9D+4"+2",+43+2
3,+4
,inishD+2
"+7.5",+7.5
3+7.53,+7.5
8/18/2019 Mod3 Funda Proj Network PERT
11/23
Deter'ine the duration ofthe roject
ritical Path
ritical Path! E6
• Path &5 2 :0.
8/18/2019 Mod3 Funda Proj Network PERT
12/23
Deter'ine the duration ofthe roject
ritical Path
8/18/2019 Mod3 Funda Proj Network PERT
13/23
9ssessing #is:s
• #is: is a measure of the "robability(and consequences) of not com"letinga "roect on time.
•
maor res"onsibility of the "roectmanager at the start of a "roect is todevelo" a ris$management "lan.
• #is:-Manage'ent Plan identies
the $ey ris$s to a "roect?s success and"rescribes ways to circumvent them.
8/18/2019 Mod3 Funda Proj Network PERT
14/23
• @ith PERT?s three timeestimates, we get amean (average) time and a variance for
each activity and each path.
–
@e also get a project mean timeand variance.
• %n order to com"ute "robabilities (assuming a
normal distribution) we need the activity
means and variances.
– -ost com"uter "ac$ages calculate this for you.
9ssessing #is:s
8/18/2019 Mod3 Funda Proj Network PERT
15/23
A
3
:8
6
;9
B
0
C
08
7
>
&
:8
E
40
%
:9
5inish+tart
:4
5
:8
8 >
> ;;
> :> :> 9>
44 9=:4 44
9> 3;
:4 4=
:4 44 3; 3>8 :4
0< 3;
9; 3;
9> 3;
40 9>
:> 9>
;9 9>
:0 40
> :>
4 :0
8 >
*atestnishtime
3; 3>
*ateststarttime
Path Time
(w$s)
%A ;;;;
5A 4<4<
6BA 3=7&CBA 3>7EBA 0;
9ssessing #is:s
8/18/2019 Mod3 Funda Proj Network PERT
16/23
•@hat is the "robability that our sam"le"roect will nish in 3> wee$s as scheduledD
:88 (@hyD)
–7ecause we used P-F• (This means we were certain of all of our activity
times.)
– %f we weren?t certain, we should have used PERT
• Gou can?t do ris$ analysis if you use P-
9ssessing #is:s
8/18/2019 Mod3 Funda Proj Network PERT
17/23
• alculate standard deviation – +tandard deviation average deviation from the
estimated time• +&2(TPT8)H3
– higher the +& is the greater amount of uncertainty
e1ists
• alculate variance – reIects the s"read of a value over a normal
distribution• J2+&4
– a large variance indicates great uncertainty, asmall variance indicates a more accurate estimate
9ssessing #is:s
8/18/2019 Mod3 Funda Proj Network PERT
18/23
(variances of activities along critical ath); T <
σ
/
.80 = .80 = /.80 = 5.44 = 2. .07
; 8/ < 17
.07
!hat is the Probabilit& of it ta:ing 8/%ee:s$ritical Path B - D - > - ? < @ 17 %ee:s
T 8/ %ee:s 17 %ee:s
*oo$ u" K value in normal distribution tableP# 2 .
8/18/2019 Mod3 Funda Proj Network PERT
19/23
*oo$ u" the K value (8.
8/18/2019 Mod3 Funda Proj Network PERT
20/23
Proect duration (wee$s)
3> =4
Probability ofta$ing =4 wee$sis 8.
8/18/2019 Mod3 Funda Proj Network PERT
21/23
• ssume a PERT "roect critical "ath ta$es 42 da&s, and that
the variance of this "ath is 4.:0= – Gou wish to $now the "robability of the "roect going over 04 days.
• om"ute the standard deviation of the critical "ath. (Ta$e the
square root of the variance of 4.:0=) +td. &ev. 2 :.039
– POM/QM software gives you the variance of the critical path.
• om"ute the A value! K 2 (absolute time diOerence) H +td.&ev.
%n this e1am"le, K 2 (04 days 08 days) H :.039 2 .615
• *oo$ u" the K value of .615 in a Mormal &istribution table to
get the "robability of the "roect ta$ing 04 days.
• +ubtract it from :88 to get the "robability of going over 04.
9ssessing #is:s
8/18/2019 Mod3 Funda Proj Network PERT
22/23
*oo$ u" the K value (:.;39) in the table of normal
distribution.
(%n this case you need to inter"olate between the K values of .>;:; and .
>:0=)
.>:;> or >:.;> is the "robability of the "roect ta$ing u" to
04 days.
9ssessing #is:s
8/18/2019 Mod3 Funda Proj Network PERT
23/23
Than: &ou for attention
9n& Cuestions $$$$